TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:

= ON TIME

=3-5 DAYS LATE

=6+ DAYS LATE

SINGLE DUCT SDV

Supership* (5 Business Days)

Standard Construction (0)

Unit Attenuator (1) Configuration

Quickship 10 Day 15 Day

X

X X

X X X X

X X X X

1/2" Dual Density (0) 1" Dual Density (1)

Liner

No Liner (3) Insulguard (2)

22 Gauge (0)

X X

X X X X X

22 Gauge w/ Access Door (1) 20 Gauge (2)

Casing Options

20 Gauge w/Access Door (3) 22 Gauge w/Access Door and Cam Lock Fastener (4) 20 Gauge w/Access Door and Cam Lock Fastener (5)

X

TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB

X

X

TUC

TRB

X

X

TUC

TRB

TUC TUC TUC TUC TUC TUC

TRB TRB TRB TRB TRB TRB

TUC

TRB

4,5,6,7,8,10,12,14,16

X X X

X X X

X X X

24 Standard Rectangular (0)

X

X

X X

Right Hand ( R ) Left Hand ( L )

Inlet Size Discharge Options

X

One Round Outlet (1) All Multiple Outlets (A,B,C,D,E,F,G,H,J,K,L,M)

X X X X X

X X X X X

TUC TUC TUC TUC TUC

TRB TRB TRB TRB TRB

X

X

TUC

TRB

X

TUC

TRB

All Analog All Pneumatic

Control Type No Controls/No Controls Enclosure All DFMT

X X

Factory mounted DDC**

Unit All Unit Accessories Accessories (A,D,E,G,H,J,K,L,S) All Standard Electric Heat (E1X, E2X, E3X, E4X, E6X, E9X) Electric Heat All SCR Electric Heat Codes (C11, C21, C31, C41, C61, C91) One Row (W11, W21)

Hot Water Heat

Two Row (W21, W22) Three or Four Row (W13, W23, W14, W24)

X

X X X

Electric Heat Accessories Fused Door Interlock Disc. Sw. (K)

Non-Fused Door Interlock Disc. Sw. (L)

TRB

X X

TUC TUC

TRB TRB

X

TUC

TRB

X X

X X X

TUC TUC TUC

TRB TRB TRB

X

X

TUC

TRB

X X

Mercury Contactors ( B ) Fusing ( C )

Manufacturing Location

TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC

Galvanized Sheet Metal (4) Enviroseal (5)

25 30 Day Day

X X X X X X X X X X X X X

X

Electric Heat (3)

Standard (20 Day)

* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) TRB (Tarboro) Effective Date:

8/2/2016

TUC (Tucson)

TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:

= ON TIME

=3-5 DAYS LATE

=6+ DAYS LATE

SINGLE DUCT ROUND Standard (20 Day)

Manufacturing Location

X X X

X X X X X X X X X

TRB TRB TRB TRB TRB TRB TRB TRB TRB

X

X

TRB

15 Day

Standard (25 Day)

Manufacturing Location

Inlet Air Sensing (3S)

X X

X X

TUC TUC

Inlet Air Sensing And Total Air Sensing (3Y)

X

X

TUC

X

X

TUC

X X X X X X X X X X X

Factory mounted DDC**

X X X

X X X X X X X X X X X X X X X X

TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC

Unit Accessories All Unit Accessories (A, D, E, G, H, J, K, L, S)

X

X

TUC

SDR Unit Configuration Liner Casing Options Inlet Size

Standard Construction (0) No Liner (3) All Casing Options All Inlet Sizes

Quickship 10 Day 15 Day

X X X X

All Analog All Pneumatic

Control Type

No Controls/No Controls Enclosure All DFMT Factory mounted DDC**

Unit Accessories All Unit Accessories (D, E, G, H, J, K, L, S)

DUAL DUCT DDV Total Air Sensing (3H, 3T, 3Y)

Sensor

Unit Configuration Standard Construction (0) Liner Casing Options

All Liners All Casing Options 4-4, 4-5, 4-6 5-5, 5-6, 5-7 6-6, 6-7, 6-8 7-7, 7-8

Inlet Size

8-8, 8-10 10-10, 10-12 12-12, 12-14 14-14, 14-16 16-16

Quickship

All Analog All Pneumatic

Control Type

No Controls/No Controls Enclosure All DFMT

* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) Effective Date:

8/2/2016

TRB (Tarboro) TUC (Tucson)

TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:

= ON TIME

=3-5 DAYS LATE

=6+ DAYS LATE

DUAL SINGLE DUCT DSV Inlet Air Sensing (3C) Sensor Unit Configuration Standard Construction, No Mixing Baffle (0) 1/2" Dual Density (0), 1" Dual Density (1), No Liner (3)

Liner

Insulguard (2)

X X X X

Galvanized Sheet Metal (4) Enviroseal (5)

Casing Options Inlet Size

Quickship 10 Day 15 Day

All Casing Options All Sizes (Unequal inlet sizes not available)

X X X

No Controls/No Controls Enclosure, All DFMT

Control Type

All Analog All Pneumatic Factory Mounted DDC**

Unit Accessories All Unit Accessories (A, D, E, G, H, J, K, L, S)

X X X

Standard (20 Day)

Manufacturing Location

X X X X X X X X X X X X X

TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC

Standard (25 Day)

Manufacturing Location

X X X X

TRB TRB TRB TRB

X

TRB

X X X X X X X*** X X X X X X

TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB

FAN POWERED CONSTANT FPS Liner Casing Options Inlet Size

Quickship 10 Day

15 Day

All Liners All Casing Options All Casing Sizes and Inlet Sizes Standard Flat (0)

Discharge Options Slip and Drive ( A ), Discharge Attenuator ( B ), HW Coil Motor Voltage

Access Door ( C ) All Motor Voltages With SCR All EON Voltage Codes All Pneumatic, No Controls/No Controls Enclosure, All DFMT

Control Type

All Analog Factory Mounted DDC**

Unit Accessories All Unit Accessories (A, D, E, F, N, R, S, T) All Electric Heat Codes Electric Heat Hot Water Heat

One Row (W11, W21) Two Row (W12, W22) Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )

* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) *** FPS Size 7 with electric heat is 5 weeks Standard and not available on Quickship Effective Date:

8/2/2016

TRB (Tarboro) TUC (Tucson)

TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:

= ON TIME

=3-5 DAYS LATE

=6+ DAYS LATE

FAN POWERED VARIABLE FPP Liner Casing Options Inlet Size

Quickship 15 Day

All Liners All Casing Options All Casing Sizes and Inlet Sizes Standard Flat (0)

Discharge Options Slip and Drive ( A ), Discharge Attenuator ( B ), HW Coil Motor Voltage Control Type

Access Door ( C ) All Motor Voltages With SCR All Analog, All Pneumatic, No Controls/No Controls Enclosure, All DFMT Factory Mounted DDC**

Unit Accessories All Unit Accessories (A, D, E, F, N, R, S, T) All Electric Heat Codes Electric Heat Hot Water Heat

One Row (W11, W21) Two Row (W12, W22) Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )

Standard (25 Day)

Manufacturing Location

X X X X

TRB TRB TRB TRB

X

TRB

X

TRB

X

TRB

X X X X X X X X X

TRB TRB TRB TRB TRB TRB TRB TRB TRB

INDUCTION IDV Unit Configuration Standard Construction (0) Liner Casing Options Inlet Size

No Liner (3) All Casing Options All Inlet Sizes All Analog All Pneumatic

Control Type

No Controls/No Controls Enclosure All DFMT Factory mounted DDC**

Unit Accessories All Unit Accessories (A, D, E, G, H, J, K, L, S) Hot Water Heat All Hot Water Coils

Standard (30 Day)

Manufacturing Location

X

TUC

X X X X X X X X X X

TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC

* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) TRB (Tarboro) Effective Date:

8/2/2016

TUC (Tucson)

TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:

= ON TIME

=3-5 DAYS LATE

=6+ DAYS LATE

SINGLE DUCT EXHAUST RRV Unit Configuration Liner Casing Options Inlet Size Inlet/Discharge Options Control Type

Standard (25 Day)

Manufacturing Location

X X X X X CALL

TUC TUC TUC TUC TUC TUC

X

TUC

X X

TUC TUC

Standard Construction (0) No Liner (3) All Casing Options All Inlet Sizes Slip/Slip Bellmouth/Slip, Bellmouth/Flange, Flange/Flange All Analog, All Pneumatic, No Controls/No Controls Enclosure, All DFMT Factory mounted DDC**

Unit Accessories All Unit Accessories (D, E, G, H, J, K, L, S)

BYPASS BPS Unit Configuration Standard Construction (0) All Inlet Sizes Inlet Size Control Type

All Analog, All Pneumatic, No Controls/No Controls Enclosure, All DFMT Factory mounted DDC**

Unit Accessories All Unit Accessories (C, D, E, G, H, J, K, L, S)

Quickship 15 Day

Standard (25 Day)

Manufacturing Location

X X

X X

TRB TRB

X

X

TRB

X X

X X

TRB TRB

* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page)

TRB (Tarboro) Effective Date:

8/2/2016

TUC (Tucson)

TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:

= ON TIME

=3-5 DAYS LATE

=6+ DAYS LATE

LOW PROFILE FAN POWERED CONSTANT Quickship

LPC Liner Casing Options Inlet Size

10 Day

15 Day

All Liners All Casing Options All Casing Sizes and Inlet Sizes

Discharge Options Standard Flat (0) Motor Voltage

All Motor Voltages All Pneumatic, No Controls/No Controls Enclosure, All DFMT

Control Type

All Analog Factory Mounted DDC**

Unit Accessories All Unit Accessories All Electric Heat Codes (E1X, E2X, E3X, E4X, E6X, E9X) Electric Heat Hot Water Heat

One Row (W11, W21) Two Row (W12, W22) Mercury Contactors ( B )

Electric Heat Accessories

Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )

Standard (25 Day)

Manufacturing Location

X X X

TRB TRB TRB

X

TRB

X X X X X X X X X X X X X

TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB

Standard (25 Day)

Manufacturing Location

X X X

TRB TRB TRB

X

TRB

X X X X X X X X X X X X X

TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB

LOW PROFILE FAN POWERED VARIABLE Quickship

LPV Liner Casing Options Inlet Size

10 Day

All Liners All Casing Options All Casing Sizes and Inlet Sizes

Discharge Options Standard Flat (0) Motor Voltage

All Motor Voltages All Pneumatic, No Controls/No Controls Enclosure, All DFMT

Control Type

All Analog Factory Mounted DDC**

Unit Accessories All Unit Accessories All Electric Heat Codes (E1X, E2X, E3X, E4X, E6X, E9X) Electric Heat Hot Water Heat

One Row (W11, W21) Two Row (W12, W22) Mercury Contactors ( B )

Electric Heat Accessories

Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )

15 Day

** See FMA Lead Time Program Update (last page) TRB (Tarboro) Effective Date:

8/2/2016

TUC (Tucson)

TERMINAL UNIT FMA LEAD-TIME Following policy enacted September 9, 2013 When a terminal unit order with FMA Controls is received, it will be evaluated and entered into the system with a PENDING SHIP DATE. This ship date is assigned in accordance with our Standard Lead Time and Variable Lead Time programs. FMA Paperwork will be sent to the representative informing them of the factory order number and the address to ship the controls. The PENDING SHIP DATE is contingent upon each of the following conditions: 1. Controls must be received at the plant by noon 10 business days prior to the scheduled ship date (pending ship date). 2. The controls must be clearly labeled with the factory order number. 3. The quantities and model number for the controls and other components must match the FMA Paperwork sent to the rep. Omission of any of these requirements will result in the order being placed on hold. An acknowledgement will be faxed stating your order’s hold status. Once the issue causing the hold is resolved, the standard lead time will start over. If you have any questions regarding changes to the program please do not hesitate to contact Tuttle & Bailey®.