Essent Biomass Conference 2009 Day 2
Mastering Biomass November 5 2009
Welcome from the Chairman
Pier Nabuurs Chairman of the Executive Board KEMA
Opening Address
Huib Morelisse Chief Technology Officer Essent
Welcome to Day 2 of the Essent Biomass Conference 2009
4
Essent Conference 20092009 EssentBiomass Biomass Conference
Day 1: Key emerging themes
o Cooperation: Politicians/Companies
o Stability: Support mechanisms/Criteria
o Sustainability: Long term well balanced solutions
o Transparancy: Facts vs Fiction and Rational vs Emotional
5
Essent Conference 20092009 EssentBiomass Biomass Conference
Day 2: “Deep dive” into technologies o The “making of” the wood gasifier
“goudvergasser houtvergasser” (gold gasifier wood gasifier)
o New promising technologies o
Torrefaction
o
Pyrolysis
o Zero emission power plant
concepts 6
Essent Conference 20092009 EssentBiomass Biomass Conference
Looking forward: Right time for joint action? o
No doubt that large scale sustainable use of biomass is needed to meet targets….
o
No single party can achieve this alone…
o
Lets explore ways how to cooperate!
7
Essent Conference 20092009 EssentBiomass Biomass Conference
Essent‘s wood gasifier project and process re-design
Wim Willeboer Manager Process Technology
Amer 9 with Wood Gasifier
9
Essent Biomass Conference 2009
Demolition wood
10
(before shreddering)
Essent Biomass Conference 2009
Wood gasifier: Starting points • Demolition wood: qualities A and B • Wood consumption: 150.000 t/a, - replacing 80.000 t/a coal - avoiding 190.000 t/a CO2
• Gas burnt in Amer 9 boiler • No negative effects on Amer 9: - availability - fly ash quality (certified)
• Low emissions • No waste water
11
Essent Biomass Conference 2009
Energy balance Amer 9 with gasifier coal: 1380 MWch ∆ coal: -80 MWch •
Amer 9
•600 MWe (∆ = 0) •350 MWth (∆ = 0)
•project
•Demolition wood •84 MWch
•Gasifier
•Own consumption •0.75 MWe
•Woodgas •63 MWch •steam •15 MWth
∆ Ε -0.25 MWe (coal mills)
Equivalent E-production on demolition wood: 33 MWe
12
Essent Biomass Conference 2009
Gasifier
13
Essent Biomass Conference 2009
Development and commercialisation of new technology • Original gasifier concept: proven components but: the complete concept was new
• After two substantial modification actions by the supplier the plant was still not viable
• Essent then started its own process re-design (especially for starting-up and cooling-down)
14
Essent Biomass Conference 2009
Development and commercialisation of new technology (continued) • Three project phases were necessary in stead of one: - Contracting, construction, commissioning (1998-2000) - Substantial modifications and long commissioning periods (2001 – 2003) - Re-design by Essent, construction and commissioning (2004 – 2005)
15
Essent Biomass Conference 2009
Original gasifier process scheme (1998 – 2000) • Plaatje met het originele schema incl. filters en natte wassing
16
Essent Biomass Conference 2009
Project phase 1: Contracting, construction, first commissioning • Contracts for demolition wood and installations: 1998 • Erection 1999 – 2000 • First commissioning 2000; results: - Gas cooler: • fouling • blocking with fly ash - Filters: • Damaged filter elements • Fire possible with O2 containing gas (at start-up and shut-down) - Wet scrubbing: • Solids in water • Extensive wear
17
Essent Biomass Conference 2009
Project phase 2: Substantial modifications and long commissioning periods (2001 – 2003) • Gas cooler modified: outlet temperature raised to 450 °C
• Filters replaced by cyclones
• Wet scrubbing removed (by-passed)
18
Essent Biomass Conference 2009
Gasifier process scheme after two modifications (2003)
19
Essent Biomass Conference 2009
Ultimo 2003: goodbye to supplier Several problems remained - Unavoidable (fly ash) fire in gas cooler during start-up - Agglomeration tendency of bed material - Fast gas cooler fouling - Safeguarding system too complex and thus unreliable - Four different automation programmes - Sensitivity of the plant for metal parts in the fuel 20
Essent Biomass Conference 2009
Project phase 3: Essent’s redesign, plant modification and commissioning (2004 – 2005) • Metal catcher in fuel supply (not successful in the end) • Avoiding agglomeration: - Coarser sand - Start-up burner outside the gasifier
• Oxygen-free operation under all circumstances: - Under-stoichiometric operation of start-up burner - Fluidisation with steam in stead of air during start-up and cooling-down - Result: ignition of fly ash in the system definitely avoided!
21
Essent Biomass Conference 2009
Project phase 3: Essent’s redesign, plant modification and commissioning (2004 – 2005) (continued) • Automation concept: - Push button start-up in any condition - Avoiding false starts (avoiding damaging temperature gradients)
• Safeguarding: - Focus on O2 and temperature - O2 < x % with x only dependent on temperature - Simple and clear
22
Essent Biomass Conference 2009
Technology development sometimes suffers from political issues 2006: Gasifier operation stopped due to new Dutch law (BVA): • Amer 9 considered as waste incinerator based upon
the input of the gasifier; Essent did not accept • European Parliament: Dutch interpretation of the EU
Waste Incineration Directive is too stringent • Essent’s wood gas is as clean as clean biomass and
it has been put on the ‘white list’ • End of 2006: gasifier restarted on demolition wood 23
Essent Biomass Conference 2009
New technology needs time to grow up! • 1994 – 1996 Pre-scouting and feasibility studies • 1996 – 1998 Project preparations • 1998 Contract awarding on wood supply and installations • 2000 First commissioning phase • 2005 First commercial operation • 2007 – 2009 Commercial operation with steady improvement of availability
24
Essent Biomass Conference 2009
Conclusion After more than ten years:
BLACK SHEEP has turned into MILK COW! (although the milk still needs stimulation!)
(“So, why don’t we build another one?”) 25
Essent Biomass Conference 2009
Gasifier modifications and commissioning
Martijn Spanjers Process Engineer
Gasifier
27
Essent Biomass Conference 2009
Process scheme gasifier
28
Essent Biomass Conference 2009
Start up curve
29
Essent Biomass Conference 2009
Modifications - starting points Main principle: oxygen-free operation under all circumstances
• Minimal air amount Lambda = 1
• No wood burning
• No high (flame-)temperatures • No water injection
---> Temperature [C]
• Smooth transition into gasification Lambda = 0,27 Temperature = 840 C
---> Lambda [-]
30
Essent Biomass Conference 2009
Modifications and commissioning
(1)
Main principle: oxygen-free operation under all circumstances
• Start-up burner: - Separate burner outside gasifier (avoid agglomeration due to high (flame-)temperature) - Under-stoichiometric - Temperature control with steam-injection (instead of air)
• Fluidisation of gasifier: - Fluidisation with steam in stead of air during start-up - Fluidisation with air during gasification, however also gasification with steam fluidisation possible
31
Essent Biomass Conference 2009
Modifications and commissioning • Gasification always with same fuel to air ratio (lambda ± 0,27): - No combustion mode on wood - No transition to gasification with water injection - Complete load range of fuel
• Automation and safeguarding concept: - Push button start-up in any condition - Transition between phases: based on temperature - Safeguarding on one criterion: O2 < x % (x = f(T))
32
Essent Biomass Conference 2009
(2)
Modifications and commissioning • Process parameters:
(3)
Sand specifications - particle diameter distribution 100
• •
Avoid agglomeration Lower velocity
---> w%cumulative
- Bed material: quartz sand 280 µm
90
Fine (original)
80
Normal (currently in use)
70
Coarse
60 50 40 30 20 10
- Gasification temperature: 840 C
0 0
•
Avoid agglomeration
•
Tar formation (amount vs. composition)
100
200
300
400
500
600
700
800
900 1000 1100 1200 1300 1400 1500
---> diameter [um]
Conclusion: Simple and clear safeguarding and start-up procedure. 33
Essent Biomass Conference 2009
Commissioning – start of learning curve (#trips/kton wood) 10,00
Apr - Jun 05
Jul - Sep 05
Oct - Dec 05
8,00 7,00 6,00 5,00 4,00 3,00 2,00 1,00
34
Essent Biomass Conference 2009
Regular shut down
Unit 9
Measuring problems
Electric
Process control
Gascooler
Circulating fluidised bed
Gas composition
0,00
Wood logistic system
---> Number [#/kton wood]
9,00
Gas cooler • Cooling syngas from 840 to 450 °C • Production of 10 – 14 t/h steam • Pneumatic knockers • Efficiency
Example of start-up with clean gas cooler 1,20
Efficiency factor [-]
1,00 0,80 0,60 0,40 0,20 0,00 16:00
35
V1B OVO V1A ECO 0:00
8:00
16:00
Essent Biomass Conference 2009
0:00
8:00
16:00
Cyclone and syngas composition Syngas to unit 9
• Two parallel cyclones
• 60-80% separation of fly ash: - Separation of heavy metals - Permit for syngas as clean biomass
36
Essent Biomass Conference 2009
Conclusion
• Successful oxygen-free operation under all circumstances • Simple and clear safeguarding • Simple and straightforward automation and process control • Steady and stable gasification without agglomeration • Syngas as clean as clean biomass: on ‘white’ list.
Successful gasification process
37
Essent Biomass Conference 2009
Wood gasifier AC 9 Operational experience 2007-2009
Fred Hooijmaijers Asset Engineer
Operational experience 2007-2009 • Operational results • Performance killers & issues • Two examples of improvements • Maintenance strategy • Lessons learned • Prognosed operation 2009-2013
39
Essent Biomass Conference 2009
Operational results 2001-2009 Wood gasifier; operating hours/year
40
5000 hours ≈ 100.000 ton demolition wood Essent Biomass Conference 2009
Performance killers wood gasifier
41
Essent Biomass Conference 2009
Operational issues 2007-2009 • Wood quality; reduction of metal parts due to extensive wood quality control.
• Operator experience; start up and shut down procedures. Automation optimization.
• Trips due to instrumentation; O2-measurements. • Refractory damage; due to frequent flushing with cold N2. • Bottom ash blockages; agglomerates and metal parts from the wood.
• Partial blockage of gas cooler; due to fouling with a mixture of fly ash and tar.
42
Essent Biomass Conference 2009
Example: O2-instrumentation
43
Essent Biomass Conference 2009
(1)
Example: O2-instrumentation
(2)
• Principle: 2 out of 3 O2-optical cross duct sensors. • Problems: - Gasifier trips due to wrong detection (fouling and dust clouds). - Maintenance intensive; daily cleaning, outlining problems. - Refractory damage due to frequent flushing with cold nitrogen.
• Solutions: - Downstream repositioning of O2-sensors, less blocking due to dust and tar. - Mechanical fixation to solve outlining problems. - Reduced path length and reduced tube diameter.
• Result: - Reduction of false O2-trips > 50%
44
- Substantial reduction of maintenance effort. Essent Biomass Conference 2009
Example: gas cooler cleaning
45
Essent Biomass Conference 2009
(1)
Example: gas cooler cleaning
Significant increase of cleaning interval
46
Essent Biomass Conference 2009
(2)
Example: gas cooler cleaning
(3)
Partial blockage of gas cooler; due to fouling with a mixture of fly ash and tar.
• Significant increase of cleaning interval from 2 to 4 months, due to; - Reduction of trips. - Fluidization with steam instead of air on the siphon bottom of the gasifier. - Slight reduction of gasification temperature to 840 ºC.
• Side effect is increase of tube leakages due to local erosion. 47
Essent Biomass Conference 2009
Maintenance strategy From breakdown maintenance to preventive maintenance.
• As is: - Many unplanned outages due to breakdown of non redundant components. - Opportunity based cleaning and repair of gas cooler.
• To be: - 3 to 4 planned outages per year, mainly driven by cleaning interval of gas cooler. - Combine this activity with preventive maintenance actions and inspections. Scope is based on operational experience over the last years.
48
Essent Biomass Conference 2009
Lessons learned • Commitment of operations and maintenance is a critical success factor.
• At the background ongoing technical support and trouble shooting necessary.
• No standard technology for traditional power plants; link with other industries, like petro-chemical and wood industry is needed.
• Lack of redundancy, asks for a strong preventive maintenance program.
• Over 1,3 Mio Euro improvement program in 2009-2010 to increase availability > 5000 EOH/year.
49
Essent Biomass Conference 2009
Prognosed 2009-2013 Wood gasifier; operating hours/year
50
Essent Biomass Conference 2009
Thank you for your interest
Have a nice site visit! 51
Essent Biomass Conference 2009
Innovative Technologies: Torrefaction and Pyrolysis Biomass pre-treatment options for source-to-power chain optimization and for broadening feedstock options
Jan de Jong Innovation Manager
Content 1. Introduction
2. Technology assessment -
Some basics
-
Torrefaction
-
Pyrolysis
3. Chain analysis
4. Conclusions
53
53
Essent Biomass Conference 2009
Why considering torrefaction and pyrolysis? Biomass (raw material) is a rather difficult fuel:
availability nearby energy-density hydrophilic Handling at power plant (co-) combustion Increasing competition (e.g. oil-industry)
Note: “Biomass”: fulfils the accepted sustainability criteria,
54
54
Essent Biomass Conference 2009
Torrefaction offers the solution for most of these difficulties? And what about pyrolysis? Investigation:
Focus on
Upstream application
Downstream (co-)combustion (-gasification)
Wood pellets: reference
Performed by Jacobs Consultancy Reviewed by experts from Twente University Led by Innovation (BU New Energy) Steered by experts from relevant BU’s
55
55
Essent Biomass Conference 2009
Basically rather similar processes with mainly two output streams Torrefaction 250-400 oC Dry Biomass
slow
Hot Hot pyrolysis pyrolysis gases gases
Bio-coal (Char)
Pelletizer briquetizer
Process: heat
virtually oxygen free
Combustion
endotherm Main parameters: - Particle size - Temperature - Residence time -Gas velocities
Hot Hot pyrolysis pyrolysis gases gases
Pyrolysis 400 – 600 oC Dry Biomass
fast
Hot Hot pyrolysis pyrolysis gases gases Bio-Coal Bio-Coal (Char) (Char) heat Combustion
char char Non Noncondensible condensiblegases gases
56 56
Bio-coal: Pellets Briquettes
Essent Biomass Conference 2009
Cooler/ Condenser
Bio-oil: Emulsion
Pyrolysis has some basic advantages over torrefaction for some biomass types • Opens up the agro-residues market for (co-)combustion • Valuable minerals stay upstream / fertilizer
But: in (co-)gasification low melting components can be very welcome
Biomass type
Origin
Ash-content
(typical age)
Low temperature melting components / chlorides
“old”
Wood (> 10 y)
low
low
“young”
Agro-residues ( 50%
Expectations (expressed by potential technology providers) need still to be proved! Tests will start after first delivery from “Stramproy” 58
58
Under investigation
Essent Biomass Conference 2009
Attention: biocoal is pyrophobic
Ash composition will hardly differ from woodpellets
Torrefaction: many demo-initiatives/still a lot to prove
No commercially operating installations yet Different process types under development e.g.: developed from Slow scratch /scientifically based (e.g. ECN) Slow existing process equipment (e.g. Stramproy) Fast existing process equipment (e.g. Topell) … Different process conditions and product properties Room for optimization / Optimization through cooperation !?
Lightly torrefied (brown)
Intensively torrefied (black)
…. optimization .... Energy loss •Energy density •Hydrofobicity •HSE •Milling •Combustion •…. • costs
59
59
Essent Biomass Conference 2009
Commercially operating pyrolysis installations available But bio-oil is not an “ideal” fuel
Emulsion: mixture of oils, water and fines High oxygen content Corrosive: pH ~ 2.5: stainless steel required Pungent odour Not stable: ”ages” with time HSE aspects
Suitable for co-combustion in a: Coal fired PP ?
R&D going on in upgrading pyrolysis oil Combined Cycle ?
Remark on downstream application: hot gas combustion: “nasty” condensation step can be avoided (e.g. RWE Conthermplant in Hamm (D)) Can be attractive alternative for locally available biomass / waste streams
60
60
Essent Biomass Conference 2009
LCA-analysis: the CO2-footprint Internal research
LCA-stages included by JC
HARVESTING
TRANSPORT
(Grading, planting, fertilization, pesticide usage, machinery)
Only applicable in case of energy-crops, not for by-products
Input data for this specific case calculation: • biomass source: saw-dust (= residue) with 60% dm from eastern Canada (BC) • Mean (truck) distance raw material: 110 km to lumber mill + 28 km to production plant • Distance to Vancouver Sea Port: 780 km (by train) • sea transport distance to EU (via Panama Canal): 15.500 km
61
61
Essent Biomass Conference 2009
Power Plant conversion
Pyrolysis Pyrolysis plant plant
COMBUSTION
Gate delivery PP
Torrefaction Torrefaction plant plant
Ship Transport
Wood Wood pellet pellet plant plant
Train to seaport
Truck-2 transport Truck-2 transport transport Truck-2
Lumber mill mill Lumber
Truck-1 transport transport Truck-1
Tree harvesting harvesting Tree
Re-forestation Re-forestation
PRODUCTION
Conclusions
(1/2)
1. Torrefaction and pyrolysis technologies offer potential chain advantages 2. Torrefaction: o still in the development phase / several (pre-)commercial initiatives o Bio-coal properties far from uniform; therefore … o optimization potential in process development (through cooperation !?) o Essent starts testing bio-coal as delivery from “Stramproy” begins o Bio-coal from agro-residues not suitable for significant cocombustion rates 3. Pyrolysis: o development clearly ahead of torrefaction; o Technology commercial available although poor in number o opens up the (large) market of agro-residues for co-combustion
62
62
Essent Biomass Conference 2009
Conclusions
(2/2)
4. CO2-footprint: o o o
Bio-coal and bio-oil: very good score compared to (dutch) hurdle rate Bio-coal: better than wood pellets Bio-oil: hardly any difference with wood pellets
5. Essent will further assess torrefaction and pyrolysis as these technologies provide significantly potential: o o
63
63
In optimizing the chain from biomass source to green power and therefore .. In reaching sustainability targets more efficiently
Essent Biomass Conference 2009
Low carbon IGCC
Jan Eurlings Manager Conceptual Design
Introduction • Increasing emphasis on Carbon Capture & Storage (CCS)
• Pre-combustion capture closest to maturity
• (Un)availability coherent performance data
65
Essent Biomass Conference 2009
CCS: CO2 Capture and Storage
66
Essent Biomass Conference 2009
IGCC: Integrated Gasification Combined Cycle IGCC CCS
Air Nitrogen
Gasification Island
ASU
Steam, BFW El. Power Syngas
Coal
Coal Milling and Drying
Gasification
Gas cleaning
CO2 capture
Hydrogen
Power Island
CO2 Auxiliaries
PSA
Waste Disposal e.g. Slag, Filter Cake Waste Water
67
Utility Supply
H2 networks
Sulfur
CO2Transport & -Storage
Essent Biomass Conference 2009
Refinery
Power
Design study
(launched 2009)
Deliverables:
• Process design IGCC+CCS • Plant performances • Insight key performance drivers (technologies) • Lowest integral power price (€/MWh), at a • carbon emission