TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:
= ON TIME
=3-5 DAYS LATE
=6+ DAYS LATE
SINGLE DUCT SDV
Supership* (5 Business Days)
Standard Construction (0)
Unit Attenuator (1) Configuration
Quickship 10 Day 15 Day
X
X X
X X X X
X X X X
1/2" Dual Density (0) 1" Dual Density (1)
Liner
No Liner (3) Insulguard (2)
22 Gauge (0)
X X
X X X X X
22 Gauge w/ Access Door (1) 20 Gauge (2)
Casing Options
20 Gauge w/Access Door (3) 22 Gauge w/Access Door and Cam Lock Fastener (4) 20 Gauge w/Access Door and Cam Lock Fastener (5)
X
TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB
X
X
TUC
TRB
X
X
TUC
TRB
TUC TUC TUC TUC TUC TUC
TRB TRB TRB TRB TRB TRB
TUC
TRB
4,5,6,7,8,10,12,14,16
X X X
X X X
X X X
24 Standard Rectangular (0)
X
X
X X
Right Hand ( R ) Left Hand ( L )
Inlet Size Discharge Options
X
One Round Outlet (1) All Multiple Outlets (A,B,C,D,E,F,G,H,J,K,L,M)
X X X X X
X X X X X
TUC TUC TUC TUC TUC
TRB TRB TRB TRB TRB
X
X
TUC
TRB
X
TUC
TRB
All Analog All Pneumatic
Control Type No Controls/No Controls Enclosure All DFMT
X X
Factory mounted DDC**
Unit All Unit Accessories Accessories (A,D,E,G,H,J,K,L,S) All Standard Electric Heat (E1X, E2X, E3X, E4X, E6X, E9X) Electric Heat All SCR Electric Heat Codes (C11, C21, C31, C41, C61, C91) One Row (W11, W21)
Hot Water Heat
Two Row (W21, W22) Three or Four Row (W13, W23, W14, W24)
X
X X X
Electric Heat Accessories Fused Door Interlock Disc. Sw. (K)
Non-Fused Door Interlock Disc. Sw. (L)
TRB
X X
TUC TUC
TRB TRB
X
TUC
TRB
X X
X X X
TUC TUC TUC
TRB TRB TRB
X
X
TUC
TRB
X X
Mercury Contactors ( B ) Fusing ( C )
Manufacturing Location
TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC
Galvanized Sheet Metal (4) Enviroseal (5)
25 30 Day Day
X X X X X X X X X X X X X
X
Electric Heat (3)
Standard (20 Day)
* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) TRB (Tarboro) Effective Date:
8/2/2016
TUC (Tucson)
TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:
= ON TIME
=3-5 DAYS LATE
=6+ DAYS LATE
SINGLE DUCT ROUND Standard (20 Day)
Manufacturing Location
X X X
X X X X X X X X X
TRB TRB TRB TRB TRB TRB TRB TRB TRB
X
X
TRB
15 Day
Standard (25 Day)
Manufacturing Location
Inlet Air Sensing (3S)
X X
X X
TUC TUC
Inlet Air Sensing And Total Air Sensing (3Y)
X
X
TUC
X
X
TUC
X X X X X X X X X X X
Factory mounted DDC**
X X X
X X X X X X X X X X X X X X X X
TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC
Unit Accessories All Unit Accessories (A, D, E, G, H, J, K, L, S)
X
X
TUC
SDR Unit Configuration Liner Casing Options Inlet Size
Standard Construction (0) No Liner (3) All Casing Options All Inlet Sizes
Quickship 10 Day 15 Day
X X X X
All Analog All Pneumatic
Control Type
No Controls/No Controls Enclosure All DFMT Factory mounted DDC**
Unit Accessories All Unit Accessories (D, E, G, H, J, K, L, S)
DUAL DUCT DDV Total Air Sensing (3H, 3T, 3Y)
Sensor
Unit Configuration Standard Construction (0) Liner Casing Options
All Liners All Casing Options 4-4, 4-5, 4-6 5-5, 5-6, 5-7 6-6, 6-7, 6-8 7-7, 7-8
Inlet Size
8-8, 8-10 10-10, 10-12 12-12, 12-14 14-14, 14-16 16-16
Quickship
All Analog All Pneumatic
Control Type
No Controls/No Controls Enclosure All DFMT
* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) Effective Date:
8/2/2016
TRB (Tarboro) TUC (Tucson)
TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:
= ON TIME
=3-5 DAYS LATE
=6+ DAYS LATE
DUAL SINGLE DUCT DSV Inlet Air Sensing (3C) Sensor Unit Configuration Standard Construction, No Mixing Baffle (0) 1/2" Dual Density (0), 1" Dual Density (1), No Liner (3)
Liner
Insulguard (2)
X X X X
Galvanized Sheet Metal (4) Enviroseal (5)
Casing Options Inlet Size
Quickship 10 Day 15 Day
All Casing Options All Sizes (Unequal inlet sizes not available)
X X X
No Controls/No Controls Enclosure, All DFMT
Control Type
All Analog All Pneumatic Factory Mounted DDC**
Unit Accessories All Unit Accessories (A, D, E, G, H, J, K, L, S)
X X X
Standard (20 Day)
Manufacturing Location
X X X X X X X X X X X X X
TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC
Standard (25 Day)
Manufacturing Location
X X X X
TRB TRB TRB TRB
X
TRB
X X X X X X X*** X X X X X X
TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB
FAN POWERED CONSTANT FPS Liner Casing Options Inlet Size
Quickship 10 Day
15 Day
All Liners All Casing Options All Casing Sizes and Inlet Sizes Standard Flat (0)
Discharge Options Slip and Drive ( A ), Discharge Attenuator ( B ), HW Coil Motor Voltage
Access Door ( C ) All Motor Voltages With SCR All EON Voltage Codes All Pneumatic, No Controls/No Controls Enclosure, All DFMT
Control Type
All Analog Factory Mounted DDC**
Unit Accessories All Unit Accessories (A, D, E, F, N, R, S, T) All Electric Heat Codes Electric Heat Hot Water Heat
One Row (W11, W21) Two Row (W12, W22) Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )
* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) *** FPS Size 7 with electric heat is 5 weeks Standard and not available on Quickship Effective Date:
8/2/2016
TRB (Tarboro) TUC (Tucson)
TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:
= ON TIME
=3-5 DAYS LATE
=6+ DAYS LATE
FAN POWERED VARIABLE FPP Liner Casing Options Inlet Size
Quickship 15 Day
All Liners All Casing Options All Casing Sizes and Inlet Sizes Standard Flat (0)
Discharge Options Slip and Drive ( A ), Discharge Attenuator ( B ), HW Coil Motor Voltage Control Type
Access Door ( C ) All Motor Voltages With SCR All Analog, All Pneumatic, No Controls/No Controls Enclosure, All DFMT Factory Mounted DDC**
Unit Accessories All Unit Accessories (A, D, E, F, N, R, S, T) All Electric Heat Codes Electric Heat Hot Water Heat
One Row (W11, W21) Two Row (W12, W22) Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )
Standard (25 Day)
Manufacturing Location
X X X X
TRB TRB TRB TRB
X
TRB
X
TRB
X
TRB
X X X X X X X X X
TRB TRB TRB TRB TRB TRB TRB TRB TRB
INDUCTION IDV Unit Configuration Standard Construction (0) Liner Casing Options Inlet Size
No Liner (3) All Casing Options All Inlet Sizes All Analog All Pneumatic
Control Type
No Controls/No Controls Enclosure All DFMT Factory mounted DDC**
Unit Accessories All Unit Accessories (A, D, E, G, H, J, K, L, S) Hot Water Heat All Hot Water Coils
Standard (30 Day)
Manufacturing Location
X
TUC
X X X X X X X X X X
TUC TUC TUC TUC TUC TUC TUC TUC TUC TUC
* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page) TRB (Tarboro) Effective Date:
8/2/2016
TUC (Tucson)
TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:
= ON TIME
=3-5 DAYS LATE
=6+ DAYS LATE
SINGLE DUCT EXHAUST RRV Unit Configuration Liner Casing Options Inlet Size Inlet/Discharge Options Control Type
Standard (25 Day)
Manufacturing Location
X X X X X CALL
TUC TUC TUC TUC TUC TUC
X
TUC
X X
TUC TUC
Standard Construction (0) No Liner (3) All Casing Options All Inlet Sizes Slip/Slip Bellmouth/Slip, Bellmouth/Flange, Flange/Flange All Analog, All Pneumatic, No Controls/No Controls Enclosure, All DFMT Factory mounted DDC**
Unit Accessories All Unit Accessories (D, E, G, H, J, K, L, S)
BYPASS BPS Unit Configuration Standard Construction (0) All Inlet Sizes Inlet Size Control Type
All Analog, All Pneumatic, No Controls/No Controls Enclosure, All DFMT Factory mounted DDC**
Unit Accessories All Unit Accessories (C, D, E, G, H, J, K, L, S)
Quickship 15 Day
Standard (25 Day)
Manufacturing Location
X X
X X
TRB TRB
X
X
TRB
X X
X X
TRB TRB
* Maximum 25 Pieces ** See FMA Lead Time Program Update (last page)
TRB (Tarboro) Effective Date:
8/2/2016
TUC (Tucson)
TERMINAL UNIT LEAD-TIME SCHEDULE COLOR CODES:
= ON TIME
=3-5 DAYS LATE
=6+ DAYS LATE
LOW PROFILE FAN POWERED CONSTANT Quickship
LPC Liner Casing Options Inlet Size
10 Day
15 Day
All Liners All Casing Options All Casing Sizes and Inlet Sizes
Discharge Options Standard Flat (0) Motor Voltage
All Motor Voltages All Pneumatic, No Controls/No Controls Enclosure, All DFMT
Control Type
All Analog Factory Mounted DDC**
Unit Accessories All Unit Accessories All Electric Heat Codes (E1X, E2X, E3X, E4X, E6X, E9X) Electric Heat Hot Water Heat
One Row (W11, W21) Two Row (W12, W22) Mercury Contactors ( B )
Electric Heat Accessories
Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )
Standard (25 Day)
Manufacturing Location
X X X
TRB TRB TRB
X
TRB
X X X X X X X X X X X X X
TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB
Standard (25 Day)
Manufacturing Location
X X X
TRB TRB TRB
X
TRB
X X X X X X X X X X X X X
TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB TRB
LOW PROFILE FAN POWERED VARIABLE Quickship
LPV Liner Casing Options Inlet Size
10 Day
All Liners All Casing Options All Casing Sizes and Inlet Sizes
Discharge Options Standard Flat (0) Motor Voltage
All Motor Voltages All Pneumatic, No Controls/No Controls Enclosure, All DFMT
Control Type
All Analog Factory Mounted DDC**
Unit Accessories All Unit Accessories All Electric Heat Codes (E1X, E2X, E3X, E4X, E6X, E9X) Electric Heat Hot Water Heat
One Row (W11, W21) Two Row (W12, W22) Mercury Contactors ( B )
Electric Heat Accessories
Fusing ( C ) Manual Reset Cutout ( F ) Fused Door Interlocking Disconnect Switch ( K ) Non-Fused Door Interlocking Disconnect Switch ( L )
15 Day
** See FMA Lead Time Program Update (last page) TRB (Tarboro) Effective Date:
8/2/2016
TUC (Tucson)
TERMINAL UNIT FMA LEAD-TIME Following policy enacted September 9, 2013 When a terminal unit order with FMA Controls is received, it will be evaluated and entered into the system with a PENDING SHIP DATE. This ship date is assigned in accordance with our Standard Lead Time and Variable Lead Time programs. FMA Paperwork will be sent to the representative informing them of the factory order number and the address to ship the controls. The PENDING SHIP DATE is contingent upon each of the following conditions: 1. Controls must be received at the plant by noon 10 business days prior to the scheduled ship date (pending ship date). 2. The controls must be clearly labeled with the factory order number. 3. The quantities and model number for the controls and other components must match the FMA Paperwork sent to the rep. Omission of any of these requirements will result in the order being placed on hold. An acknowledgement will be faxed stating your order’s hold status. Once the issue causing the hold is resolved, the standard lead time will start over. If you have any questions regarding changes to the program please do not hesitate to contact Tuttle & Bailey®.