PUC Docket No. 40443 EXHIBIT CTB-14

Turk Plant February 2007 Cost Estimate Summary

Category Land Acquisition Intemal Labor & Expenses Engineering & Professional Services Engineered Equipment Materials Construction Labor & Services Start-up Fuel and Sorbents Capital Spare E ui ment Other (Tax, Ins., & Esc.) AEP Allocations Activiated Carbon Injection (Mercury Control System) Contingency Total Project

Total Project (Millions) $13.00 $48.00 $57.60 $318.70 $204.80 $518.80 Note 1 Note 2 $73.70 $34.20 $3.40 $75.00 $1,347.20

Note 1: Start-up fuels and sorbents required prior to commissioning are not included. Note 2: Capital Spares are not included.

537

PUC Docket No. 40443 EXHIBIT CTB-15

This Exhibit is HIGHLY SENSITIVE under the terms of the Protective Order. The information is 'available for review at the Austin offices of American Electric Power Company (AEP), 400 West 15th Street, Suite 1520, Austin, Texas, (512) 481-4562, during normal business hours.

538

PUC Docket No. 40443 EXHIBIT CTB-16 Page 1 of 6

PROJECT CHANGE REQUEST LOG Status

PCR No.= Year.Month.Number.Revision-Department

Draft E-Engineering Routing M-Management Rou ' > 14d C-Cost O-Operations L-Construction Approved iNot A roved : D-Delay

Status Approved:

PCR No. 06.08.01.00

Subject E Steam Turbine-Generator & BFPT Cost Variance

Approved Approved •>'

06.10.03.00 06.09.01.01

C Alstom Letter of Credit & Euro Hedging C Capital Cost Recovery

,-Approved Approved , Approved Approved Approved Approved Approved Approved Approved roved Approved

06.09.02.00 06.10.01.00 06.10.01.01 06.10.02.00 06.10.04.00 06.12.01.00 07.02.01.00 07.02.02.00 07.02.03.00 07.04.01.00 07.04.02.00

E E E C E C E C C E M

Aproved

07.04.02.01

Boiler & AQCS Cost Variance Powdered Activated Carbon (PAC) Injection System for Mercury Control ACI System for Mercury Control - Revision B&W Letter of Credit Start-up Boiler Feed Pump B&W Tube Mad Escalation Relocation of the Bottom Ash Conveyor Additional Air Modeling Work (TRC) Additional Archaeological surve URS EPC Contract Negotiation EPC Contract

complete 08/09/06

11/07/06 11/03/06 09/14/06 12/14/06 08/27/08 12/11/06 11/07/06 12118/06 02/23/07 03/28/07 03/28/07 08/20/07 08/24/07

M EPC Contract-Reconcile

Approved Approved Approved Approved Not oired Approved NotApproved proved^ Approved Approved Approved Approved Approved e Approved Approved Nat. Approved Approved Approved Approved . Approved Approved 'Approved Not - roved ,Approved Approved Approved Approved Approved Approved Approved. Approved Approved . ° Approved Approved ,

07.04.02.02 07.04.03.00 07.04.03.01 07.04.03.02 07.06.01.00 07.06.01.01 07.06.02.00 07.06.02.01 07.06.02.02 07.07.01.00 07.07.02.00 07.07.03.00 07.07.03.01 07.07.03.02 07.07.04.00 07.07.04.01 07.07.04.02 07.07.04.03 07.07.04.04 07.08.01.00 07.09.01.00 07.09.01.01 07.09.02.00 07.09.02.00 07.09.03.00 07.09.03.01 07.09.03.02 07.10.01.00 07.10.02.00 07.10.02.01 07.10.02.02 07.10.03.00 07.10.03.01 07.10.03.02

04/22/08

M E C C E E E E C L M E E E C C C C C E E E E E E E C E E E E E E E

12/15/10 04/26/07 03/31/08 03/31/08 07/01/07 08/20/07 07/01/07 08/20/07 01/12/11 07/12/07 09/07/07 07/17/07 12/11/08 07/02/09 08/27/07 04/01/08 05/23/08 12/01/10

Approved--

07.10.04.00

-E Positive Cocking Condenser Isolation Valves

EPC Contract Ad'ustment for CHAT Installation B&W Damper Elimination Turbine Bypass Scope Transfer Transfer Dry FGD Work scope from Install to OEM Contract 2nd Lowering Well 2nd Coal Handling Lowerin Well Rivenroater Intake Rivennrater Intake Rivenwater Intake Revision Construction Elevator 2nd Cab Service Building LEED Certification AQCS Lime Gravimetric Feeder AQCS Lime Gravimetric Feeder - LABOR AQCS Lime Gravimetric Feeder - LABOR Revision Spare Parts-Boiler Feed Pump Balance of Capital Spares Balance of Capital Spares Capital Spares Update Capital Spares Update Conventional DCS I/O for B&W & Alstom scope Second Manway for Deaerator Second Manway for Deaerator Delay BFPT ex-works. Eliminate TAL valve. Delay BFPT ex-works Additional 5-ton hook on bridge crane Additional 5-ton hook on bridge crane Additional 5-ton hook on bridge crane ID Fan CT for Protective relaying capability FGD & Lime dust controls Material Handling DRB Meeting - LABOR Material Handling DRB Meeting - LABOR Revision AQCS Pulse Jet Fabric filter Air Compressor AQCS Pulse Jet Fabric filter Air Compressor - LABOR AQCS Pulse Jet Fabric filter Air Compressor- LABOR Revision

08/29/07 09/07/07 10/08/07 10/01/07 10/22/07 10/02/07 10/11/07 02/01/08 10/09/07 10/09/07 12/11/08 07/02/09 10/16/07 12/11/08 07/02/09

10/24/07

539

PUC Docket No. 40443 EXHIBIT CTB-16 Page 2 of 6

Status

PCR No.

Subject

Complete

Approved . Proved ..

07.10.05.00 07.10.05.01

D Shaw Stop Work & Delay Full Notice Claim D RECONCILE-Shaw Stop Work & Delay Full Notice Claim

10/15/07 05/29/08

Approved, Approved . Approved ,Approved Approved-

07.10.06.00 07.10.06.01 07.10.06.02 07.11.01.00 07.11.02.00

E E E E C

Approved Approved -.'

07.11.02.01 07.11.02.02

12/03/07 12/11/08 07/02/09 12/03/07 12/03/07

C Credit for Assigned Contracts C Credit for Assigned Contracts-RECONCILE

01/29/08 05/29/08

Approved Approved,

07.12.01.00 07.12.02.00

E Contract Amendment 4 (Weld Overlay & Copes Vulcan Valves) E FD Fan Rainhood Removal

01/28/08 04/08/08

roved.

AQCS Structural Design Enhancements AQCS Structural Design Enhancements - LABOR AQCS Structural Design Enhancements - LABOR Revision Addition of Speed Probes & Elimination of Skid Mounting Bolts Credit for Assigned Contracts

07.12.02.01

C FD Fan Rainhood Removal Reconcile

08/04/08

Approved Approved

07.12.03.00 07.12.03.01

E Boiler Penthouse Handrail E Boiler Penthouse Handrail Labor Adjustment

01/28/08 04/09/08

-Approved

07.12.03.02

E Boiler Penthouse Handrail Labor Adjustment - Reconcile

12/11/08

07.12.03.03 07.12.04.00 08.01.01.00 08.01.02.00 08.01.02.01 08.02.01.00 08.02.02.00 08.02.02.01 08.03.01.00 08.03.01.01 08.03.01.02 08.03.01.03 08.03.02.00 08.03.02.01 08.03.03.00 08.03.04.00

07/02/09 04/21/08 02/28/08 02/25/08 09/23/08 04/21/08 02/26/08 01/12/11 08/08/08 02/09/09 02/09/09 10/01/10 04/14/08 09/12/08 05/01/08 06/27/08

04/22I08 05/02/08 05/15/08 05/15/08 08/01/08 03/23/09 05/08/08 05/01/08 07/01/08 06/16/08 09/08/08

ApPrWed .. Approved Approved Approved Approved Approved Approved • Approved Approved Approved"rbved.r Not Approved proved Approved Not oveft-A-roved Approved

08.03.05.00

Approved Approved Approved Approved Not"Et uired Approved Approved Not Approved Not A roved Approved Not- .' 6rovelf

08.04.01.00 08.04.02.00 08.04.03.00 08.05.01.00 08.05.01.01 08.05.01.02 08.05.02.00 08.05.03.00 08.05.04.00 08.05.05.00 08.06.01.00

E Boiler Penthouse Handrail Labor Ad'u'stmenf- Reconcile Revision Control Logic Diagrams Milestone Change E Disturbance Fault Recorder (CR 0010) E Topcoat aint for Interior Steel E Topcoat paint for Interior Steel - Revision/Reconcile E Sloped Cooling Tower Basin C Additional Land and Associated Cost C Additional Land and Associated Cost Revision C AEPSC Budget Increase D AEPSC Delay C AEPSC Budget Increase C AEPSC Oct 2010 Revised Budget E Axle Fan Emergency Lube Oil System Change C Axle Fan Emergency Lube Oil System Change-Reconcile E Upgrade Aux Boller E Economizer Inlet Terminal Point Location Fly Ash/Bottom Ash Removal System Design Changes in Exchange for Coal E Handlin Enclosures and FARS Upgrades C B&W Erection Cost C B&W Pipe Material Escalation Alstom Generator Protection Cubicle Design Revision M Independent Monitor M Independent Monitor- Revision M Independent Monitor Budget Transfer M Independent Cost Review E Hydrostatic Test Pump E Redundant CEMS D DELAY-Temp North Access Road Improvement M Larger Service Building

04/08/08

Approved

08.06.02.00

D DELAY-B&W Equipment Unloading

06/13/08

Approved Approved Approved Approved Approved = Approved Approved Approved ApprovedAved Approved Approved

08.06.02.01 08.06.02.02 08.06.02.03 08.06.03.00 08.06.04.00 08.06.04.01 08.06.05.00 08.06.05.01 08.06.05.02 08.07.01.00 08.07.01.01 08.07.02.00

D D D D M C E E E D C E

12/01/08 07/02/09 07/31/09 06/23/08 06/11/08 09/16/08 08/06/08 10/19/09 12104109 07/31/08 02/10/11 08/07/08

DELAY-B&W Site Delay Costs DELAY-BWCC Equipment Unloading and pre FNTP Costs-Reconcile DELAY-BWCC Post FNTP Maintenance & Rehandle DELAY-Additional Storage Areas Altemative Site Investigation Alternative Site Investigation-RECONCILE Low Voltage Arc Resistance Switch ear Low Voltage Arc Resistance Switch ear REVISION Low Voltage Arc Resistance Switch ear CONTRACT REVISION Property Tax Increase Property Tax Increase Revision Transfer SDA HV & Atomizer Pit Cooling Design from Shaw to B&W

Approved

08.07.03.00

E AQCS 30% Operability & Maintainability

08/08/08

Approved ' Approved ,Approved

08.07.04.00 08.08.01.00 08.08.01.01

E Slur Agitator Monorails & Trolleys, PJFF Hopper nuclear level controls E Low Voltage Motor Control Centers E Low Volta e Motor Control Centers Revision

08/07/08 01/07/09 01/04/10

Approved

08.08.02.00

E Removal of Coal Sampling System

09/02/08

540

PUC Docket No. 40443 EXHIBIT CTB-16 Page 3 of 6

Status

_

PCR No.

"

Subject

Com olete

,Approved, ••

08.08.03.00

E Mercury Monitoring

04/06/09

Approved Approved

08.08.03.01 08.08.04.00

C Mercury Monitorin - Contract Reconcile E Redundant CEMS

roved,. Approved,

04/06/09

08.09.01.00 08.09.01.01

M Realized B&W FX Costs M Realized B&W FX Costs 2

09/12/08 11/11/08

Approved Approved

08.09.01.02 08.09.01.03

M Realized B&W FX Costs (3) M Realized B&W FX Costs (4)

02/27/09 12/04/09

08.09.01.04 08.09.01.05 08.09.02.00 08.09.03.00

M M L L

Realized B&W FX Costs (5) Realized B&W FX Costs (6) QA/QC Budget Rig in Guidelines

07/09/10 01/07/11 09/25/08 10/01/08

Approved . Approved Approved " ved `-Approved Approved

08.10.01.00 08.10.01.01 08.10.01.02 08.10.01.03 08.10.02.00 08.10.02.01

D D D D D D

DELAY-Alstom & Off Site Warehouse DELAY-Alstom & Off Site Warehouse-Transportation DELAY-Alstom & Off Site Warehouse-Transportation Revision DELAY-Alstom Equipment Transportation RECONCILE DELAY-Added Security/Fence DELAY - Added Security Fence Reconcile

12101/08 05/18/09 01/06/10 06/10/10 12/01/08 02/09/09

roved A5proved A roved•. --

08.10.03.00 08.10.04.00 08.11.01.00

E Rec cle Ash Silo Roof Modification L Third Party Crane Inspection E ASME B31.1 Code

10/23/08 11/19/08 11/11/08

Approved

08.11.02.00 08.11.03.00 08.11.03.01 08.11.04.00 08.11.04.01 08.12.01.00 08.12.01.01 08.12.01.02 08.12.02.00 08.12.02.01 08.12.02.02 08.12.03.00 08.12.03.01

M D D D D E E E D D D L L

11/25/08 12/01/08 01/05/09 12/01/08 01/05/09 06/01/09 08/20/09 12/21/09 12/17/08 03/30/09 09/28/09 01/16/09 02/27/09

' A roved Approved Approved Not: veeF

Approved Approved, Approved Approved . Not Approved -'Approved A-roved .-• Approved Approved Approved ' Approved Approved -

Builders Risk DELAY-12kV Temp. Power DELAY-12kV Temp. Power-RECONCILE DELAY-Tem Warehouse Shelving DELAY-Temp Warehouse Shelving - RECONCILE Lower Furnace Cable Openings Lower Furnace Cable Openings Lower Furnace Cable Openings Fixed/Markup Revision DELAY-B&W Warran Extensions DELAY-B&W Warranty Extensions DELAY-B&W Warran Extensions BWCC Crane Mats BWCC Crane Mats-Sales Tax

Approved

08.12.03.02

L BWCC Crane Mats Pile Protection

06/25/10

Approved •

08.12.03.03

C BWCC Crane Mats Pile Protection Reconcile

07/08/11

Approved

08.12.04.00

D DELAY-South Storm Water Detention Pond & Access Road Remediation

01/16/09

Approved Approved

09.01.01.00 09.01.01.01

C Shaw Steel Escalation C Shaw Steel Escalation Revision

01/16/09 09/20/10

Approved Approved Approved Approved Approved Not A raNedAS Not Approved At iyot A roved .,Approved, `

09.01.02.00 09.01.03.00 09.01.03.01 09.01.04.00 09.01.04.01 09.01.05.00 09.01.06.00 09.01.07.00 09.01.05.01

D D D D D C C C C

01/16/09 01/16/09 07/02/09 01/27/09 02/22/11 02/01/09 02/01/09 02/01/09 02/27/09

Approved

09.01.05.02

C Exhibit X Scope Transfer & Reconciliation

03/16/10

09.01.05.03 09.01.05.04 09.01.06.01 09.01.07.01 09.03.01.00 09.04.01.00 09.04.01.01 09.04.02.00 09.04.02.01 09.04.03.00 09.04.03.01 09.04.04.00 09.04.04.01

C C C C E D D L L D D E E

01/12/11 03/16/11 02/27/09 02/27/09 03131/09, 04/06/09 11/09/10 04/06/09 01/04/11 04/06/09 03/16/11 04/07/09 07/02/09

A roved Approved. _ Approved .. Approved • Approved ., Approved Approved A 7ovetl Approved A roved A roved Approved . "Approve'

DELAY-Shaw Extend Overhead & FNM DELAY-Air Permit Appeal Stay of Construction DELAY-Air Permit Appeal Stay of Construction-Reconcile DELAY-Upgrade Bridle Creek existing bridge DELAY-Upgrade Bridge Creek existing bridge RECONCILE Exhibit X Reconciliation Cl Budget Increases Cl Version 3 Escalation, Contingency Adjustment and Delay Budget Exhibit X Reconciliation Exhibit X #9PAC Reconciliation Exhibit X #9, PAC Reconciliation Revision Cl Budget Increases Cl Version 3 Escalation, Contingency Adjustment and Delay Budget Vibration Monitoring Wetland Delineation Delay Wetland Delineation Delay Revision Environmental Support of Off Site RR Work Environmental Support of Off Site RR Work Reconcile Delay Temp Warehouse Heating Delay Tem p Warehouse Heating Revision P92 Flux Core Arc Welding Toughness Testing P91 & P92 Materials Confirmatory Testing

541

PUC Docket No. 40443 EXHIBIT CTB-16 Page 4 of 6

Status Approved.

PCR No. 09.04.04.02

Subject E P91 & P92 Materials Confirmatory Testing Reconcile

Complete 02/25/11

Approved

09.04.05.00

M ADEQ Annual Emissions Fee

04/08/09

Not -' Cisred Approved_

09.05.01.00 09.05.02.00

O High Fidelity Simulator M B&W Transportation Escalation

07/01/09 06/01/09

Approved

09.05.02.01

M B&W Transportation Escalation (2)

12/21/09

A roved 'Approved Approved

09.05.02.02 09.05.02.03 09.05.02.04

M B&W Transportation Escalation ( 3) M B&W Transportation Escalation (4) M B&W Transportation Escalation (5)

08/26/10 02/01/11

- Approved

09.06.01.00

E

tVot.'/•1 roved

09.06.02.00

B&W l&C Change PJ air compressor & Lime Handling E-Stops for Compatibility w/ Shaw I&C E Ammonia Bulk Storage Tank Access

-Approved -

09.06.03.00

E Relocation of B&W 382 Valve

Approved

09.06.03.01

M Shaw 382 offset w/ Engineering

11/05/09

09.07.01.00

D B&W OEM Delay

08/01/09

i+1otA

-^':'

07/22/09 06/30/09 07/22/09

Approved

09.07.01.01

D B&W OEM Delay Revision

09/23/09

Aved Approved Approved Approved Approved Aroved

09.07.01.02 09.07.02.00 09.07.02.01 09.07.03.00 09.07.03.01 09.07.04.00

D D D E E L

12/21/09 08/13109 12/21/09 07/22/09 02/25/11 07/29/09.

Approved

09.07.04.01

L BWCC Windbox Hanging Revision

12/21/09

Approved A roved Not A- r4ved Approved Approved Approved

09.07.05.00 09.07.05.01 09.08.01.00 09.08.01.01 09.08.02.00 09.08.02.01 09.08.03.00

E Auxiliary Boiler FGR Upgrade Auxiliary Boiler FGR Upgrade Contract Revision D Delay-Shaw SubconVactor D Dela -Shaw Subcontractor Revision M Reroute Railroad Layout M Reroute Railroad Layout Reconcile D Delay-Shaw FNM & Site Indirect Escalation

08/12/09 09/09/10 10/27/09 04/29/10 08/05/09 11/01/10 08/13/09

04/29/10

Not Approved A roved

B&W OEM Delay RECONCILE BWCC Delay BWCC Delay RECONCILE Welded Radiograph Plugs in Lieu of Threaded Welded Radiograph Plugs in Lieu of Threaded Reconcile BWCC Windbox Hanin

09.08.03.01

D Delay-Shaw FNM & Site Indirect Escalation Revision

Approved' 'Approved Approved Approved Approved Approved Approved Approved Approved Approved Approved A roved • Approved

09.08.03.02 09.08.04.00 09.08.05.00 09.08.06.00 09.08.06.01 09.08.07.00 09.09.01.00 09.10.01.00 09.10.01.01 09.11.01.00 09.11.01.01 09.11.01.02 09.11.02.00

D D D E E D M E E C C C E

Approved

09.11.02.01

C Topcoat of Large Bore Boiler & AQCS Piping Supplied by B&W Reconcile

roved Approved A roved Approved Approved Approved Approved Approved

09.11.03.00 09.11.03.01 09.11:04.00 09.11.04.01 09.11.05.00 09.11.05.01 09.11.05.02 10.01.01.00

D D E C L L L E

Approved

10.01.02.00

E Radiography of BWCC Boiler Pressure Part Field Welds

02/15/10

Approved Approved Approved Approved Approved Approved Approved Approved .

10.01.03.00 10.01.03.01 10.01.04.00 10.01.04.01 10.01.04.02 10.01.05.00 10.01.05.01 10.02.01.00

E M E E E E M D

Fire Protection Cross Tie Off Set Soot Blower Steam Cross Tie with FP Cross Tie DCS Alarm Rationalization DCS Alarm Rationalization Revision DCS Alarm Rationalization Revision Additional CT's on CHAT Additional CT's on CHAT Reconcile Delay - SWPPP Cost

01/25/10 01/29/10 03/01/10 04/19/10 09/07/10 02/15/10 06/16/10 02/10/10

Delay-Shaw FNM & Site Indirect Escalation Settlement Delay-Site Security Delay-Shaw Extended Warranty B&W Auma Drives Upgrades B&W Auma Drives Upgrades Labor Revision Delay-Shaw TFA's AEPSC-Proect Management Addition of 138kV Circuit Breaker Addition of 138kV Circuit Breaker Revision AEP Legal Budget Increase AEP Legal Budget Increase Revision AEP Legal Budget Increase Revision Topcoat of Large Bore Boiler & AQCS Piping Supplied b y B&W

Off Site RR Wetland Delineation Delay Off Site RR Wetland Delineation Delay Reconcile Transformer Storage Pad [Transformer Storage Pad Reconcile Additional Office Trailer Additional Office Trailer - Safety Staff Additional Office Trailer - New Safety Staff Soot Blower Steam Cross Tie

10/21/10 08/18/09 09/14/09 09/21/09 09/22/09 09/15/09 09/22/09 11/23/09 01/12/11 12/17I09 10/27/10 05/19/11 01/05/10 07/08/11 11/23/09 11/01/10 02/15/10 07/08/11 12/09/09 02/10/10 03/23/10 01/26/10

542

PUC Docket No. 40443 EXHIBIT CTB-16 Page 5 of 6

Subiect

Complete

Status

PCR No.

Approved -

10.02.02.00

L Switchyard Alternate Entrance

02/10/10

Approved

10.02.03.00

D DELAY - Shaw Double Handling

03124/10

Approved Approved

10.02.04.00 10.02.04.01

M Utili - Gas Line Relocation Support M Utility - Gas Line Relocation Support Reconcile

02110/10 05/31/11

Approved Aproved

10.02.05.00 10.02.05.01

M Shaw Wiring of AEP Construction Office M Shaw Wiring of AEP Construction Office Reconcile

02/10/10 01/04/11

Approved Approved Approved

10.02.06.00 10.02.06.01 10.02.07.00

M Dff Site RR - Mulch Utility Corridor M Off Site RR - Mulch Utility Corridor Reconcile D DELAY-34.5Kv Underground Feeder

02110/10 07/18/11 02/10/10

Aroved

10.02.07.01

D DELAY-34.5Kv Underground Feeder Revision

03/16/11

Approved Approved Approved Approved .

10.02.08.00 10.02.08.01 10.02.09.00 10.02.09.01

L L L L

A' roved..

10.02.10.00

D Alstom Mana ement Delay

02/15/10

Approved ° .,A roved

10.02.10.01 10.02.11.00

D Alstom Management Delay Reconcile E Normalize & Temper of CSEF Weldolet & Swee let Connections

06/10/10 02/24/10

Approved

10.02.11.01

E Normalize & Temper of CSEF Weldolet & Sweepolet Connections Revision

02/25/11

Plant Personnel Trailer Plant Personnel Trailer Revision BWCC Tower Crane Pad BWCC Tower Crane Pad Reconcile

03/12/10 09/07/10 02/17/10 06/10/10

loved

10.03.01.00

L River Water Intake Area Wash Out

03/29/10

-A --roved•

10.03.01.01

L River Water Intake Area Wash Out Reconcile

03/16/11

Approved

10.03.02.00

C Shaw LD/BWCC Acceleration

04/12/10

wroved

10.03.03.00

C Inspection of Alstom Stator

04/06/10

Approved

10.03.03.01

M Inspection of Alstom Stator Reconcile

01/04/11

A-roved

10.04.01.00

D Delay-Shaw Extended Home Office Staffing Impacts

04/29/10

Approved Approved

10.04.01.01 10.05.01.00

D Delay-Shaw Extended Home Office Staffing Impacts Settlement M BWCC Constructive Acceleration

10/21/10 06/17/10

Approved

10.05.01.01

M BWCC Constructive Acceleration Revision

07/23/10

roved . roved 'Approved Approved

10.05.01.02 10.06.01.00 10.06.01.01 10.06.02.00

M L L E

BWCC Constructive Acceleration Revision Alslom Bearing Pedestal Alstom Bearing Pedestal Reconcile Pulverizer Start Warning System Addition

04/18/11 06/18/10 06/01/11 08/26/10

Approved,

10.06.02.01

E Pulverizer Start Warning System Addition Revision

09/26/11

Approved Approved

10.06.03.00 10.06.03.01

E B&W AQCS Tank Inspection Changes E B&W AQCS Tank Inspection Changes Revision

08/04/10 08/26/10

Npt A_oved',

10.08.01.00

E Aux Boiler NOx CEMS Equipment Addition

08/31/11

Approved NotA ued Approved ' Approved-

10.08.02.00 10.08.03.00 10.08.04.00 10.08.05.00

CO Detection AEP Designer at Site For Start Up Commissioning L Lube Oil System for Howden Fans E AQCS Mix Slurry Tanks Exhausts Reroute

12/01/10 08/09/10 08/10/10

Approved

10.08.05.01

E AQCS Mix Slur Tanks Exhausts Reroute Revision

12/01/10

Aproved

10.08.05.02

M AQCS Mix Slurry Tanks Exhausts Reroute Reconcile

01/04/11

B&W Grating Penetrations

10/25/10

Nuclear Instrument Sources Shipment Delay Nuclear Instrument Sources Shi ment Delay Reconcile Low Fidelity Simulator Deletion Wetland Mapping Wetland Mapping Reconcile Landfill Redesign and Permit Delay Landfill Redesign and Permit Delay Revision B&W Insulation & Lagging Revision Corps 404 Permit Suspension O&M Bud t Increase O&M Budget Increase Revision O&M Budget Increase Revision AEP Construction Management Equipment Fuel and Maintenance

10/01/10 01/04/11 09/13/10 12/10/10 05/31/11 11/08/10 09/07/11 11/05/10 11/09/10 02/10/11 03/09/11 04/28/11 01/24/11

Approved .

10.09.01.00

Approved Approved Approved A roved Approved Approved Approved Approved A roved Not FS ' " ed ` Approved : Approved, Approved

10.09.02.00 10.09.02.01 10.09.03.00 10.10.01.00 10.10.01.01 10.11.01.00 10.11.01.01 10.11.02.00 10.11.03.00 11.01.01.00 11.01.01.01 11.01.01.02 11.01.02.00

D D E C C M M M M M M M L

Approved

11.01.03.00

L Landfill Synthetic Liner Addition

A rovedApproved Approved Approved Approved

11.01.03.01 11.02.01.00 11.02.02.00 11.02.03.00 11.03.01.00

L M M E E

Landfill Synthetic Liner Addition Revision Raw Water Alternate Source Sales & Use Tax Coal Yard Protective Layer Sodium Bi-Sulfate Injection

01/31/11 09/07/11 02/15/11 02/10/11 06/23/11 04/01/11

543

PUC Docket No. 40443 EXHIBIT CTB-16

Page 6 of 6

Subject

Complete

Status Approved proved

PCR No. 11.03.01.01 11.04.01.00

E Sodium Bi-Sulfate Injection M Auxiliary Boiler Change

04/06/11

Approved

11.04.02.00

C B&W TFA Budget Increase

04/06/11

Approved . Approved Approved roved Approved -

11.04.03.00 11.04.04.00 11.04.04.01 11.05.01.00 11.05.02.00

E C C E C

Approved. Approved

11.05.03.00 11.05.04.00

C Shaw Exhibit T E PFOO

05/31/11 05/27/11

roved Approved

11.05.05.00 11.06.01.00

06/01/11 06/09/11

Approved

11.06.01.01

M- roved

11.06.02.00

L Contractor Resource Sharing C CI Version 4 Escalation, Contingency Adjustment and Delay Bud et CI Version 4 Escalation, Contingency Adjustment and Delay Budget C Reconcile C Start U Fuel & Sorbents

Approved

11.07.01.00

L Field Paintin OEM Equipment

07/18/11

Approved'

11.07.02.00

L Rota

Approved

11.07.03.00

E Active Coal Pile Waiting System

Awroved' Approved Approved Approved . Approved Approved Approved Approved 'Approved A roved Approved, Approved Approved 'Approved Approved Approved Approved Approved A.roved Approved. Approved Approved Approved

11.07.04.00 11.07.05.00 11.07.06.00 11.07.07.00 11.07.08.00 11.08.01.00 11.08.02.00 11.08.03.00 11.08.04.00 11.08.05.00 11.09.01.00 11.09.02.00 11.09.03.00 11.09.04.00 11.09.05.00 11.11.01.00 11.12.01.00 12.01.01.00 12.01.02.00 12.01.03.00 12.02.01.00 12.03.01.00 12.03.02.00

C E E E E E E E M L L E

Approved

12.03.03.00

C Exhibit T-Fuel Escalation

04/04/12

Approved ^^ roved

12.03.04.00 12.03.05.00

M Productivity Stud M Shaw Acceleration

04/04/12 05/10/12

E C E 0 E M E L 0

Dust Emission Modification Alstom TFA Support Alstom TFA Support Revision Alstom Generator Synch open loop control in the TCS US Custom Tariff

Car Unloader Change Condition

Backchar e Hydraulic Cabinet pads*, Howdan TFA Delay Modifications to Coal Pile Run-off Pond Radio Equipment Building Installation Admin Bldg Alternate Feed Revision to B&W Instrument Installation Drawings Natural Gas Emergency Shut Off Coal Yard Survey Control Monuments & Reference Points L ic.Chan e Requests Settlement Leachate Pond Differing Site Conditons Structural Steel Rework for Material Staging Ba house Bag Leak Detection System Addition Mercury Stud Plant PI Historian B&W Target Price Stator Cooler Make-up River Temperature Monitoring Buoys NH4 PHA Resolution Boiler Hydrostatic Testing Environmental Permit Settlement II Control Logic for NPDES Pond Management Hope Warehouse Concrete Repair Entrainment Testing

06/01/11 05/06/11 10/28/11 05/31/11 05/31/11

08/02111 07/11/11 07/18/11

07118/11 07/18/11 08/19/11 08/09/11 08/16/11 08/02/11 09/27/11 08/19/11 08/30/11 09/26/11 09/02/11 09/22/11 10103/11 10/14/11 10/03/11 11/17/11 12/16/11 12716/11 02109/12 02/08/12 02115/12 02108/12 04/04/12 04/04/12

544

PUC Docket No. 40443 EXHIBIT CTB-17 Page 1 of 2

The original Turk cost estimate was developed in four phases: Project Design Basis, Conceptual Estimate, Scope and Estimate Refinement, and Final Proposal development. The first three phases ran somewhat concurrently because the deliverables, scope of work and estimate were further refined and detailed as the process progressed. Project Design Basis-The first step of the Project Design Basis phase was the hiring of an architect-engineering firm, Sargent & Lundy, having substantial and recent experience in the design and construction of a pulverized coal facility. AEP Engineering and Sargent & Lundy together defined a Design Basis using the December 2005 Request for Proposals that SWEPCO had issued to obtain power resources, as SWEPCO witness Brice discusses in his testimony. This Design Basis was the start of developing the scope of work. The scope of work included initial design documents - general arrangements, flow diagrams and one-line diagrams, and draft engineered equipment specifications. Conceptual Estimate-The second phase, Conceptual Estimate, utilized the information from the project Design Basis phase, and AEP's and Sargent & Lundy's

experiences on prior projects. A Work Breakdown Structure was established to ensure all • the scope of work was accounted for and then estimated. The conceptual estimate was a detailed estimate in that it was built system by system "bottom up" based on commodity quantities and unit prices, labor productivity and hourly crew wage rates, and an equipment list. During this phase, vendors were solicited for a"furnish and erect" price for the major pieces of equipment and work.

This solicitation process resulted in

obtaining firm prices for the supply and erection ' of the steam generator, turbine, and AQCS.

545

PUC Docket No. 40443 EXHIBIT CTB-17 Page 2 of 2

Scope .and Estimate Refinement-The third phase, Scope and Estimate Refinement, was the evaluation, refinement, and check of the scope of work and estimate. This involved introducing a third-party General Work Contractor (GWC) with international experience in constructing similar projects to confirm that the aggregate was reasonable for the project. The GWC, who also involved specialty contractors, reviewed the scope of work and estimate and compared it to recent similar projects it had been involved with. During this process, AEP and Sargent & Lundy discussed and reconciled the differences to ensure the scope of work was complete and all costs were accounted for. Final Proposal-The final phase in developing the proposal estimate was escalating the costs and performing a risk analysis of the proposal to calculate a cost at commercial operation for the proposed power plant. The estimate input was based on 2005 costs with escalation factors applied to the monthly cost projections that Sargent & Lundy developed based on past similar projects. The contingency was developed through probability analyses of 45 major risk areas within the estimate. A group of experienced personnel reviewed the results of the analysis to gauge the confidence level of the estimated cost for the area. Then a composite analysis was performed to determine the figure that was used.

546

PUC Docket'No. 40443 EXHIBIT CTB-18

%ili,lLrRItA^41^ FiftT^^iC P^D11lt'E^t ,

^n8;t'^r ^1^Ciitp t^aY7cr:• •;s^e xs,

.

1.ti't,em

,

t4plk ^ t^C^1f1t&;ti^p -

June^ ^:5, 2p1,9

^es%+tath^c^

Mr. Carl Monroe, Executive Vice President and Chief Operating Officer

Southwest Power Pool, Inc. 415 North McKinley, tf 140 Plaza West Little Rock, AR 72205-3020

Mr. Michael Heycck Sr. Vice President, Transmission American Electric Power Service Corporation 700 Morrison Road Gahanna, OH 43230 Re:

J. Limar Stall Generating Facility Notice of Commercial Operation Date

Messrs. Monroe and Heyeck: On June 15, 2010, Southwestern Electric Power Company has completed the Trial Operation of the J. Lamar Stall Unit 6A, 6B, and 6S at Arsenal Hill Power Station covered by the Intcrconnection Agreement (SPP Service Agreement #. 1898) dated December 30, 2009. This letter will provide notice consistent with Appendix E of said Agreement, that Southwestern Electric Power Company commenced commercial operation of J. Lamar Stall Unit 6A, 63, and 6S at the Arsenal. Hill Power Station, effective as of June 16.20 10.

Thank you"i, Sincerely,

Mark C. McCullough Sr. Vice President, Fossil & Hydro Generation American Electric Power Service Corporation 155 West Nationwide Boulevard

Columbus, 01-1 43215

547

PUC Docket No. 40443 0 6fi)CH % CTB-19 gelof6

AM ERICANS

^^^WRIC

P-OWEN Date:

October 6, 2008

Subject:

SWEPCO John W. Turk Jr. Power Plant Project Change Request-for additional provision of all Low Voltage Motor'Control Centers (MCCs) to' have remote racking capability.

From:

M. D. Fry

To:

(}^J^ I c,l ^ ^p^ 1. J. L. Hettingerv A

z. D. A. Bauer

IC7 [^`^1 Ub/ 16 1.241 &, uvr

4. NUd 5. J. G. DeRuntz 6. J. A. Kobyra -4osc /1Z^S^vvB 7. M. Jasper jr►^V'^ . 6 t G^8 8,: M. J. Finissi ' , 9. W. L. Sigmon Jr.:^ 10'. D. A. Bauer/M. D. Fry ^ 11.A. W. Rentzsch

y--?hi^ t,a1 ov /Z ^/ / ^,1^ ^ w, ^JL ^1R ^y[o^i f^ wo,b.=-i 15 5^xl^vrv^ra^ C.a^v 2^+^O 'F^ V^ ^3.DMuelman ppP^N•at

r.*k At ^(^Goarr^k^+^/^^f f,s^,,.L t i/7 J01

A Project Change Request (PCR) is attached describing the basis for the additional requirement for all of the Low Voltage (LV) MCCS to include remote racking capability for removing starter buckets. The AEP Safety and Health Generation Department will issue a new corporate policy, in the near future, that will require that a MCC be de-energized in order to. remove a MCC bucket. This policy is being impierriented as a means to mitigate potential hazards to personnel in terms of electrical arc-flash events by not allowing personnel to withdraw a MCC bucket from the main bus while energized. This policy is placing safety at the forefront. However, removing a MCC from service, in most instances, will mean that the unit will experience a curtailment or perhaps even an outage. A new product line has recently come into production, from an approved supplier of MCCs, that provides remote racking capability. This would allow removal of a MCC bucket while energized. without requiring personnel to be inside the flash boundary. By specifying the remote racking capability In the MCCs for Turk Plant we can improve safety and unit availability, simultaneously. For existing plants ESEE has been installing arc-flash safety switches on the feeder breaker for each MCC. This temporarily changes the breaker settings to incorporate instantaneous protection in order to limit the incident energy at the respective MCC. This is done, however, at the expense of protection coordination and therefore carries. some risk to the unit. 11

548

PUC Docket No. 40443 EXHIBIT CTB-19 Page 2 of 6

And, while providing protection to personnel by lowering the Incident energy, they, are still in harms way in the fact that personnel is required to be in front of the MCC to remove the bucket. The cost for the installation of the arc-flash safety switches has been approximately $1;000,000 per plant, Standard Operating Procedure, SOP-730.12, "Standard Operating Procedure Personnel Safety Design Configuration Requirements"' discusses the goal and objective for the engineering and design of new facilities to, minimize the routine use of Personal Protective Equipment (PPE) of all kinds. The use of MCCs with remote racking capability is in line with this objective.

^ The LV MCCs have not yet been specified for the Turk Project, so; this request istimely. NGDE is requesting a change in the project work scope and the tcan'sfer of funds from contingency in the amount of $1,200,000. A Project Change Request (PCR) is attached to describe the basis for the addition of remote racking capability, for all LV MCCs.

{

If you are in agreement. with this request, please sign. the attached PCR and forward it as indicated. Regards,

Monte Fry NGDE

^

549

PUC Docket No. 40443 EXHIBIT CTB-19 Page 3 of 6

PROJECT CHANGE REQUEST (PCR)

PCR NO. 08-08-01

PROJECT NO.

1.137$

PLANT

John W.. Turk, Jr. Power Plant

PROJECT TITLE

Turk PC Unit 1

PCR SUBJECT

for LV MCCs

DATE. 10-06-08

Remote racking capability

0

REVISION NO.

1. DESCRIPTION OF CHANGE AND BACKGROUND INFORMATION The AER Safety, and Health Generation Department will issue a new corporate policy, in the near future, that will require that a MCC be de-energized in order to remove a MCC bucket. This policy is being implemented as a means to mitigate potential hazards to personnel in terms of electrica.J, arc-flash events by not allowing, personnel to withdraw a MCC bucket from the bus while energized. This policy places safety at the forefront. However; removing a MCC from service, in most instances, will mean a unit curtailment o'r,pe"rhaps even an outage. A new product line. has recently, come into production, from an approved supplier of MCCs, that provides remote racking capability. This would allow removal :of a MCC bucket while energized and provide a means for personnel to be outside.of the flash boundary. By specifying remote racking capability for the MCCs'at Turk we can improve safety and unit availability, simultaneously. SOURCE OF CHANGE

2.I DESIGNATED CHANGE X1 Scope of Wo.rk

Vendor Related Modification

Scope of Services (by others)

1. . _. 3.

X

Schedule

Construction Related Modification

Other

Qther

SUMMARYESTIMATES Material Cost Change $

ui pment Cost Changes$ •Eq_ Description of Schedule Impact

rt M Work. Hours (all Disciplines) 1r

_

Labor Cost Change $_

ti^ 1

Work Hours (all Disciplines)

^y

^

Total Cost Chan ge $ 1,200OOO

1,200,000

^"L9'°$

No anticipated schedule impact.--

- ...._____

4.

Engineering/Design Related Modification

..._....^

^.^..^_.

...

..^... „ .

_

...._._ ._.^... ..

DESCRIPTION OF ACTIONS REQUIRED & DOCUMENTS AFFECTED

The scope change for LV arc-resistant switchgear inciudes: 1: LV MCCs with remote racking capability for all MCCs. This document contains information confidential and proprietary to AEPSC. It shall not be reproduced in whole or in part or released to any third party without the expressed written consent of AEPSC..

Page 1 of-4

550

PUC Docket No. 40443 EXHIBIT CTB-19 Page 4 of 6

PROJECT CHANGE REQUEST (PCR)

i

r

This document contains information confidential and proprietary to AEPSC. It shall not be reproduced in whole or in part or released to any third party without the expressed written consent of AEPSC.

Page 2 of 4

551

PUC Docket No. 40443 EXHIBIT CTB-19 Page 5 of 6 a`>

m m r

o U)

w

0

0

a w

F-

F-

X

^

0)

w

411

0

0

0

O

O

O

7

Z

O

0

w

2 U. F-

r

N

fA

49

SID.

{q . f9

J

L)

V

0

J

V' 0

J

O

fl^

a

m CO

m CO

^ W 0.

C

_

U N

L W

aa 2! o

w «g

Va

vs

vt

^sr es

c ^

V ^ O

F

.0) n c ., c o ^ u

.^

g

c.i 3 Na c N w w Q ff

v, ED 7 N

'

^

2 X

J3 W J

tA

N?

v . )^

CL

I

.S w



1

fsa

%

rn

OLO

tt^

L9

Q

a

W

p F

to

u> 4&

a?_+ v m.^ a

Q

U),

p H

m

m

CO

N

vs

y

C T O C

c10 oy N w

C y .

^

0 Q

^. ._ j

S c o •c m .. ^ Q Cu

N

,(D

c O y

L .

0 O ^O 3

Qf°

552

PUC Docket No. 40443 EXHIBIT CTB-19

Page 6 of 6

PROJECT CHANGE REQUEST-(PCR) ._.^.. . . _ ..__^,^.... ..__ , .

.... _,.

^,. .,. -^_. ...._._

. _ ,. ._

-,

'(PREPARE SEPARATE ESTIMATE SHEET IF SPACE BELOW INSUFFICIENT) ENGINEERING & SERVICES COST CHANGE: LIST DOCUMENTS IMPACTED ON SEPARATE SHEET DESCRIPTION

WORK HOURS

AREA

DEPT./CONTRACT NO.

COST

SERVICES _

{

r

ORIGINATOR

-- -. . ...

a

.

.

f

_. ^,_

.

i^.. .. _.....^._ 3.

,

,

DATE

Monte D. F^

TOTAL

EXPENSES ..

-

.

._. . .__ _ ^

October 6, 2008

APPROVALS PROJECT MANAGER

._

NEW GENERATION DESIGN MANAGER

.

PROJECT ENGINEER

r,.

_

DATE ^_^.. .__.^ ..^--_

.. .. _.

DATE

.._ . _

.

.

DATE

PROJECT DIRECTOR

DATE

SENIOR VP ENG. P&FS

,.

_

..- ^ . ^

- .- ._ ,

DATE

SITE MANAGER

VP NEW.GENERATIO

^.

---^Z9

DATE ATE

. /

o q. .

._. _.._^_^.

This documerit contains inf.ormatlon confidential and proprietary to.AEPSC. It shall not be reproduced in whole or in part or released to any third party without the expressed written consent of AEPSC.

. . .

Page 4 of 4

553

EXECUTIVE SUMMARY OF JOHN C. HENDRICKS John C. Hendricks is the Director - Air Quality Services in the Environmental Services Division of American Electric Power Service Corporation.

Mr. Hendricks's responsibilities

include overseeing all air permitting and compliance activities for the American Electric Power generation fleet. In addition, he provides guidance to other AEP business units on upcoming and current air regulatory initiatives.

Mr. Hendricks's testimony: describes the acquisition of the environmental permits for the Turk Plant; discusses the environmental regulations that will result in Southwestern Electric Power Company being required to procure air emission allowances to support the operation of its generating units; describes the Environmental, Safety and Health areas of the Environmental, Safety, Health, and Facilities organization of AEPSC and the necessary services they provide to SWEPCO; and demonstrates the reasonableness and benefit of the affiliate costs charged to SWEPCO for these services.

Mr. Hendricks confirms that SWEPCO has received the environmental permits and licenses needed to construct the Turk Plant. He notes that one operational permit - an industrial storm water discharge permit from the Arkansas Department of Environmental Quality (ADEQ) - needs to be received prior to the commercial operation of Turk. The application for this permit is anticipated to be submitted in the third quarter of 2012. Mr. Hendricks also details the history and current status of SWEPCO's Air Permit application with the ADEQ.

He explains that unexpected permitting issues with the Air Permit

impacted Turk's construction schedule.

He concludes that while the permitting issues were not

reasonably foreseeable, SWEPCO proactively and prudently planned and managed the permit and appeal process to minimize impacts to both the schedule and costs by working with the appropriate agencies and using in-house and external expertise to remediate the permitting issues as quickly as

1

554

possible. Mr. Hendricks also states that SWEPCO prudently planned and managed the Corps of Engineers permitting process, despite a delay that arose during the processing of the COE Section 10/404 Permit. Mr. Hendricks also describes the Clean Air Interstate Rule, Cross State Air Pollution Rule, and Mercury and Air Toxics Standards Rule, which are the primary environmental drivers that will result in the need for SWEPCO to procure air emission allowances and the increased use of consumables associated with the operations of air pollution control devices in the future. Mr. Hendricks notes that SWEPCO is requesting that the costs and revenues from these allowances be considered eligible fuel costs on a prospective basis.

In addition, Mr. Hendricks describes the' services provided to SWEPCO by groups in the Environmental, Safety and Health organization of AEPSC. He provides descriptions of each group's responsibilities, including specific services provided to SWEPCO during the test year by the

Environmental Services and Safety & Health groups. During the test year, SWEPCO was charged $3,931,513 for services performed by AEPSC's Environmental, Safety and Health organization.

To support the reasonableness of these charges,

Mr. Hendricks presents evidence detailing historical cost trends; process improvements aimed at achieving efficiency; staffing trends; outsourcing activities; proof of benefits to SWEPCO; and non-duplication of services between SWEPCO and the AEPSC Environmental, Safety and Health organization. Taken as a whole, Mr. Hendricks's testimony demonstrates the reasonableness and necessity of the Environmental, Safety and Health affiliate charges.

2

555

PUC DOCKET NO. 40443 PUBLIC UTILITY COMMISSION OF TEXAS

APPLICATION OF SOUTHWESTERN ELECTRIC POWER COMPANY FOR AUTHORITY TO CHANGE RATES AND. RECONCILE FUEL COSTS

DIRECT TESTIMONY OF JOHN C. HENDRICKS FOR SOUTHWESTERN ELECTRIC POWER COMPANY

JULY 27, 2012

PUC DOCKET NO. 40443

DIRECT TESTIMONY JOHN C. HENDRICKS

556

TESTIMONY INDEX SUBJECT

PAGE

I.

INTRODUCTION ...................................................................................................... 3

II.

PURPOSE OF TESTIMONY .................................................................................... 5

III. IV.

OVERVIEW OF ENVIRONMENTAL PERMITS AND LICENSES FOR TURK . ................................................................:.......................... 6 ADEQ AIR PERMIT ................................................................................................. 6

V.

TURK AIR PERMIT AND AUXILIARY BOILER ............................................... 14

VI.

CORPS OF ENGINEERS STREAMS AND WETLANDS (SECTION 10/404) PERMIT ... ...............:...............................................................15

VII.

ENVIRONMENTAL REGULATIONS AND EMISSION ALLOWANCES/CONSUMABLES ....................:..................................................19

VIII.

ENVIRONMENTAL, SAFETY AND HEALTH AFFILIATE CHARGES .......... 23 A. Organization Of Environmental, Safety, Health and Facilities ......................... 23 B. Environmental, Safety, Health and Facilities Services ...................................... 29 C. Reasonableness of SWEPCO Affiliate Charges ................................................ 33

IX.

SUMMARY AND CONCLUSION ........................................................................ 41

EXHIBITS EXHIBIT

DESCRIPTION

EXHIBIT JCH-1

Components of Turk Air Permit

PUC DOCKET NO. 40443

2

DIRECT TESTIMONY JOHN C. HENDRICKS

557

1 2

I. INTRODUCTION Q.

3 4

PLEASE STATE YOUR NAME, BUSINESS ADDRESS AND POSITION IN THE COMPANY.

A.

My name is John C. Hendricks. I am Director - Air Quality Services in the

5

Environmental Services Division of American Electric Power Service Corporation

6

(AEPSC), whose address is 1 Riverside Plaza, Columbus, Ohio. AEPSC provides

7

engineering, financing, accounting, and similar planning and advisory services to the

8

subsidiaries of the American Electric Power System- (AEP), one of which is

9

Southwestern Electric Power Company (SWEPCO).

10

Q.

11 12

PLEASE PROVIDE A REVIEW OF YOUR EDUCATIONAL AND PROFESSIONAL BACKGROUND.

A.

I received a Bachelor of Science degree in 1975 in Chemistry and a Master of Science

13

degree in 1978 in Water Resources Management from the University of Wisconsin.

14

My professional experience includes 31 years with AEP. I began my career as a

15

laboratory chemist in •1979 with responsibilities for designing and performing

16

environmental studies to address issues related to wastewater discharge, solid and

17

hazardous waste management, and polychlorinated biphenyls (PCB) remediation. I

18

then held various staff positions within AEPSC's Environmental Services Division

19

with responsibilities for wastewater permitting, solid and hazardous

20

management,

21

development.

22

Environmental Manager with responsibilities for AEPSC's two natural,gas pipeline

23

companies, its river transportation company and its two coal companies. I became

PUC DOCKET NO. 40443

waste

PCB and PCB remediation projects, and federal regulatory Subsequently in 2002, I was promoted to the position of

3

DIRECT TESTIMONY JOHN C. HENDRICKS

558

1

Manager of the New Generation Environmental Licensing section in 2004. I was

2

appointed to my current position in 2010.

3

Q.

WHAT ARE YOUR RESPONSIBILITIES IN YOUR CURRENT JOB POSITION?

4

A.

My current responsibilities include overseeing all air permitting and compliance

5

activities for the AEP generation fleet.

6

include providing guidance to other AEP business units on upcoming and current air

7,

regulatory initiatives.

8

Q.

9

HAVE YOU PREVIOUSLY SUBMITTED TESTIMONY BEFORE THE PUBLIC UTILITY COMMISSION OF. TEXAS (PUC OR COMMISSION) OR ANY

10 11

Additionally, I have responsibilities that

REGULATORY COMMISSION? A.

Yes. I have testified on behalf of SWEPCO before the PUC in Docket No. 33891,

12

which was the Turk Power Plant (Turk) certificate of convenience and necessity

13

(CCN) case, and the Arkansas Public Service Commission (APSC) in Docket

14

No. 06-154-U, the case in which SWEPCO received a certificate of environmental

15

compatibility and public need for Turk. I have also submitted testimony before the

16

PUC in Docket No. 37364, the case in which SWEPCO most recently requested an

17

adjustment to its base rates in Texas and in Docket No. 39708 in which SWEPCO

18

requested construction work in progress for Turk.

PUC DOCKET NO. 40443

4

DIRECT TESTIMONY JOHN C. HENDRICKS

559

I

II. PURPOSE OF TESTIMONY

2

Q.

WHAT IS THE PURPOSE OF YOUR TESTIMONY IN THIS PROCEEDING?

3

A.'

The purpose of my testimony is to describe the acquisition of the environmental

4

permits for the Turk Plant, and how SWEPCO prudently planned and managed the

5

Turk permitting process.

6

I also discuss the environmental regulations that will result in SWEPCO being

7

required to procure air emission allowances to support the operation of its generating

8

units, to support the Company's request that allowances to be considered as eligible

9

fuel expenses prospectively.

10

I will also describe the Environmental, Safety and -Health areas of the

11

Environmental, Safety, Health, and Facilities organization of AEPSC and the

12

necessary services they provide to SWEPCO.

13

reasonableness and benefit of the test year amount of affiliate charges to SWEPCO

14

for these services through discussion of the historical cost trends for providing these

15

services to SWEPCO, process improvements aimed at efficiency, staffing trends, use

16

of outsourcing, and a description of how the services Environmental, Safety and

17

Health provides are not duplicative of any that SWEPCO currently provides for itself.

18

Q.

19 20

I will also demonstrate the

ARE YOU SUPPORTING THE COSTS FOR THE,ENTIRE ENVIRONMENTAL, SAFETY, HEALTH, AND FACILITIES ORGANIZATION?

A.

No. SWEPCO witness Jeffrey Parlet is supporting the Real Estate and Workplace

21

Services , group.

22

Services groups.

PUC DOCKET NO. 40443

My testimony only covers the Environmental, Safety & Health

5

DIRECT TESTIMONY JOHN C. HENDRICKS

560

1

Q.

2 3

WHAT WAS YOUR INVOLVEMENT IN THE TURK PERMITTING ACTIVITIES?

A.

-

Prior to my current position, I was manager of the New Generation Environmental

4

Licensing section. In that role, I was responsible for obtaining all the necessary

5

environmental permits and licenses for the Turk facility.

6 7. 8

111. OVERVIEW OF ENVIRONMENTAL PERMITS AND LICENSES FOR TURK Q.

9 10

TURK? A.

11

12

Yes, SWEPCO has received the environmental permits and licenses needed to construct Turk.

Q.

13 14

HAS SWEPCO RECEIVED ALL PERMITS TO CONSTRUCT AND COMPLETE

ARE THERE OTHER ENVIRONMENTAL PERMITS OR LICENSES NECESSARY TO OPERATE TURK?

A.

Only one operational permit needs to be received prior to the commercial operation of

15

Turk. An industrial storm water discharge permit from the Arkansas Department of

16

Environmental Quality (ADEQ) is required. The application for this permit is

17

anticipated to be submitted in the third quarter of 2012.

18 19

IV. ADEO AIR PERMIT •

20

Q.

21 22 23

Q .

PLEASE BRIEFLY DESCRIBE THE NATURE AND SCOPE OF THE AIR PERMIT.

A.

State agencies such as the ADEQ are charged with implementing federal and state air quality laws and regulations through their own environmental permitting procedures.

PUC DOCKET NO. 40443

6

DIRECT TESTIMONY JOHN C. HENDRICKS

561

1

Four basic air permits pertain to the Turk Plant: a state construction permit (Permit-

2

to-Install or PTI); a Prevention of Significant Deterioration (PSD) or PSD permit; a

3

Clean Air Act Title V Operating permit; and an Acid Rain Program permit. Each of

4

these permits is described in EXHIBIT JCH-1. The ADEQ has authority to issue all

5

four of these permits and combine them into one overall permit, which I refer to as

6

the Air Permit.

7

Construction of the emission units at Turk was not allowed to start until the

8

Air Permit had been received from the ADEQ.

9

allowable emission rates, applicable emission controls, - and any operational

10

constraints necessary to protect the ambient air quality for each significant plant

11

emission point. Detailed air modeling was performed and included in the Air Permit

12

application to demonstrate that the proposed plant's emissions would not exceed any

13

applicable air quality standard.

14

Q.

15

The ADEQ permit specified

WHEN DID SWEPCO FIRST FILE ITS AIR PERMIT APPLICATION AT THE ADEQ?

16

A.

SWEPCO filed its Air Permit application on August 9, 2006.

17

Q.

WHAT IS THE STATUS OF THE AIR PERMIT TODAY?

'18

A.

The ADEQ issued the Air Permit on November 5, 2008. The Air Permit was

19

'contested both administratively and in court by several parties, but the last of these

20

appeals was withdrawn after a settlement was reached in December 2011 as

21

SWEPCO witness Venita McCellon-Allen discusses in more detail in her testimony.

22

The Air Permit is final and in effect.

PUC DOCKET NO. 40443

7

DIRECT TESTIMONY JOHN C. HENDRICKS

562

1

Q.

2 3

HOW MUCH TIME DID SWEPCO INCORPORATE INTO THE INITIAL PROJECT SCHEDULE FOR PROCESSING THE AIR PERMIT APPLICATION?

A.

SWEPCO's initial schedule allowed slightly more than one year for processing this

4

permit application. This date was reasonable for planning purposes because

5

SWEPCO had been in frequent contact with the ADEQ management concerning the

6

timeline for issuance of the final Air Permit both before and after submittal of the

7

permit application to the agency.

8

issued well within one year from when the permit application was submitted. This

9

information was the basis of my February 2007 direct testimony submitted in the

10

Turk Certificate of Convenience and Necessity case in' PUC Docket No. 33891 or

11

when SWEPCO anticipated receiving the permit.

12

Q.

13 14

The ADEQ had indicated the permit would be

PLEASE. DESCRIBE SWEPCO'S TEAM THAT PREPARED THE AIR PERMIT APPLICATION.

A.

SWEPCO used two national consulting firms and internal resources from AEPSC's

15

Environmental Services Division to prepare the permit application.

16

Consultants (Trinity), a national consulting firm with offices in Little Rock, Arkansas,

17

and prior permitting experience with the ADEQ, was hired to prepare the permit

18

application and perform air quality modeling to confirm that the plant's emissions

19

would not exceed the national ambient air quality standards. The Trinity permitting

20

team had extensive experience in permitting for coal-fired plants in several states.

Trinity

21

In addition, TRC Companies, Inc. (TRC), another national consulting firm,

22

was used to perform the Class I visibility modeling to support the permit application.

23

Class I areas are those areas designated by the federal government as having high

PUC DOCKET NO. 40443

8

DIRECT TESTIMONY JOHN C. HENDRICKS

563

I

scenic value and are accorded specific protection from impacts to visibility and other

2

air quality-related values. The team from TRC for this project also had extensive

3

experience in performing Class I modeling for coal-fired power plants.

4

Experienced management and staff from AEP's Environmental Services

5

Division provided technical information, including descriptions of equipment and

6

emission controls, and comparative information from other coal plant permits, and

7

overall coordination of the permitting processes.

8

Q.

WHY WAS THE TURK AIR PERMIT DELAYED?

9

A.

Issuance of the Turk Air Permit was delayed due to a combination of several

10

developments, all of which occurred after the issuance of the draft permit. These

11

developments included the issuance of a judicial decision and resulting changes in the

12

applicable regulations, requests by Environmental Protection Agency (EPA) and the

13

Federal land manager (FLM) for additional visibility modeling, and negotiation of

14

mitigation measures in response to the FLM's comments on the draft permit. These

15

circumstances are discussed in more detail below. Company witness Christian T.

16

Beam discusses the construction and monetary impact from this delay.

17 18

EPA changed the approved model for Class I visibility modeling late in the permit process for Turk:

19 20 21 22 23 24 25 26 27 28

In June 2007, almost a year after SWEPCO had filed its application, the EPA approved an updated version of the model (CALPUFF) it requires applicants to use to assess Class I visibility impacts. Applicants who seek an Air Permit for a large source (such as the Turk Plant) must demonstrate that emissions from this source will not result in a significant impact to visibility and air quality-related values in nearby Class I areas. SWEPCO demonstrated this in January 2007 using the model that was considered acceptable at that time (by the EPA and state environmental agencies, including the ADEQ). When the EPA approved a modified version of this model in June 2007,

PUC DOCKET NO. 40443

9

DIRECT TESTIMONY JOHN C. HENDRICKS

564

I 2 3 4 5

SWEPCO was required to rerun the Class I modeling using the updated model version. The modeling was redone expeditiously by SWEPCO's consultant, TRC, over a reasonable time frame of several months. A report was prepared and submitted to ADEQ in September 2007 for review and approval.

6 7 8

ADEQ reversed its position and required SWEPCO to address concerns raised by the FLM regarding Class I visibility impacts late in the permitting process:

9 10 11 12 13 14 15 16 17 18 19 20 21

In the draft Turk Air Permit, issued in May 2007, the ADEQ determined that modeled impacts to the closest Class I area (Caney Creek Wilderness Area in western Arkansas) from emissions from the^ Turk Plant were insignificant and therefore acceptable. However, in January 2008, ADEQ required SWEPCO to address the concerns raised in comments submi'tted by the Caney Creek FLM on this issue. SWEPCO engaged in negotiations with the FLM to develop mitigation measures that could be included in the Turk Air Permit. Additional modeling and other information had to be submitted to support the proposed mitigation measures. Without this mitigation, the FLM would have objected to the final Air Permit, and the ADEQ would not proceed with permit issuance. The delay associated with this issue was 6 to 7 months.

22 23 24

EPA's Clean Air Mercury Rule was overturned in court, requiring an additional, lengthy permitting process late in the overall permit process:

25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

In February 2008, the D.C. Circuit Court of Appeals vacated the EPA's Clean Air Mercury Rule (CAMR). This rule, among other things, required that new major sources such as the Turk Plant meet stringent emission standards for mercury.. The draft Air Permit issued by ADEQ in May 2007 regulated mercury based on the requirements contained in the CAMR. As a result of the CAMR's vacatur, ADEQ required SWEPCO to prepare and submit an application for development of case-by-case ' Maximum Achievable Control Technology (MACT) emission limits for mercury and several other hazardous air pollutants to the agency for review and approval: Preparation of the MACT application and supporting information, review and preparation of a draft MACT determination by the ADEQ, and subsequent public notice of the MACT determination and preparation of responses to comments by ADEQ took approximately eight to nine months.

PUC DOCKET NO. 40443 '

10

DIRECT TESTIMONY JOHN C. HENDRICKS

565

1 2

US EPA Region 6 required additional modeling analysis late in the permitting process and well after the comment period had ended:

3 4 5 6 7 8 9 10 11 12 13 14

In February 2008, EPA Region 6 objected to the inventory of sources approved by the ADEQ for the multisource Class I modeling. (When performing a Class I modeling analysis, other sources in the vicinity of the proposed source must also be modeled. The sources modeled along with their locations and emissions are included in the inventory of sources that must be approved by the permitting authority.) Although ADEQ had approved the inventory of sources modeled for the Turk Plant's Class I modeling and EPA's objections came approximately six months after the comment period had closed for the draft Air Permit, ADEQ required resolution of these objections prior to completion and issuance of the final permit. ' The resolution of this issue took approximately five months.



15

SWEPCO and its team worked diligently to address each development as it

16

occurred. In the end, these developments did not alter the design of the Turk Plant or

17

its planned emission controls.

18

delayed by 14 months.

19

Q.

20 21

However, the issuance of the final Air Permit was

WERE THESE ISSUES RESPONSIBLE FOR THE DELAY IN ISSUING THE AIR PERMIT REASONABLY FORESEEABLE?

A.

No.

SWEPCO took - all reasonable steps to avoid any delays by engaging in

22

continuing discussions with the ADEQ prior to and following the submission of the

23

permit application. The timing and substance of the judicial decision on CAMR and

24

. EPA's issuance of new modeling guidance were wholly outside of SWEPCO's .

25

control and not reasonably predictable. The FLM's concerns were not justified based

26

on the initial visibility modeling results, and are inconsistent with the most recent

27

federal guidance.

28

additional sources in the, visibility modeling inventories was contrary to ADEQ's

29

prior approval of SWEPCO's modeling protocol, and did not materially alter the

PUC DOCKET NO. 40443

EPA's insistence on including different emission estimates and

11

DIRECT TESTIMONY JOHN C. HENDRICKS

^7^^

1

results. Thus SWEPCO had no reasonable basis to expect the issuance of the Air

2

Permit to be delayed.

3

Q.

DID SWEPCO PRUDENTLY MANAGE THESE PERMITTING ISSUES ONCE

4

THEY AROSE IN LIGHT OF THE INFORMATION AND ALTERNATIVES

5

AVAILABLE AT THE TIMES IN QUESTION?

6

A.

7

Yes, it did. As each issue arose, SWEPCO took immediate and appropriate action to minimize, as much as possible, their impact to the permit schedule.

8

Q.'

WHAT SPECIFIC STEPS DID SWEPCO TAKE TO MANAGE THESE ISSUES?

9'

A.

SWEPCO immediately'contacted the appropriate regulatory authority to discuss the

10

necessary actions to address the issue raised.

11

throughout the process to address each of the issues.

12

immediately commissioned its consultants to perform the necessary work to address

13

these issues. For example, SWEPCO undertook the following actions:

These contacts were maintained In addition, SWEPCO

14 15

Concerning the issue of ADEQ deferral to the FLM on Class I impacts:

16 17 18 19 20 21 22 23 24

SWEPCO immediately met with local FLM management and staff to identify their concerns and the path to resolution of this issue. SWEPCO also met with Department of Interior representatives (who oversee this FLM branch) to clarify the issue and necessary resolution steps. SWEPCO's Class I modeling consultant TRC was immediately directed to perform the necessary modeling to demonstrate an acceptable solution. Finally, SWEPCO arranged meetings with all agencies involved (ADEQ, FLM, and EPA) to articulate our proposed solution and to get concurrence on it from each agency.

25

Concerning the vacatur of the Clean Air Mercury Rule:

26 27 28 29

_

SWEPCO met with ADEQ immediately after the D. C. Circuit Court of Appeals vacated CAMR to determine the next steps to address this development. The US EPA was also consulted concerning the -appropriate path forward and the scope of work necessary to satisfy

DIRECT TESTIMONY PUC DOCKET NO. 40443

12

JOHN C. HENDRICKS

567

1 2 3 4 5 6 7 8 9 10

the regulatory requirements. SWEPCO then began preparing the necessary information to develop the application required by ADEQ to fully address this issue. SWEPCO stayed in frequent contact with ADEQ permitting staff as the application was reviewed, and promptly supplemented the information until a draft case-by-case MACT determination was proposed for public comment by ADEQ. SWEPCO also prepared detailed responses to comments received on the proposed MACT determination to assure that all relevant information in support of ADEQ's determination was reflected in the adniinistrative record.

11 12

Concerning the issues involving the ADEQ and US EPA Region 6 (change in apprQved model and modeling inventory issue):

13 14 15 16 17 18 19 20 21 22 23 24

SWEPCO in each case immediately arranged meetings with senior management of both agencies to determine exactly what the issues were, what had to be done to address them, who within the agencies was responsible for working with the Company to address the issue, and to establish a timeline to resolve the issues as expeditiously as possible. SWEPCO also contacted US EPA headquarters to receive guidance on how best to address the issues. SWEPCO immediately directed its modeling consultant (TRC) to perform the additional modeling and analysis to address each of the issues. Finally, SWEPCO remained in frequent contact with the EPA Region .6 and ADEQ during this process to make sure the work being done would meet the agencies' needs and that it would be reviewed promptly.

25

Q.

26 27

YOU MENTIONED THAT THE AIR PERMIT WAS APPEALED. WHAT STEPS DID SWEPCO TAKE TO MANAGE THE SITUATION?

A:

SWEPCO sought to ensure that construction could continue without delay while the

28

appeals proceeded.

29

process, and was upheld at each stage without change.

30

stakeholders and settled all litigation in December of 2011.

31

demonstrate that SWEPCO proactively and prudently planned and managed the

32

permitting appeal process.

PUC DOCKET NO. 40443

The Air Permit has remained in effect throughout the appeals

13

SWEPCO engaged the These measures

DIRECT TESTIMONY JOHN C. HENDRICKS

568

1 2

V. TURK AIR PERMIT AND AUXILIARY BOILER Q.

DID THE DESIGN FOR THE TURK PLANT AUXILIARY BOILER CHANGE

3

FROM WHAT WAS INCLUDED IN THE ORIGINAL AIR PERMIT

4

APPLICATION?

5

A.

As SWEPCO witness Mr. Beam discusses, as the detailed design phase progressed,

6 7

the auxiliary boiler was modified. Q.

WHY WASN'T THE AIR PERMIT APPLICATION CHANGED TO REFLECT

8

THE MODIFIED AUXILIARY BOILER PRIOR TO ISSUANCE OF THE FINAL

9

AIR PERMIT?

10

A.

An accurate profile of projected emissions from the modified boiler was not

11

developed until after the final permit was issued. Therefore the permit application

12 13

. Q.

14 15

could not have been modified prior to final permit issuance. WHY WASN'T THE FINAL AIR PERMIT MODIFIED TO INCLUDE THE MODIFIED AUXILIARY BOILER DESIGN?

A.

Discussions were held with the ADEQ on the process for modifying'the final Turk air

16

permit to include the modified auxiliary boiler. Although the change to the auxiliary .

17

boiler would have resulted in lower emissions, the ADEQ determined that this change

18

was significant enough to warrant a minor permit modification.. A minor permit

19

modification requires at least a 30-day public comment period, and ADEQ would

20

have to respond to all comments received prior to issuance of a final permit. The

21

modified permit would have been subject to additional appeals, with the prospect of a

22

stay on construction of the auxiliary boiler pending resolution of any appeals. Based

23

on SWEPCO's experience with the initial Air Permit appeals, the risk of further

PUC DOCKET NO. 40443

14

DIRECT TESTIMONY JOHN C. HENDRICKS

569

1

delays associated with this process was determined to be significant enough that the

2

permit modification for a modified auxiliary boiler was not pursued.

3 4 5

VI. CORPS OF ENGINEERS STREAMS AND WETLANDS (SECTION 10/404) PERMIT

6

Q.

WHAT IS A CORPS OF ENGINEERS (COE) SECTION 10/404 PERMIT?

7

A.

A Section 10/404 permit regulates both the placement of structures in navigable

8

waters under Section 10 of the Rivers and Harbors Act, as well as the discharge of fill

9

material into waters of the United States, including wetlands, per Section 404 of the

10

Clean Water Act (CWA). The Section 10/404 permit was required before certain

11

construction activities could commence so that impacts associated with the filling of

12

approximately eight acres of wetlands and streams (out of the almost 3,000 acre Turk

13

site) could be assessed and appropriate mitigation measures developed. The

14

construction associated with this permit includes roads, pipelines, a rail spur, the

15

water intake structure, and transmission line river crossings for the Turk -site.

16

Q.

WHAT DELAYS AROSE DURING THE PROCESSING OF THIS PERMIT?

17

A.

Due to mapping errors by one of SWEPCO's consultants, approximately 2.5 acres of

18

jurisdictional areas were impacted on the Turk site prior to the COE Section 10/404

19

permit becoming final. As a result, certain construction activities were restricted, and

20

the issuance of the final permit was delayed.

21

Q.

PLEASE EXPLAIN.

22

A.

On March 9, 2009, the same day that SWEPCO received the permit documents from

23

the COE, it was confirmed that jurisdictional areas on the Turk site were incorrectly

DIRECT TESTIMONY PUC DOCKET NO. 40443

15

JOHN C. HENDRICKS

570

1

mapped by SWEPCO's wetland consultant, FTN Associates (FTN). This mapping

2

was used to locate the jurisdictional areas in the field, which were then marked with

3

high visibility fencing to ensure that no activities would commence in these areas

4

prior to the COE's permit becoming final.

5

mapped, the marked areas in the field were incorrectly located. The errors in location

6

ranged from approximately 180 to 500 feet. Although the marked-off areas were not

7

disturbed, approximately 2.5 acres of jurisdictional areas, which should have been

8

marked-off but were not because of the erroneous maps, were unintentionally

9

impacted. The actual impacts to the jurisdictional areas occurred in late 2008 and

10

early 2009. SWEPCO self-reported this error and the accidental impact to unmarked

11

jurisdictional areas to the COE instead of completing the signature/countersignature

12

process that would have finalized the permit.

13

Q.

14 15

Because .the areas were incorrectly

WHY DID SWEPCO•NOT SIGN AND RETURN THE PERMIT IT RECEIVED ON MARCH 9, 2009?

A.

SWEPCO is required by law to immediately report any violations of the C.WA, and

16

the COE cannot issue a permit for an activity for which there is an associated

17

unresolved violation of the CWA. Therefore, had SWEPCO signed and returned the

18

permit, the COE could not have countersigned it until the violation that resulted from

19

the mapping issue was resolved. The COE's procedures require that it first resolve

20

the enforcement matter associated with the violation before issuing any required

21

permits.

22

resolution.

23

July 7, 2009.

In this case the COE referred the enforcement matter to the EPA for

The enforcement matter was expeditiously resolved with the EPA on

PUC DOCKET NO. 40443

16

DIRECT TESTIMONY JOHN C. HENDRICKS

571

1

Q.

HOW WAS THIS MAPPING ERROR DISCOVERED?

2

A.

An FTN employee was performing field verification of the location of jurisdictional

3

areas as a final check prior to on-site development activities adjacent to the wetlands

4

nearby and noted discrepancies between his field notes and the marked locations of

5

two jurisdictional areas. This discrepancy was then reported to SWEPCO.

6

Q.

WHAT DID SWEPCO DO IN RESPONSE?

7

A.

All work was stopped within 500 feet of all jurisdictional areas and SWEPCO began

8

an investigation to determine if violations of the CWA had occurred.

9

violations were confirmed, SWEPCO immediately self-reported the impacts to the

When the

10

COE.

11

contracted to correctly locate and mark the wetland coordinates in the field.

12

jurisdictional areas near any current or planned construction activities were flagged

13

with high visibility roping with a minimum buffer of 25 feet incorporated in the

14

flagging as an extra precaution. This remapping action successfully prevented any

15

further intrusion into the jurisdictional areas.

16

this situation, as well as the costs resulting from them. Q.

19 20

All

SWEPCO witness Mr. Beam describes the other actions taken in response to

17 18

A second consulting company, MTG Engineers & Surveyors (MTG), was

DID SWEPCO PRUDENTLY PLAN AND MANAGE THE COE PERMITTING PROCESS?

A.

Yes, it did.

SWEPCO retained FTN, a well-respected and experienced firm, to

21

perform the wetlands delineation and mapping work. FTN, which was founded in

22

1980 and has offices in both Little Rock. and Fayetteville, Arkansas, brought specific

23

local consulting expertise. In fact, the COE (Vicksburg District) has contracted with

PUC DOCKET NO. 40443

17

DIRECT TESTIMONY JOHN C. HENDRICKS

572

1

FTN in the past for various services, including development of protocols for the

2

Corps' Wetland, Delineation Manual and guidance for COE field personnel in wetland

3

creation, restoration, and enhancement projects. In addition, SWEPCO used high

4

visibility fencing to demarcate the jurisdictional areas so that on-site activities would

5

not impact these locations.

6

SWEPCO, on several instances, asked FTN to reconfirm the locations of these

7

jurisdictional areas at the site prior to initiating development work in the vicinity of

8

these areas. SWEPCO reasonably relied on FTN's expertise and had every reason to

9

believe that the mapping was in qualified hands and had been done correctly.

Finally, as a further precaution against any impacts,

10

However, inadvertent errors by FTN's mapping department were used to mark

11

the jurisdictional areas in the field, and these errors lead to the accidental

12

jurisdictional impacts.

13

Q.

14 15

CAN YOU PROVIDE SOME PERSPECTIVE ON THE IMPACT TO THE JURISDICTIONAL AREAS?

A.

Yes. While not justifying the error, it should be noted that the impacted wetlands

16

were unexceptional and appeared virtually identical to the surrounding non-

17

jurisdictional areas.

18

ultimately authorized by the final permit and did not require restoration.

19

remaining impacts occurred in an area that was extremely difficult to properly

20

classify. The COE conducted some initial soil analysis in this area, and then required

21

SWEPCO to do additional analysis in order to better define the wetland boundaries.

22

Although there is no question that SWEPCO should not have disturbed these

23

jurisdictional areas while the permit application was pending, upon receipt of the

PUC DOCKET NO. 40443

A portion of the impacts occurred in a manner that was

18

The

'DIRECT TESTIMONY JOHN C. HENDRICKS

573

1

final, signed COE permit, SWEPCO was authorized to disturb these areas in exactly

2

the manner that it did, and has undertaken the required restoration activities.

3

Q.

WHAT IS THE CURRENT STATUS OF THE SECTION 10/404 PERMIT?

4

A.

SWEPCO received the final permit from the COE in December 2009. The permit

5

was challenged in federal court and a settlement by the litigating parties was reached

6

in December 2011 resolving the legal challenges surrounding the pen-nit, as

7

SWEPCO witness Ms. McCellon-Allen discusses in her testimony.

8 9 10

VII. ENVIRONMENTAL REGULATIONS AND EMISSION ALLOWANCES/CONSUMABLES

11

Q.

WHAT IS THE PURPOSE OF THIS SECTION OF YOUR TESTIMONY?

12

A.

In this section of my testimony, I briefly describe the primary environmental

13

rulemaking that will drive the need to procure air emission allowances and the

14

increased use of consumables associated with the operations of air pollution control

15

devices in the future. SWEPCO witness Paul W. Franklin discusses the allowances

16

and consumables and their relationship to the burning of fuel. SWEPCO is requesting

17

that the costs and revenues from these allowances be considered eligible fuel costs on

18

a prospective basis, as SWEPCO witness Randall Hamlett.discusses in his testimony.

19

Q.

20 21

PLEASE DESCRIBE THE RELEVANT -ENVIRONMENTAL REGULATIONS DRIVING THE NEED TO OBTAIN AIR EMISSION ALLOWANCES.

A.

The Clean Air Interstate Rule and the Cross State Air Pollution Rule are the primary

22

environmental drivers that would result in the need to procure additional air emission

23

allowances. These are described further below:

PUC DOCKET NO. 40443

19

DIRECT TESTIMONY JOHN C. HENDRICKS

574

1

Clean Air Interstate Rule (CAIR) - was finalized by EPA iii 2005, and established a

2

cap and.trade program to reduce emissions of NO,, and SO2 in covered states. Phase

3

1 caps for NO,, and SO2 were effective in 2009 and 2010, respectively, with further

4

reductions required by a Phase II cap starting in 2015. Under CAIR, SWEPCO must

5

comply with annual' SO2 and NO,, programs in Texas and Louisiana, and seasonal

6

NOX programs in Arkansas and Louisiana *

7

allowances is allowed under CAIR. CAIR was appealed to the courts and remanded

8

to EPA by the D. C. Circuit Court of Appeals in July 2008.

9

Cross State Air Pollution Rule - The Cross State Air Pollution Rule (CSAPR) was

10

published in the Federal Register on August 8, 2011; and serves as the replacement

11

for CAIR.

12'

Louisiana), and mid-western states, as well as the District of Columbia. The final

13

rule defines state obligations to reduce emissions of NOX and SO2 that, according to

14

EPA, significantly contribute to another state's fine particulate and ozone

15

nonattainment and maintenance areas.

Unrestricted interstate trading of

CSAPR affects 28 eastern, southern (including Texas; Arkansas and

16

Along with other requirements, the final CSAPR establishes state-specific

17

annual emission "budgets" fdr S02 and NOx. The EPA's approach for obtaining

18

these emission reductions requires each state to limit its emissions to a prescribed cap.

19

Based on this cap, each emitting unit within the affected states has been allocated a

20

specified budget of NO,, and SO2 allowances for the applicable compliance period.

21

An annual cap for S02 and NO,, and an ozone season cap for NOX emissions apply in

22

Texas. .

SWEPCO's other service territories, Arkansas and Louisiana, must

.

PUC DOCKET NO. 40443

'

.

20

.

DIRECT TESTIMONY JOHN C. HENDRICKS

575

1

implement programs only for NO,, during the ozone season, from May through

2

September each year.

3

NOX allowance trading is allowed between all covered states. SO2 allowance

4

trading, however, is restricted to states within the same group. Texas is a Group 2

5

state and limited to trading with the seven other Group 2 states. In addition, during

6

Phase 2 of CSAPR (beginning in 2014), restrictions are imposed on the amount of

7

interstate trading allowed.

8

exceed its annual allocation by 18% or more, those units within the state that have

9

also emitted 18% or more above their allocations will be subject to an allowance

10

penalty. In Arkansas, Louisiana, and Texas, seasonal NOX emissions cannot exceed

11

the state budget by more than 21%, or the sources whose emission exceed that

12

threshold are subject to an allowance penalty. Sources whose emissions exceed their

13

allocations by less than these thresholds (called the "assurance level") are not subject

14

to penalties as long as they hold sufficient allowances to cover their actual emissions.

In Texas, if the state's annual NOX or S02 emissions

15

CSAPR was set to be effective beginning on January 1, 2012, but the D.C.

16

Circuit Court of Appeals issued an order to stay the rule on December 30, 2011.

17

While the appeal of CSAPR is pending and until further order of the Court, CAIR

18

will remain in effect.

19

Q.

20 21

PLEASE DESCRIBE THE RELEVANT- ENVIRONMENTAL REGULATIONS DRIVING THE NEED TO USE MORE CONSUMABLES.

A.

The environmental regulation that will drive an increase in the use of consumables is

22

the Mercury and Air Toxics Standards Rule (MATS). This rule replaced the former

23

Clean Air Mercury Rule (CAMR) that was vacated in 2008 by the D.C. Circuit Court

PUC DOCKET NO. 40443

21

DIRECT TESTIMONY JOHN C. HENDRICKS

576

1

of Appeals. The final MATS Rule became effective on April 16, 2012, with

2

compliance required within three years of this date. This rule regulates emissions of

3

hazardous air pollutants (HAPs) from coal and oil-fired electric generating units.

4

HAPs regulated by this rule are: 1) mercury; 2) several non-mercury metals such as

5

arsenic, lead, cadmium and selenium; 3) various acid gases including hydrochloric

6

acid;.and 4) many organic HAPs. The MATS rule includes stringent emission rate

7

limits for several individual HAPs, including mercury. In addition; this rule contains

8

stringent emission rate limits for "surrogates" representing two classes of HAPs, acid

9

gases and non-mercury particulate metal HAPs.

The surrogate for non-mercury

10

particulate metal HAPs is filterable particulate matter, while hydrogen chloride (HCl)

11

and/or SO2 (for units equipped with a scrubber) are the surrogates for acid gases.

12

Q.

WILL CSPAR AND MATS RESULT IN THE PURCHASE OF MORE

13

ALLOWANCES AND/OR THE USE MORE CONSUMABLES BY SWEPCO IN

14

THE FUTURE FOR COMPLIANCE?

15

A.

Yes.

For example, under CSAPR, the SWEPCO power plants in Texas will be

16

required to hold SO2 allowances to cover emissions on an annual basis, as well as

17

NO, on an annual basis (Annual NOX) and NOX on a seasonal basis (Seasonal NOX).

18

SWEPCO is allocated an amount of allowances during each year under these

19

regulations, but it is not forecasted that these allocations, which are allocated at zero

20

cost, will be sufficient to cover SWEPCO's emissions. SWEPCO, therefore, will

21

need to purchase allowances from the market, at whatever cost the market supports.

22

These market purchases will be a necessary cost for SWEPCO to comply with

PUC DOCKET NO. 40443

22

DIRECT TESTIMONY JOHN C. HENDRICKS

577

I

CSAPR. SWEPCO witness Mr. Franklin describes the increased use of consumables

2

associated with MATS compliance in more detail in his testimony.

3

Q.

YOU MENTION ABOVE CAIR IS IN PLACE WHILE CSAPR IS 'STAYED.

4

DOES THIS CHANGE THE POSITION, ON AN ENVIRONMENTAL BASIS,

5

THAT EMISSION ALLOWANCES BE CONSIDERED FUEL COSTS?

6

A.

No. Under the most likely paradigm, CSAPR will be implemented in some form with

7

targeted state reductions for SO2 and NO, - Even while the rule is stayed, CAIR

8

remains in place and is also an allowance trading program.

9

emission allowance program is in place and will result in the need of the consumption

10

or procurement of allowances in the future.

11

^

12 13

VIII. ENVIRONMENTAL. SAFETY AND HEALTH AFFILIATE CHARGES

14

A. Organization Of Environmental.

15

Safety. Health and Facilities

16

Q.

17 18 19

In either scenario, an

PLEASE. DESCRIBE HOW THE AEP ENVIRONMENTAL, SAFETY, HEALTH AND FACILITIES ORGANIZATION IS STRUCTURED.

A.

The reporting. structure of the Environmental, Safety, Health, and Facilities organization is shown in Figure 1 below.

PUC DOCKET NO. 40443

23

DIRECT TESTIMONY JOHN C. HENDRICKS

578

1

Figure 1

2

Q.

WHAT ARE THE MAJOR FUNCTIONS OF EACH OF THESE GROUPS?'

3

A.

The major functions of Environmental, Safety and Health are outlined below, except

4

for Real Estate and Workplace Services, which falls under the Facilities portion of the

5

organization and will be discussed in the testimony of SWEPCO witness Jeff Parlet.

6

Environmental Services

7

The primary role of Environmental Services is to provide permitting and compliance

8

support, guidance, procedures, recommendations and training for AEP's operating

9

companies in order to maintain and improve their. -environmental programs and

10.

enhance compliance with environmental laws, regulations, and policies.

11

this effort, Environmental Services is also involved in the development process for

12

environmental regulations, coordinating with other groups within the Environmental,

13

Safety and Health as well as with operating company staffs. Environmental Services

PUC DOCKET NO. 40443

24

As part of

DIRECT TESTIMONY JOHN C. HENDRICKS

579

1

supports AEP's corporate strategies and values concerning the environment, safety,

2

and health.

3

Environmental Services includes the four following sections: Air Quality

4

Services,

5

Remediation Services, and Analytical Chemistry Services. In addition, there are a

6

small number of employees involved with strategy and compliance planning.

Water and Ecological Resource Services, Land Environment and

7

Air Quality Services, Water and Ecological Resource Services, and Land

8

Environment and Remediation Services are responsible for preparing and submitting

9

applications to obtain environmental permits for AEP operations, providing guidance

10

and training for operations staff regarding compliance with permits and overall

11

,

regulations, submittal of compliance reports to state and federal agencies, reporting

12

and cleanup of spills, conducting site inspections, and arranging for disposal of solid

13

wastes.

14

distribution operations; and transmission, as well as general support on broader

15

environmental issues and regulatory programs that have impacts on SWEPCO

16

operations. Finally, the Analytical Chemistry Services section provides customized

17

analytical services to help resolve problems of a chemical or physical nature that

18

occur at operations facilities. This support covers generating plants and distribution

19

and transmission operations.

This effort includes direct support for SWEPCO's generation plants,

20

Environmental Services staff is located primarily in Columbus, OH and

21

surrounding areas, Shreveport, LA, and Dallas, TX, including a chemistry laboratory

22

in Shreveport. In addition, Environmental Services staff with primary responsibility

PUC DOCKET NO. 40443

25

DIRECT TESTIMONY JOHN C. HENDRICKS

580

1

for compliance support for distribution and transmission are located throughout the

2

AEP service territory, including employees in Shreveport, LA and Longview, TX.

3

Safety & Health

4

The Safety & Health organization at AEP provides support in all areas of

5

occupational safety and health, public and contractor safety, industrial hygiene,

6

ergonomics, health and wellness, and training. Its staff consists of safety and health

7

generalists and specialists who hold professional degrees and certifications in many

8

areas, including nursing, occupational health, industrial hygiene, and public safety.

9

Safety & Health is generally organized according to the function being supported, for

10

example generation, or program area, such as industrial hygiene.

11

groups ensure that the Safety & Health policies and procedures within AEP's

12

operating companies, such as SWEPCO, are aligned with AEP's corporate Safety &

13

Health policies and procedures as well as federal standards from agencies such as the

14

Occupational Safety and Health Administration.

These support

15

Safety & Health is comprised of six primary groups covering safety and health

16

for generation, transmission, and distribution operations, safety and health training,

17

industrial hygiene, and public safety.

18

generation, transmission, and distribution operations, and develop initiatives and

19

programs to foster a: safety and health culture in these organizations. The Zero Harm

20

initiative was introduced at the corporate level to challenge employees to not be

21

satisfied until zero harm is achieved - i.e., every employee goes home safe and

22

healthy at the end of his/her workday. A spin-off of this initiative, Target Zero, was

23

introduced to generation to promote the same ideals of a zero harm culture.

PUC DOCKET NO. 40443

26

The Safety & Health groups support AEP's

DIRECT TESTIMONY JOHN C. HENDRICKS

581

1

Safety & Health support staff for AEP's transmission organization have

2

facilitated Safety Stand Downs and periodic visits to communicate corporate policies

3

on vehicle safety, fire retardant clothing, hazard assessments, and recognition for

4

employee safety efforts.

5

The transmission, generation, and distribution organizations have been

6

utilizing Safety & Health's Human Performance Initiative as an error reduction

7

system for employees and have also partnered with AEP distribution to update the

8

Contractor Safety Oversight Programs for each organization. AEP distribution is

9

assisted by Safety & Health in the area of strategic communication with safety alerts

10 11

and safety bulletins for communication of significant issues. -

Another key

communication tool is the Serious Event conference call, which ensures that critical

12

issues and events are communicated quickly across the organization with an emphasis

13

on immediate corrective actions.

14

The Safety & Health Training Team is involved with communicating AEP

15

safety and-health programs to AEP's operating companies, ensuring that a consistent

16

message is conveyed system-wide. Program and initiative-specific training is also

17

facilitated by this group through Safety & Health Summits. For example, the Safety

18

and Health Industrial Hygiene (IH) group conducted a welding fume study to better

19

characterize exposure potential, implemented sharing of air sample analysis across

20

the AEP system through the IH database, and coordinated a radio frequency (RF)

21

safety workshop that led to the updating of the RF Safety Manual. The IH group also

22

determined a simple statistical process for negative exposure assessment to ensure

23

that sampling is representative of actual industrial exposure hazards.

PUC DOCKET NO. 40443

27

DIRECT TESTIMONY JOHN C. HENDRICKS

582

1

The Safety & Health Public Safety group facilitates AEP's outreach plan for

2

elimination of preventable electrical contacts and public fatalities by producing, in

3

conjunction with AEPSC Corporate Communications, safety videos, multiple Internet

4

website communications, television safety advertising, and publishing articles in

5

Consumer Circuit, AEP's customer publication. The Safety & Health Public Safety

6

group also provides safety content for employee communications about public safety.

7

Other Environmental, Safety and Health Groups

8

In addition .to Environmental Services and Safety & Health, which I discussed above,

9

the Environmental, Safety and Health

organization includes staff that support

10

programs in environmental public policy, external environmental affairs, strategic

11

policy analysis, sustainability programs, and environmental and safety management

12

systems.

.

13

The Governmental & Environmental Affairs and Environmental Public Policy

14

groups assist with development of corporate positions on environmental public

15

policies, coordinating this

16

SWEPCO's. The Governmental & Environmental Affairs group does not engage in

17

legislative advocacy.

18

effort

with

operating company staffs, including

Strategic Policy Analysis provides timely, accurate, and proactive analysis for

19

corporate decision-making on environmental investments in AEP's system-wide-

20

least-cost environmental compliance plan (e.g., air emission and CO2 cost analyses).

21

The Environment and Safety - Strategy and Design team supports the design and

22

execution of strategic plans within the Environmental, Safety and Health organization

23

and coordinates with AEP's operating companies and business units to ensure that

PUC DOCKET NO. 40443

28

DIRECT TESTIMONY JOHN C. HENDRICKS -

583

1

corporate Environmental, Safety and Health strategic plans integrate and align with

2

their needs. This group also oversees AEP's sustainability performance reporting.

3

The Environmental, Safety & Health Management Systems Team oversees the

4

implementation of a program at AEP generating plants to emulate international

5

standards for environmental, safety, and health management systems.

6

reports to Environmental, Safety & Health leadership through the Managing Director

7

of Governmental & Environmental Affairs.

8 9

B. Environmental, Safety, Health and Facilities Services Q.

10 11

This team

WHAT SERVICES WERE PROVIDED TO SWEPCO BY ENVIRONMENTAL,

SAFETY AND HEALTH DURING THE TEST YEAR? A.

Environmental, Safety and Health provided a multitude of services to SWEPCO

12

during the test year, which are described below, organized by group and section.

13

While all groups within Environmental, Safety & Health provided services, the

14

following summary is limited to the two largest organizations - Environmental

15

Services and Safety & Health - as these groups provided the bulk of support to

16 '

SWEPCO.

17

Services Provided by Environmental Services

18

Environmental Services provided support for permitting and associated compliance

19

activities necessary to meet the requirements of federal and state regulatory programs.

20

protecting air, water, and land resources.

21

supported

22

inventories, preparing the annual Title V compliance certification as well as

23

semiannual and quarterly deviation reports, providing corrective action responses to

Specifically, the Air Quality section

SWEPCO's generating facilities by reviewing annual emissions

PUC DOCKET NO. 40443

29

DIRECT TESTIMONY JOHN C. HENDRICKS

584

1

notice of violations, completing required Energy Information Agency reporting, and

2

preparing Title V permit renewal applications as needed.

3

Similarly, the Water and Ecological Resources section provided support for

4

National Pollutant Discharge Elimination System (NPDES) permits for wastewater

5

and storm water discharges by scheduling biomonitoring -testing, including preparing

6

and submitting required reports; facilitating NPDES permit renewals by performing

7

discharge sampling, preparing the application, and meeting with agency officials to

8

negotiate final terms and conditions; preparing stormwater construction permit

9

-

documents such as notices of intent and termination and stormwater pollution

10

prevention plans; and providing ongoing assistance to plants through evaluations and

11

inspections of wastewater treatment facilities.

12

Land Environment and Remediation Services coordinated sampling of

13

groundwater monitoring wells, including preparation of sampling and analysis plans

14

and submission of reports to the appropriate agency; provided training for -Plant

15

Environmental Coordinators on waste-related recordkeeping, reporting, and preparing

16

shipments of waste for disposal, as well as the standards of the Emergency Planning

17

and Community Right-to-Know and Toxic Substances Control Act requirements,

18

such as assisting with collecting samples for Polychlorinated Biphenyls (PCB)

19

analysis.

20

obtaining the environmental permits needed for Turk.

All of the' above groups in Environmental Services also assisted 'with

21

The section's Regional Environmental Coordinators are responsible for

22

providing waste-related compliance ' services to SWEPCO's Transmission and

PUC DOCKET NO. 40443

DIRECT TESTIMONY 30

-

JOHN C. HENDRICKS

585

1

Distribution groups through conducting site visits to T&D facilities and coordinating

2

clean-up and reporting of oil and chemical spills.

3

Finally, the Analytical Chemistry Services group supported SWEPCO by

4

performing analysis of samples collected at its facilities as required for permitting and

5

compliance activities. Services Provided by Safety and Health

6 7

Safety & Health groups supporting the generation, transmission, and

8

distribution operations of SWEPCO provided services including site inspections of

9

SWEPCO-owned facilities to conduct safety/health assessments, maintaining Safety

10

& Health corporate-wide databases to facilitate knowledge sharing, creating safety

11

bulletins, issuing guidance on safety footwear and implementation of fall protection

12

while climbing wood poles, and conducting business unit-specific safety conferences.

13

In addition, Safety & Health provided expertise and interpretation of the rules,

14

regulations and policies that govern our business with respect to safety and health,

15

and, where applicable, changed or modified those policies and procedures to meet or

16

exceed the associated federal and/or state standard. The Industrial Hygiene group of

17

Safety & Health conducted assessments at SWEPCO service centers to monitor

18

exposure to chemicals, provided mandated training for asbestos compliance with

19

federal and state regulations, and served as a technical resource to plant Industrial

20

Hygiene'coordinators. The Safety & Health team provided leadership and guidance as

21

well as identification and correction of weaknesses in the Safety and Health

22

Management System. Safety

23

recommendations to prevent unwanted incidents, injuries, and illnesses. Safety &

PUC DOCKET NO. 40443

& Health provided proactive solutions and

31

DIRECT TESTIMONY JOHN C. HENDRICKS

586