Development and Commercialization Status of HTS Cable System in Korea LS Cable & System Superconducting Cable Business Task Force Team Jin Bae Na, Ph.D. Oct. 30, 2013
Development of HTS Cable in Korea ► R/D program in Korea ► Overview of LS CNS Status
Demonstration of 22.9kV/50MVA HTS Cable System Demonstration of 22.9kV/150MVA HTS Cable System
Development of 80kV/500MW HTS Cable System Future Plan
’01
MEST1)
’02
’03
’04
’05
Developing
Developing
22.9kV /50MVA 30m (1-Φ)
22.9kV /50MVA 30m (3-Φ)
’06
’07
Carrying out Int’l Certification & Long-term Test
22.9kV/50MVA 100m
DAPAS3) Program
Demonstration in Actual Grid MKE2)
’08
’09
’10
’11
Progressed
’12
’13
’14
’15
’16
Demonstration in Actual Grid
154kV/1GVA 100m
Actual Grid (ICHEON S/S)
Actual Grid (ICHEON S/S)
22.9kV/50MVA 500m
22.9kV/150MVA 100m
Pilot Project
Basic R/D for
DC 200kV
Actual Grid (JEJU Island)
DC 80kV/500MW 500m Actual Grid (JEJU Island)
154kV/500MVA 1km Commercial Target
1)MEST:
Developing
Ministry of Education, Science & Technology DC 2)MKE: Ministry of Knowledge & Economy 3)DAPAS: Development of Advanced Power System by Applied Superconductivity Technologies
200kV/5GW 3/Page
via National and In-house Projects
22.9kV
AC
▪ 50MVA Completing Commissioning & Demonstration in 2011 ▪ 150MVA Ongoing Development & Demonstration till 2013
154kV ▪ 1GVA Completing Development & Long term Test in 2011 ▪ 600MVA Ongoing Development & Demonstration till 2016
80kV
DC
▪ 500MW 200kV ▪ 5GW
Completing Development in 2013
Completing Basic R/D in 2011 Planning Development and PQ test till 2016 4/Page
Contents Development of HTS Cable in Korea
Demonstration of 22.9kV/50MVA HTS Cable System ► Components ► Installation ► Operation
Demonstration of 22.9kV/150MVA HTS Cable System Development of 80kV/500MW HTS Cable System
Future Plan
Air view of HTS Cable System in Icheon S/S Bending point: total 9 with 90° bending angle
4
2
5
3
1 1 2 3 4 5
22.9kV/50MVA HTS Cable Termination Joint Bay Cooling System Offset System 6/Page
Overview of HTS Cable System in Icheon S/S KEPCO Icheon Substation Electrical Characteristics - Nominal Voltage: 22.9kV - Rated Current: 1.25kA Physical Characteristics - Cable Length: ~ 500m - Cold Dielectric Design - 3 phases in One Cryostat - HTS wire: YBCO Coated Conductor Hardware
- 300m and 200m HTS Cable - Outdoor Termination (3-Φ in 1 Cryostat) - Joint bay (3-Φ in 1 Cryostat) Installation/Commissioning: July 2011
Grid Application: Aug. 19, 2011 7/Page
HTS Cable Specification Characteristics - 22.9kV (Nominal), 13.2kV (Phase) - 1,260A (50MVA) - Short Circuit Rating: 25kA/30cycle (Cu Stabilizer) - Application of Cryogenic System (Open-loop type) Design - Cold Dielectric - Outer Diameter: 151mm
- Seamless Al Cryostat - PVC Sheath - Insulation Level up to 35kV Grade Coverable range: 13.2kV ~ 35kV - 3-core type Seamless Al Cryostat - Fault Current By-pass with Stabilizer 8/Page
Termination & Joint
Termination
Pre-fabricated
Compact Design 3-Φ in one cryostat (22.9kV) Maximum Operating Pressure : 15bar
•Jointing at site
Pre-fabricated components Polymer composite Bushing
Joint Bay Compact Design (500mm Ø, 3.5m L)
Insulation Level up to 35kV Grade Coverable range: 13.2kV ~ 35kV Pre-fabricated components Maximum Operating Pressure: 15bar Pre-fabricated
9/Page
Cooling system Overview Open-loop type using Decompression unit Capacity: 6.5kW @ 69K
Buffer for balancing System pressure and fault current 10/Page
Cooling system Specification Item
Operating Condition
Specification
Inlet Temp. of Cable
69K
Inlet Temp. of Cable
73K
Circulation Flow rate of LN2
0.5kg/s
Pressure
3barG ~ 7.5barG
Fault Current
25kA, 30cycles
Cable & Termination
4,100W
Cooling System
800W
Cable & Termination
1.4bar
Cooling System
1.1bar
Heat Load
Difference of Pressure
11/Page
Cooling system Photos of 22.9kV/50MVA Cooling System Open-loop type - Decompression Unit Heat exchanger in decompression cryostat Vaporizer and decompression pump
12/Page
HTS Cable Manufacturing Stranding of Former
Wrapping & Cushion Layer
Stranding of HTS & Conductor Screen
Electric Insulation & Insulation Screen
Former is wound up using stranding machine. The diameter and the surface of former should be controlled precisely to make even and uniform shape of HTS wires
Stainless steel and carbon paper tapes shall be wound to bind the former according to the designed diameter
HTS wires and LPP papers shall be wound over the cushion layer, which will be controlled together using stranding machine modified for HTS cable
During the lapping of LPP papers, tension shall be carefully controlled for insulation quality and bending characteristic
MLI Taping
Outer Cryostat
Outer Jacket
After cleaning the surface of inner cryostat, MLI is wrapped and 4 Teflon spacers shall be stranded on the surface of MLI
The height and pitch of corrugated Al cryostat is critical to bending characteristic
During the extrusion, cable diameter is measured by X-ray scan
Inner Cryostat The height and pitch of corrugated Al cryostat is critical to bending characteristic
Vacuum Conditioning The vacuum region between inner and outer cryostat of the cable shall be subjected to vacuum pumping for at least 30 days at a temperature of 30℃
13/Page
HTS Cable Type Test on previous proto-type of 22.9kV/50MVA Test
Details - Long term test (load cycle test)
22.9kV 50MAVA HTS Cable 30m Proto type test (2005)
Result Pass
- DC critical current
Pass
- Withstand voltage test
Pass
- AC loss measurement
Pass
- Long term test (cool down test)
Pass
- Summary of the test results
22.9kV 50MVA HTS Cable 100m type test (2007)
- Cable bending test
Pass
- Load cycle (cooling circuit and Cryostat pressure check)
Pass
- Thermal cycle (shrinkage of cable)
Pass
- Dielectric loss factor (Tan δ)
Pass
- Dielectric security
Pass
- Partial discharge
Pass
- DC critical current
Pass
- Visual inspection of HTS cable sample
Pass 14/Page
Control system Evaluating Unmanned Operation System for Cooling System MS
HMI (Server PC)
Local Network
Input Control Value
HMI (Client PC)
User
Date Acquisition Ethernet Control Net
ProfiBus
PLC duplex configuration (watchdog, quick change when Failed)
LTS No.
JTS
REM PLC
STS Item
DUM PLC
Specification
1
MS(Master Station)
• Notifying Alarm and trip to the SCADA and User by E-mail and SMS.
2
CS(Control System)
• Communicating with REM, DUM and Cryogenic Refrigerant by profibus
3
REM(Reservoir Module)
4
DUM(Decompression Unit Module)
5
Cryogenic Refrigerant
6
LTS(Load Termination System)
7
JBS(Joint Bay System)
8
STS(Source Termination System)
• Controlling Reservoir Module Independently by PLC. • controlled by CS and Communicating with CS. • DUM and Cryogenic Refrigerant: Operated by the Temp. of the HTS Cable.
• Explosion-proof type(IP 55) • Controlled by CS and Communication with CS. 15/Page
Control system Action Plan According to Fault Level Level 3 2 1
Action Engineers standby within 24hrs Alarming for observation to decide cutting power or not Engineers standby within 5hrs & Clearing alarms after measures Stopping the operation: Cutting power
countermeasure Sending SMS to people in charge Informing to 2nd line of SCADA Sending SMS to people in charge Informing to 1st line of SCADA Sending SMS to people in charge
Condition for Deciding Faults Step
Level
1
Deciding Faults
Breakdown Fulfilling conditions: Inner pressure of Reservoir & Load-side termination
2
Fire 1
Setup
Maintaining Time
Under 2barG
10sec.
Installing the fire alarm in Cooling room and Joint room Over 75K
10sec.
4
Explosion & Fulfilling conditions: Inlet temp. of cable (2 points), Joint (2 points) Damage of HTS wire Fulfilling conditions: Pressure of outlet of circulation pump & source-side termination
Over 6.5bar G
0.5sec.
5
Breakdown Fulfilling conditions: Inner pressure of Reservoir & Load-side termination
Under 2.5barG
10sec.
6
Explosion & Fulfilling conditions: Inlet & Outlet temp. of cable (4 points), Joint (2 points) Damage of HTS wire Fulfilling conditions: Pressure of outlet of circulation pump & Source-side termination Flow rates of LN2 Maintaining Fulfilling conditions: Vacuum condition of cable, joint & termination Cooling Fulfilling conditions: Inner pressure of pneumatic tank system Fulfilling conditions: Level of LN2 tank Whole Informing people in charge after checking malfunction or abnormality of all sensors system
Over 73K
20sec.
Over 6bar G
5sec.
Under 0.2kg/s
10sec.
Over 0.1torr
10sec.
Under 4.2bar
10sec.
Under 15%
10sec.
3
7 8
2
9 10 11
12
3
16/Page
Test Specifications and Results Item
Standard
Spec.
Result
1
DC Voltage Test (Jacket)
IEC 60840
10kV for 1min.
Pass
2
Heat Loss Measurement
LS Standard
3.5W/m
Pass
3
DC IC Measurement
KS C 6111-6
3.27kA@70K
Pass
4
AC loss Measurement
LS Standard
1.25W/m/Phase
Pass
5
DC Voltage Test
KEPCO Standard
46kV for 10min.
Pass
6
Visual Inspection
LS Standard
Drawing
Pass
the world’s first experience to measure AC loss at rated current (1,250A) in actual power grid
17/Page
Trend of Load Current vs. Quantity of Heat Capacity Starting Demonstration: Aug. 19, 2011 - Load current: 300A (connected to 2 D/L) Increasing Load Current: Oct. 6, 2011 - Present load current: 600A ~700A (connected to 5 D/L for full load) At peak time (winter), load current was around 900A.
Momentary build-up due to loop current at connecting 5 D/L
Oct. 6
Oct. 7
1-day trend during Increasing Load Current to 600A
Aug. 19
Mar .31
20 months trend from starting demonstration
18/Page
Trend of vacuum HTS cable length of 22.9kV/50MVA - 500m (Two span : Connection with joint bay) Operation period - Total 20 months - Unmanned operation during18 months 1 Cable span 200m Cable span 300m
0.1
Vacuum [torr]
0.01 1E-3
20 months trend from starting demonstration - Very stable the degree of vacuum - Under 6.0E-6 torr
1E-4 1E-5 1E-6 1E-7 1E-8 8-1-2011
12-1-2011
4-1-2012
8-1-2012
12-1-2012
4-1-2013
Date 19/Page
Development of HTS Cable in Korea Demonstration of 22.9kV/50MVA HTS Cable System Demonstration of 22.9kV/150MVA HTS Cable System ► Component ► Installation
Demonstration of 80kV/500MW HTS Cable System Future Plan
Air view of HTS Cable System in Icheon S/S
4
1
2
3
1 2 3 4
22.9kV/150MVA HTS Cable Termination Cooling System in Container U-bending area 21/Page
Overview of HTS Cable System in Icheon S/S KEPCO Icheon Substation Electrical Characteristics - Nominal Voltage: 22.9kV - Rated Current: 3.75kA Physical Characteristics - Cable Length: ~ 100m - Cold Dielectric Design - 3 phases in One Cryostat - HTS wire: YBCO Coated Conductor Hardware
- Compact cooling system in 40ft container house - Outdoor Termination (3-Φ in 1 Cryostat) Installation/Commissioning: October 2013 Grid Application: Nov. 01, 2013
22/Page
HTS Cable Specification Characteristics - 22.9kV (Nominal), 13.2kV (Phase) - 3,750A (150MVA) - Short Circuit Rating: 25kA/30cycle (Cu Stabilizer) - Application of Cryogenic System (Hybrid type) Design - Cold Dielectric - Outer Diameter: 159mm
- Seamless Al Cryostat - PVC Sheath - Insulation Level up to 35kV Grade Coverable range: 13.2kV ~ 35kV - 3-core type Seamless Al Cryostat - Fault Current By-pass with Stabilizer 23/Page
Cooling system Overview Hybrid type : Close loop + Open loop - Using 4kW Stirling refrigerator - Using decompression unit Capacity: 10kW @ 69K PCS (Pressure Control System) Seperator
Filter Unit CP (Circulation Pump) Unit
DC (Decompression) Unit
24/Page
Development of HTS Cable in Korea Demonstration of 22.9kV/50MVA HTS Cable System Demonstration of 22.9kV/150MVA HTS Cable System
Development of 80kV/500MW HTS Cable System ► Component ► Installation ► Operation
Future Plan 25/Page
Photo of KEPCO power testing site in Gochang
2
E 1
3 E 1 2 3
80kV/500MW HTS Cable Outdoor Terminations Joint Bay Offset System
26/Page
HTS Cable Specification Characteristics - 80kV (Nominal) - 3,125A (500MVA) - Short Circuit Rating: 6.25kA/30cycle (Cu Stabilizer) - Application of Cryogenic System (Close-loop type) Design - Cold Dielectric - Outer Diameter: 149mm
- Seamless Al Cryostat - PVC Sheath - Insulation Level up to DC 200kV : Coverable Range : DC 80 ~ 200kV - Fault Current By-pass with Stabilizer
27/Page
HTS Cable Type test process of 80kV/500MW According to Electra TB-538, Electra 219 and Electra 189 Jointing & Assembling Cryostat
Leak test
Vacuum exhausting & Assembling Bushing
- 1x10-8 mbar•ℓ/sec
Cool - down - According to company regulation
24hr Polarity reversal test - Recommendation : Electra 219 - Test voltage : ± 1.45Uo, 8cycles
Thermal contraction
measurement - Movement by traction force
48hr Positive Load cycle test - Recommendation : Electra 219 - Test voltage : 1.85Uo, 3cycles Warm-up
Pressure test - According to Cigre W/G B1-31
24hr Negative Load cycle test - Recommendation : Electra 219 - Test voltage : - 1.85Uo, 8cycles
S/I Switching Imp. test - Recommendation : Electra 219/189 - Test voltage : Uo ± 144kV Long term reliability test
24hr Positive Load cycle test - Recommendation : Electra 219 - Test voltage : + 1.85Uo, 8cycles
S/I Lightning Imp. test - Recommendation : Electra 219/189 - Test voltage : Uo ± 285kV
Special test Subsequent DC test - Recommendation : Electra 219 - Test voltage : 1.85Uo / 2hr
28/Page
Load cycle test of DC 80 kV/500MW Starting Operation: Dec. 20, 2012 - No quench / No breakdown
24 hr load cycle test of polarity reversal
48 hr load cycle test of positive pole 29/Page
Long term test Experienced 4th cool-down process - No quench / No breakdown
Additional test Voltage Test of DC 200kV class - No quench / No breakdown
24 hr load cycle test of positive
24 hr load cycle test of polarity reversal 30/Page
Development of HTS Cable in Korea
Demonstration of 22.9kV/50MVA HTS Cable System Demonstration of 22.9kV/150MVA HTS Cable System Development of 80kV/500MW HTS Cable System Future Plan ► Development & Demonstration of Transmission Level HTS Cable System
Summary
Title: Development & Demonstration of Transmission level HTS Cable System Period: July, 2011 ~ June, 2016 (60months) Supervision: KEPCO Participant: LS CNS, KERI & Several Universities Research Funds: USD70M (Government: USD22M , KEPCO: USD18M, LS CNS: USD30M)
Composition & Aim of Project Supervision (KEPCO] ○ Finding the way of institutional support for commercialization ○ Selecting the site for demonstration ○ Review of Standard for product & test Participant 1 (KEPRI) ○ Grid Analysis & Relevant effect ○ Grid Operation System ○ Verification of HTS Cable
Participant 2 (LS CNS) ○ Development of HTS Cable ○ Installation & Operation in Grid ○ Localization of HTS Cable & Cryogenic System
Participant (KEPRI) ○ Development of SFCL ○ Performance Evaluation & Installation in Grid ○ Development of the Method for O&M 32/Page
Overview of Pilot Application
33/Page
E-mail :
[email protected]