A healthy worker, in a healthy workplace, making healthy lifestyle choices
Occupational Health in Design The Power to Make a Difference
Eric Ball Senior Occupational Hygienist
01296 310450 |
[email protected]
How does this work on Major Construction Projects? Four key elements to occupational health risk management: 1.Focussing on the worker, to reduce the negative impact of health on work; 2.Focussing on the workplace to ensure that work is designed in order to reduce the impact of work on health; 3.Focussing on wellbeing, to encourage employee general health and wellbeing and, 4.Focussing on the wider community to improve the health of local populations 01296 310450 |
[email protected]
How does this work
• A holistic occupational health programme must have prevention at its core.
• A hygiene led service anticipates and recognises health hazards before they arrive on site.
• Integration with design aids this enables full application of the hierarchy of control, prior to the evaluation, control and prevention of the residual risks 01296 310450 |
[email protected]
Why should we integrate health into design? •
Moral
o Worker health
•
Contractual
o Works Information •
Legal
o The Health and Safety at Work etc. Act 1974 o Construction (Design and Management) Regulations 2015
o Specific Regulations (ALARP) •
Economic
o Cost effective and healthy e.g. the Elliot Method 01296 310450 |
[email protected]
Why else should we integrate health into design •
Approx. 46% of construction industry accidents could have been prevented by design (HSE research report 218 & 156)
•
Construction industry saw 30 fatalities in 16/17, suggesting that 14 accidents could have been prevented by design
•
If 47% of deaths caused by occupational ill health could have been prevented through design intervention this equates to around 1,800 preventable ill health deaths
•
The methods of work and materials used to realise designs have a massive influence over the future health of construction worker
01296 310450 |
[email protected]
When should we be thinking about this?
• Concept Design
• Detailed Design • Construction and handover • When and who else has influence? 01296 310450 |
[email protected]
Concept Design
• It is easy to detach from the implications later on
• Site layout may determine construction techniques
• First opportunity to identify ground conditions that may result in ill health
• Significant impact on forgotten health issues – such as fatigue and mental wellbeing 01296 310450 |
[email protected]
Concept Design
• Soils behind sheet piling stabilised with Polyurethane foam
• Planned Oxygen/Propane cutting of the sheet piling • Exposure of foam to naked flames releases Hydrogen Cyanide
• Remaining soils stabilised with a sandwich layer of water based acrylic foam against the piling
• Safer alternative found to have exactly the same stabilisation properties as polyurethane foam 01296 310450 |
[email protected]
Concept Design
• Early designs did not require roof access, such that detailed design made not account for it
• Late in the planning the scope changed for lighting • Attempts made to design access from pool side • Ultimately temporary access had to be introduced, leading to manual handling issues during lighting maintenance.
01296 310450 |
[email protected]
Concept Design
• Water Treatment Works project for enlargement of a number of works.
• Consideration was being given to bulk chemical delivery for treatment of water supply
• Previous sites had issue with the powdered state of chemical so liquid would be preferred
• Option not considered viable in some aspects due to insufficient space for infrastructure required. 01296 310450 |
[email protected]
Detailed Design
• Often the main point of any serious consideration of OH
• Techniques and methodologies decided upon • Use of specific materials • Opportunity to influence temporary works – which is a major influencer on OH as the demolition requirement becomes more
pertinent 01296 310450 |
[email protected]
Detailed Design
• Decisions not finalised for the numbers of bio-mass reactors to be installed. Reactors required various ducts to pass through the concrete floor.
• In the pouring of the first floor, large removable sections were designed in to allow for variations.
• Avoided the noise, HAV and respirable silica exposures that would be anticipated from cutting
holes to fit the ducting once the design had been finalised.
01296 310450 |
[email protected]
Detailed Design
• All these projects used similar hazardous chemicals for surface preparation
• In each circumstance, this was specified by design
• Challenging the suppliers enabled the use of considerably safer alternatives. 01296 310450 |
[email protected]
Other influencers on the design
• Who else has valuable input? • Client • Construction Teams • Procurement Teams • Project Risk Managers • Environment Teams • Safety Teams 01296 310450 |
[email protected]
Constructability
• Often the typical point of serious consideration of OH
• Techniques and methodologies decided upon
• Use of specific materials • Consideration of operational and maintenance activities 01296 310450 |
[email protected]
Constructability
• Early designs had left specific techniques for waterproofing to be left open to contractors choice
• Allowed for trialling of different techniques (sprayed chemical or mechanically fixed lining)
• Input from OH team was able to direct design team to remove one option from the multiple compounds being considered.
• Other sites without the input from OH lead to temporary site shut down 01296 310450 |
[email protected]
Tools for Designers
• Comparative Risk Assessment
• Use to provide a semi quantitative analysis during option control workshops 01296 310450 |
[email protected]
Tools for Designers
• BIM • Computer modelling can be used to incorporate known health and safety hazards
• Hazard Identification workshops used to identify key ergonomic hazards with water dosing units
• These were inputted to the BIM system, ensuring that designers knew about the positioning, access, and routes required to and from chemical storage
01296 310450 |
[email protected]
Tools for Designers
• RAG Lists • Don’t simply prevent options
but provide alternatives and controls 01296 310450 |
[email protected]
Thank you for listening! Do you have any questions? • RAG Lists
01296 01296310450 310450 | |
[email protected] [email protected]