Quartz Digital Concealed

Quartz Digital concealed standard with fixed head

Quartz Digital concealed standard with adjustable head

QZ.A1.BR.05

QZ.A1.BV.05

Quartz Digital concealed pumped with fixed head

Quartz Digital concealed pumped with adjustable head

QZ.A2.BR.05

QZ.A2.BV.05

Quartz Digital Concealed installation instructions

Page 2

Components (HP/Combi)

Components (Gravity)

Components (HP/Combi)

Components (Gravity)

Quartz Digital Concealed installation instructions

Page 3

Important information Safety information This product must be installed by a competent person in accordance with all relevant current Water Supply Regulations. ALL SHOWERS REQUIRING AN ELECTRICAL CONNECTI0N MUST BE INSTALLED BY A QUALIFIED PERSON FOLLOWING THE LATEST REVISION OF BS 7671 (WIRING REGULATIONS) AND CERTIFIED TO CURRENT BUILDING REGULATIONS. This system should be installed so that other taps or appliances operated elsewhere within the premises do not significantly affect the flow. The shower must not be used with a hot water supply temperature of over 65ºC. The processor is supplied factory pre-set at maximum temperature of 45ºC. The maximum temperature is fully adjustable to suit site conditions. If adjusted, we recommend the outlet temperature is set to a MAXIMUM of 46ºC. THE DIGITAL PROCESSOR MUST BE INSTALLED IN AN ACCESSIBLE LOCATION FOR SERVICING AND MAINTENANCE. The Digital processor must be installed in an accessible location for servicing and maintenance. The Digital processor must not be installed in situations where either the ambient temperature is likely to exceed 40ºC or where freezing may occur. The control must not be installed in situations where the ambient temperature is likely to fall below 5ºC or rise above 70ºC. We do not recommend the use of Quartz Digital in steam therapy facilities. This appliance must be earthed.

Cables which are chased into the wall must be protected by a suitably sized conduit or sheathing to allow for removal in the event of service and maintenance purposes. Ensure that the conduit is run to avoid the controller fixing holes. Surface mounted cables must also be protected by a suitable approved conduit, even in a loft, where there may be a risk of damage from vermin. The power lead must only be replaced by the manufacturer or his accredited agent. The user control is supplied from a safety low voltage source. This product is suitable for domestic use only.

This product is not intended for use by persons (including children) with reduced physical, sensory or mental capabilities or lack of experience and knowledge, unless they have been given initial supervision or instruction concerning the use of the product by a person responsible for their safety. Children should be supervised to ensure they do not play with the product.

Quartz Digital Concealed installation instructions

Page 4

Installation of Digital pumped processor (for gravity stored systems) The Quartz Digital pumped shower system is designed to operate up to maximum static pressure of 100kPa ((1 bar)(10 metres head)(14.5psi)). Under no circumstances must the pumped processor be connected directly to the water main or in line with another booster pump. The minimum actual capacity of the cold water storage cistern should be not less than 225 litres (50 gallons). The capacity of the hot water cylinder must be capable of meeting anticipated demand.

Installation of Digital standard processor (for balanced high pressure and unvented systems, combination boiler systems and separately pumped gravity systems) Pressures: The Quartz Digital standard shower system is designed to operate up to a maximum static pressure of 700kPa ((7 bar)(100psi)). Where pressures are likely to exceed 700kPa ((7 bar)(100psi)), a pressure reducing valve must be fitted to the incoming mains supply. A setting of 400kPa ((4 bar)(60psi)) is recommended. It should be noted that daytime pressures approaching 600kPa ((6 bar)(80psi)) can rise above the stated maximum overnight.

Special notes for combination boiler systems The appliance must have a minimum domestic hot water rating of 24kW (80,000BTU) and be of the type fitted with a fully modulating gas valve. If in any doubt, please contact the appliance manufacturer before installation commences. PLEASE NOTE: DUE TO PERFORMANCE CHARACTERISTICS OF COMBINATION BOILERS, THE SHOWER FLOW RATE MAY VARY WITH CHANGES TO THE MAIN INLET TEMPERATURE. INLET TEMPERATURE CHANGE MAY ALSO CAUSE THE DIGITAL CONTROLLER TO FLASH. THIS IS NOT NECESSARILY CHANGING THE OUTLET TEMPERATURE.

DUE TO THE PERFORMANCE CHARACTERISTICS OF COMBINATION BOILERS, THE OPERATION OF THE ‘BOOST’ BUTTON ON THE SHOWER CONTROLLER MAY NOT OFFER A SIGNIFICANT INCREASE IN FLOW RATE.

Special notes for separately pumped gravity systems We recommend a twin ended pump with a MINIMUM pump rating of 1.5 bar. For optimum performance a twin ended 2.5 bar pump should be used. The minimum actual capacity of the cold water storage cistern should be not less than 225 litres (50 gallons). The capacity of the hot water cylinder must be capable of meeting the anticipated demand. THIS PRODUCT IS NOT SUITABLE FOR USE WITH A SINGLE ENDED PUMP.

Connections This product incorporates ‘push-fit’ type connections. Tube should be cut using a rotary type cutter and lubricated using a silicone-based lubricant or petroleum jelly (Vaseline or similar) prior to insertion into the fitting. If plastic pipe is used, the tube insert must not increase the tube diameter or extend the cut-off length by more than 2mm. TO MAXIMISE FLOW RATES WE RECOMMEND USING COPPER PIPE WITH THE MINIMUM AMOUNT OF ELBOWS.

Quartz Digital Concealed installation instructions

Page 5

Pipe sizing Long pipe runs, on both inlet and outlet, will reduce the flow rate at the shower head. 22mm pipe work should be used on the inlets and reduce down to 15mm as close to the valve as possible to reduce pressure losses and help maintain flow rate. If using 15mm then copper pipe is preferred, and minimise the number of elbows used. If long pipe runs are unavoidable on the outlet, use copper pipe rather than plastic, particularly if a diverter is used, and minimise the number of elbows as the pipe inserts are very restrictive.

Flushing Some modern fluxes can be extremely corrosive and, if left in contact, will attack the working parts of this unit. All soldering must be completed and the pipe work thoroughly flushed out in accordance with current Water Supply Regulations prior to connection of the product.

After installation Familiarise the end user with the Quartz Digital operation and hand them this guide. Complete and post the guarantee card or register online at www.aqualisa.co.uk

Quartz Digital Concealed installation instructions

Page 6

Installation instructions

!

In addition to the guide below it is essential that the written instructions overleaf are read and understood and that you have all the necessary components (shown overleaf) before commencing installation. The Quartz Digital shower system is supplied with universal fixings intended to secure it to a suitable wall.

To ensure safe operation and installation of this product, the processor MUST be

90mm

2

265mm

445mm

installed in one of the orientations shown.

270mm

1

70mm 350mm

Isolation valves are supplied with the Digital processor and must be fitted on both inlets and the blended water outlet. For all water systems inlet pipe work should be run in 22mm as close to the processor as possible before reducing down to 15mm. Outlet pipe work should be run in 15mm, copper pipe is preferable. All pipe work should be supported.

!

The inlet supply centres are 48mm. The inlet supply centres deviate from EN1111 and EN1287, but are deemed to be a special case. Please note arrow on isolation valve to indicate direction of flow. Compression fittings should not be used on inlet and outlet spigots.

Quartz Digital Concealed installation instructions

Page 7

3

Choose the position for your Digital processor as close to the shower control as possible. The processor may be sited in the roof space above the proposed shower site, in the airing cupboard or behind a screwed bath panel if more convenient. If siting in the roof space, ensure that freezing cannot occur and that no insulation material is placed under or over the processor. Please refer to the system layout diagrams overleaf.

!

THE PROCESSOR MUST BE SITED IN A POSITION THAT IS SAFELY ACCESSIBLE FOR SERVICING AND COMMISSIONING PURPOSES. WHEN FITTED IN THE LOFT SPACE, THE ROUTE TO AND THE AREA AROUND THE PROCESSOR MUST BE BOARDED TO ENSURE A SAFE WORKING ENVIRONMENT. The optimum position for the Digital processor is in the roof space above the shower site to take full advantage of the ease and speed of installation please refer to the note above. The distance between the Digital processor and shower control must be within range of the 10m data cable supplied.

4

Place the Digital processor on a solid mounting surface, mark and prepare the fixings before securing the processor to the mounting surface using the screws provided.

5 !

Flush through both hot and cold supply pipes.

The maximum hot water inlet temperature must be no more than 65˚C.

Quartz Digital Concealed installation instructions

Page 8

6

Attach the supply pipes to the Digital processor, ensuring that the cold and hot feeds are fitted into the appropriately marked inlets.

! 7

DO NOT SOLDER NEAR TO PLASTIC COMPONENTS.

Run a pipe from the mixed water outlet on the Digital processor through the wall to the proposed siting for the shower hose outlet, fixed head or diverter depending on the system purchased.

8

Place the paper template on the wall in the desired location for the shower control and mark all fixing points and the data cable entry point. Remove the template and drill a Ø16mm hole at the appropriate position for the data cable.

!

The data cable should be run in conduit to allow for replacement if required.

!

If installing this Quartz Digital as a replacement shower, it may be necessary to purchase a Quartz Digital retro-fit wall plate to first cover the existing hole in the tiling. The cavity in the wall should be plugged using a suitable material for the wall plate and controller to be secured to. Contact our Customer Service Department to purchase a chrome (part no. 223121) retro-fit wall plate.

9

Drill and prepare the four wall fixings for the controller using the fixings provided.

Quartz Digital Concealed installation instructions

Page 9

10

Feed the control connection end of the data cable through the centre hole in the mounting template. Run a bead of silicone sealant in the mastic groove on the back of the mounting plate and press into position onto the finished wall surface. Ensure the data cable is held securely by the narrow middle slot of the mounting plate and fix to the wall using the screws provided.

11

Plug the data cable into the rear of the controller and slide onto the mounting plate. Secure the controller to the back plate with the fixing screw located at the base of the controller using a small Posidrive screw driver.

12

Connect the outlet pipe to the mixed water outlet on the Digital processor. Using pipe clips as appropriate, ensure that all pipe work is perpendicular to the processor, i.e. not putting any strain on the fittings.

!

Do not solder any additional pipe work to the 15mm copper pipe from the Digital shower system as the low voltage data cable could be damaged. Instead, use push-fit fittings where necessary, to connect additional copper piping. TO ENSURE OPTIMUM PERFORMANCE USE THE MINIMUM AMOUNT OF ELBOWS. TO MAXIMISE FLOW RATES WE RECOMMEND USING COPPER PIPE WITH THE MINIMUM AMOUNT OF ELBOWS.

!

BEFORE ANY ELECTRICAL ADJUSTMENT IS ATTEMPTED, THE ELECTRICITY SUPPLY MUST BE TURNED OFF AT THE MAINS SWITCH. ELECTRICAL INSTALLATION MAY ONLY BE CARRIED OUT BY A QUALIFIED PERSON.

Quartz Digital Concealed installation instructions

Page 10

13

Connect the processor power lead to a double pole 3 amp fuse switched spur incorporated in the fixed wiring circuit, in accordance with current wiring rules. Ensure that this is located in an accessible, dry location and not in the bathroom.

!

THIS APPLIANCE MUST BE EARTHED We recommend protecting surface mounted cables in suitable approved conduit to avoid the risk of damage from vermin. The data cable and power lead should also be clipped in place with ‘P’ clips or similar to avoid accidents.

14

Unscrew the single fixing on top of the processor box and carefully tilt the lid up and off the location lugs and pull the lid clear.

15

Connect the low voltage data cable into the socket adjacent to the temperature adjuster as indicated on the label. Feed the cable out of the processor box ensuring it is correctly routed within the data cable channel.

!

A further data cable socket has been provided for use with a secondary Digital dual switch start/stop controller. This can be accessed by carefully snapping and removing the entry pillar and connecting the cable as described above.

Quartz Digital Concealed installation instructions

Page 11

16

Connect the power to the processor and press the ‘start/stop’ button on the controller to turn the shower on. Ensuring the hose washers are fitted at either end of the shower hose, attach the hose and flush the system through for 15 seconds to clear any debris before fitting the shower head. Thread the shower hose through the hose restraint before attaching the head and fitting it to the handset holder. Turn the shower off and isolate the processor from the electricity supply.

17

The Digital processors are supplied factory set with the flow rate at either ‘NORMAL HP’ or ‘NORMAL GRAVITY’ mode depending on which shower system has be ordered. STANDARD PROCESSORS ON BALANCED HP SYSTEMS: Standard processors fitted to balanced high pressure systems may be set to ‘NORMAL HP’ or for water economy ‘ECO’ modes. STANDARD PROCESSORS ON COMBINATION BOILER SYSTEMS: For Standard Digital processors installed on combi boiler systems, for optimum performance we recommend setting the flow rate to the ‘COMBI’ mode. N.B. The ‘ECO’ flow rate mode should not be selected for shower systems fitted to combination boilers. PUMPED PROCESSORS: Pumped processors fitted to gravity systems may be set to ‘NORMAL GRAVITY’ or for water economy ‘ECO’ flow rate modes.

!

WHEN MAKING ANY ADJUSTMENT TO THE PROCESSOR SETTINGS THE POWER MUST BE ISOLATED.

Quartz Digital Concealed installation instructions

Page 12

18

Re-instate the electricity supply to the processor. Press the ‘start/stop’ button on the controller to turn the shower on. The processor will start in the highest flow rate or ‘boost mode’. Press the ‘boost’ button to revert to the ‘normal’ flow rate. The processor will now provide both ‘normal’ and ‘boost’ modes.

19

Run the shower at maximum temperature (factory pre set to 450 C). If required, maximum temperature adjustment can be made with a flat bladed screwdriver using the ‘MAX’ TEMP ADJUSTMENT’ control as indicated. When the temperature has been set to the desired position carefully replace the Digital processor lid and secure the fixing hand tight only.

!

Site conditions can affect temperature settings, installer to adjust as required. ALL COPPER PIPE WORK MUST BE CROSS-BONDED AND CONNECTED TO A RELIABLE EARTHING POINT.

Adjustable height head

1

Prepare two fixing points 642mm-655mm vertically apart using a spirit level to facilitate if necessary. Fit the rail end clip into position and loosely fit the lower bracket into position.

2

Pass the rail through the handset holder whilst keeping the slider levers depressed with the handset holder pointing in a downward direction. Carefully slide the gel hanger onto the rail under the handset holder.

Quartz Digital Concealed installation instructions

Page 13

3

Current water supply regulations state the handset should not be allowed to pass a point 25mm above the spill over level of the bath or shower tray. If this cannot be achieved, the hose must be passed through the gel hanger which has been designed to also be utilised as a hose restraint.

4

Fit the rail into the rail end bodies taking care to engage the location slot

5

Fit the rail end clip into position into the top rail

onto the lugs.

end body and secure the rail assembly to the wall using the screws provided, ensuring the rail and rail end bodies remain firmly engaged.

6

Place the rail end covers into position and

7

Ensure the pipe work from the processor to

push firmly into place.

the required position for the hose outlet is prepared using a ø15mm copper pipe. Slide the 15mm gripper ring down the projecting pipe up to the wall face.

Quartz Digital Concealed installation instructions

Page 14

8

Trim the projecting pipe to a length of 15-22mm measured from the finished wall surface, using a rotary type cutter. If a hacksaw is used, the pipe end must be carefully de-burred and chamfered.

9 10

Clean and lubricate the pipe using a suitable (silicone based) lubricant.

Remove the wall outlet cover plate and carefully slide the wall outlet onto the projecting pipe. Turn to the required position and mark the screw holes on the wall face.

11

Remove the wall outlet and drill and prepare the wall fixings.

12

Ensure the projecting pipe is clean and lubricate again if necessary. Run a thin bead of silicone sealant to the rear of the wall outlet. Refit the wall outlet and secure it to the wall using the screws provided. Refit the wall outlet cover plate.

Quartz Digital Concealed installation instructions

Page 15

13

Connect the hose to the wall outlet assembly after passing it through the gel hanger / hose restraint (if required) and run the shower for 15 seconds without the handset attached to clear any internal debris, which may be present.

14

Attach the conical end of the hose to the shower handset, taking care not to twist the hose, and place in the handset holder.

Fixed head

1

Cut the outlet pipe to the finished length (55mm – 150mm measured from

2

Ensure the pipe is clean and free of dust and

the finished wall surface) using a rotary type cutter.

slide the fixing bush on the pipe flush with the finished wall surface.

Quartz Digital Concealed installation instructions

Page 16

3

Slide the fixed head arm over the fixing bush flush with the wall surface and

4

Carefully remove the fixed head arm and drill and prepare the fixings using

5

Ensuring the fixing bush is clean and free of

mark the four fixing points.

the fixings provided, if suitable.

dust, fit the 15mm O ring against the end of the fixing bush. Lubricate the O ring using a suitable silicone base lubricant.

6

Refit the shower arm and secure it to the wall

7

Remove the shower head from the arm and run the shower for a few seconds

using the screws provided.

to clear any debris that may be present.

Quartz Digital Concealed installation instructions

Page 17

8

Check for leaks and if all is sound refit the shower head to the fixed arm and push the cover plate into position flush with the finished wall surface.

Quartz Digital Concealed installation instructions

Page 18

Aqualisa Products Limited The Flyer’s Way Westerham Kent TN16 1DE Customer helpline: 01959 560010 Brochure Hotline: 0800 652 3669 Website: www.aqualisa.co.uk Email: [email protected] Republic of Ireland Sales enquiries: 01-864-3363 Service enquiries: 01-844-3212

Part No: 293401 Issue 04 Jun 10

Please note that calls may be recorded for training and quality purposes The company reserves the right to alter, change or modify the product specifications without prior warning ® Registered Trademark Aqualisa Products Limited