T.R. MINISTRY OF FOOD, AGRICULTURE AND LIVESTOCK
DİYARBAKIR BATMAN SİİRT DEVELOPMENT PROJECT IFAD Loan No 718 –TR
2012 SEMI-ANNUAL REPORT (JANUARY - JUNE)
EXECUTIVE SUMMARY
As it is known that, as well as the last year for Project activities was 2012 according to the Loan Agreement, it was need to arise to extend the project for one more year as a result of analyzing and evaluating the Project budget, targeted activities and leading role and socioeconomic effect of the Project. As a consequence of the negotiations conducted between Ministry of Food, Agriculture and Livestock officials, Undersecretariat of Treasury and Ministry of Development officials, the closing date was rescheduled to be 30 June 2013 and completion date to be 31 December 2012. This time of extension provides very important advantages for impact and assessment analysis of Project activities performed from the beginning of the Project and an important opportunity and basis for activities targeted by the end of the Project. In this regard, Project activities performed in the first six-month of 2012 are the essential indicator of accumulation of knowledge and experience from the beginning of the Project to present for the Project which came to the maturity stage now. Also, these activities act as the projection for the activities performed upcoming period. If Project activities performed in the first six-month of 2012 are taken into the consideration; it attracts the attention that there are density and diversity of activities in all components of the Project. Construction of closed system irrigation canals which were planned in order for the benefit and the improvement of the quality of life for the village population were completed. These works having major social and economic effects on rural areas gain important changes on practice habits of rural people’s livestock and agricultural production and irrigation activities. Also, it is expected that farmers will gain leasing
and acting collectively habit and increase in their incomes. Meetings, farmer’s trainings and courses, agricultural tool and equipments and demonstrations under the awareness raising activities reach their aims entirely now and show their multiplier effect. In order to diversify rural income resources and increase employment in Project provinces, it is continued to contribute increase the agricultural economic growth with grant programmes realized under agricultural production and irrigation projects and economic investment projects. Also, it is taken a step importantly for not only production stage but also supporting and improvement of processing and marketing activities of Supply Chain specified by the Project. Moreover, under the component of Capacity Building for Employment; vocational trainings for employment of disadvantaged groups living in rural areas and establishment activities of greenhouses and silk fabric atelier for women living in rural areas especially have importance on encouraging women for production, providing women with integration of social and economic life and cultural dimensions in the Project provinces. Furthermore, awareness and implementation area of the Project were raised in the Project provinces. Besides, project advertising activities increasingly continue for people in rural areas, public and private sectors and local actors. PMU, PDA, MFAL and UNDP staff works coordinately, devotedly and determinedly. Consequently, all activities under the Project will be performed with higher responsibility and precisely to be successful in following years.
INDEX SECTION 1 ............................................................................................ Error! Bookmark not defined. 1.1 GENERAL INFORMATION .......................................................... Error! Bookmark not defined. 1.1.1. Project Area .................................................................................. Error! Bookmark not defined. 1.1.2.Project Target Group ..................................................................... Error! Bookmark not defined. 1.1.3.Objectives of Project ..................................................................... Error! Bookmark not defined. 1.1.4. Companent of Project ................................................................... Error! Bookmark not defined. 1.1.4.1. Component A – Village Improvement Program........................ Error! Bookmark not defined. 1.1.4.2. Component B – Rural Economic Growth.................................. Error! Bookmark not defined. 1.1.4.3. Component C – Capacity Building for Employment ................ Error! Bookmark not defined. SECTION 2 ............................................................................................ Error! Bookmark not defined. 2.1. Activities Realized in 2012 by Components ................................... Error! Bookmark not defined. 2.1.1. Component A – Village Improvement Program........................... Error! Bookmark not defined. 2.1.1.1. Component A1: Awareness Raising .......................................... Error! Bookmark not defined. 2.1.1.2. Component A2: Farmers’ Education and Training ................... Error! Bookmark not defined. 2.1.1.3. Component A3: Infrastructure for Village Improvement .......... Error! Bookmark not defined. 2.1.2. Component B - Rural Economic Growth .................................. Error! Bookmark not defined. 2.1.2.1 Component B2: Contributory Grants ......................................... Error! Bookmark not defined. 2.1.3. Component C – Building Capacity for Employment ................... Error! Bookmark not defined. 2.1.4. Component D –Organization and Management of the Project..... Error! Bookmark not defined. SECTION 3 ............................................................................................ Error! Bookmark not defined. 3.1. FINANCING, COST AND EXPENDITURES OF THE PROJECTError! Bookmark not defined. ANNEX 1SCHEDULE OF PROJECTACTIVITIES BY COMPONENTSFOR 2012Error! Bookmark not defined.
TABLE INDEX
Table 1. Farmer Education and Training Activities Realized in 2012………………………………………………….………..10 Table 2. Distribution of Farmers’ Education and Training Activities in 2012 by Provinces …………….……..…..…11 Table3. DBSDP Farmer Education and Training Activities (According to AWPB) …………………………………………..11 Table 4. Demonstrastion Activities In 2012……............................................................................................12 Table 5. Closed System Irrigation System Investment............................…..………………………………..…….…..……14 Table 6. 2012 Dbsdp Agricultural Production And Irrigation Projects ……………..……………………………..….……….16 Table 7. 2012 Dbsdp Agricultural Production And Irrigation Projects Grant Programme (General)……….......18 Table 8. Economic Investment Projects In Diyarbakir ……………..……………………………………..…………………...……19 Table 9. The Activities Under Capacity Building For Employment In 2011 (General)……………………….…….….…20 Table 10. List Of Project Staff ………….…………………….…………..………………….…………………………………………..……..21 Table 11.Financing Sources and Investment Amount of the Project …..……………………….…………………………….24 Table 12. Summary of Expenditures by Loan Categories and by Financiers for 2012 (USD)..……………….……..25 Table 13. Summary of Expenditure Categories by Financiers for 2012 (USD)......……………………………...……….26
ABBREVIATIONS
RA Regional Administrator DBSDP Diyarbakır Batman Siirt Development Project SHW State Hydraulic Works F/PO Finance/Procurement Officer IFAD International Fund for Agricultural Development AP Animal Ponds SPA Special Provincial Administration PFE Provincial Field Engineer PDA Provincial Directorate of Agriculture BDS Business Development Specialist M&E Monitoring and Evaluation GICGC Guidelines for Implementation of the Contributory Grant Co-financing CPMU/MFAL Central Project Management Unit/MFAL PA Program Administrator PAU Project Administration Unit PMU Project Management Unit PIM Project Implementation Manuel PSA Program Support Associate (UNDP/CO) SIP Strategic Investment Program TEDAŞ Turkish Electricity Distribution Corporation MFAL Ministry of Food, Agriculture and Livestock GDAPD General Directorate of Agricultural Production and Development SCM Supply Chain Management NRDS National Rural Development Strategy UNDP United Nations Development Program UNDP/CO UNDP/Turkey Country Office (Ankara) AWPB Annual Work Plan and Budget
SECTION 1 1.1 GENERAL INFORMATION 1. The Project is being implemented by the Ministry of Agriculture and Rural Affairs, General Directorate of Agricultural Production and Development. UNDP assists the programme administration for project implementation in the scope of flow of funds, accounting and supply of goods and services, and also will provide 752.000 USD financing as a grant for the 5 year implementation of the Project. 2. Project was included in 2006 investment program with the decision of the Higher Planning Council dated 22.11.2006 and numbered 2006/87. “Loan Agreement” was signed on 5 March 2007 between the financing institution IFAD and the Undersecretariat of Treasury on behalf of GoT and adopted by the Cabinet on 14 May 2007. 3. “Grant Agreement” was signed on 19 June 2007 between the Undersecretariat of Treasury and UNDP. 4. “Service Agreement” has been signed on 6 September 2007 between our Ministry, Ministry of Foreign Affairs and UNDP. 5. The Project was put into force on 19 December 2007 after all necessary conditions were fulfilled, and the closing date was identified by IFAD to be 30 June 2013 and completion date to be 31 December 2012. Negotiations have been completed between MFAL and the Undersecretariat of Treasury. As a result of meeting, implementation period of project was extended and the closing date was identified by IFAD to be 30 Haziran 2014 and completion date to be 31 Aralık 2013 has been revised. 1.1.1. Project Area 6. The Project area covers Diyarbakır, Batman and Siirt Provincial borders of South-eastern Anatolia. 7. The climate is harsh with severely cold winters and hot dry summers. Precipitation ranges from about 200-700 mm. In Diyarbakır the average January temperature at nights is -24°C and maximum temperature in July and August can reach 46°C. The growing season is short. 8. Total agricultural land of three provinces in the Project area is 994,869 ha, forest area is 473,376 ha and pastureland is 451,764 ha. Total land is 2,430,362 ha.
9. The most important potential natural resource in the Project provinces in GAP region is water potential of watershed of Euphrates and Tigris Rivers. Also, natural resources such as petroleum, copper, marble seam with colored streak, forest, pastures and culture and
tourism resources exist in the region. Rich and high quality marble reserves in Diyarbakır are attractive commercially.
1.1.2. Project Target Group 10. Primary target group is poorer rural men, women and young people living in the project provinces. Secondary target group is new or established businesses with sustainable profit. 1.1.3. Objectives of the Project 11. Main objective of the Project is to improve economic and social status of the poor people living in rural areas in accordance with Turkey’s National Rural Development strategies, plans and programs. 12. Project’s primary objectives are to; a)
b)
c)
Improve the quality of life of population and economic efficiencies of agricultural enterprises being poor due to current production and employment patterns in poor rural villages in the Project area, Develop both on- and off-farm income sources and establish new businesses through developing Supply Chain Management and increase employment through the establishment of new and expansion of existing profitable businesses, Optimize employability of members of the target groups through enhancement of individual and organizational skills necessary to achieve objectives (a) and (b).
1.1.4. Components of the Project 13. Investment activities of the project are implemented under three main components; a) Village Improvement Program, b) Rural Economic Growth, and c) Capacity Building for Employment. On the other hand, the following component was designed as a fourth component for sound and effective implementation of the Project and realization of necessary planning and budget control activities; d) Project Coordination and Management Component. 1.1.4.1. Component A – Village Improvement Program
14. Selected economic and social investments will be supported under this component to improve the living standards of poor villages. This component comprises three subcomponents;
a) b) c)
Awareness raising, Farmer Education and Training, Infrastructure Investments for Village Improvement.
15. Awareness Raising sub-component comprises the activities for raising awareness of rural population about existing financial and social development support types and resources that are necessary for determining investment opportunities at village level and facilitating these kinds of investments. 16. With Farmer education and training sub-component, firstly it is targeted to determine cost effective and sustainable earnings in subsistence and semi-subsistence farming systems in Project villages. Secondly, it is targeted to develop related training curriculum, materials and a training menu. Lastly, by using the training menu, it is aimed to ensure that farmers demand special trainings on their needs, to be provided by PDAs through increasing demonstrations and technological transfer programs. 17. Under the Infrastructure Investments for Village Improvement sub-component, investments are provided for the benefit of the village population and to increase quality of life in villages within the Project Area meeting the criteria for public infrastructure implementations. 1.1.4.2. Component B – Rural Economic Growth 18. This Component includes measures for diversification of rural income resources and increasing employment in Project provinces. Rural Economic Growth Component is composed of three main sub-components; a) Rural Supply Chain Management, b) Contributory Grants, c) P/DDA Staff Capacity Building, 19. Investment needs and opportunities determined by Supply Chain Management SubComponent will form a basis for investments to be supported by the Project. 20. Under the Contributory Grant Sub-component, it is targeted to provide contributory cofinancing and also leverage fund by loans that investors provide from their own resources or financial institutions in order to improve facilities determined under SIP ‘Strategic Investment Plan’ to accelerate the economic growth in the Project area. 21. Under the P/DDA Staff Capacity Building sub-component, it is targeted to develop institutional capacity by improving knowledge and skills of technical staff in Provincial and District Directorates of Agriculture on Strategic Investment Plans. 1.1.4.3. Component C – Capacity Building for Employment
22. This component seeks to enhance access of surplus labour in the participatory Project villages to employment with better salaries in rural economy. 23. Targets of the component and approaches to realize these targets are (i) to determine knowledge and skills that employers need potentially, information on number of persons
to be employed and whether or not there are staff having right knowledge and skills via a study in the overall Project area; (ii) to analyze trends, opportunities and problems of labor market in the region; (iii) to develop appropriate training program to increase employability in the target groups; (iv) to improve support activities necessary to develop productivity structure of labor market and (v) to provide training for persons who are interested in obtaining necessary skills and knowledge for fitting potential vacant positions. SECTION 2 2.1. Activities Realized in 2012 in Period of January to June by Components 2.1.1. Component A – Village Improvement Program 2.1.1.1. Component A1: Awareness Raising 24. Including information especially on DBSDP, information regarding existing projects in each Project Province, subjects and targets of supports, eligibility criteria, type of support, ways of granting the support, application procedures and contact information of the places where support is provided are compiled under an introduction and information brochure. The brochure, preparation phase of which is complete, will be printed within August. 25. In order to achieve the Project target, impact and sustainability in each Project province and to generally introduce and evaluate project activities, project publicity meetings will be held in August and September with wide participation. Works on organizing the meetings are continuing. 26. Rural Development Regional Meeting will be held with the participation of all public institutions and organizations, especially DBSDP, and private sector enterprises active in the Project provinces and working on rural development. Preparation activities for the meeting were initiated under the management of the Regional Administrator. 27. Regular meetings are being held with sector representatives and stakeholders on subjects under the activity are of DBSDP. Periodical meetings are continuing to be held with Karadağ Development Agency, Dicle Development Agency, Diyarbakır Chamber of Commerce, Batman University and Dicle University, which are active in the Region. 28. Information dissemination activities are continuing in Diyarbakır, Batman and Siirt provinces provided by PAU regarding general progress of the Project, grant schemes and Farmer Education and Training programmes. 29. www.dbskp.org web site is regularly updated. The importance of effectiveness of project activities is conveyed through the current web site. Moreover, a space for marketing is being developed on the web site. With this space it is aimed that the producers and buyers meet on a common platform. 2.1.1.2. Component A2: Farmer Education and Training 30. Farmers received detailed and practical training on “Dairy Cattle Breeding” with 4-day trainings in SÜTAŞ Aksaray Training Centre. Generally, necessary information was
provided for the producers on subjects needed by the farmers such as practical trainings on feeding and maintenance of animals, milking, storing and processing milk under hygienic conditions. 31. Practical training on site was provided for vineyard producers regarding “Viniculture”. Trainings were provided regarding modern viniculture (Wired Training System) which has newly started to disseminate in the region, and general information was conveyed to the farmers on problems that they face or can face during production (applying pesticides, ploughing the vineyard, using wired training etc.). 32. “Modern Viniculture Training” was provided for producers in Batman Province, Gercüş District Vineyard Demonstration area and in Vineyard Facilities established in Beşiri District under 50% Grant Programme. Practical training was provided on adaptation to wired training system and pruning techniques suitable for wired training system. 33. Training was provided for the farmers who will use the Closed System Irrigation Channels that were established in Diyarbakır and Batman Provinces. As well as providing practical training on site, the farmers received training from Şanlıurfa Bozova Central Irrigation Union. These training will continue in line with the needs. 34. Beekeeping farmers in Siirt Province received training from Ordu Apiculture Research Institute. Table.1. Farmer Education and Training Activities Realized in 2012 (GENERAL) Number of Number of Participant Subject Place of Education Education Male Female Total SÜTAŞ Eğitim Merkezi Dairy Cow Breeding 2 37 37 Merkezi / Aksaray Tekirdağ Bağcılık Araştırma Viniculture 1 30 30 İstasyonu Müdürlüğü Batman Üniversitesi – ALATA Fruit Growing Education Bahçe Kültürleri Araştırma 10 59 2 61 İstasyonu Trainning and courses for the members of Cooperatives On-site Education for Diyarbakır ve Batman İlleri Demo 4 111 6 117 Producer alanları Exhibition TÜYAP/Diyarbakır 1 25 25 Antepfıstığı Araştırma İstasyonu Sapling Grafting Education 1 25 25 Müdürlüğü Training of Irrigation and 6 279 279 Irrigation Tehcnicals Bozova Merkez Sulama Birliği Arıcılık Araştırma Enstitüsü Apiculture Training 1 27 1 28 Müdürlüğü/Ordu TOTAL 26 593 9 602
Education Period(day) 8 4 5
4 1 2 10 4 38
Table.2. Distribution of Farmers’ Education and Training Activities in 2012 by Provinces Diyarbakır Batman Siirt Subject Dairy Cow Breeding Viniculture Fruit Growing Education Trainning and courses for the members of Cooperatives On-site Education for Producer Exhibition Sapling Grafting Education Training of Irrigation and Irrigation Tehcnicals Apiculture Training
Total
Number Number Number of Female Male Total of Female Male Total of Female Male Total Education Education Education
1
16
16
1
21
21
37
1 10
2
6
1
4
59
65
25
25
232 232
2
2
59
52
6
332 338
30
30
61
61
52
117 25
1
17
17
1
25
25
1
30
279
27
28
1 8
General Total
14
2
149 90
4
1
82
91
602
Table.3. DBSDP Farmer Education and Training Activities (According to AWPB) 2012 PLANNED
Total
1
3
9
4
107
12
112
2
50
6
170
2
1
25
1
1
25
1
3
105
1
1
30
3
33
684
1
2
1 1
1
14
1
16
1
65
2
4
1
3
Siirt
2
Batman
2
Siirt
1
Total Total Number Number of of Educati Participan on ts
Number of Education Diyarbakır
Dairy Cow Breeding Viniculture Fruit Growing Education Trainning and courses for the members of Cooperativ es On-site Education for Producer Exhibition Sapling Grafting Education Training of Irrigation and Irrigation Tehcnicals Apiculture Training
Batman
Subject
Diyarbakır
Number of Education
2012 REALIZED
2
66,7%
37
56,9%
1
25,0%
30
28,0%
10
10
83,3%
61
54,5%
2
4
66,7%
117
68,8%
1
100,0%
25
100,0%
1
100,0%
25
100,0%
1
6
200,0%
279
265,7%
1
1
100,0%
28
93,3%
3
26
78,8%
602
88,0%
1
1
4
8
% % Percenta Total Percenta Total ge of Number ge of Number Total of Total of Number Educati Realized Participan of on Educatio ts Participa n nt
1
15
DEMONSTRATION 35. In Diyarbakır and Siirt Provinces, selections were made regarding the fruit varieties that could be grown in the region. Areas were identified through District Directorates in the regions that could be suitable for the selected fruit varieties where orchards can be established. Suitability of the selected fruit variety was identified by taking soil samples and meteorological data from the identified areas. In line with the advice received from Stations and Agricultural Research institutions, instead of the previously identified Pear variety for Diyarbakır, semi-dwarf apple was planted based on information regarding difficulty of finding certified sapling and difficulty of adaptation in the region. Orchard establishment was completed in line with the varieties identified with the relevant Stations. Details are provided in Table 4. Table.4. 2012 DBSKP DEMONSTRATIONS (GENERAL) PLANNED ( According to AWPB ) Konu
Diyarbakır Batman Siirt ( da )
( da )
Total Area
( da ) ( da )
REALIZED ( According to AWPB )
Number Diyarbakır Batman Siirt of Total Farmers ( da ) ( da ) ( da )
Total Area ( da )
Number of Total Farmers
Cherry
20
20
2
20,23
20,23
2
Apricot
20
20
2
18,64
18,64
2
Plum
20
30
3
16,33
24,83
3
Half Dwarf Apple
20
20
2
13,8
13,8
2
14,59
2
10
8,5
High Training Fence System (Vineyard)
20
20
2
Nektarine
10
10
1
10
10
1
Pomegranate
20
20
2
8,75
8,75
2
0
-
0
-
Corn (for Silage)
40
40
2
Clover
15
15
2
Solar Energy System TOTAL
30 135
30
60
30
6
225
24
14,59
69
0 41,84 110,84
36. Activities are continuing regarding Silage Maize and Alfa Alfa orchards planned to be established in Çermik and Hani Districts of Diyarbakır Province where Closed System Irrigation Channel was installed. 37. Batman PAU is continuing preparing the technical specifications of Solar Energy systems to be installed in Batman Province for demonstration. 38. On site education and training activities are continuing for the demonstration areas established in Batman Province in the previous years. Using the established orchards for on site education and training activities in the region also shows that important areas were created.
14
AGRICULTURAL MACHINERY AND EQUIPMENT 39. 10 Grape Crushing Machines for Diyarbakır province and 3 Stalk Choppers for Batman province which were included in 2011 AWPB but the procurement of which were made in 2012 were delivered to the Provincial and District Directorates of Food, Agriculture and Livestock. Moreover, 2 Sapling Hole Drills planned to be procured for Batman province in the 2012 AWPB were procured. 40. In order to ease and provide more accuracy for the measurements during identification works of Diyarbakır, Batman and Siirt PMUs, 0-150 mm Digital Caliper, 500 mm Water Level, 0-25 mm Digital Micrometre, Digital Altimeter were procured (1 each). 41. For Siirt Province, procurement process is continuing regarding 2 Branch and Leaf Shredders included in 2011 AWPB and 1 Straw Baling Machine, 1 Stubble Drill and 1 Poisonous Wheat Preparation and Packing Machine, which were planned to be procured in 2012 AWPB. 42. It is planned that the required energy for irrigating the orchards established in Batman Province with Drip Irrigation Systems is provided by Solar energy systems. Feasibility studies for 4 orchards where the systems will be built by Batman PAU in line with the plans are finalized.
43. Preparation of technical specifications in line with the finalized feasibility studies for the procurement of solar energy systems is continuing..
2.1.1.3. Component A3: Village Improvement Infrastructure 44. Regarding the Closed System Irrigation Channels planned to be built in Diyarbakır (Hani District –Centre, Kulp District -İslamköy village and Çermik District -Karakaya and Artuk villages) and Batman (Kozluk District -Tosunpınar village) provinces, construction contract was signed on 26-07-2011, location was handed over on 12-09-2011 and construction started as of this date. It is planned that closed system irrigation channels construction works will be finalized by the end of August 2012. Details on closed system irrigation channels are provided in Table 5.
Table.5. 2012 DBSDP Closed System Irrigation Canal Investments
NO 1 2 3 4 5
Province Diyarbakır Diyarbakır Diyarbakır Diyarbakır Batman
District Hani Kulp Çermik Çermik Kozluk
Village Merkez İslamköy Karakaya Artuk Tosunpınar TOTAL
Population 3.480 2.500 150 400 500 7.030
Number of Irrigation Area (da) Households 580 169 22 53 70 894
5.140 530 307 108 300 6.385
Irrigation Channel Length (m.) 19.004 3.620 2.270 503 3272 28.669
45. Water quality analyses for assessing the treatment capacity and sufficiency of sewage systems, which were built in the scope of DBSDP, under different climate conditions were made with samples from Diyarbakır (2 samples), Batman and Siirt (1 sample each) and a report was prepared. 46. The survey project was finalized regarding the 19 km field road planned to be made as per the Protocol signed with Diyarbakır Special Provincial Administration. Tender announcement will be made for the construction works. 47. 8 destinations were identified for the field roads planned to be made in Siirt province. Activities have started regarding 4 of the 8 destinations identified.
2.1.2. Component B – Rural Economic Growth 2.1.2.1 Component B2: Contributory Grants 48. Grant announcement was made for Agricultural Production and Irrigation Projects on 05.12.2012 in line with Batman Province Strawberry Sector Strategic Investment Plan. As a result of the grant announcement, which ended on 13.01.2012, 100 Agricultural Production and Irrigation Projects were received. Contracts were signed with 52 project owners which were found eligible for grant in accordance with the assessments made in line with grant announcement criteria. 49. The second Grant announcement was made for Batman Province Strawberry Sector on 07.05.2012. As a result of the grant announcement, which ended on 25.05.2012, 44 Agricultural Production and Irrigation Projects were received. The assessment of received applications is continuing. 50. Grant announcement was made on 15.05.2012 for the establishment of Vineyards, Almond and Apple Orchards in line with Diyarbakır Province Fruit Production Strategic Investment Plan. As a result of the grant announcement, which ended on 15.06.2012, 81 Agricultural Production and Irrigation Projects were received. The assessment of applications is continuing. 51. Grant announcement was made on 21.05.2012 for Construction of Sheep and Goat Stables and procurement of Machinery and Equipment in line with Siirt Province Sheep Breeding Strategic Investment Plan. Deadline of the grant announcement is 06.07.2012.
Investment Type
Table 6. AGRICULTURAL AND IRRIGATION PROJECTS – GENERAL CONDITIONS 2012 CUMULATIVE (2011 İNCLUDED) Total Total Area Amount Area Amount Approved Payment Canceled Approved Payment Canceled (da) Grant (da) Grant ( ( TL ) TL ) 1364, 7
Almond
85
63
125
Half Dwarf Apple
24
14
14
Vineyard
144
68
104
63
42
65
261,2 935,4 7 483,9 4
35
294
Pomegranate Strawberry
55
45
294
615.180
Milk Sector
TOTAL
55
45
294
615.180
55 18
10
8
389
197
351
696.981,63 189.449,63 1.073.264,11 276.960,24 615.180,25 194.085,41
3339 3.045.921,27
52. Works are continuing regarding announcing new period grant programmes in 2012 in Batman and Siirt Provinces within the scope of Agricultural Production and Irrigation Projects.
Table.7. 2012 DBSDP AGRICULTURAL PRODUCTION AND IRRIGATION PROJECTS GRANT PROGRAMME (GENERAL) Percentange of Total Project Total Amount Total Amount Payment Amount Number of Investor Budget ( TL ) Grant ( TL ) Grant (%) 6 319.676,58 159.838,29 52,20% TOTAL 16 612.445,00 306.222,50 100%
53. It can be stated that the orchard facilities established in the scope of grant programme and demonstrations are effective for the producers to produce in wider areas.
ECONOMIC INVESTMENT PROJECTS 54. Partial milestone payments were made for Eğil Milk Producers’ Association and S.S. Üçtepe and Köseli Agricultural Credit Cooperative which are continuing to be established in Diyarbakır Province in 2012. Details are provided in Table 8. Table.8. ECONOMIC INVESTMENT PROJECTS IN DİYARBAKIR
Yatırımın türü Süt Sektörü (Hayvan Barınağı inşaatı, makine ekipman alımı ve Süt Toplama Ağı) Toplam
Toplam Proje Tutarı ( TL )
Gerçekleşen Hibe Ödemesi Tutarı ( TL )
Yatırımın İli
Yatırım Sayısı
Diyarbakır
2
386.714,00
193.357,00
2
386.714,00
193.357,00
55. Grant announcements were made in the scope of Economic Investment Projects for establishment of Grape Processing (Grape Juice, Molasses (pekmez), Paste with Walnut (sucuk), Dried Pulp (pestil) etc. production) and Packing Facility (Construction, Rehabilitation), and procurement of machinery and equipment, and for establishment of Milk Processing and Packing Facility (Construction, Rehabilitation) for Milk and Milk products (Cheese, Yogurt, Ayran, Butter etc. production) and procurement of machinery and equipment. 8 Economic Investment Project applications were received. The assessment of applications are continuing.
2.1.2.1
Component B3: Capacity Building for PDFAL Personnel
56. In the sub-component Capacity Building for Provincial Directorate of Food, Agriculture and Livestock Personnel, practical trainings are provided regarding new production methods in order to increase professional knowledge capacity of the Technical Staff. 57. A group of 28 people including 14 Technical Personnel and 14 Farmers from Diyarbakır and Batman provinces carried out a technical visit to Manisa and İzmir provinces regarding marketing. Milk production, milk processing and marketing, viniculture, grape processing and marketing facilities were visited in Manisa and İzmir provinces. Also during the visit, experiences were shared with successful cooperatives in the region. 2.1.3. Component C – Capacity Building for Employment 58. Two Certified Grafting Master Training programmes were carried out in Batman province, one in Gercüş Public Training Centre, and one in Beşiri District Directorate of Agriculture. In total 34 people were trained in the scope of these trainings. 34 people who participated in these trainings received promotion packages containing pruning scissors, grafting knife, pruning saw, grafting paste and graft. Approximately 50% of the people who received training in Batman province stated that they were employed as a result of this training programme. Interviews and efforts are continuing for the employment of the remaining people who participated in the training. Table.9. TRAININGS FOR MFAL STAFF IN 2011 (GENERAL) Number of Number of Participant Number of Participant Educations (by province) (by gender) Siirt
Diyarbakır
Batman
Siirt
Inoculation
Batman
Silk Fabric Atelier (Procurement of MahcineEquipment)
Total
Diyarbakır
SUBJECT
Female
-
-
-
-
-
-
-
-
-
-
2
-
2
-
34
-
-
34
34
-
-
-
-
34
34
-
Animal Keeping
-
-
-
-
-
-
TOTAL
-
2
-
2
-
34
Male
Total
59. A location was allocated for silk textiles workshop through Kulp District Directorate of Agriculture and District Governorate. Feasibility study was carried out for the selected location, and needs were identified. Technical specifications are being prepared for the procurement to be carried out in line with the needs. 60. Activities are continuing for the livestock maintenance training planned to be organized in Batman and Diyarbakır.
2.1.4. Component D – Project Organization and Management 61. Existing staff in Ankara Central Unit and Diyarbakır, Batman, Siirt provinces are continuing their works for the project activities. 62. English language trainings were completed for PAU staff in the Project provinces, respectively 7 people in Diyarbakır, 6 in Batman and 4 in Siirt. Table.10. List of PMU Staff
General Directorate of Agrarian Reform
MFAL
Organizations
DİYARBAKIR PROVINCE MANAGMENT BATMAN PROVINCE MANAGMENT SİİRT PROVINCE MANAGMENT
MFAL
DİYARBAKIR ( CENTER OFFİCE)
UNDP
Name
Title
Unit
Ahmet Zahir ERKAN
Head of Department
General Directorate of Agrarian Reform
Dr. Şule ÖZEVREN
Projects Manager
General Directorate of Agrarian Reform
Mustafa Fuat BUZ
Agriculture Engineer
General Directorate of Agrarian Reform
Meltem BAŞOL
Agriculture Engineer
General Directorate of Agrarian Reform
Burak ELDEM
Project Administrator
DBSDP
Murat AKBAŞ
Religion Administrator
Project Managment Unit
Yunus BİRCAN
BDS
Project Managment Unit
Murat BATURAY
Civil Engineer
Project Managment Unit
Murat GÜNSEL
Civil Engineer
Project Managment Unit
Cihad KAYHAN
PFO
Project Managment Unit
Casim Can HİNDİOĞLU
M&E Specialist
Project Managment Unit
Dr. Ali Rıza BOZ
Branch Manager
Project Managment Unit
Yusuf YILMAZ
Agriculture Engineer
Project Managment Unit
Murat ACAR
Agriculture Engineer
Project Managment Unit
Behiye ERTAŞ
Agriculture Engineer
Project Managment Unit
Muhterem Savaş KOÇ
Agriculture Engineer
Project Managment Unit
Yusuf ALP
Branch Manager
Project Managment Unit
Yusuf ŞİMŞEK
Agriculture Engineer
Project Managment Unit
Zeki EDİS
Agriculture Engineer
Project Managment Unit
M. Cengiz ARSLANOĞLU
Agriculture Engineer
Project Managment Unit
M. Salih SÜNER
Agriculture Engineer
Project Managment Unit
Selim DÖĞER
BDS
Project Managment Unit
M. Hakan DEMİRHAN
Branch Manager
Project Managment Unit
Yunus EREN
Agriculture Engineer
Project Managment Unit
Nezir EKİNCİ
Agriculture Engineer
Project Managment Unit
SECTION 3 3.1. FINANCING, COST AND EXPENDITURES OF THE PROJECT 63. The Project is financed by the Government of the Republic of Turkey, International Fund for Agricultural Development (IFAD), United Nations Development Program (UNDP) and Project Beneficiaries. Implementation period is 5 years and its budget is approximately 37 million USD. Distribution of financing sources is indicated in Table 11.
Table.11. Financing Sources and Investment Amount of the Project Amount ( Million USD)
Financing Source
Government Budget
4,454
External (IFAD Loan)
24,104
UNDP Grant
0,752
Beneficiary Contribution
7,607
Total
36,919
Table.12 Summary of Expenditures by Loan Categories and by Financiers for 2012 (USD)) PLANNED BALANCE BY CATEGORY PY 2012- june Incoming Balance
Allocated
Total disb. and advance at PY start Including MAFAL-13)
Outstanding balance on disb.
Outstanding balance on disb.
Expenditure not yet claimed/foreseen for PY 2012- june
Outstanding balance on expenditure
SDR
SDR
SDR
USD
USD
USD
IFAD Loan
No Name 1
CIVIL WORKS
2
EQUIPMENT & MATERIALS
TRAINING 3a WORKSHOPS & STUDIES TRAINING 3b WORKSHOPS & STUDIES 4
TECHNICAL ASSISTANCE-(TA)
5
CONTRIBUTORY GRANTS
PROJECT STAFF 6a SALARIES AND ALLOWANCES
Expenditure Reallocations
Outstanding balance at PY end
USD
USD
USD
5.504.634
428.366
650.067
388.258
261.809
75.744
186.065
264.000
70.465
193.535
293.699
52.832
240.867
165.168
75.699
1.350.000
608.869
741.131
1.124.703
94.741
1.029.962
255.154
774.808
130.000
555
129.445
196.439
196.439
45.000
151.439
400.000
96.172
303.828
461.074
24.305
436.769
25.695
411.074
6.030.000
1.624.061
4.405.939
6.686.233
147.590
6.538.643
2.162.580
4.376.063
1.250.000
516.346
733.654
1.113.356
87.116
1.026.239
132.713
893.526
OPERATING AND MAINTENANCE
375.000
6.630
368.370
559.020
559.020
6c
IMPLEMENTATION SUPPORT
475.000
419.035
55.965
84.929
84.929
93.000
0
93.000
141.132
141.132
1.528.364
-1.528.364
-2.500.000
8.846.767
7.453.233
11.310.653
Advance and adj. for exch. rate variation TOTAL
Outgoing Balance
5.933.000
6b
99 UNALLOCATED
Planned expenditure and reallocations
16.300.000
559.020
58.187
26.743
141.132
-180.631
794.843
10.515.810
2.920.240
0
7.414.938
Table.13. Summary of Expenditure Categories by Financiers for 2011 (USD) AWPB
Source of funding USD
Category
Gov. budget. (INSOURCE) Description/Specification
A-Köy Geliştirme Programı
A1-Bilinçlendirme
A2-Çiftçi Eğitim ve Öğretimi
Total Exp. (2008-2012Including June)
Total Exp. for Period (2012Including June)
IFAD Loan Purchased by UNDP
Provinces and Stamp TAX
UNDP Grant
Clients
IFAD Gov
10.922.736,34
1.510.388,01
421,32
0,00
III-i
949,68
0,00
IV
2.682,43
0,00
VI-ii
1.254.123,07
146.599,49
80.568,83
69.818,44
41.358,44
41.358,44
22.857,46
0,00
III-ii
1.493,51
0,00
IV
9.391.773,38
66.030,66
III-i II
1.298.124,99 1.296.736,10
1.388,89
I
535,14
0,00
177.919,75
24.305,09
162,16
0,00
B-Kırsal Ekonomik Büyüme
6.204.180,12
479.358,03
B2-Katkı Hibeleri
6.159.315,12
466.071,10
39.931,40
13.286,93
4.933,60
0,00
36.036,46
27.692,17
33.732,54
27.692,17
2.303,92
0,00
2.522.461,16
108.589,32
76.447,26
0,00
II
93.217,37
0,00
III-ii
160.461,86
1.583,72
871.420,69
104.110,31
676.359,30
2.895,29
644.554,70
0,00
A3-Köy İyileştirme Altyapısı
B4- TİM Çalışanlarına Yönelik Kapasite Oluşturma
C-İstihdam İçin Kapasite Oluşturma
D-Proje Koordinasyonu ve İdaresi
III-ii 24.305,09
IV VI-ii
201.279,78
264.791,32 13.286,93
V III-i III-ii
9.094,95
18.597,22
III-i II
1583,72 104.030,08 2745
IV 80,23
VI-i
150,29
VI-ii VI-iii
ANNEX-1
SCHEDULE OF PROJECT
ACTIVITIES BY COMPONENTS
FOR 2012
ANNEX 1: SCHEDULE OF PROJECT ACTIVITIES BY COMPONENTS FOR 2012 Component A: Village Improvement Programme Component
Budget (USD)
Activities
A 1. Awareness Raising Project Publicity Brochure
5.000
Determining the content of the brochure, publishing and distributing
Project Publicity Meeting
20.000
Arrenging Project publicty meetings in each Project provinces
Rural Development Programmes Regional Meeting
20.000
Introducing rural development programmes in Project region
J F M A M J J A S O N D Details/Steps
Component A: Village Improvement Programme Component A 2. Farmer’s Training and Education
Budget (USD) Activities
Farmer trainings and courses
162.000
Demonstrations
256.000
Agricultural Tool and Equipment
218.000
A 3. Infrastructure for Village Improvement Remaining Progress Payment for construction of 2011 “Closed System Irrigation Channels” Remaining Progress Payment for construction of 2011 “HIS Ponds”
1.300.000
Determining the content of training and courses, procurement and carrying out Determining the demo areas, procurement and making the gardens Preparing the technical specifications, procurement and transferring the equipment to the district directorates of agriculture
Completion of construction and temporary acceptance
80.000
Making remaining progress payment
Consultancy service for civil works
50.000
Calling for tender, evaluating the tenders, concluding an agreement
Provincial Field Engineer (12 months full time)
60.000
Recruited of a PSE’s
Wastewater quality analysis
4.000
Field roads rehabilitation Total Component A
516.304 2.691.304
Procurement and reporting
J F M A M J J A S O N D Details/Steps
Prepared by the PMU and PAU’s.
Prepared by the PMU and PAU’s.
Prepared by the PMU and PAU’s.
Component B: Rural Economic Growth Component
Budget (USD)
Activities
B 1. Rural Supply Chain Management Conducting VCAs (Value Chain Analysis) for the most promising subsectors in each Project province.
Studies on Supply Chain Management and marketing analysis B 2. Contributory Grants Grant Cofinancing and Beneficiaries' contribution
4.800.000
Preparing new SIPs for 2013 B 3: Capacity Building for PDFAL Staff Technical personnel trainings, courses 45.000 and technical visits Total 4.845.000 Component B
Appraising CG applications and preparing the MoU for disbursement of grants. Determining the new SIPs as a result of supply chain managment analysis and preparing them
Determining the content of training and courses, procurement and carrying out
J F M A M J J A S O N D Details/Steps
Component C: Capacity Building for Employment Component
Budget (USD)
Vocational Trainings and Procurement of 104.000 MachineEquipment Needs assessment and labour market analysis Total 104.000 Component C
Activities Preparing the training programme based on the Regional Needs To be undertaken in conjunction with the Value Chain Analysis
J F M A M J J A S O N D Details/Steps
Component D: Project Organisation and Management Component Studies and Workshops Annual Programming Workshop Evaluation and monitoring
English course
Budget Activities (USD)
15.000 AWP&B Updating the database, baseline studies, surveys for impact assessment To continue for English language 17.325 course for all PAU staff
Project Staff Regional Administrator (1) Business Development Specialist (3) Finance/Procurement Officer (1) Monitoring/Evaluation Specialist (1)
42.000 60.000 30.000 30.000
J F M A M J J A S O N D Details/Steps
Component D: Project Organisation and Management Component
Budget (USD)
Activitie s
J F M A M J J A S O N D
Fees Allowances National Travel
2.250 900
Office Operation Costs Translation services
2.000
UNDP/CO Management UNDP/CO ISS
128.620
UNDP/CO GMS
40.000
Government Contribitions Taxes, fares etc
92.391
Stationary expenses, fuel-oil, fares etc.
135.870
Total Component D
626.35 6
GENERAL TOTAL