SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION Página 1 de 7 Fecha de Impresión: 25/07/2015 7:20:38 OPERACIONES CON TORRES: 24/07/2015 06:00am AL 2...
4 downloads 0 Views 85KB Size
SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

Página 1 de 7 Fecha de Impresión: 25/07/2015 7:20:38

OPERACIONES CON TORRES: 24/07/2015 06:00am AL 25/07/2015 06:00am RIG: POZO:

SINOPEC 127 OSO-A025 ABANDONO OSOA-025

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) CIRCULANDO EN DIRECTA CON 3-1/2" TUBO DIFUSOR @ 8350 FT PARA HOMOGENIZAR DETALLE: COLUMNAS PREVIO SEGUNDO TAPON DE ABANDONO RIG: POZO:

CCDC-036 PAKA NORTE-A015 PKNA-015

EN COMPLETACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: CORRIENDO EQUIPOS B.E.S. C/TUBING D/3 1/2" TTGM-3 - 9.2 #/FT A 8613' RIG: POZO:

CCDC-052 AUCA-C162 EN COMPLETACION ACAC-162 MD (Pies): 11,276.7 TVD (Pies): 9,961.6 PROD.ESTIMADA: (BPPD) DETALLE: POZO CERRADO PARA TOMAR B'UP POR 32 HS RIG: POZO:

CCDC-068 AUCA-L138 EN COMPLETACION ACAL-138 MD (Pies): 10,492 TVD (Pies): 10,403.6 PROD.ESTIMADA: (BPPD) TEC. DE CIA DYGOIL SLICK LINE ARMA UNIDAD CON PULLING TOOL Y BAJA A RECUPERAR DETALLE: BOMBA JET 11K ALOJADA EN CAMISA DE CIRCULACION DE 3 1/2" UBICADA @ 9995'. OPERACION EN CURSO RIG: POZO:

CCDC-069 AUCA SUR-D023 ACSD-023

EN COMPLETACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) CÍA CASING TEAM BAJANDO BHA DE PRODUCCIÓN + EQUIPO BES, CON TUBING 3-1/2", EUE, 9.3 DETALLE: LB/FT, N-80-Q, R-2., CHINA A 7808 FT. RIG: POZO:

GEOPETSA-04 AUCA-M143 ACAM-143

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD)

EN COMPLETACION

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

Página 2 de 7 Fecha de Impresión: 25/07/2015 7:20:38

DETALLE:

SLB-WL DESARMANDO HERRAMIENTAS DE REGISTROS ELECTRICOS: USIT-CBL-VDL-GR-CCL.

RIG: POZO:

SAXON 47 SECOYA OESTE-A001 SCOA-001

EN COMPLETACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) BAJADO BHA DE LIMPIEZA TANDEM EN 3 1/2" DRILL PIPE SUBIENDO TUBO X TUBO, MIDIENDO, DETALLE: CALIBRANDO Y PROBANDO CIRCULACIÓN, 9000' DENTROL DEL POZO RIG: POZO:

CCDC-039 CUYABENO-H069 CYBH-069

EN MOVILIZACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: DESARMADO 100 %, MOVILIZADO 80 %, ARMADO 50 % RIG: POZO:

SINOPEC 119 CONONACO-F055 CNOF-055

EN MOVILIZACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) ESPERANDO LUZ DE DIA PARA CONTINUAR CON OPERACION DE DESARME, MOVILIZACION Y DETALLE: ARMADO DEL RIG 119 RIG: POZO:

SINOPEC 128 CHONTA ESTE-A004 CHEA-004

EN MOVILIZACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: ESPERANDO LUZ DEL DIA PARA CONTINUAR OPERACIONES DE TRASTEO RIG: POZO:

SINOPEC 168 EDEN YUTURI-J185 EDYJ-185

EN MOVILIZACION

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) ESPERANDO LUZ DEL DÍA PARA CONTINUAR ARMANDO EL TALADRO SINOPEC 168 EN EL PAD " J DETALLE: ". RIG: POZO:

CCDC-038 PARAHUACU NORTE-A001 PRNA-001 MD (Pies): 5,860 TVD (Pies): 5,858.8 PROD.ESTIMADA: (BPPD)

EN PERFORACION

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

DETALLE:

Página 3 de 7 Fecha de Impresión: 25/07/2015 7:20:38

PERFORANDO SECCION DE 12-1/4" MANTENIENDO VERTICALIDAD HASTA 5860'

RIG: POZO:

CCDC-066 AUCA-M144 EN PERFORACION ACAM-144 MD (Pies): 9,272 TVD (Pies): 8,414.1 PROD.ESTIMADA: (BPPD) DETALLE: BAJA CALIBRANDO HOYO DE 12-1/4" CON BHA # 03 DIRECCIONAL @ 8990'. RIG: POZO:

HILONG 17 PAYAMINO-G029 EN PERFORACION PYMG-029 MD (Pies): 3,387 TVD (Pies): 3,370.2 PROD.ESTIMADA: (BPPD) PERFORANDO SECCION DE 16" CON BHA #2 DIRECCIONAL BROCA PDC Y MOTOR DE FONDO @ DETALLE: 3387'. RIG: POZO:

NABORS 794 PALO AZUL-N050H EN PERFORACION PLAN-050HR1 MD (Pies): 11,375 TVD (Pies): 10,027.5 PROD.ESTIMADA: (BPPD) DETALLE: SACANDO BHA #9 CONVENCIONAL HASTA 500 FT. RIG: POZO:

PETREX 5824 NENKE-B003 EN PERFORACION NNKB-003 MD (Pies): 6,743 TVD (Pies): 6,391.8 PROD.ESTIMADA: (BPPD) DETALLE: PERFORANDO CON BHA DIRECCIONAL # 5 CON BROCA PDC DE 8.5" A 6743' RIG: POZO:

PTX 3 SHUSHUQUI-B025 EN PERFORACION SHHB-025 MD (Pies): 290 TVD (Pies): 290 PROD.ESTIMADA: (BPPD) DETALLE: MUELEN EQUIPO DE FLOTACION CON BHA DIRECCIONAL # 02 A 288' RIG: POZO:

SINOPEC 156 CONONACO-C058 EN PERFORACION CNOC-058 MD (Pies): 8,576 TVD (Pies): 8,363 PROD.ESTIMADA: (BPPD) DETALLE: CORTNADO CABLE DE PERFORACION

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

Página 4 de 7 Fecha de Impresión: 25/07/2015 7:20:38

RIG: POZO:

SINOPEC 191 OSO-I145 EN PERFORACION OSOI-145 MD (Pies): 5,274 TVD (Pies): 5,236.8 PROD.ESTIMADA: (BPPD) DETALLE: REALIZANDO CEMENTACION DEL REVESTIDOR DE 13 3/8". RIG: POZO:

SINOPEC 220 OSO-G104 EN PERFORACION OSOG-104 MD (Pies): 9,549 TVD (Pies): 8,796.5 PROD.ESTIMADA: (BPPD) DETALLE: RETIRANDO FUENTES RADIOACTIVAS @ 180' RIG: POZO:

HILONG 18 APAIKA-A013 APKA-013

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) BAJANDO BHA DE PESCA CON OVERSHOT DE 5-3/4" EN 3-1/2" D.P A LAS 06:HRS 6000 FT DETALLE: DENTRO DEL POZO RIG: POZO:

DYGOIL-30 SHUSHUFINDI-L225 SHSL-225

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) SACANDO Y QUEBRANDO 5 1/2" TUBERIA BTC. FUERA DEL POZO 3600 FT. TUBERIA SALE CON DETALLE: ARRASTRE. RIG: POZO:

GEOPETSA-05 LAGO AGRIO-041 EN WORKOVER LGA-041 MD (Pies): 3,000 TVD (Pies): 3,000 PROD.ESTIMADA: (BPPD) BAJANDO BHA # 2 DE LIMPIEZA CON 6 1/8" BROCA TRIC. EN 2 7/8" IF DP. A LAS 06H00 DENTRO DETALLE: DEL POZO 3000' RIG: POZO:

GEOPETSA-06 PALO AZUL-D019 PLAD-019

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: ARMANDO SUBESTRUCTURA DEL EQUIPO. RIG: POZO:

HILONG 28 PAKA SUR-C018 PKSC-018

EN WORKOVER

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

Página 5 de 7 Fecha de Impresión: 25/07/2015 7:20:38

MD (Pies): 0 TVD (Pies): 0 PROD.ESTIMADA: (BPPD) REALIZANDO PRUEBA DE PRODUCCIÓN EN ARENA "T sup." A LA ESTACIÓN CON EQUIPO BES SLB DETALLE: D800N 2 BOMBAS (134+ 168) 302 STG, 150 HP, OPERACION SIN TERMINAR. RIG: POZO:

NABORS 813 AUCA-B016 ACAB-016

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) BAJANDO BHA DE PESCA # 3 CON 6 1/8" ZAPATA Y SKIRTED MILL DE 4 7/8" EN 3 1/2" IF DP A DETALLE: 200' RIG: POZO:

NABORS 814 OSO-A073 EN WORKOVER OSOA-073 MD (Pies): 5,295 TVD (Pies): 4,686 PROD.ESTIMADA: (BPPD) SACANDO BHA DE CEMENTACIÓN CON STINGER 7" EN 3-1/2" DRILL PIPE QUEBRANDO A LOS DETALLE: CABALLETES. A LAS 06:00 HRS 5043' FUERA DEL POZO (160 JUNTAS EN LOS CABALLETES). RIG: POZO:

NABORS 815 GACELA-F009 GCLF-009

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: TÉCNICO CIA. BAKER ATLAS, ARMANDO CAÑONES 4-1/2" DE 5 DPP, CARGAS EXTRA-DP. RIG: POZO:

NABORS 819 YANAQUINCHA OESTE-B016 YNOB-016

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: INSTALA + NIVELA SUB ESTRUCTURA DEL RIG. RIG: POZO:

PETROTECH 04 AUCA SUR-C010 ACSC-010

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DESPLAZANDO FLUIDO DEL POZO 188BLS PROGRAMADO. A LAS 06:HRS 34 BLS DESPLAZADOS, DETALLE: PI= 4271 PSI RIG: POZO:

SAXON 32 SHUSHUFINDI-N125

EN WORKOVER

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

Página 6 de 7 Fecha de Impresión: 25/07/2015 7:20:38

SHSN-125 MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: RETIRANDO HERRAMIENTAS, PLANCHADA. RAMPA Y SUBESTRUCTURA RIG: POZO:

SAXON 34 EDEN YUTURI-G036 EN WORKOVER EDYG-036 MD (Pies): 9,254.1 TVD (Pies): 7,043.6 PROD.ESTIMADA: (BPPD) DETALLE: DESPLANDO A SUPERFICIE LA PÍLDORA VISCOSA. RIG: POZO:

SAXON 53 SHUSHUFINDI-C250 EN WORKOVER SHSC-250 MD (Pies): 9,305 TVD (Pies): 9,091.3 PROD.ESTIMADA: (BPPD) A LAS 06:00 HRS RIH EQ BES D460N EN 3-1/2" TSH 9.2 LPP L80 CLASE "B" (MISMA QUE SALIO DETALLE: DEL POZO) EN PARADAS. DENTRO DEL POZO 8500' (135 PARADAS). RIG: POZO:

SAXON 55 SHUARA-009 SHA-009

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA:350 (BPPD) DETALLE: PROBANDO FUNCIONAMIENTO DE BOP DE 11" X 5000 PSI RIG: POZO:

SAXON 56 SHUSHUFINDI-I134 SHSI-134

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: BAJANDO TUBERIA TSH-BLUE PROBANDO CON 3000 PSI. DENTRO DEL POZO 2800 ft. RIG: POZO:

SINOPEC-905 EDEN YUTURI-D085 EN WORKOVER EDYD-085 MD (Pies): 7,015 TVD (Pies): 6,796.2 PROD.ESTIMADA: (BPPD) REALIZANDO REUNION DE SEGURIDAD CON TODO EL PERSONAL INVOLUCRADO PARA DAR DETALLE: INICIO AL EVENTO DE MOVILIZACION DEL RIG SINOPEC 905 DESDE EL PAD "D" HASTA EL PAD "T". RIG: POZO:

TRIBOILGAS-006 FRONTERA-002

EN WORKOVER

SUMARIO DE OPERACIONES PRODUCCION Y PERFORACION

Página 7 de 7 Fecha de Impresión: 25/07/2015 7:20:38

FRN-002 MD (Pies): 20 TVD (Pies): 20 PROD.ESTIMADA:250 (BPPD) BAJAN EQUIPO BES GE TD 1000 EN 3-1/2" EUE TUBERIA CLASE "A" MIDIENDO, CALIBRANDO Y DETALLE: PROBANDO CON 3000 PSI CADA 22 PARADAS A LAS 06H00 DENTRO DEL POZO 1800' RIG: POZO:

TRIBOILGAS-008 DRAGO NORTE-C036 EN WORKOVER DRRC-036 MD (Pies): 10,404 TVD (Pies): 10,083.9 PROD.ESTIMADA: (BPPD) BAJAN BHA MOLEDOR CON 6 1/8" JUNK MILL (HERRAMIENTA SIN CARACTERISTICAS PARA DETALLE: PERFORAR DENTRO DE UN POZO DIRECCIONAL, CENTRALIZADOR MUY CORTO)EN 3 1/2" TUBERÍA D. P. DENTRO DEL POZO: 5200' RIG: POZO:

TRIBOILGAS-102 GUANTA-C013 GNTC-013

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) DETALLE: FORZAR CEMENTO A U SUPRIOR Y DAÑO DE CASING DE 9385 FT A 9549 FT RIG: POZO:

TRIBOILGAS-104 LAGO AGRIO-B009B EN WORKOVER LGAB-009B MD (Pies): 10,098 TVD (Pies): 10,098 PROD.ESTIMADA: (BPPD) DETALLE: DESARMANDO Y RETIRANDO 11" x 5M PSI B.O.P RIG: POZO:

TRIBOILGAS-107 SANSAHUARI-A014 SNSA-014

EN WORKOVER

MD (Pies): TVD (Pies): PROD.ESTIMADA: (BPPD) Por seguridad esperando luz del día para movilizar Rig. TBG 107 desde el pozo SNS014 hacia el DETALLE: pozo CYB-050. DESCRIPCION DE UNIDADES: BPPD: Barriles de Petróleo por día