Offshore Renewable Assets Mitigating Risk While Driving Costs Down
PPA energy Overview
PPA energy International advisors on technical regulation Undertaking technical & economic studies Developing & implementing technical innovations International consultancy advice on network business management (asset management, pricing, technical performance) Electricity industry worldwide Established 1997 London – Guildford - Johannesburg 2
BPP-TECH Overview
BPP-TECH Design analysis & review of subsea equipment Subsea power cables & umbilicals Riser management systems for drilling vessels Project management & QA/QC Insured risk & failure analysis Product development Hydrocarbon, renewable, marine, insurance industries Established in 1981 London - Houston - Aberdeen 3
Petrofac - TNEI
TNEI Overview
Leading many of the offshore initiatives Supporting several R2 & R3 projects Leading Asset Delivery for OTCG HVDC experience – onshore and offshore Extensive engagement on the issues of developing and delivering offshore transmission Transmission, Distribution, Generation, Offshore wind, Oil & Gas Established in 1997, part of Petrofac since 2010 Manchester - Newcastle 4
OFTO –Ownership
Transmission Cable
Source: RBC capital markets
Assessing overall project and operational risk and mitigation strategies Will they last the 20-year design life?
6
Technical Design Issues
Offshore power cable network redundancy Down time reduction and repair planning Cable performance and sea bed scour monitoring Rapid deployment of repair capability Long term cable life assessment Planning for replacement costs
7
Design & Risk Mitigation
Cable & configuration design Installation, dynamic & fatigue analysis Cable array & power conditioning system engineering Cable protection, J-tube, I-tube & bend restrictor engineering Mechanical & thermal service life assessment Reviews of sea bed scour potential & monitoring philosophy Cable & material qualification testing Environmental impact assessment Subsea cable supply & quality assurance/quality control Failure scenario & repair planning
Sources of Failure Risks
9
Design flaws Manufacturing defects Damage during installation Mechanical fatigue and thermal degradation Sea bed scour effects (spanning, fatigue, impact damage) Damage from marine life
Many of the risks are interrelated
Asset Management
Asset lives not well understood Asset ageing and failure modes in UK/deep water situations Costs of maintenance intervention much higher than on land Access issues - seasonal challenges Regulatory mechanisms not fully defined
10
How do OFGEM’s availability payments drive design options, level of redundancy, interconnection, specifications of plant & cable assets?
11
Cash flows
Energy revenue + ROCs + Carbon credits
Xxxxxxxxxx Xxxxxxxxxx xxxxxxxxxx
Xxxxxxxx Xxxxxxx xxxxxxxx
Financial Overview
230 MW of generation = £653.2 million of capital investment (at approx £2840 per kW Cable link to shore cost approx. £120 million The generator earns £ 93.2 million in total per year Generator exposure to outages is £255k per day on an average day
13
This OFTO earning £18.2m per annum.
The OFTO
Average penalty per day of outage is £82.7k (82.7k x 22 = 1820k) OFTO’s worst case risk is losing 50% of revenue equivalent to £9.1 million or 110 days, but this risk spread over 5 years. This would equate to a loss of earnings of approx £28 million for generator Both Planned and unplanned outages are taken into account as Outage. 14
OFTO Risk
If OFTO can increase availability by 2% over the 25 year life of the project this is worth: NPV of £1.87 million OFTO (at 9% discount rate) Cost of maintenance intervention to OFTO +/- NPV £1.5 million. Total NPV of increase in OFTO availability, assuming it leads to maintenance reduction is: £ 3.36 million For the Generator, NPV of reduction in loss of earnings is £18 million (at 10% discount rate) 15
Scaling up to Round 3
Is an NPV the right way to look at these types of risk? A £9.2 million loss of revenue in year 10 is still a serious threat to business continuity Do you mitigate risks by building network functionality/redundancy, or by making financial provisions? Who is rewarded to building extra functionality? And How?
16
Cash flows
£ 93m per year 230 MW
Energy revenue + ROCs + Carbon credits
Xxxxxxxxxx Xxxxxxxxxx xxxxxxxxxx
£ 23m per year
£ 18m per year
Xxxxxxxx Xxxxxxx xxxxxxxx
How can you drive down costs at the same time as you drive up availability as well as managing risk?
18
Key Network Design Issues
How should operational experience and financial model influence network design? NPV analysis on designs changes the weighting between near-term and far-term events This is significant for low probability high consequence events such as 3rd party damage
Good design and planning upfront can create robust networks that are safe investments
19
What does good design mean?
Single circuit security Loss of circuit is total loss of power export capability from offshore site Loss of power to offshore so emergency power conditions, i.e. diesel bunkering 1GW @35% for 3 month repair time £75.6M in lost production plus repair bill
1GW
1GW
Multiple circuit security Loss of circuit results in reduction of export capability to 50% Power retained offshore so no emergency power requirements Offshore site constrained to 50% but with 35% capacity factor, constraint is lower Lost production ~1/4 of single circuit loss
100%
50%
20
Future Offshore Networks
Location C 500 MW
Argyll Array 500 MW
Argyll HUB
Hunterston Islay 500 MW Coolkeeragh HUB Location J 300 MW
Coleraine HUB Location K 300 MW Tidal 200 MW Coleraine
Coolkeeragh
21
Actual Network Configuration
Multiple HVDC links
Flexible sizing to match project build-out
Phased construction
No DC circuit breakers 3-end multi-terminal
Multiple paths for power export
not “redundancy” in the conventional sense Offline reconfiguration allows for outages but maintain majority export 22
Future Networks
23
What if:
Future Networks
The output and performance of every asset in an array cluster was known and understood? Where and when the next cable , transformer or switchgear failure was known BEFORE if occurred? Generators with dynamic voltage control rode though faults, with zero fault current and recovered instantly? Circuit were longer, lower voltage, lower loss and higher capacity? Secure meshed networks had no offshore circuit breakers? Offshore platforms and hubs were smaller and lighter?
Working Together
Asset Management Policy
Asset Management Strategy
Information, risk management and planning
Implementation and operation
Design analysis & review of subsea equipment Riser Management Systems Project Management & QA/QC Insured risk & failure analysis, Product development
Direct experience dealing with lenders, due diligence etc. Operational and financial experience with network businesses Excellent networks with universities and innovators in supply chain Extensive regulatory experience, including with Ofgem. Leading edge thinking around offshore regulation
Provision of high quality specialist professional engineering Concept engineering and feasibility investigations Power system planning and analysis Technical due diligence & failure investigation 25