Preliminary Outlook and Discussion: Ontario Supply/Demand Balance to 2035 Prepared for discussion with the IESO Stakeholder Advisory Committee
March 23, 2016
Purpose
• Describe the planning process envisioned by Bill 135
• Provide some planning context • Invite your input
2
Bill 135 planning process
IESO Technical Report “Ontario Planning Outlook”
Bill 135 “Energy Statute Law Amendment Act, 2015”
Government’s Long-Term Energy Plan
IESO Implementation Plan
3
The IESO is beginning work on a new planning advisory product: the “Ontario Planning Outlook” (2016). The Outlook will provide planning context for policy makers and industry stakeholders and serve as an early input into the government’s Long-Term Energy Plan development process. Elements of the Planning Outlook: A. Review
B. Outlook
C. Discussion
D. Synthesis
E. Guidance for Action
• “Where are we
• “Where are we going/what is the path we are currently on?”
• “What are some of
• “What do we make of all of this/how do we interpret this/what does it/could it mean?”
• “What do we do with this information?”
and how did we get here?”
• Review of historical trends 2005 – 2014
• Deterministic, “Status quo” outlook
the important considerations?”
• Investigation of relevant issues, trends, uncertainties, opportunities and risks
• Development of integrated themes and insights
• Advice, identification of key indicators and trigger points
4
Summary • The projection for long-term electricity demand growth is effectively flat: demand growth is expected to be offset by conservation savings • Ontario is adequately supplied and will remain adequate for the foreseeable future - Requirements for additional supply are generally not expected to emerge until at least the mid-to-late 2020s
• The timing and extent of eventual need for additional supply is a moving target • Operational and regional considerations may drive focus in the meantime
Analysis is underway, the values in the following slides should be treated as indicative for now
5
Ontario has undergone net growth in electricity supply in recent years 45 40 +2
+1
+1
Refurbished Nuclear
New Hydro Resources
New Demand Response Capacity
Installed Capacity (GW)
35 +5
30 -6
+5
Coal Shutdown
Non-Hydro Renewables
25 20 15 10 5 0 2005
New Natural Gas Resources
2014
6
Ontario electricity demand has not grown within the same period Peak Demand (MW)
27,000
2005
2006
2007
2008
2009
2010
2011
2012
2013
2008
2009
2010
2011
2012
2013
2014
26,000 25,000 24,000 23,000 22,000 21,000
Ontario Demand IESO Grid Demand
20,000
Energy Demand (TWh)
160 155 150 145 140
135 130
Ontario Demand IESO Grid Demand
125 2005
2006
2007
2014 7
Rising capacity margins have been the result, particularly in the winter 7,000
6,000
7,000
Resources Above Requirement (MW, seasonal weather normal)
6,000
5,000
5,000
4,000
4,000
3,000
3,000
2,000
2,000
1,000
Summer
1,000
Winter
-
Summer 2009
Summer 2010, Winter 2009/10
Summer 2011, Winter 2010/11
Summer 2012, Winter2011/12
Summer 2013, Winter 2012/13
Summer 2014, Winter 2013/14
8
Ontario’s electricity production mix has evolved over the past decade: coal-fired production has been replaced by production from natural gas-fired, nuclear, and renewable sources. About 90% of Ontario’s electricity production now comes from non-fossil sources.
(includes exports)
Annual Ontario Energy Production (TWh)
180 160 140 120 100
80 60 40 20 0 2005
2006 Nuclear
2007
2008
2009
Coal
Oil & Gas
Hydro
2010
2011
Non Hydro Renewables
2012
2013
2014
Other
9
Meanwhile, Carbon dioxide emissions from electricity generation in Ontario have declined by over 80%
CO2 Emissions (megatonnes)
40 35 30 25
20 15 10 5 0
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
10
Recent investments in Ontario’s transmission infrastructure have supported objectives related to the elimination of coal-fired generation, improving reliability, enhancing interconnections with neighbouring jurisdictions and connecting renewable generation. Major Ontario transmission investments between 2005 and 2015 are summarized below. Legend 1 Parkway TS 2 North Sault Ste. Marie Reinforcement 3 Local Generation 4 Hydro Quebec Interconnection 5 North-South Series Compensation and Northeast SVC 6 Nanticoke and Kitchener Area SVCs 7 Bruce to Milton 8 Lambton to Longwood 9 Station Improvements 10 Niagara Area Reinforcement
11
Ontario’s total cost of electricity service grew by about 55% between 2004 and 2014. Generation was the largest driver. 20 $0.3
18
$1.1
$0.3
$0.1
$0.0
16
Billions (Nominal)
12 10
8
$3.4
$5.0
14
$1.6 $0.3
$1.0 $0.8 $2.3 $1.3
6 4
$1.0 $0.9
$11.8 $6.7
2 0
2004
Generation
Generation
Conservation
Conservation
Transmission
Distribution
Transmission
Wholesale Charges
Distribution
DRC
Regulation
2014
DRC
12
More supply is on the way: some is contractually committed but not yet in service, some has been directed but has not yet been secured 45
Installed Capacity at Year-End (GW)
40
Contracts Reaching Term
35 30
Directed
25
Committed
20
15 10
Existing
5 0 2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
13
2035
Long-term net demand growth will remain moderate as conservation savings offset projected economic growth 35,000 Historical
Projected
240
30,000
Peak Demand
Conservation
220
Peak Demand (MW)
200 20,000
180 15,000
Energy Consumption
Energy Consumption (TWh)
25,000
Conservation
160
10,000
2035
2034
2033
2032
2031
2030
2029
2028
2027
2026
2025
2024
2023
2022
2021
2020
2019
2018
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
120
2003
0
2002
140
2001
5,000
Electrification assumptions in the reference demand forecast: • • •
Continuation of current trend of a modest decline in electric fuel share for space and water heating attributable to low natural gas costs and expansion of gas systems Transit lines that are scheduled to be electrified and have committed funding 50% annual increase in EV sales over next 5 to 10 years, sales levels stabilize thereafter; 600,000 EVs on the road by 2035
14
Effort will be required to meet conservation targets established in the 2013 Long-Term Energy Plan
Planned savings from future programs & Codes and Standards
15 NOTE: Savings at the generator level, which accounts for transmission and distribution losses.
Potential impact on Ontario’s energy demand
• What charging energy demand would be if some of today’s passenger vehicles were EV. • One million EVs would require about 3 TWh electricity each year, representing 2% of Ontario’s grid demand. Number of EVs EV registered in Ontario by December 2015 5% of today's passenger v ehicles were EV 13% of today's passenger v ehicles were EV 20% of today's passenger v ehicles were EV 100% of today's passenger v ehicles were EV
5,400 385,500 1,002,300 1,542,000 7,710,000
Annual EV Percentage of charging energy Ontario's grid demand (GWh) energy demand 18 0.01% 1,180 0.9% 3,068 2.2% 4,720 3.4% 23,600 17%
16
Potential impact on Ontario’s peak demand •
Peak impact under different scenarios to charge one million EVs Evenly distributed 24/7
Charger type
All types of chargers
Charging pattern
Throughout a day
Daily load profile
20% lev el-1 60% lev el-2 20% lev el-3 20% daytime 30% ev ening 50% night
10% lev el-1 50% lev el-2 40% lev el-3 40% daytime 50% ev ening 10% night
10%
10%
9%
9%
9%
8%
8%
8%
7%
7%
7%
6%
6%
6%
5%
5%
5%
4%
4%
4%
3%
3%
3%
2%
2%
2%
1%
1%
1%
0%
0%
I mpact on grid peak demand (MW)
0% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
342
328
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
496
Charging scenarios vary significantly, affected by: – – –
•
Convenience dominant with minimal load management
10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
•
Effective load management with some convenience
Time of charging Type of charger Status of battery
It will be important to maintain tools to assist in managing the timing of charging loads.
17
Electrification of Transit Expected in service date 2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Beyond 2025
GO Rail system (GTA) Hamilton LRT (Hamilton) ION LRT (Waterloo / Kitchener)
Stage 1
Stage 2
Hurontario - Main LRT (Mississauga) Confederation Line LRT (Ottawa)
Stage 1 Stage 1
Stage 2 Stage 2
Eglinton crosstown (Toronto) Sheppard east (Toronto) Finch west (Toronto)
•
•
•
Reference case forecast (blue in the chart) includes projects under construction or have funding committed. High case (green in the chart) also includes stage 2 projects being planned. Challenge to estimate electricity demand as details are not available for most projects. Power needs highly depend on service level (eg. service frequency and number of passengers) and technology. Electricity demand estimate was based on Metrolinx’s GO electrification study and traction power consumptions of existing transit systems such as TTC and CTrain. 18
On the current path, the renewable share of Ontario’s total electricity production will have increased by 20 percentage points between 2005 and 2035: a doubling. The nuclear share will have declined by 20 percentage points from today’s level.
~20% ~30%
~40%
~20% ~10%
~50%
Note: values in figure above are rounded
~10% ~20%
~60% ~40%
19
Ontario’s resource requirement is the amount of available capacity required to meet the NPCC reliability criterion of an annual loss of load expectation of 0.1 days per year. The resource requirement includes some available capacity that is in excess of Ontario’s demand. The fraction of the resource requirement that is in excess of Ontario’s demand is referred to as the “reserve margin” or “planning reserve”. Ontario’s target reserve margin reflects the expected internal supply mix, forecast demand levels and their uncertainties, major transmission limits and both scheduled and unscheduled resource outages. 35
Resource Requirement 30
Reserve Margin
Demand (GW)
Net of Conservation
25
20
Peak Demand
15 Planning Reserve Margin 10
5
Summer Peak Demand (after conservation) Summer Resource Requirement (Demand + Planning Reserve)
0 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
20
While Ontario’s installed capacity is about 39 GW, the contribution of that capacity during peak periods (a.k.a. the “effective contribution”) tends to be lower due to temperature and weather effects. Although contributions vary by individual technology, the effective contribution of Ontario’s supply mix as a whole is about one third lower than its installed capacity. The effective contribution of Ontario’s supply mix is generally higher in the winter than in the summer. 45
Capacity (GW)
40
35
30
Installed Capacity
25
Capacity Contribution to Summer Peak Capacity Contribution to Winter Peak 20 2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
21
Contribution at Time of Summer Peak (GW)
Ontario will have sufficient supply over the next decade. Additional resources may eventually be required. Needs have been reduced and deferred since LTEP 2013. 35
Summer Peak Demand
Additional resources needed to meet resource requirement
Summer Resource Requirement
30 25
Resources with expired IESO contracts Directed
20
15
Committed
10 5
Existing
0 2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
6
Resources Above Requirement at Time of Summer Peak (GW)
4 2 0 -2 -4 -6 -8
-10
Existing, Committed & Directed Capacity (excludes expired contracts) Existing, Committed, Directed and "Assumed" Capacity (includes expired contracts)
-12
22
Longer-term CO2 emissions will remain well below historic levels, but will fluctuate in step with production from Ontario’s natural gas-fired fleet. Natural gas-fired generation will tend to be highest when nuclear output is lowest, such as during refurbishments and upon Pickering retirement. Ontario Electricity Sector CO2 Emissions (MT)
40 35 30 25 20 15
Range with/ without emissions from imports
10 5 0
2005
2007
2009
2011
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
23
Future transmission investments will be influenced by changes in demand/supply patterns, customer choice and regional planning, and performance of existing assets/end of life considerations. Some current initiatives are identified below.
Current transmission planning initiatives 1 East-West Tie 2 Line to Pickle Lake 3 Remote Communities Connection Plan 4 Northwest Bulk Transmission Line 5 Supply to Essex County Transmission Reinforcement 6 West GTA Bulk Reinforcement 7 GTA West Transmission Corridor 8 Guelph Area Transmission Refurbishment 9 Special Protection Systems 10 Clarington TS 11 Quebec Interconnection Reinforcement
24
While Ontario will remain adequately supplied for at least the next decade, its supply system will soon enter a period of sizeable and rapid transition. The transition will introduce some prospect of implementation, performance and availability risk and will require our attention
Resources Above Requirement at Time of Summer Peak (GW)
3
2
1
0
A Moving Target -1
-2
-3 2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
25
One aspect of the upcoming transition relates to the substantial resource turnover anticipated in coming years. The turnover will be driven by nuclear retirements, nuclear refurbishments and by the commissioning of substantial amounts of renewable and natural gas-fired resources. Together, all of this presents some risk of a “many moving pieces” variety. Installed Capacity Turnover, 2016 - 2035 (MW)
10 8 6 +8
4 2
+4
0
-3
-2 -4
+4
-1
-8
-6 -8
-10
Refurbishment outages at Bruce and Darlington
Pickering Retirement
Non-Utility Generator Committed Resources Contracts Reach Term
Directed Resources
Returns from RefurbishmentOutages at Bruce and Darlington
26
The figure below illustrates the tightly coupled nature of the planned nuclear refurbishment programme: many refurbishment outages in a relatively short period of time, sometimes in parallel 2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2031 2032
2033
2034
Bruce 1 Bruce 2 Bruce 3 Bruce 4
Bruce 5 Bruce 6 Bruce 7 Bruce 8 Darlington 1 Darlington 2 Darlington 3
Darlington 4 Pickering 1 Pickering 4 Pickering 5 Pickering 6 Pickering 7 Pickering 8 2015
2016
2017 2018
2019
2020
2021 2022
2023
Refurbishment Outage
2024
2025 2026 2027
2028
2029 2030
Projected End of Service
27
While the turnover risk described stems from a variety of resource types, some pose greater overall risk than others and call for prioritized focus in risk assessment and mitigation planning. Nuclear refurbishments are a prominent example.
28
The effect of ageing on generator reliability is another issue to watch. As illustrated in the figure below, generator reliability can change over time. “Breaking in” failures are of particular concern during a unit’s infancy, “wearing out” failures are of particular concern during a unit’s twighlight years.
Forced Outage Rate
Decreasing Forced Outage Rate
Constant Forced Outage Rate
Increasing Forced Outage Rate
Wear Out Failures
Breaking In Failures
Time This type of figure is sometimes referred to as a “bathtub curve” 29
The issue of ageing is relevant in light of the “demographic” distribution of Ontario's generator fleet: about 40% of Ontario’s total capacity is less than 15 years old, about 45% of Ontario’s capacity is greater than 30 years old Cumulative Installed Capacity (%)
100%
Biomass
90%
Solar
80%
Wind
70%
Water
60%
Gas
50%
Nuclear
40% 30% 20% 10% 0%