SRT Investment Plan to modernize railway infrastructure
Double Track
Rolling Stock & ICD II
KINGDOM OF THAILAND
Area: Population: Currency: Language: Capital:
513,115 sq. km. (198,115 sq. mi.) 66,720,153 persons baht (1 US$ ~ 30 baht) Thai Bangkok
MYANMAR VIETNAM
LAOS
Chiang Mai
Existing Railway Network Coverage: 47 Provinces (from 76 provinces)
Total Route Length 4,035 km.
Nong Khai
Total Track Length 4,500 km. THAILAND Ubon Ratchathani Nakhon Ratchasima
Aranyaprathet Bangkok
CAMBODIA
Sattahip
Northern Line 781 km. Northeastern Line 1,093 km. Eastern Line 527 km. Southern Line 1,569 km. Mae Klong Line 65 km.
GULF OF THAILAND
Single Track 3,677 km. (91.2%) Double Track 251 km. (6.2%) ANDAMAN SEA Padang Besar Sungai Kolok
MALAYSIA
Triple Track 107 km. (2.6%)
Chiang Mai Nong Khai
Ubon Ratchathani Bangkok
Nakhon Ratchasima Aranyaprathet
Sattahip
Rail Size 50 Pound / yard 60 Pound / yard 70 Pound / yard 80 Pound / yard 100 Pound / yard
50 Pound / yard
Padang Besar Sungai Kolok
60 Pound / yard
80 Pound / yard
44% Age
% 1 8 35 20 36
> 46 > 43 ~ 44 ~ 33 3~ 9
70 Pound / yard
100 Pound / yard
Type of Sleeper Chiang Mai
38%
%
Timber Sleeper
33
Two Block Concrete Sleeper
5
Mono Block Concrete Sleeper
62
Nong Khai
Ubon Ratchathani
Nakhon Ratchasima Bangkok
Aranyaprathet
Timber Sleeper 15 cm. Two block Concrete Sleeper
Sattahip
20 cm. Mono block Concrete Sleeper
Padang Besar Sungai Kolok
20 cm.
Rail Service ♠ Service area : 47 provinces ♠ No.of Station : 440 stations ♠ Passenger Train : 288 trains/day ♠ Passenger per annum : 41.0 million passengers. ♠ Passenger Revenues : 3,687 million baht
♠ Freight Train : 63 trains/day
♠ Freight per annum : 10.9 million ton ♠ Freight Revenues : 1,615 million baht 6
Cabinet Resolution on 27 April 2010 Rail Infrastructure Development Program amounting 176,808 Million Baht (6 Billion USD) in five year period: - Upgrading of existing infrastructure - Acquisition of new rolling stocks - Construction of double tracks - Construction of ICD 2 Infrastructure to be born by the government while rolling stocks to be absorbed by SRT
Update on Projects and Budgets according to the urgent rail infrastructure development program (176,808.28 Million Baht: 6 billion USD) 1. Civil Work:
Track Rehabilitation Phase 5 (Distance = 308 km.)
Track Rehabilitation Phase 6 (Distance = 278 km.)
Track Strengthening 5 section (Distance = 1,037 km.) Section
Distance (km.)
Chachoengsao – Sriracha - Laemchabang
84
Phitsanulok - Chiangmai
362
Nong Pladuk Junction – Hua Hin
149
Khlong Pai - Ubon Ratchathani
369
Khlong Pai - Mab Kra Bao
73
Total
1,037
1. Civil Work: (Cont.)
Bridge Strengthening : 1,434 bridges
Fencing : 1,649 km.
2. Signaling and Telecommunication:
Telecommunication and Centralized Traffic Control Center
Level Crossings
Three Aspect Color
3. Rolling Stocks:
13/50 Locomotives + 56 Locomotive Refurbishment
115 Sleeping Coaches
Locomotive Depots
4. Double Tracks 6 Sections
5. 2nd ICD
MYANMAR VIETNAM
LAOS
Chiang Mai
Nong Khai
Phase 5
THAILAND Ubon Ratchathani Nakhon Ratchasima
Aranyaprathet
CAMBODIA
37
5-2: Suranarai – Bua Yai 5-3: Chira – Bua Yai
192
Phase 6 Bua Yai Junction – Nongkhai
Padang Besar Sungai Kolok
MALAYSIA
8,508
79 308
Under construction (Progress = 82.51%) Expected to finished on 30 June 2013
GULF OF THAILAND
ANDAMAN SEA
Distan Cost ce (million (km.) baht)
5-1: Kaeng Khoi– Kaeng SuaTen
Total
Bangkok
Sattahip
Track Rehabilitation Phase 5 & 6
Distan Cost ce (million (km.) baht) 278
6,779
Under construction (Progress = 83.06%) Expected to finished on 30 June 2013
MYANMAR LAOS
Chiang Mai
Double Tracks 6 Sections
VIETNAM
Distanc e (km.)
Cost (million baht)
Chacheongsao –Klong Sip Kao–Kaeng Khoi
106
11,348.36
2
Lopburi – Paknampho
118
7,860.00
3
Map Kabao - Thanon Jira
132
11,640.00
CAMBODIA4
Thanon Jira – Khon Kaen
185
13,010.00
5
Nakhon Pathom - Hua Hin
165
16,600.00
6
Prachuap Khiri Khan – Chumphon
167
17,000.00
873
77,458.36
Nong Khai
THAILAND
Section 1 Ubon Ratchathani
Nakhon Ratchasima
Aranyaprathet Bangkok
Sattahip
GULF OF THAILAND
Total
Detailed Design Completed
1 ANDAMAN SEA
2
3
5
6
Padang Besar Sungai Kolok
MALAYSIA
4
Under Detailed Design
State Railway of Thailand
Diesel Electric Locomotive Fleet GEA
HITACHI
ALSTHO M
GE
4523-4560
4501-4522
4101-4420
4001-4050
Number of Trains
36
21
102
45
Purchase Year
1996
1993
1974 - 1981
1964-1967
Duration of Service (Year)
17
20
28 – 39
46 - 49
Power (HP)
2400
2900
2250
1320
DESCRIPTION
ALS
HID
TOTAL
204
GEA
State Railway of Thailand
SRT Main line Locomotives
GEA = 36 cars, 17 years old
HID = 21 cars, 20 years old
ALS = 102 cars, 28 – 39 years old
GE = 45 cars, 46 – 49 years old
Transport Infrastructure Development Strategy
Connectivity
Shift Mode from road to the lower cost modes, rail/water
Modal Shift + Multimodal
Facilitate passenger and freight transport to domestic regional hubs and neighboring countries
Mobility Develop and improve the existing transport system to enhance mobility
2 Trillion Baht Budget (2013 – 2020) to Develop Transport Infrastructure Sector
Budget Proportion (preliminary)
Rail Road Water Air Custom Department
82.57 12.15 1.51 0.61
Other
3.16
Total
100.00
SRT 62.59%
MRT 19.97%
Major Components of Railway Development Projects under the 176 billion baht (Civil Work, Level crossings, Signaling, Telecommunication, and 5 Double Tracking Sections) 3 New Lines (one – meter gauge) 6 Double Tracking Sections 4 High Speed Lines
Red Line (3 sections) ARL connecting two Airports
Projects in the North 1) Double Tracking Projects Section
Chiang Khong
Lop Buri – Pak Nam Pho
148
Pak Nam Pho – Denchai
285
Total
Chiang Rai
Distance (km.)
2
Chiangmai
433
Denchai
2) New Line Route
Distance (km.)
Denchai – Chiang Rai – Chiang Khong
326
1 Pak Nam Pho
3) High Speed Train
3
Route
Distance (km.)
Bangkok - Chiangmai
745
Lop Buri
Double Track New Line High Speed Train
Bangkok
Projects in the Northeast 1) Double Tracking Projects (Upper Northeast) Section
Distance (km.)
Mab Kra Bao – Jira
132
Jira – Khon Khaen
187
Khon Khaen – Nong Khai
174
Nong Khai
Nakon Phanom
1
2) Double Tracking Projects (Lower Northeast) Section Jira - Ubonratchathanee
Mukdahan Khon Khaen
Distance (km.)
Roi Et
309
3) New Line
Jira
Route
3
Ban Phai
Distance (km.)
Ban Phai–Nakon Phanom
347
Phachi – Nakorn Luang
23
2 Nakhon Ratchasima
4
Ubonratchathane e
Mab Kra Bao
Bangkok
4) High Speed Train Route
Distance (km.)
Bangkok - Nakhon Ratchasima
256
Double Track New Line High Speed Train
Projects in the South 1) Double Tracking Projects Section
Nakon Prathom
Distance (km.)
Nakon Prathom – Hua Hin
165
Hua Hin – Prajuab Kirikan
90
Prajuab Kirikan – Chumporn
167
Chumporn – Surat Thanee
167
Surat Thanee – Padang Besar
339
2) High Speed Train Route
Distance (km.)
Bangkok - Huahin
225
2 Hua Hin Prajuab Kirikan
1 Chumporn
Surat Thanee
Padang Besar
Double Track High Speed Train
Bangkok
Projects in the East 1) High Speed Train Route
Distance (km.)
Bangkok– Pattaya - Rayong
221
Bangkok
1 Pattaya
High Speed Train
Rayong
Future Railway Network after 2 Trillion Baht Investment Plan
Existing
Future after 2 trillion investment
Single Track
3,677 (91.2%)
1,436 (30.5%)
Double Track
251 (6.2%)
3,163 (67.0%)
Triple Track
108 (2.6%)
108 (2.5%)
4,035
4,707
Total
High Speed Train
Chiangmai
Bangkok
Nakhon Ratchasima
Hua Hin Rayong
High Speed Train
Route
Distance (km.)
Bangkok - Chiangmai
745
Bangkok - Nakhon Ratchasima
256
Bangkok - Huahin
225
Bangkok– Pattaya - Rayong
221
Total
1,447
Route
Distance (km.)
1
Bangsue – Makkasan – Huamak , Bangsue - Hualamphong
25.9
2
Bangsue – Taling Chan
15.26
3
Taling Chan - Salaya
14.0
4 Rangsit – Thammasart University 5
Airport Link Extension (Phayathai – Donmuang)
4
Don Muang Airport
10.0 21.8
5 3
2
1 Suvarnabhumi Airport
3th (CT Platform)
2nd (LD Platform) 1st (Concourse)
3th (CT Platform) 2nd (LD Platform) 1st (Concourse)
3th (CT Platform) 2nd (LD Platform) 1st (Concourse)
Parking area = 1,600 cars
3th (CT Platform) 2nd (LD Platform) 1st (Concourse)
26
Benefit
1. All level crossings in the project area will be eliminated. 2. A modern electrified commuter train will be introduced. 3. Increase in efficiency, safety and reliability in train operation. 4. Enhanced modal shift from road to rail. 5. Saving in energy consumption.
Major Rules Item
SRT commuter train
SRT passenger train
Design Max. Speed
160 km/h
120 km/h
Gauge
1.000 m
1.000 m
Structural Profile
W3500 x H4250 & H5900
Loading Profile
W2920 x H4050 & H5650
Max. Axle Load Horizontal Min. Curve Radius (R)
16 tf
1600 m. for Vmax =160 km/h 900 m. for Vmax =120 km/h (400 m in special, 200 m in extreme case)
Vertical Min. Curve Radius Max. Gradient for Main Line
16 tf (SRT passenger train) 20 tf (SRT freight train)
Main Line : 5,000 m 3.5 %
1.0 % (1.2% in special)
Max. Cant (Cmax)
90 mm.
90 mm.
Height of Platform
1,100 mm.
500 mm.
Length of Platform
210 m.
500 m.
STATE RAILWAY OF THAILAND
30
KPIs and Targets KPIs and Targets 1. Logistic Cost per GDP (%)
Fiscal Year 2012 2022 15.2
13.2
2. Inter-city Personnel Car Used (%)
59
40
3. Speed (km./hr.) - Passenger Trains - Freight Trains 4. Rail Transportation Portion (%)
60 39
100 60
2.5
5.0
5. Fuel Used (million baht per year)
> 100,000
6. MRT in Bangkok Metropolitan Portion (%)
5
> 30
7. Ridership (million passengers per year)
45
75
8. Travel Time (hr.) (area = 300 km. from Bangkok)
3
1.5 31
(End of Presentation)