Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

FIRST LINK Let's keep progressing, we are the First

First Link for Communication 

First link for communication is an affiliate of Al-Wafi group (Amman-Jordan), the company established in 2007.



First Link Is a Telecom Service Providing Company Formed by a Team of Dedicated Professionals, with Experience in Wide Range of Telecom Projects.



First Link has become main contractor for MTN Sudan Company, main contractor for JET.NET For Networking and newly for ZAIN Sudan.

Our Vision Best Service for latest technology and highest standard for Telecommunication services.

Our Target 

To Create a Self-Learning Sustainable & Progressive Business Environment.



To establish a reputation in the service sector for Dependability Response to Changes Providing Value Addition Delivering High Quality Service

Quality & safety 

First Link is strongly committed to guarantee both quality & application of safety standards.



We are committed to integer Q&S objectives into our management at all levels. This is critical to our business success because it reduces risk & adds value to our services

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Our Business        

Turnkey Construction Projects (Civil Work, Power, Finishing … etc) Telecom Services Power Services Consultancy and supervision Maintenance (Building and GSM Sites) Logistic Services Acquisition Services Product Development

We undertake    

GSM CDMA Wi-MAX Services (Civil / Power).

EQUIPMENT KNOWLEDGE     

ERICSSON NOKIA SIEMENS MOTOROLA ALCATEL LUCENT HUAWEI

FIRST LINK Scope of Work: The First Link for communication interacts in several fields such as:               

Site Survey. Site Acquisition, Contracts & Administrative Procedures. Site Engineering, Survey & Design. Geotechnical Soil Survey. Site Construction / Civil & Electrical. Switch Construction / Civil & Electrical. Switch preparation (Raised floor, False Ceiling,…). Sales Point Construction. Radio Equipment Installation. BTS testing & commissioning. LOS Survey. MW Equipment Installation. MW Alignment, Testing & Commissioning. V-SAT Installation. Consultancy (Civil, Telecom and Power).

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

First Link Team First Link has about 50 permanent employees working in following departments:

-

4 4 3 4 3 6 6

-

8 Working chiefs and team leaders with 3 to 10 years of experience form global companies (France telecom, Ericsson, Motorola, Orascom, etc) in the telecommunication field. 14 technicians, electricians, installers, with experience from 3 to 7 years. 18 employees for civil works. 12 technicians for shelter and tower installation. 8 employees are working at offices, planning, studies, calculation, etc...

-

Civil Work Teams. Telecom Installation Teams. Tower Installation team. Power Teams. Commissioning Teams. Quality Team. Office Work Engineers.

Working Equipment -

All required tools for installation and commissioning. Computers. Fully equipped working team trucks and workshops. Cars, light utility vehicles. Pickup trucks.

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Working Tools and Measuring Equipment -

-

Equipment and tools for all stages: implementation, GPS, Digital Cameras, Electronic equipments including all radio measuring devices and all necessary equipments in each different phase. Two Site Master (for bands 10 MHz to 3 GHz, band 900 MHz, band 1800MHz. BER tester for MW Link Stability. Fixed and portable computers. GSM portable phones. Required materials and tools for our activities. Drills. Electric screwdriver. Personal safety equipment. Measuring materials. Specific materials according to the equipment and the types of work.

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

First Link Departments: CIVIL Department -

Building Construction (Design, Drawings and Construction) GSM Site Construction (Design, Drawings and Construction) Tower design and tower checking Operation and maintenance

Transmission implementation Department -

LOS Check Link Budgeting Site Survey Installation, Integration and Commissioning microwave links Integration of node switches Fiber Optics installation and routing

TELECOM Department -

BTS installation, integration and commissioning. Power Installation (PDB, ATS, Rectifier,…). Cell Enhancers. Repeaters. Cell Boosters. Benchmarking. Drive test. Operation and maintenance. Indoor coverage survey. Indoor design.

Design Department -

Design building and sites using design software (Auto-Cad). Structural Calculation for building design. Tower design and load calculation.

Logistic Department -

Warehousing materials. Transportation. Supply materials.

Consultancy DEPARTMENT -

Consulting on GSM site construction (civil, power and telecom). Consulting on building construction.

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Our main Costumers -

Mtn Sudan Zain Sudan Jet Net (wi-max operator) Ericsson Huawei ZTE

Project list Mtn Sudan (GSM operator) 2007 Construction: -

Constructing about 46 sites with different categories (Civil, Tower, shelter, Power, and Telecom). Constructing and installing 5 BSC’s. Civil Constructing for MSC in Portsudan. Constructing 2 V-sat with different diameters.

Telecom: -

Installation, testing, commissioning and alignment for more than 150 Ericsson MW links. Installation, testing and commissioning for more than 50 Ericsson RBS’s and Alcatel BTS’s (Macro and Micro).

Logistic: -

Supply, install, and operate 4 mobile cars.

Power: -

Installation of Backup Battery system for road sites.

2008 Construction: -

Constructing about 39 sites with different categories (Civil, Tower, shelter, Power, and Telecom). Constructing and installing 2 BSC’s. Preparation for 2 MSCs in Omdurman and Manchya.

Sudan- Khartoum

-

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Civil construction for MSC in Juba (Juba-Hajar). Constructing 4 V-sat with different diameters.

Telecom: -

Installation, testing, commissioning and alignment for more than 120 Ericsson MW links. Installation, testing and commissioning for more than 50 Ericsson RBS’s and Alcatel BTS’s (Macro and Micro).

Site Repair: -

Repairing 400 GSM sites (repairing shelters, tower, earth, corrosion, ….etc).

Consultancy: -

Make full supervision on civil work for MTN new GSM sites in southern Sudan. - Site Handover, soil test, excavation, concrete work, tower and shelter erection. Make full supervision on power and telecom work for MTN new sites.

2009 Construction: -

Constructing about 23 sites with different categories (Civil, Tower, shelter, Power, and Telecom). Civil construction for CSP in Aljenina. Civil construction for Service Center in Juba. Construction of 4 Sales Point in Khartoum (Kiosk). Constructing 4 V-sat with different diameters.

Telecom: -

Installation, testing, commissioning and alignment for more than 100 Ericsson MW links. Installation, testing and commissioning for more than 30 Ericsson RBS’s and Alcatel BTS’s (Macro and Micro).

Site Repair: -

Repairing 350 GSM sites (repairing shelters, tower, earth, corrosion, ….etc).

2010 Construction: -

Constructing new MSC in Wad Madany. Preparing Conference room in Manchya. Preparing two CSPs in Khartoum and Shandi.

Telecom: -

Telecom and power works (BTSs, Microwave links, Rectifiers…). Site Modification project.

Quality assurance: -

Auditing on new site construction. Making SOA, PAC and FAC acceptance on all new sites for 2010, 2011 and 2012.

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

2011 Telecom: -

Telecom and power works (BTSs, Microwave links, Rectifiers…). Site Modification project.

Quality assurance: -

Auditing on new site construction. Making SOA, PAC and FAC acceptance on all new sites for 2011 and 2012.

Jet.net for networking 2009 -

Acquisition for 50 sites. Survey, Design and Structural Study for 25 RT sites. LOS Check for more than 40 Links. Constructing of 25 RT sites. Constructing of Data Center with all accessories (Design, Power, Air Conditions, …)

zain 2008 Construction - Constructing of 5GF sites in Kurdofan area. Site Repair: - Repairing 30 GSM sites (repairing shelters, tower, earth, corrosion, .etc).

2009 Site Repair: - Repairing 20 GSM sites (repairing shelters, tower, earth, corrosion, .etc).

Ericsson 2010 -

Acquisition for 36 sites. Survey, Design and Structural Study for 32 GF sites. LOS Check for more than 36 Links. Constructing of 25 GF sites. Supply of metal parts for GSM sites.

2011 -

Constructing of 16 GF sites. Supply of metal parts for GSM sites. Telecom Installation and commissioning.

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

HUAWEI 2011 -

Zain Swap Project (swap more than 18 sites in Darfour and Kurdofan zones) Radio and Transmission survey for more than 40 sites in Darfour and Kudofan zones. Constructing of 36 GF sites. Supply of metal parts for GSM sites. Telecom Installation and commissioning. Quality assurance and supervision on Sudani-phase H project. Quality assurance and supervision on MTN TK project. MTN 3G project-30 sites

ZTE 2011 -

Constructing of 2 GF sites. Telecom installation and commissioning. MTN 3G project-20 sites. Supply of metal parts for GSM sites.

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Address Company name:First Link for Communication

Location:Sudan - Khartoum – Al-Taif

Telephone:00249183258150

Fax:002491505164379

E-mail:[email protected]

Sudan- Khartoum

Mobile: 00249922211184 Tel: 00249183258150 Fax: 002491505164379 Web site: firstlink-sd.com

Personal contact:1- General Manager Eng: Mahmoud Allauzi International phone number: 00962795356588 E-mail: [email protected]

2- Executive Manager Eng: Bashar Alzoubi Local phone number: 00249922211184 International phone number: 0096279595831 E-mail: [email protected]