INTERIM FINANCIAL REPORT No. 03 PERIOD JULY – SEPTEMBER 2013 Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Project Sour...
Author: Claude Miles
11 downloads 3 Views 3MB Size
INTERIM FINANCIAL REPORT No. 03 PERIOD JULY – SEPTEMBER 2013

Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Project Sources & Uses of Funds for the quarter ending September 30, 2013 Currency: IDR Actual / I Year-To Date 2

Current Quarter /iv 1

Cumulative To-Date 3

Planned* Year-To Date 5

Current Quarter/iv 4

IFR-1 Variance in % Current Year-To Cumulative Quarter/iv Date To-Date/iv 7=1/4 8=2/5 9=3/6

Cumulative To-Date 6

Sources of Funds (by Category) GOI (Counterpart; RP Murni; SBUN)

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

0.00%

0.00%

0.00%

The World Bank

Rp

198,309,954

Rp

401,340,504

Rp

6,945,576,954

Rp

7,672,700,598

Rp

25,178,723,258

Rp

25,178,723,258

2.58%

1.59%

27.59%

Total Sources of Fund

Rp

198,309,954

Rp

401,340,504

Rp

6,945,576,954

Rp

7,672,700,598

Rp

25,178,723,258

Rp

25,178,723,258

2.58%

1.59%

27.59%

Civil Works under part 1 of the project WP-1

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

0.00%

0.00%

0.00%

Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project

Rp

198,309,954

Rp

401,340,504

Rp

6,945,576,954

Rp

7,672,700,598

Rp

25,178,723,258

Rp

25,178,723,258

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

0.00%

0.00%

0.00%

Rp

198,309,954

Rp

401,340,504

Rp

6,945,576,954

Rp

7,672,700,598

Rp

25,178,723,258

Rp

25,178,723,258

Non Bank Financed (Rupiah Murni)

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

Rp

-

0.00%

0.00%

0.00%

Total Uses of Fund

Rp

198,309,954

Rp

401,340,504

Rp

6,945,576,954

Rp

7,672,700,598

Rp

25,178,723,258

Rp

25,178,723,258

2.58%

1.59%

27.59%

Uses of Funds (by Category)

Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project Unallocated Subtotal

-

-

-

-

NOTE: Sources of Fund: Actual: diisi dengan total realisasi SPM untuk GOI dan total disbursement WB ke Special Account (RKBI) Planned: Diisi dengan anggaran (budget) yang disetujui, khusus untuk current quarter diisi dengan forecash quarter sebelumnya Uses of Fund Actual: diisi dengan realisasi SPM GOI pendamping dan BLN (WB) untuk kategori pengeluaran yang bersangkutan Planned: Diisi dengan anggaran (budget) untuk GOI pendamping dan BLN (WB) Current Quarter diisi dengan SPM GOI pendamping dan BLN (WB) yang dikeluarkan pada kwartal tersebut Year to Date diisi dengan akumulasi SPM yang dikeluarkan dalam tahun tersebut Cummulative to Date diisi dengan akumulasi SPM yang dikeluarkan dari awal proyek (project effective) sampai dengan periode pelaporan Non Bank Financed diisi dengan rupiah murni yang dikeluarkan GOI berkaitan dengan kegiatan proyek, tetapi bukan pengeluaran pendamping Loan Category

-

-

Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Project Sources & Uses of Funds for the quarter ending September 30, 2013 Currency: IDR IFR-2 Expenditure in the Current Quarter Uses of Funds (by Category)

1 Civil Works under part 1 of the project WP-1 2 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project

GOI Counterpart Rp 2

Total Rp 1 -

Others Donor Rp 3

SBUN Rp 4

Outstanding 5

Charged to WB Sp. Acc Rp 6

Charged to WB Sp. Acc US$ 7

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

198,309,954.00

-

-

198,309,954.00

19,746.38

3 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project 4 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project 5 Unallocated Non Bank Financed (Rupiah Murni) Total uses of Funds

198,309,954

198,309,954.00 Average Exchange rate: Rp

19,746.38 10,042.85

Expenditure in the Year to Date Uses of Funds (by Category)

Total Rp 8

Others Donor Rp 10

GOI Counterpart Rp 9

SBUN Rp 11

Outstanding 12

Charged to WB Sp. Acc Rp 13

Charged to WB Sp. Acc US$ 14

1 Civil Works under part 1 of the project WP-1 2 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project

401,340,504.00

401,340,504.00

40,578.78

3 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project 4 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project 5 Unallocated Non Bank Financed (Rupiah Murni) Total uses of Funds

401,340,504.00

-

-

-

-

401,340,504.00 Average Exchange rate: Rp

40,578.78 9,890.40

Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Project Sources & Uses of Funds for the quarter ending September 30, 2013 Currency: IDR IFR-2 Cumulative Expenditure to Date Uses of Funds (by Category)

Total Rp 15

GOI Counterpart Rp 16

Others Donor Rp 17

SBUN Rp 18

Outstanding 19

Charged to WB Sp. Acc Rp 20

Charged to WB Sp. Acc US$ 21

1 Civil Works under part 1 of the project WP-1 2 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project

6,945,576,954.00

6,945,576,954.00

714,755.81

3 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project 4 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project 5 Unallocated Non Bank Financed (Rupiah Murni) Total uses of Funds

6,945,576,954.00

-

-

-

-

6,945,576,954.00 Average Exchange rate: Rp

714,755.81 9,717.41

1-A

Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Special Account Activity Statement for the Reporting Period of July - September 2013 Bank Indonesia Account No: 601.306.411.980 USD Part I 1. Cummulative advances to end of current reporting period 2. Cummulative expenditures to end of last reporting period 3. Outstanding advances to be accounted (1-2)

2,207,915.00 695,009.43 1,512,905.57

Part II 4. Opening SA balance at beginning of reporting period (as of July 01, 2013) 5. Add/Substract:Cummulative adjustments (if any) *) 6. Advances from the World Bank during reporting period 7. add 5 and 6 8. Outstanding advances to be accounted for (4+7) 9. Closing SA balance at end of current reporting (as of September 30, 2013) 10. Add/substract; cummulative adjusment (if any) **) 11. Expenditures for current reporting period 12. Add 10+11 13. Add 9+12 14. Difference (if any) 8-13

1,512,905.57 1,512,905.57 1,493,159.19 19,746.38 19,746.38 1,512,905.57 -

***)

Part III 15. Total Forecasted amount to be paid by World Bank 16. Less: Closing SA balance after adjustment 17. Cummulative adjustment (if any) ****) 18. Add 16+17

1,493,159.19 1,493,159.19 1,493,159.19

19. Cash requirement from WB for next six months (15-18) Rounding =================== * Explanation for item 5 (if not zero):

-

Amount (+/-)

Remarks

** Explanation for item 10 (if not Zero):

Amount (+/-)

Remarks

*** Explanation for item 14 (if not Zero):

Amount (+/-)

Remarks

**** Explanation for item 17 (if not Zero):

Amount (+/-)

-

Remarks

Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Statement Sheet for Payments of Contracts Subject to Prior Review Quarter : III ( July - September 2013) 1-B

Ln/Cr/TF No: Sheet No: 2

1

3a

3b

4

Cross-Ref SP2D No.

Date of Payment (SP2D)

5

6

7

9

8

8043-ID 1 of 1

10

11

12

13

Disbursement Category Ite m Cat No. No.

(1)

Description

Office Issuing SP2D

Contract No. and Date

Supplier/ Contractor Name

Contract Value (Incl.Add)

Total Ammount Paid to Contractor

WB Amount of WB portion Financing paid %

Exchange Amount charged WB's Rate Contract ref. to SA Applied **/ (USD eqv)

Civil Works under part 1 of the project WP-1

Subtotal

(2)

Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project - Core Team Consultants

- Core Team Consultants

Subtotal

(3)

Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project

(4)

Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project

Rp

-

Rp

-

USD

-

Rp

-

Rp

-

USD

-

Subtotal

Subtotal

(5)

Unallocated

Subtotal

TOTAL

1-C Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Summary Statement Expenditures for Contract Not Subject to Prior Review Quarter : III ( July - September 2013) Ln/Cr/TF No: Sheet No: 2

1

3

Disbursement Category Item No.

Cat No.

Description

4

5

6

Total Paid to Country of Threshold for SOEs Number of SP2D suplier/consulta Contractors/Expendi (USD eqv) covered tures (Excl. GOI and nt/training

7

WB Financing (%)

8

9

10

Amount of WB Portion Paid

Average Axchange Rate

Amount charged to SA (USD eqv)

Rp

USD

19,746.38

Others)

(1)

8043-ID 1 of 1

Civil Works under part 1 of the project WP-1

Subtotal

(2) Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project Incremental Operating Coast

1

Subtotal

Rp

198,309,954

100.00%

Rp

198,309,954

9,745

Rp

198,309,954

100.00%

Rp

198,309,954

USD

19,746.38

Rp

198,309,954.00

Rp 198,309,954.00

USD

19,746.38

(3) Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project

Subtotal

(4) Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project

Subtotal

(5)

Unallocated

Subtotal

Grand Total

1-C2

Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Statement Sheet for Payments of Contracts Not Subject to Prior Review Quarter : III ( July - September 2013) Ln/Cr/TF No: Sheet No: 2

1

3a

3b

4

5

6

7

8

9

Total Ammount Paid to Contractor

WB Financing %

8043-ID 1 of 1

10

11

12

Disbursement Category Item No. Cat No.

Description

CrossOffice Issuing Ref SP2D SP2D No.

Date of Payment (SP2D)

Contract No. and Date

Supplier/ Contractor Name

Contract Value (Incl.Add)

Amount of WB portion paid

Exchange Amount charged Rate to SA Applied (USD eqv)

Rp Rp Rp Rp Rp Rp Rp Rp Rp

25,194,700.00 5,509,091.00 5,081,818.00 5,231,545.00 80,100,000.00 9,024,600.00 9,051,200.00 50,074,200.00 9,042,800.00

Rp Rp Rp Rp Rp Rp Rp Rp Rp

(1) Civil Works under part 1 of the project WP-1

Subtotal

(2)

1 2 3 4 5 6 7 8 9

Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project

PB Karena SALAH PEMBEBANAN CV ANDHIKA KENCANA TRD CORP CV MULTI ARTHA Bendahara Pengeluaran SNVT 10842601 AA 023161 PT HATIKA WISATA MAKMUR PT GARUDA MAS RENTALINDO PT GARUDA MAS RENTALINDO Bendahara Pengeluaran SNVT Pembinaan Admin dan P2 PT GARUDA MAS RENTALINDO

Subtotal

KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta KPPN V Jakarta

991191C 991192C 991195C 995615C 995619C 005341D 005347D 008435D

26-Jun-13 26-Jun-13 26-Jun-13 04-Jul-13 04-Jul-13 25-Jul-13 25-Jul-13 31-Jul-13

Rp Rp Rp Rp Rp Rp Rp Rp Rp

25,194,700.00 5,509,091.00 5,081,818.00 5,231,545.00 80,100,000.00 9,024,600.00 9,051,200.00 50,074,200.00 9,042,800.00

100% 100% 100% 100% 100% 100% 100% 100% 100%

Rp

198,309,954.00

Rp

Rp

198,309,954.00

Rp

9,806 9,934 9,934 9,934 9,960 9,960 10,270 10,270 10,288

USD USD USD USD USD USD USD USD USD

2,569.31 554.57 511.56 526.63 8,042.17 906.08 881.32 4,875.77 878.97

198,309,954.00

USD

19,746.38

198,309,954.00

USD

19,746.38

(3) Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 3 of the project

Subtotal

(4) Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 4 of the project

Subtotal

(5)

Unallocated

Subtotal

TOTAL

1-D Western Indonesia National Roads Improvement Project Loan IBRD No. 8043-ID Project Cash Forecast For the Quarter Ending September 30, 2013

Disbursement Category

(a)

(b)

(c)=(a)+(b)

(d)

(e)

(f)

Cash Requirement for Quarter ending 31-Dec-13 (IDR)

Cash Requirement for Quarter ending 30-Jun-14 (IDR)

Total Cash Requirement for six mos. Ending 30-Jun-14 (IDR)

GOI Cash Requirement for six mos. Ending 30-Jun-14 (IDR)

WB Cash Requirement for six mos. Ending 30-Jun-14 (IDR)

WB Cash Requirement for six mos. Ending 30-Jun-14 (USD)

2 Goods, Non Consulting Services, Consulting Services and Incremental Operating Cost under part 2 of the project

Total NOTE:

7,672,700,598

9,377,745,176

17,050,445,774

-

17,050,445,774

1,493,159.19

7,672,700,598

9,377,745,176

17,050,445,774

-

17,050,445,774

1,493,159.19