TarBuster™ Drill and Case SYSTEM

T

ar zones are unpredictable. They can not be seen seismically. A zone can be from several feet to over 150 feet thick, with various levels of mobility, and it comes as no surprise to operators that tar zones can present major difficulties for drilling. The tar can plastically deform into the wellbore, circulation is lost, increased shock and vibrations occur; the tar sticks to the Bottom Hole Assembly (BHA) and drill pipe, clogs flowlines and soils handling equipment.

The Dril-Quip TarBuster Drill and Case System was designed to deal with the many problems caused by tar zones. The TarBuster System allows for casing shoe or bit and underreamer options to get the casing to the desired depth, and is capable of more aggressive drilling than with casing and reamer shoe. The main components of the TarBuster System are the Liner Hanger Setting Adapter (LHSA), the Liner Hanger Setting Adapter Running Tool (LHSART) and the Liner Top Isolation Packer (LTIP). The BHA is attached to the inner string below the LHSA. The LHSA is run on the first trip and the LTIP, with bidirectional slips, is run on the second trip.

1

Liner Hanger Setting Adapter Running Tool (LHSART)

Liner Hanger Setting Adapter (LHSA)

Liner Hanger Setting Adapter Running Tool Drill Pipe Connection

Features: • Ream or drill in • Right- or left-hand torque • Hydraulic functions are port-isolated to prevent premature actuation • Liner/casing rotation enhances flow-by, helping to clear tar and debris from the hydraulic tool and out of the hole • Reduced length (less than half the length of a standard liner) provides less flow restriction

Top View of AntiRotation Keys for Bidirectional Connection

Top View of Spline to Mandrel

Flow-By Exit Slots

• Over four times more flow-by than conventional running tool; returns are taken up the I.D. annulus of the tool • Developed with the aid of Computational Fluid Dynamics (CFD) analysis

Top View of Hydraulic Flow Path

Hydraulic Release Piston C-Ring Ball Seat Clutch Profile Split Load Ring

Secondary Release Housing with AntiRotation Keys

Drill-Down Shoulder Centralizer Fins Top View of Centralizer Fins

Anti-Rotation Keys for Bidirectional Connection

Setting Ball Diverter

Drill Pipe Connection

2

Liner Hanger Setting Adapter Features:

Tie-Back Receptacle Tie-Back Profile for Liner Top Isolation Packer

Clutch Profile Split Load Ring Profile Anti-Rotation Slot for Secondary Mechanical Release Drill-Down Shoulder

Liner Hanger Setting Adapter Body

Casing Thread

3

Liner Top Isolation Packer Features:

Tie-Back Receptacle

Running Adapter

Tie-Back Receptacle

Running Adapter

Upper Body Lock Ring

Upper Body Lock Ring

Pusher Sleeve

Pusher Sleeve

Packer

Packer Packer Cone

Packer Cone Lower Body Lock Ring

Upper Slip Cone Bidirectional C-Ring Slip

Lower Slip Cone Molded Seals for Tie-Back to Liner Setting Adapter Split Lock Ring for Tie-Back to Liner Setting Adapter

Lower Body Lock Ring

Upper Slip Cone Bidirectional C-Ring Slip Lower Slip Cone Molded Seals for Tie-Back to Liner Setting Adapter Split Lock Ring for Tie-Back to Liner Setting Adapter

4

T ar B uster R unning P roce dures Running Procedures to Install Liner Hanger Setting Adapter (LHSA) 1. After hole interval is drilled, POOH with Bottom Hole Assembly (BHA) while boosting riser. 2. Pump viscous sweeps to help clean hole. 3. Run casing with liner shoe as specified by customer procedure. An open-ended shoe with 45 degree inverted bevel is recommended. 4. Place false rotary on top of last casing connection. 5. Run BHA and inner string. 6. Make up Liner Hanger Setting Adapter Running Tool (LHSART) with LHSA to inner string. 7. Lower TarBuster assembly through rotary and trip into the hole. 8. Turn on pumps once in 13 5/8" cased hole to wash liner down as needed or as per customer procedure. 9. Begin to rotate casing two stands from 13 5/8" casing shoe, with circulation. 30 RPM in cased hole suggested. 10. In open hole, adjust pump rate and weight on bit according to torque and hole conditions; monitor returns. 11. Continuing to rotate pipe, increase to 60 RPM in open hole. Continue into hole until TD is reached. 12. Rig up Cementing Manifold onto last stand of the landing string. 13. Launch 2" setting ball from the Cementing Manifold. 14. Circulate ball at 1-2 bpm to chase ball down. Shut pumps down before the ball reaches the ball seat to prevent inadvertently engaging the LHSART. 15. With the setting ball on seat, pressure up to 2,000 psi to hydraulically release LHSART. 16. Pick up LHSART to check for release. 17. While tripping out of the hole with LHSART and BHA, wash liner top in preparation for tieback with Liner Top Isolation Packer (LTIP). 18. Pull out of the hole.

5

Running Procedures to Install Liner Top Isolation Packer (LTIP) 1. Pick up and run the cementing drill pipe, stinger and (Halliburton Fas Drill?) Squeeze Packer, properly spaced out for squeeze job.

22. Pressure down annulus to 1,000 psi to test packer seal; hold test pressure for 5 minutes.

2. Pick up the LTIP with LTIP Running Tool and make up to cementing drill pipe.

23. Bleed off pressure.

3. Make up landing string to LTIP Running Tool and trip into the hole per pipe tally.

25. Rotate drill string to set the Halliburton Fas Drill Squeeze Packer to isolate the drill pipe annulus to squeeze the liner shoe.

4. Inside casing, wash and clean the hole per operator's procedures. 5. Wash and clean the liner top at 200 to 300 GPM, prior to stabbing into liner top to avoid damaging seals. 6. Tag LHSA to locate latch ring. 7. Slack off 60,000 lbs at the tool to expand load ring into profile in tieback and lock load ring. 8. Pick up 100,000 lbs over drill pipe weight to verify that load ring is engaged into tieback.

24. Pick up running tool above the liner top.

26. Pump and displace cement per operator’s procedure. 27. Pull stinger out of the Halliburton Fas Drill Squeeze Packer and circulate per operator’s procedure. 28. Pull out of the hole with the running tool and stinger.

9. Slack off to neutral weight. 10. Rig up cementing manifold. 11. Drop 3" setting ball from surface and circulate to running tool. 12. With setting ball on seat, pick up 100,000 lbs over drill pipe weight to put liner in tension. 13. Pressure to 1,000 psi to set bidirectional slip and suspend liner in tension. 14. Slack off 60,000 lbs at the tool, then pick up 60,000 lbs over drill pipe weight to aid in setting the slip. Repeat, increasing setting load to 100,000 lbs. 15. Slack off 40,000 lbs at the tool onto the slip. 16. Pressure to 2,000 psi to release running tool from LTIP, then release pressure to 500 psi and hold. 17. Pick up running string and check that running tool is released from the packer. If running tool is released you will note pressure drop in drill pipe within 4-6" of pipe movement at the running tool. 18. Pick up running tool's Packer Setting Assembly (PSA) above the liner top. 19. Slack off PSA back into the Tieback of the LTIP to trip and "arm" the Packer Setting Ring on the PSA. 20. Pick up running tool's PSA above the liner top a second time to release Packer Setting Ring. 21. Slowly slack off 100,000 lbs at the tool to set the packer seal. Add slow rotation of the drill pipe while slacking off to aid in working down the drill pipe weight.

6

Worldwide Sales & Service DRIL-QUIP WESTERN HEMISPHERE

DRIL-QUIP EASTERN HEMISPHERE

DRIL-QUIP ASIA PACIFIC

DRIL-QUIP, INC. World Headquarters

DRIL-QUIP (Europe), Ltd.

DRIL-QUIP Asia Pacific Pte. Ltd.

DRIL-QUIP do Brasil, LTDA.

DRIL-QUIP London

DRIL-QUIP China

Macaé, Brazil Tel (55) 22 2791 8950 Fax (55) 22 2791 8989

High Wycombe, Bucks, England Tel (44) 1494 601086 Fax (44) 1494 601094

DRIL-QUIP New Orleans

DRIL-QUIP Norway

DRIL-QUIP Egypt

DRIL-QUIP The Netherlands

Alexandria, Egypt Tel (20) 3 450 0507 Fax (20) 3 450 0508

6401 North Eldridge Pkwy. Houston, Texas 77041 Tel (713) 939 7711 Fax (713) 939 8063

New Orleans, Louisiana Tel (504) 522 5566 Fax (504) 522 4426

Stoneywood Park, Dyce Aberdeen, Scotland, UK AB21 7DZ Tel (44) 1224 727000 Fax (44) 1224 727070

Stavanger, Norway Tel (47) 51 443700 Fax (47) 51 443701 Beverwijk, The Netherlands Tel (31) 251 22 9250 Fax (31) 251 22 0044

DRIL-QUIP Denmark Esbjerg, Denmark Tel (45) 7518 0944 Fax (45) 7518 0640

Shekou, P. R. China Tel (86) 75 5268 97137 Fax (86) 75 5268 97134

Zahraa El-Maadi, Cairo, Egypt Tel (20) 22 753 8809 Fax (20) 22 753 8907

DRIL-QUIP Nigeria, Ltd. Port Harcourt, Nigeria Tel (234) 84 463866 Fax (234) 84 463649 DRIL-QUIP (Ghana) Ltd. Takoradi, Ghana Tel: (233) 312 5384

www.dril-quip.com 072214T

© 2014 Dril-Quip, inc. Printed in the USA

No. 80 Tuas West Drive Singapore, 638417 Tel (65) 6861 0600 Fax (65) 6861 5700

DRIL-QUIP Oilfield Services (Tianjin) Co., Ltd. Tanggu, Tianjin, P. R. China Tel (86) 22 2580 7466 Fax (86) 22 2580 7130

DRIL-QUIP Malaysia

Kuala Lumpur, Malaysia Tel (60) 3 2168 4308 Fax (60) 3 2168 4201

D.Q. Holdings Pty., Ltd. Perth, Australia Tel (61) 8 9322 8600 Fax (61) 8 9322 8500

DRIL-QUIP Qatar

Doha, Qatar Tel (974) 44389715 Fax (974) 44417041

DRIL-QUIP Indonesia Jakarta, Indonesia Tel (62) 21 720 0612 Fax (62) 21 720 1513

Suggest Documents