Transition Method of Perpendicular Mining Districts in Surface Coal Mine Based on Combined Mining Technology Li Ma State Key Laboratory of Coal Resources and Safe Mining, China University of Mining & Technology, Xuzhou, 221116, China; e-mail:
[email protected]
Kemin Li* State Key Laboratory of Coal Resources and Safe Mining, China University of Mining & Technology, Xuzhou, 221116, China; email:
[email protected]
Xiaohua Ding State Key Laboratory of Coal Resources and Safe Mining, China University of Mining & Technology, Xuzhou, 221116, China
Zhiguo Chang Department of Mining, Xinjiang Institute of Engineering, Urumqi, 830023, China
ABSTRACT Mining districts transition method, an important issue, has to be faced with during the whole mining process of large horizontal surface coal mine, since the mine field is divided into several mining districts and the mined-out area is backfilled with overburden material. In order to ensure the first mining district turning into the second one smoothly in a right angle of Heidaigou surface coal mine, two transition methods are proposed, which contain fan advance of working face and gentle slope inner-dumping, and the gentle slope inner-dumping method is determined as the optimal transition mode for Heidaigou surface coal mine with considering the adaptation of the combined mining technology to the two transition methods. The gentle slope inner-dumping constraint condition is determined and the optimizing model of uncovered end-wall height is established for mining area perpendicular transition on the basis of the principle that the average stripping ratio is not more than the economic stripping ratio, and the optimal uncovered end-wall height is 87.88m for gentle slope inner-dumping. The research conclusions have important reference and guidance significance for similar surface coal mine on researching transition method.
KEYWORDS: surface coal mine;combined mining technology;perpendicular mining area;transition method
- 5085 -
Vol. 18 [2013], Bund. U
5086
INTRODUCTION Surface mining is a broad term which refers to the removal of the soil and strata over a mineral or fuel deposit and the removal of the deposit itself, the stripped materials mined out is dumped into the designated location via transport equipments. The land occupation expense of external dump and stripping haulage cost account for about 2/5 of the cost in the view of cost structure of surface coal mine. To reduce the cost, the stripped materials are usually dumped into the mined-out area as the external dumping is replaced by the internal dumping, which can not only save the land acquisition costs and reduce the haulage distance as well. For the rich resource reserves and horizontally buried ore body, the open-pit is usually divided into several mining districts to reduce the haulage distance and capital construction volume, so that the initial production stripping ratio can be decreased and the internal dumping can be realized as soon as possible (JI, 2011). However, re-stripping and continuous production are the major problems when the previous mining district is close to the end of mining according to the particularity of the open pit mine shapes (SHANG, 2004). Simultaneously, the layout of in-pit development haulage system and rational utilization of dumping space will be subject to different impacts in the transition period (LIU, 2001; XU, 2006). The mining method of one coal field divided into several districts and achieving inner dumping has been adopted in large surface mines since 1980s, as the service life of first mining district is coming to the end, the surface mines are now facing the problems related to the steering from the first mining district to the second one. CAI Qingxiang et al. (1996) analyzed basic mining districts transition methods of Anjialing surface coal mine and confirmed that the gentle slope mining with uncovered end-wall in a right angle was the optimal scheme. ZHOU wei et al. (2009) analyzed the influence factors of innerdumping covering height under the parallel mining districts condition and gave the corresponding calculation method. SHANG Tao et al. (2005) analyzed the problems encountered during the transition period of Antaibao open-pit mine, and proposed the corresponding solution methods. GU Zhenghong et al. (1995) determined that inner-dumping with leaving ditch was superior to recutting ramp in mining districts steering from the point of technical economy. The researches above are all on the conditions of discontinuous mining system of single-bucket excavatorbucket, there are not any research based on the combined mining technology. The paper based on the background of the combined mining system adopting in Heidaigou surface mine, the first mining area is gradually reaching the limit and in order to ensure the normal production steady, it is significant to research and optimize the reasonable transition method from the first mining area turning to the second one in a right angle of Heidaigou surface coal mine.
THE ENGINEERING BACKGROUND Heidaigou surface mine lies in the middle of Zhunge’er coal field with horizontal ore body, and it is divided into three mining districts. The first mining district started operation in the July of 1992 and was put into production in the October of 1999.The designed production capacity is 12Mt/a, and the coal production exceed 30Mt in 2012 after twice capacity expansion,Therefore, it has become the largest surface coal mine in production capacity with single pit. Combined mining technology is adopted in Heidaigou, in which the upper loess is stripped by continue system of bucket wheel excavator; The shovel-truck discontinued system is applied in central rock thickness of 45~75m, with the bench height of 15~20m; And casting blast-dragline stripping technology is adopted in bench height of 40~45m over the coal roof; The shovel-truck,
Vol. 18 [2013], Bund. U
5087
Th e
fir
st
m
in
in g
di str ict
crusher and belt conveyer consist the semi-continued technology for coal exploiting. Figure 1 is the divided mining districts sketch map of Heidaigou surface coal mine, the perpendicular mining districts transition method is the problem to be solved under the condition of adopting the combined technology.
The
third
m in
The seco nd m
in g d
i n in
istri ct
g dis trict
Figure 1: The divided mining districts of Heidaigou surface coal mine
MINING DISTRICTS TRANSITION METHODS OF COMBINED TECHNOLOGY The basic mining districts transition methods According to the positional relation of the two adjacent perpendicular mining districts and formation characteristics of the new mining working face, the mining districts transition method can be classified as two basic modes, which are fan advance of working face and gentle slope inner-dumping (Cao, 2012).
(1) Fan advance of working face Before the first mining district reaching the pit limit, working face should be rotated around one side in the form of the fan advancing, until the new working face in the second mining district is formed, then the mining districts transition is completed. As shown in figure 2, the volume of stripping and excavating is stable and without the re-stripping phenomenon of covering end-wall during the whole fan advance transition period.
(2) Gentle slope inner-dumping When the first mining district is closed to the pit limit, the whole end-wall near the second mining district is not be covered with inner dumped materials and a ditch is left at the boundary of the mining district, then it can be used as the working slope of the new mining district, shown in figure 3. The method can reduce the re-stripping overburden volume of the second mining district, but it can also result in the inner-dump space reduction and the haulage system cannot be
Vol. 18 [2013], Bund. U
5088
arranged at the end-wall, so that the bilateral transportation routes turns to the single one, which makes the transportation distance increased.
mining district Ⅰ
mining district Ⅰ
mining district Ⅱ
Figure 2: Fan advance of working face
mining district Ⅱ
Figure 3: Gentle mining inner-dumping
Adaptation of combined mining technology to transition methods Compared to gentle slope inner-dumping, the working face of fan advancing is inclined with the end-wall, and the mining width is not fixed along the working face, the enlarged working line length makes it more difficult of organization and management. For the gentle slope innerdumping, due to the reduction of the covering materials volume to the working slope of second mining district, the inner dump space in the first mining district reduced so that the external dumping volume and the haulage distance increased. Under the special conditions of adopting combined mining technology in Heidaigou surface coal mine, the shovel-truck discontinuous technology is characteristic of flexible and stronger adaption for the working face and suitable for various kinds of working face layout forms. Considering the particularity of dragline working and shifting of belt-conveyor, both of them have a higher requirement for the working face layout, so the mining technology of bucketwheel- excavator system and dragline are the key restrictive factors of influencing mining districts transition selection.
Vol. 18 [2013], Bund. U
5089
Table 1: Different mining technology adaption to transition methods production technology
gentle slope inner-dumping
fan advance of working face
shovel-truck discontinuous technology
high
higher
higher
low
higher
low
high
high
bucket-wheel-excavator-belt conveyor continuous technology dragline stripping technology shovel-truck-crusher-belt conveyor semicontinuous
As shown in the table 1, BWE system and dragline technology have a higher adaption to gentle slope inner-dumping transition method. For the technology including truck of discontinuous and semi- continuous, the gentle slope inner-dumping method has a greater adaption to fan advance of working face. Hence, considering the restrictive requirement of BWE system and dragline technology, the gentle slope inner-dumping is selected as the applied transition method for Heidaigou surface mine’s turning.
OPTIMIZATION ON THE INNER-DUMPING COVERING HEIGHT The gentle slope inner-dumping constraint condition of mining area perpendicular transition Adopting the gentle slope inner-dumping method in mining area perpendicular transition, overburden material dumped in the terminal stage of the first mining area must be re-stripped when exploiting coal seams of the second mining area under the inner-dump.
B
I
ΔH α C
res
J G
K
E
g pin p i tr
H
β F
h
Figure 4: The gentle slope inner-dumping transition model of perpendicular mining area As can be seen from figure 4, the sectional area of coal under the covered end-wall can be calculated as:
= S1 h ( 2 H − 2∆H + h ) cot α
(1)
where, S1 is the sectional area of coal exploited under the covered end-wall, m2 ; α is the entity end-slope angle, °; H is the distance of the coal seam to the surface, m; ∆H is the height of uncovered end-wall, m; h is the thickness of coal seam, m.
Vol. 18 [2013], Bund. U
5090
Meanwhile, the sectional area of rock need to be removed can be expressed as:
= S2
1 2 [( H + h) 2 − ∆H 2 ] ⋅ (cot α + cot β ) + ( H − ∆H ) cot α 2
(2)
where, S 2 is the sectional area of rock to be removed, m2 ; β is slope angle of the inner dump, °. Consequently, the height of uncovered end-wall should meet the conditions as the formula (3) according to the principle of average stripping ratio being not more than the economic stripping ratio (GUO, 2010).
η
1 2 ( H − ∆H 2 )(cot α + cot β ) + ( H − ∆H − h) 2 cot α 2 ≤η j h(2 H − 2∆H + h) cot α
(3)
where η is the average stripping ratio; η j is the economic stripping ratio.
The uncovered end-wall height optimizing of gentle slope inner-dumping Due to the end-wall being not covered completely, there are two factors constituting the economic benefit of gentle slope inner-dumping in perpendicular transition, one is the increased haulage expense C1 and another is decreased re-stripping expense C2 , which can be expressed as:
Q ⋅ ∆L ⋅ γ ⋅ c 1000 C2 = Sg ⋅ l1 ⋅ a
C1 =
(4) (5)
where γ is average bulk density of overburden material, t/m3 ; c is ton-km freight of truck, RMB/t·km ; l1 is the length of the new mining area, m ; a is the secondary stripping unit expense, RMB/ m3 ; ∆L is the increased haulage distance, m; Q is the increased transportation volume, m3 ; S g is the sectional area of the covered end-wall, m2 . And there are relations as the follows:
∆L = l − (2 H − ∆H ) cot β
(6)
Q= l1 ⋅ [l − ( 2 H − ∆H ) cot β ] ⋅ ∆H / 2
(7)
S= ( H ∆H − ∆H 2 / 2) ⋅ (cot α + cot β ) g
(8)
Taking the time value of money into consideration, the total benefit J of the gentle slope inner-dumping in mining area perpendicular transition can be expressed as:
= J C2 (1 + ρ )
−
l1 d
-C1
(9)
where d is the advancing length per year, m/a; ρ is the annual interest rate, %. According to the formula (4) to formula (9), the relationship between the total benefit J and the uncovered end-wall height ∆H can be simplified as:
Vol. 18 [2013], Bund. U
5091 J = I1∆H 3 + I 2 ∆H 2 + I 3 ∆H
(10)
l − l1rc ⋅ cot 2 β l1rc ⋅ (l − 2 H cot β ) cot β l1a (cot α + cot β ) d where= I1 = − ⋅ (1 + ρ ) , , I2 2000 1000 2
= I3
l − l1rc ⋅ (l − 2 H cot β ) 2 − l1aH (cot α + cot β ) ⋅ (1 + ρ ) d 2000
Then taking the derivative of the formula (10), the two extreme value can be obtained as:
-2I ± 4 I 22 − 12 I1 I 3 ∆H = 2 6I1
(11)
According to the actual situation of Heidaigou surface coal mine, the parameters for calculating the optimal uncovering end-wall height of gentle slope inner-dumping are listed in Table 2.
Table 2: The parameters for calculating the optimal uncovering end-wall height parameters
symbol
unit
value
working face length
l
m
2159
γ
kg/m3
1.49
overburden material haulage cost
c
Yuan /t·km
3.6
entity end-slope angle
α
°
38°
slope angle of the inner dump
β
°
26°
distance of the coal seam to the surface
H
m
170
coal seam thickness
h
m
average bulk density of overburden material
30 3
the secondary stripping expense
a
Yuan /m
14
advancing length per year
d
m
340
annual interest rate
ρ
%
5
Vol. 18 [2013], Bund. U
5092
440
375
375
375
375
375
375
375
375
375
375
375
375
440
7000
18500
19000
19500
20000
20500
21000
21500
22000
22500
23000
23500
24000
7000
北 440
440
6500
6500 1217.203
1208.319
1216.257
1235.9
1238.570
1204.4
1204.3
1200.6
1253.485 1255.089
1189.2
1229.2
1220.4
1238.392
1186.4
1215.261
1234.464
1210.799
1237.255 1216.449
1231.4
1226.370
1214.357
1242.7
1226.631
1237.116
1244.7
1199.431
1236.275
I
1212.480
1205.599
1219.418
1260.223
1245.373
1228.9 1239.525 1228.962
1276.916
1311.922
1239.2
1276.069
1203.7
1244.581
1277.574 1260.358
1244.130
1259.084
1251.387
1214.384
1218.182
1247.2
1248.082
1247.3
1287.800 1288.130 1287.200
440
1287.999
1241.520
440
1242.872
1259.000
1250.948
1274.982
6000
1248.505 1251.43
1231.0
1287.300
1286.339
1215.068
1251.230
1213.600 1251.980
1214.85
1249.630
1287.433
1279.146
6000
1287.052
1259.233
1289.159
1248.995
1250.247
1218.574
1242.080
1280.034 1212.301
1287.500 1289.164
1276.679
1276.821
1287.800
1246.702 1256.796
1217.556
1241.344
1276.856 1256.8
1256.808 1273.995
1243.097
1233.868
1278.296
1276.988 1273.757
1268.837
1277.900
1274.204
1260.065
1280
1260
1200
1220
1240
ter Ex
5500
1231.093
1257.7 1219.144
站
3#
1237.094
1277.018
1265.2
1249.9
1260.051
、
4#
破碎
440
1237.248 1217.770
5500
1226.397 1228.945 1252.3
1256.7 1239.810
1251.3
1265.4
1219.070
1277.2
1257.5
1276.321
1239.404
1245.4
1257.8
1219.891
1262.6
1270.3
1218.762
1286.5
1239.791
1266.7 1245.148 1249.0
1274.062
1275.2
1239.029
1279.3
1218.169
1260.860
1218.456 1218.169
1285.3
1238.810 1245.9
1273.5
1223.1
p m du
1260
1229.377
1235.113
1252.7
1241.2
l na 1260
5000
1233.786
1257.1 1256.7
1280
440
1230.974 1231.177
1260.1
440
1241.886 1232.050
1287.145
1252.1
1257.5
1291.212
1287.932
1287.8
1259.650
1260.505
1260
1239.404
1217.169
1286.439
440
5000
1259.050
1263.6
1217.982
1255.5
1254.4
1240.791 1245.417
1275.529
1259.116
1247.081 1240.029 1256.481 1216.236
1244.000
1238.846
1249.580 1216.133 1243.636
1253.033
1245.876
1200
1220
1240
1244.483
1243.894
1240
1249.537
1240.480 1212.104 1246.8 1266.88
12
1229.382
60
1241.199
1230.636
1215.948
1252.541
1239.218
440
440
1210.006
4500
1240
1233.0
站
1237.000
破碎
12
12
15
2#
1236.5
4500
1214.477
1241.664
1255.1 1253.950
In ter
1#
、
1251.2
1240.2
1220
1212.8
1220
12
80
126 0
1206.458
440
1213
1215 端帮路
4000
1240
11
1180
1160
70
1200
1241.483
1208.199 1238.472
1228.977
1240.051
1206.825 1261.529 1237.360
1224.997
na l
11
48
1148
1185.000
1179
1230.364
48
124
0
1260.742 1224.983
1239.600 440
4000
1260.425
du m p
1224.741
1240.000 1259.026
1224.824
1258.612 1258.771
1240.000
1204.031
1236.3 1259.045 1228.964 1259.304
1221.811
1241.914
1259.296 440
440
3500
11
3500
121
1245.759
3
22
11
1260.339 1230.903
63
117
9
0
1210 1195 1180
reg io
440
10
3000
120
10
1
1
62
117
117
1
11
121 3 122 3
en ch
1
co al be nc h
1216
113
7
1213
1219
1210 1216 1213
113
7
25
114
121 9 123 4
pe rc oa lb
bo tto m
1
11 37
16
0
11 11
up
120
n
11 11 25 40
114
ing
11 52
11 11 37 52
94
wo rk
11 64
11 11 49 64
120
94
ne
440
11 49
10
10
dra gli
11 72
3000
1245.500
11
02
1
114 8
1222 1219
440
440
2500 1222
27
1221
82
11
co al be nc h
1222 1222
10
1220
98
1222
11
58
idd le
11
m
2500
11
68
25
1217
1202
大 成 线 公 路
11
11
40
11 11 49 64
00 306.69
11 11 37 11 52 37
11 11 25 40
11 11 13 28
440
2000
60
2000
1215
11
440
1200 2012
1165
0
11
0
0
121 0
0
122
121
49
120
52
0
120
119
11
0
0
123
122
440
440
1500
1500
375
375
375
375
375
375
375
375
375
375
375
375
18500
19000
19500
20000
20500
21000
21500
22000
22500
23000
23500
24000
Figure 5: The planed project position of Heidaigou surface coal mine in the end of 2013 The reasonable range of the uncovered end-wall height is less than 157.7m according to the formula (3), and the height determined by formula (11) is 87.88m, which is the optimum value since within the reasonable range. At present, Heidaigou surface coal mine is being in transition gradually to the second mining district, the bottom of uncovered end-wall locates on the 30m above the casting blast bench and the uncovered height is around 80m. Figure 5 shows the planed project position of Heidaigou surface coal mine in the end of 2013, the bucket wheel excavator system has been working in the second mining district for loess stripping, and the other technology system are still working in the first mining district.
CONCLUSIONS (1) Two kinds of transition methods of fan advance and gentle slope were determined for the transition of the adjacent perpendicular mining districts in consideration of the formation characteristics of the new working face. (2) It was analyzed that the adaptation requirement of the different mining technology to the transition modes, and both the BWE system and dragline technology are the key factors, therefore, the gentle slope inner-dumping method was confirmed as the transition way for Heidaigou turning into the second mining district. (3) The gentle slope inner-dumping constraint condition of mining area perpendicular transition was confirmed on the basis of the principle that the average stripping ratio is not more than the economic stripping ratio, the optimizing uncovered end-wall height was confirmed as 87.88m in terms of the optimization model.
Vol. 18 [2013], Bund. U
5093
ACKNOWLEDGEMENT The authors acknowledge the support of the National Natural Science Foundation of China (51034005)
REFERENCES 1.
JI, C.S (2011) “Study on Turning Method Between Neighboring Mining Panels in Surface Mine” Coal Engineering, No. 12, pp 1-3,7.
2.
SHANG, T., Q. X. CAI, and Y. LIU (2004) “Optimal Selection of Pit Haulage System in Transition Period for Mining-in-Areas,” Journal of China University of Mining & Technology, Vol. 33, No.4, pp 412-416.
3.
LIU, X. Q., Z. Q. LI, and J. H. SHI (2001) “Existing Problems and Countermeasures During the Mining Districts Transition Period,”. Surface Mining Technique, No 4, pp 8-9.
4.
XU, Z. Y., Q. X. CAI, and X. Q. LIU (2006) “Some Problems and Countermeasures of Mining Area Turning for Antaibao Surface Coal Mine,” Coal Engineering, No. 12, pp 9-12.
5.
CAI, Q. X., and C. S. JI (1996) “Transition Method from One Mining Area to the Next in Large Surface Coal Mines,” Journal of China University of Mining & Technology, Vol. 25, No. 4, pp 45-49.
6.
ZHOU, W., Q. X. CAI, and Y. P. LI (2009) “Study on Inner Dumping Covering Height in Large Near Horizontal Surface Mine,” Coal Science and Technology, Vol. 37, No. 1, pp 53-55.
7.
SHANG, T.,Q. X. CAI, and Y.D. ZHANG (2005) “Analysis of Some Technological Problems for Large Surface Coal Mines in China,”. Journal of China University of Mining & Technology, Vol. 34, No. 2, pp 138-142.
8.
GU, Z. H., and S. G. LI (1995) “Study of Remained-Slope Mining In Surface Mines with a Flat-Buried Deposit,” Journal of China University of Mining & Technology, vol. 24, No. 2, pp 59-63.
9.
CAO, B. (2012) “The Optimization Research and Application of Surface Mine Transition Alternative Mode of Mining Area and Transportation Dumping Engineering under Complicated Geological Conditions,” China University of Mining & Technology (Beijing).
10. GUO, Z. C (2010) “The Calculation Method and Analysis of Reasonable Stripping Ratio,” Modern Mining, No.10, pp 116-117.
© 2013 ejge