Architectural Inspection Standard Interior Partitions

Architectural Inspection – Standard Interior Partitions  0611 Fixed Partitions – All components of the interior wall assembly excluding finish  Interi...
Author: Jean Wells
28 downloads 0 Views 7MB Size
Architectural Inspection – Standard Interior Partitions  0611 Fixed Partitions – All components of the interior wall assembly excluding finish  Interior walls are constructed of wood studs of varying sizes from 2x4 to 2x8 with  gypsum wall board each side.  Except for minor damage to the gypsum wall board in several locations, partitions are in  good condition.  Remaining life expectancy:  Over 10 years 

Deficiency 

0611­1 Damaged wall board  Minor damage to gypsum wall board  Deficiency category:  RR  Remedy  Patch wall and refinish.  Estimated Construction Cost:  $11,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 95 of 228 

Architectural Inspection – Standard Interior Partitions  0612 Soffits – Framing and sheathing of soffits and bulkheads excluding finishes  Interior soffits are constructed of 2x4 or 2x6 wood studs sizes wth gypsum wall board  finish.  Soffits are in good condition.  Remaining life expectancy:  Over 10 years  No deficiencies noted.

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 96 of 228 

Architectural Inspection – Special Interior Partitions  0623 Glazed Partitions – Glazing, glass block, frame, trim, etc.  A glazed partition of oak wood frame and wire glass occurs at the special  education/resource room (library of original design).  The wood frame is in marginal condition.  Remaining life expectancy:  5­10 years 

Deficiency 

0623­1 Damaged wood framed glass partition  The wood frame of the glass partition has damage from adjacent activity and use  especially at floor level.  Deficiency category:  RR  Remedy  Refurbish the wood frame/ finish and install a protective base up to 18” to take abuse that  occurs from carts and children.  Estimated Construction Cost:  $1,100

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 97 of 228 

Architectural Inspection – Interior Doors  0631 Personnel Doors – Door leafs, frames, finish, and hardware  Interior doors are primarily solid core wood doors with plastic laminate finish in knock  down or welded hollow metal frames.  Some aluminum frame doors occur at interior  walls of vestibules.  Most doors have magnetic hold opens.  Doors are in marginal condition.  Remaining life expectancy:  5­10 years

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 98 of 228 

Architectural Inspection – Interior Doors  Deficiency 

0631­1 Fire rated wood doors  Doors do not maintain required fire rating: Rated doors do not close and latch  automatically.  Closer force is inadequate or the doors are dragging on the floor.  Smoke  seals are damaged or missing.  Latches have been removed.  Closers have been replaced  with hold open hardware.  An unprotected louver opening occurs in a rated fan room  door.  Deficiency category:  C  Remedy  Replace door hardware, latches, smoke seals and closers to provide a complete rated  assembly.  Adjust or modify doors that drag on floors to allow free swing.  Install a  louver with damper on the fan room door.  Estimated Construction Cost:  $9,100

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 99 of 228 

Architectural Inspection – Interior Doors  Deficiency 

0631­2 Wood door sag  Pairs of doors sag at hinges causing them to not close properly.  Sagging may be due in  part to building movement and door openings being out of square.  Deficiency category:  RR  Remedy  Adjust door hardware and hinge to take up sag.  Replace doors and frames that cannot be  adjusted, and re­frame rough opening.  Estimated Construction Cost:  $3,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 100 of 228 

Architectural Inspection – Interior Doors  Deficiency 

0631­3 Aluminum Door sag  Pairs of aluminum doors sag at hinges causing them not to close properly.  Sagging may  be due in part to building movement and door openings being out of square.  Deficiency category:  RR  Remedy  Adjust door hardware and hinge to take up sag.  Replace doors and frames that can not be  adjusted, and re­frame rough opening.  Estimated Construction Cost:  $21,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 101 of 228 

Architectural Inspection – Interior Doors  Deficiency 

0631­4 Aluminum Door hardware  Aluminum doors have damaged or missing hardware (hold open and door pull).  Deficiency category:  RR  Remedy  Replace hardware.  Estimated Construction Cost:  $600

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 102 of 228 

Architectural Inspection – Interior Doors  Deficiency 

0631­5 Door frame rust  A door frame at the primary room bathrooms is rusted.  Deficiency category:  RR  Remedy  Replace door frame.  Estimated Construction Cost:  $1,500

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 103 of 228 

Architectural Inspection – Interior Doors  0632 Special Doors – Overhead doors, grilles, access doors, etc.  There are two stainless steel overhead coiling counter doors.  The doors are in good condition.  Remaining life expectancy:  5­10 years 

Deficiency 

Deficiency 0632­1 Fire rated coiling door  The coiling door does not close tightly against the counter.  The fire fly release was not  tested to assure closure on alarm.  Deficiency category:  RR  Remedy  Test the door for operation and tight closure.  Replace the door if needed.  Estimated Construction Cost:  $3,600

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 104 of 228 

Architectural Inspection – Interior Doors  Deficiency 

0632­2 coiling door abandoned  The coiling door is not used.  Deficiency category:  F  Remedy  Remove door and construct a wall.  Estimated Construction Cost:  $1,800

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 105 of 228 

Architectural Inspection – Interior Finishes  0641 Wall Finishes – Paint, wall coverings, tile, acoustic treatment, etc.  Original building: A variety of wall finishes have been used throughout the building.  Hallways have a 4’ high enameled hardboard wainscot (Marlite) and wall carpet above to  the ceiling.  Some classrooms have a prefinished hardboard wainscot (Marlite) below the  chalk and tack boards and painted gypsum board elsewhere.  Other classrooms have only  painted gypsum board.  The gym has a hardboard wainscot to 8’ with painted rough sawn  plywood up to the ceiling.  Toilet rooms have prefinished hardboard and areas behind  toilets and urinals have a retrofit wainscot of stainless steel.  A shower room has ceramic  tile walls.  1991 addition:  Hallways have wall carpet wainscot to 4’ with painted gypsum wall board  above.  The classrooms and library have wall carpet wainscot to 7’ with wood trim and  painted gypsum wall board above.  The toilet rooms have an acrylic wainscot to 4’ with  painted gypsum wall board above.  Wall finishes are generally in poor condition throughout the building.  Remaining life expectancy:  less than 5 years.

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 106 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0641­1 Enameled hardboard panels  The prefinished hardboard panels were installed as part of the original construction in  1968.   They have outlived their expected life and though repainted many times are  severly marred throughout.  Deficiency category:  RR  Remedy  Replace ~11,100 SF of the prefinished hardboard wainscot throughout.  Estimated Construction Cost:  $152,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 107 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0641­2 Wall carpet  Wall carpet is used on walls in both the original building and the 1991 addition.  Both  installtions are worn and damaged.  Deficiency category:  RR  Remedy  Replace ~6,000 SF of wall carpet throughout.  Estimated Construction Cost:  $61,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 108 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0641­3 Acrylic wall cover  Acrylic wall cover is used in the 1991 addition toilet rooms.  The wall cover is stained  and failing at corner seams.  Deficiency category:  RR  Remedy Option 1  Replace ~350 SF of wall cover throughout 1991 addition toilet rooms.  Estimated Construction Cost:  $2,800  Remedy Option 2  Replace ~350 SF of acrylic wall cover with ceramic tile at 1991 addition toilet rooms  Estimated Construction Cost:  $7,500

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 109 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

Deficiency 0641­4 stainless steel wall cover  Stainless steel wall cover has been installed over enameled hardboard behind water  closets, urinals and sinks.  The material is holding up well but the installation appears as  an after thought.  Deficiency category:  RR  Remedy  Replace ~800 SF of stainless steel wainscot at plumbing fixures.  Estimated Construction Cost:  $19,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 110 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0641­5  Painted gypsum board  Paint surfaces are marred and patched.  Deficiency category:  RR  Remedy  Repaint ~38,000 SF of interior walls throughout entire facility.  Estimated Construction Cost:  $172,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 111 of 228 

Architectural Inspection – Interior Finishes  0642 Floor Finishes – Carpet, tile, resilient flooring, etc.  The primary floor finish is carpet.  Some areas have 9x9 asbestos tile, ceramic tile, 12x12  vinyl composition tile or sheet vinyl.  The flooring is generally in poor condition throughout.  Remaining life expectancy:  less than 5 years 

Deficiency 

0642­1 Carpet  Carpet is stained and severly worn throughout the original building.  Carpet is stained in  the 1991 addition and seams are parting.  Asbestos tile may occur under the carpet.  Deficiency category:  RR  Remedy  Replace ~33,500 SF of carpet and associated base throughout school.  Estimated Construction Cost:  $282,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 112 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0642­2 12x12 vinyl tile  Gymnasium flooring is 12x12 tile.  It is cracked along a joint where a floor track was  removed.  Deficiency category:  RR  Remedy Option 1  Replace ~200 SF of cracked tile.  Estimated Construction Cost:  $1,500  Remedy Option 2  Replace ~5,400 SF tile flooring with poured urethane athletic flooring.  Estimated Construction Cost:  $114,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 113 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0642­3  Asbestos tile  Some 9x9 asbestos tile is still in place in the building.  Tile is cracked and damaged in  some locations.  Deficiency category:  H  Remedy  Remove ~9,700 SF of asbestos tile and replace with VCT.  Estimated Construction Cost:  $44,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 114 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0642­4 Sheet Vinyl  Sheet vinyl with integral cove base has failed at the juncture of wall and floor.  Flooring  is stained in areas.  Flooring has exceeded its useful life.  Deficiency category:  RR  Remedy Option 1  Replace ~2,250 SF of sheet vinyl with sheet vinyl.  Estimated Construction Cost:  $17,000  Remedy Option 2  Replace ~2,250 SF sheet vinyl with ceramic tile.  Estimated Construction Cost:  $48,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 115 of 228 

Architectural Inspection – Interior Finishes  0643 Ceiling Finishes – Painted GWB, ACT, acoustical panels, etc.  Ceilings of the original building consist of 12x12 acoustical tiles glued to furring strips,  painted gypsum board and 2x4 acoustical panels.  Ceilings of the 1991 addition are 2x4  acoustical panel ceilings.  Ceilings of the original building are in marginal condition.  Ceilings of the 1991 addition  are in good condition.  Remaining life expectancy:  Original building: less than 5 years.  1991 addition ceilings:  more than 10 years.

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 116 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0643­1 12x12 Acoustical tile  12x12 acoustical tile has been damaged by water from roof leaks or other water  penetration over the years.  Deficiency category:  RR  Remedy Option 1  Replace ~18,600 SF of damaged ceiling tiles and paint the ceiling  Estimated Construction Cost:  $57,000  Remedy Option 2  Replace ~18,600 SF of ceiling tiles.  Estimated Construction Cost:  $78,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 117 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0643­2  12x12 Acoustical tile at gym  12x12 acoustical tile has been damaged by gymnasium activities.  Deficiency category:  RR  Remedy Option 1  Repair and paint ~5,400 SF damaged ceiling tiles.  Estimated Construction Cost:  $16,000  Remedy Option 2  Replace ~5,400 SF damaged ceiling tiles.  Estimated Construction Cost:  $23,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 118 of 228 

Architectural Inspection – Interior Finishes  Deficiency 

0643­3  Water damaged 2’x4’ Acoustical panel  2x4 acoustical panel has been damaged by water from roof leaks or pipe leaks.  Deficiency category:  RR  Remedy  Repair the source of water leak and replace ~$13,624 SF of damaged ceiling panels.  Estimated Construction Cost:  $48,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 119 of 228 

Architectural Inspection – Interior Fixed Furnishings  0651 Specialties – Toilet partitions, bath accessories, marker boards, signage, etc.  Toilet compartments are either enameld steel or solid phenolic.  Thre are both enameled  steel marker boards and chalk boards.  Cork tack boards occur in each classroom.  Toilet compartments are in marginal condition.  Marker boards, tack boards and  chalkboards are in poor condition  Bath Accessories are in relatively good condition.  Signage is not uniform and does not conform to ADA.  Remaining life expectancy:  Toilet compartment 5­10 years.  Marker boards and tack  boards less than 5 years.  Bath Accessories 5­10 years. Signage less than 5 years.

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 120 of 228 

Architectural Inspection – Interior Fixed Furnishings  Deficiency 

0651­1  Toilet compartments  Enameled steel toilet compartments have exceeded their useful life are  Deficiency category:  RR  Remedy  Replace 22 enameled steel toilet compartments with stainless steel or phenolic toilet  compartments.  Estimated Construction Cost:  $49,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 121 of 228 

Architectural Inspection – Interior Fixed Furnishings  Deficiency 

0651­2  Marker boards  Marker boards are single sheet boards “piece­mealed” over existing chalk boards without  frame or even straight edges.  Deficiency category:  RR, F  Remedy  Replace 31 piece­mealed marker boards with framed and backed marker boards.  Estimated Construction Cost:  $39,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 122 of 228 

Architectural Inspection – Interior Fixed Furnishings  Deficiency 

0651­3  Chalk boards  Chalk boards were installed in the original project.  They have exceeded their useful life.  Deficiency category:  RR  Remedy  Replace 31 chalk boards with framed and backed marker boards.  Estimated Construction Cost:  $39,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 123 of 228 

Architectural Inspection – Interior Fixed Furnishings  Deficiency 

0651­4 Tack boards  Tack boards were installed in the original project.  They have exceeded their useful life.  Deficiency category:  RR  Remedy  Replace 31 tack boards with framed and backed tack boards.  Estimated Construction Cost:  $39,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 124 of 228 

Architectural Inspection – Interior Fixed Furnishings  0651­5 Toilet Accessories  Toilet accessories have been replaced over the years.  They appear to be in good  operational condition.  No deficiencies noted.

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 125 of 228 

Architectural Inspection – Interior Fixed Furnishings 

0651­6 Signage  Classroom signage, where provided, consists of 2”x 4” plastic signs with room numbers  and Braille.  The system is sporadic and difficult to identify due to size and placement.  A consistent and easily recognized signage system is not provided.  Deficiency category:  RR  Remedy  Provide 55 new signs for all rooms. .  Estimated Construction Cost:  $3,800

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 126 of 228 

Architectural Inspection – Interior Fixed Furnishings  0652 Casework/Millwork – Cabinets, countertops, cubbies, display cases, trim, etc.  Plastic laminte cabinets and countertops are installed through out the facility in both the  original building and the 1991 addition.  Original building cabinets are in poor condition.  1991 addition cabinets are in good  condition.  Remaining life expectancy:  Original building cabinets less than 5 years.  1991 addition  ,cabinets 5­1 0 years.

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 127 of 228 

Architectural Inspection – Interior Fixed Furnishings  Deficiency 

0652­1 Plastic laminate cabinets  Plastic laminate cabinets in the original building have exceeded their useful life.  Laminate faces have pulled off, doors are sagging, drawers bind.  Deficiency category:  RR  Remedy  Replace ~1,000 LF of base cabinets and 520 LF of wall cabinets in original building.  Estimated Construction Cost:  $460,000

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 128 of 228 

Architectural Inspection – Interior Fixed Furnishings  0654 Window Coverings – Drapes, blinds, black­out shades, etc.  A variety of blinds are used in the facility.  Louver blinds, rolling blinds and roman  blinds.  The louver blinds are in good condition.  Other blinds are beyond their useful life.  Remaining life expectancy:  louver blinds 5­ 10 years.  Other blinds less than 5 years

June 2005 

Auke Bay Elementary School Condition Survey Report 

Page 129 of 228 

Architectural Inspection – Interior Fixed Furnishings  Deficiency 

0654­1 Blinds  Blinds with the exception of the louver blinds are of various styles are damaged and have  exceeded their useful life.  Deficiency category:  RR  Remedy Option 1  Replace all blinds except louver blinds.  Quantity 15.  Estimated Construction Cost:  $27,000 

Remedy Option 2  Replace all blinds.  Quantity 26.  Estimated Construction Cost:  $47,000