Presentation on Annual Plan 2013-14

Planning Department, Government of Maharashtra Date : 16th May, 2013

State Economy : GSDP 15.4

16

At current Prices

14 12.0 12

10.4

10 8

8.6

At constant prices (2004-05) 9.2

7.5 6.8

6 5.9

6.1

6.7

7.4

7.9

8.4

* Advance estimates

** 2013-14

* 2012-13

2011-12

2010-11

2009-10

2008-09

4 2007-08

GSDP (Rs. lakh crore)

13.7

** Projected 2

GSDP & GDP : Growth Rates 11.3

10 9.3

8

7.1

7.1

GSDP 6

6.7

6.2

GDP 5.0

4

2.6

2

*

* 2012-13

2011-12

2010-11

2009-10

2008-09

0 2007-08

Growth Rate (per cent)

12

Advance estimates

Link

Link

Link

Link

3

100000

Rs. 83,395 Rs. 95,339

120000

Rs. 95,135 Rs. 1,09,064

Per Capita Income : Selected States

2010-11

2011-12

Per capita income (India)

Rs.

80000

Rs. 61,564

60000

Rs. 54,151 Per capita income (India)

40000

UP

WB

AP

Karnataka

Punjab

Kerala

Tamil Nadu

Gujarat

Maharashtra

Haryana

20000

4

Own Tax Revenue : Growth Rates (Per cent)

Particulars

X FYP

XI FYP

Sales Tax

15.7

17.3

Stamps & Registration Fees

22.8

13.9

State Excise Duty

14.2

21.4

Electricity Duty

8.2

15.8

Tax on Vehicles

18.3

17.9

Total Own Tax Revenue

15.1

16.5

Link Graph

5

Taxation Measures y Increase in VAT on y Unmanufactured tobacco by 12.5 per cent y Cigarette by 5 per cent y Bidi by 7.5 per cent y Increase in excise duty on liquor y Rationalisation of stamp duties y Temporary tax for drought relief y Sugarcane purchase tax from 3 to 5 per cent y VAT on Gold and Jewellery from 1.0 to 1.1 per cent 6

State’s Debt Stock Year

Interest Payment / Revenue Receipts (%)

Fiscal Deficit to GSDP (%)

18.8 (26.1)

14.4

1.7 (3.0)

2.5

18.0 (25.5)

13.3

1.4 (3.0)

2.7

17.6 (24.8)

13.5

1.6 (3.0)

Debt stock

Debt stock to GSDP

GSDP (current prices) (Rs. Lakh Crore)

(Rs. Lakh Crore)

(%)

2011-12

12.0

2.3

2012-13 (RE)

13.7*

2013-14 (BE)

15.4**

Note : Figures in brackets indicate CFRP (13th F.C).

* Advance estimates **- Projected

Link

Graph

7

Agriculture : Major Challenges

Shallow soil (40%)

Rainfed area (83%)

Low value Coarse cereals (Jowar, Bajra)

Degraded Soils (42%)

Poor financial & Market access

Small Holdings (73%) Link

8

Agriculture : Area, Production & Yield Crop

Cereals

Pulses

Foodgrains

Item Area (lakh ha.) Yield (kg/ha.) Production (lakh MT) Area (lakh ha.) Yield (kg/ha.) Production (lakh MT) Area (lakh ha.) Yield (kg/ha.) Production (lakh MT)

201011

2011-12

201213

Requirement *

90

76

68

.

1,371

1,377

1,207

.

123

104

83

133

40

33

33

767

701

667

.

31

23

22

12

130

109

101

1,184

1,172

1,032

.

154

127

104

144

.

.

9

Horticulture : A success story y Highest Production in the country : 250 lakh tonnes. y Highest production of Banana, Grapes, Pomegranate,

Sweet lime, Oranges, Cashew nut, Onion y Highest exports of Grapes, Pomegranate, Onion y Investment by Government in pre cooling, Cold-

storages, Grading & Packing units, ripening Chambers at 50 locations. y Reforms for direct marketing, private markets, PPP 10

Agriculture : Strategy for XII FYP y Form cropwise & activitywise Common Interest Groups y Develop agriculture through end-to-end projects y Emphasise Micro Irrigation y Disseminate information through ICT y Develop market-linkages for Horticulture products y Promote Agri-business & Agri-Exports through PPP-IAD

11

Agriculture

: Request for . . . .

y Implementation of Sikka Committee recommendations y Dry Land Farming Mission y Weather Based Crop Insurance y Farm Pond Lining outside NHM y Micro-Irrigation for 5 lakh ha. per year y Encouraging PPP y Accelerating formation of FIG / CIG

Link

12

Irrigation: Potential Created & Utilized Potential (Lakh ha.) Year

Potential Utilized to Created (%)

Created

Utilized

2007-08

43.3

27.6

63.8

2008-09

44.9

27.3

60.0

2009-10

46.3

25.4

54.9

2010-11

47.4

29.6

62.4

2011-12

49.3

32.5

67.4

13

Water Conservation : Check Dams y Check Dams in series in streams y Cost : Rs. 8 – 10 lakh y Capacity : 10 TCM y Construction Period : 3-6 Months

Contd..

14

Water Conservation : Check Dams y Very popular, High Demand y As a standalone watershed project y Rs. 350 crore for 2012-13 & 2013-14 y Need central support for permanent drought mitigation

15

MGNREGA : Performance

Particulars

Expenditure (Rs. crore)

2010-11

2011-12

2012-13

325

1,568

2,230

1,820

61,786

94,068

Person Days (crore)

1.9

7.7

8.3

Average Employment per household (days)

40

51

53

Works Completed (Cumulative)

16

Health : Indicators Indicators

Unit

Target for XI FYP

IMR (2011)

Per thousand live births

17

25

3

MMR (2007-09)

Per lakh live births

50

104*

3

TFR (2010)

Children / woman

2.1

1.9*

3

Institutional Deliveries ( 2009)

Per cent

-

90.7@

10

Malnutrition of Children (0 - 3 years)

Per cent

24.8

32.7+

-

Anaemia among women (15-49 years)

Per cent

24.3

57.8+

3

Present National status Rank

17

Health : Malnutrition (Per Cent)

Children State

Malnourished

Severely Malnourished

Bihar

82.1

25.9

Andhra Pradesh

48.7

0.1

Utter Pradesh

40.9

0.2

Karnataka

39.5

2.8

Gujarat

38.5

4.6

Kerala

36.9

0.1

Tamilnadu

35.2

0

Madhya Pradesh

28.5

1.9

Maharashtra

23.3

2.6

18

Education : Major Initiatives

y State Assessment & Accreditation Council y Revision of Recruitment Rules to ensure quality teachers y Sensitization workshops for stakeholders y Compulsory use of UDISE data y Self Finance Act y Independent evaluation of schemes

Link

Link

19

Water Supply & Sanitation

y Safe drinking water facilities to 94% habitations y Leading in the cleanliness campaign in India y Nirmal Gram Puraskar to 9,500 VPs y RIDF assisted Waste Water Management Projects of Rs.

100 Crore in large villages

Link Link

20

Power : Capacity Addition (MW)

As on 31st March

Expected in 2013-14

Source 2012

2013

10,366

12,446

18,836

4,198

4,609

5,164

3,066

3,066

3,066

2,740

2,740

2,740

Central Sector Allocation

5,792

6,307

6,627

Total

26,162

29,168

36,433

Thermal Renewable Hydro Natural gas

Link

Link

21

Power : Availability y Energy shortage reduced from 18% (2005) to 3% (2013) y Assured 8 to 10 hrs. power supply to agriculture y 82% feeders : load shedding free y All industrial feeders : load shedding free y Load shedding only on feeders having more than 42%

DCL y Revenue up by 10-20% in loss making areas

Link

22

Power : Consumer Focus

y 101 ATP Machines installed y Online payment and connection release facility y Real Time Gross Settlement (RTGS) y IR/RF Meters (Around 22% rise in revenue) y Automatic Meter Reading for industries y Call Centre for complaint redresal y Consumer Facilitation Centre Link

23

Roads : National Highways in selected states State

Area (Lakh Sq.Km.)

NH Length (Km.)

NH Length per 100 sq. km. area

Bihar

0.94

4,106

4.36

Uttar Pradesh

2.41

7,818

3.24

Karnataka

1.92

4,396

2.29

Gujarat

1.96

4,032

2.06

Maharashtra

3.08

5,616

1.83

Andhra Pradesh

2.75

4,537

1.65

Madhya Pradesh

3.08

5,064

1.64

Request for sanctioning 6,026 kms of NH projects Link

Link

24

Rural Roads: Rural Connectivity (PMGSY) Particulars Sanctioned

New connectivity ( km.)

Upgradation ( km.)

3,652

19,553

Expenditure upto 2012-13 (Rs. crore) 4,978

Completed

3,329

18,668

Request for sanctioning 5000 kms of roads under PMGSY

Buldhana road, a rural road joining two Tehsils in Vidarbha, Maharashtra

25

Railways : Projects with State contribution Project name

State Estimated cost contribution (Rs. crore) (%)

Ahmednagar-Parli Vaijnath

2,826

50

Wardha-Nanded-Pusad

2,548

40

Manmad-Indore

1,751

50

Wadsa Desaiganj-Gadchiroli

232

50

Nagpur-Nagbhir

376

50

Gadchandur - Adilabad

300

50

1,900

50

928

50

9,985

48

Pune-Nashik Karad-Chiplun Total

Status

Sanctioned

Approval awaited

26

Ports

y Projects delayed due to moratorium on environmental

clearance y Rewas project held up due to non-availability of Right of

Way through MbPT y Estimated Cargo handling by 2020 - 140 MTPA y Focus on ports connectivity y Need for VGF for rail connectivity

Link

27

Civil Aviation

: Airports

y 22 Airports in the State y 19 District HQs connected with airports y Night landing facilities at 4 international and 6 domestic

Airports y 4 Greenfield Airports under consideration y 4 Airports taken up for upgradation and expansion

Link

Link

28

Industry y Accounts for 10% of industrial investment in India y Attracts 1/4th of country’s FDI y Accounts for over 27% share in total exports y New Industrial Policy – 2013 y Focus on Mega Projects and MSMEs y Mega Project : Investment : 100 – 750 cr.

Employment : 250 – 1500 y 379 mega projects since 2005 y Investment : Rs. 3 lakh cr. y Employment : 3.5 lakh

Contd.. 29

Industry

y MSMEs : 1,66,578 y Clusters formed : 70 y Common Facility Centres : worth Rs. 441 cr. in last 5 yrs. y 3 MSE-CDP & 4 IIUS Clusters operational y Fly-Ash Cluster, Raisin Cluster, Garment Cluster, Textile

Cluster, General Engineering Cluster etc. y Proposals for 15 clusters ready for submission

30

Textiles y Cotton Production : 70 lakh bales, 2nd largest y Mainly in Vidarbha, Marathwada & North Maharashtra y Only 20% processed in State y Huge employment potential y Textile Policy in 2012-13 y Request to continue TUFS during entire XII FYP y Request removal of sectoral caps in TUFS 31

Housing : BSUP and IHSDP impediments

y Cost Escalation y Fixed Cost Norms of Dwelling Units in IHSDP y Reluctance for relocation : High Rise Buildings & Off-site y Slow pace of construction due to severe drought y Supreme Court’s order regarding Environmental

clearances for sand mining

Link

32

Housing : Indira Awas Yojana (Lakh)

Year

Target

Houses Completed

Percentage to the target

2008-09

1.16

1.14

98

2009-10

2.24

2.06

92

2010-11

1.55

1.58

102

2011-12

1.51

1.53

101

2012-13

1.74

1.43

82 *

*Final report awaited

Request increase in cost norms to Rs.1 lakh per unit 33

Urban Development : JNNURM 31st March, 2013

Particulars

UIG+ Bus+ UIDSSMT e-Governance

No. of Cities with approved projects

13

86

No. of Projects approved

94

95

Total cost (Rs. cr.)

12,360

2,827

GoI share (Rs. cr.)

5,491

2,261

GoI share released (Rs. cr.)

4,281

1,992 34

Mumbai Infrastructure Development y Ongoing Projects y

Metro-I : Versova-Andheri-Ghatkopar

y

Metro-III : Colaba-Bandra-Seepz

y

Mumbai Trans Harbour Link

y

Mumbai Urban Transport Project-I

y

Mumbai Urban Transport Project-II

35

Environment : Achievements y Only State which has a RRZ Regulatotion y Environment awarenessy Environment Service Scheme in schools y Call for Green Ideas – Environment protection with

community participation y Certificate Course in Waste Water Treatment Plant

Operator y Environment research sponsored in technical institutions y Environment Status Report in all districts – an inventory

of natural resources y Environment Information Centers – in all districts 36

Environment : Challenges Delays in Environment Clearance due to y High Rise Office Memorandum y Action on violations

Office Memorandum y Moratorium in Ratnagiri and Sindhudurg y Kasturi Rangan Committee Report y Mines below 5 Hectares in Environment Clearance

37

State’s Expectations . . . y Agriculture y Implementation of Sikka Committee recommendations y Dry Land Farming Mission y Weather Based Crop Insurance y Farm Pond Lining outside NHM y Micro-Irrigation for 5 lakh ha. per year y Encouraging PPP y Accelerating formation of FIG / CIG Contd… 38

State’s Expectations . . . y Water Conservation y Need central support for permanent drought mitigation y Power – Coal y Intervention of MoC for allocation of tapering coal

linkages y Dedicated transport corridor from Odisha • Roads • Sanction 6,026 kms of NH projects • Textile • Continue TUFS during entire XII FYP • Remove sectoral caps in TUFS

Contd..

39

State’s Expectations . . . y Education y

Private Aided School be brought under the purview of SSA and RMSA

y

More grants for computer aided learning

y Housing y

Relaxation in ACA release norms

y

Allow un-utilised ACA for EWS/LIG Housing in MMR, Nagpur, Pune and Nashik

y

Completion period be extended to 31st March 2015

• Revise the cost norms for DUs in-progress to Rs1.5 40 lakh Contd..

State’s Expectations . . . • Indira Awas Yojana • Increase cost norms to Rs.1 lakh per unit y Water Supply & Sanitation y

NRDWP • Increase ‘Sustainability Outlay’ from 10% to 15% • Include metering cost in project cost as 100% grants • Increase O & M outlay from 15% to 20%

Contd..

41

State’s Expectations . . . Environment Managementy Need increased focus on Waste Water Treatment y Larger outlay for National River Action Plan and National

Lake Conservation Programme y River Basin-wise action plans : technical and financial

support y Environment awareness : more funds y Solid Waste Management : financial support

42

Sectoral XII FYP and Annual Plans (Rs. Crore)

Annual Plan Sector

XII FYP

12-13

13-14

13-14 Revised

Agriculture and Allied Services

21,917

3,258

3,524

9,089

1,504

1,465

Irrigation and Flood Control

47,990

7,614

8,379

Energy

20,695

3,063

3,376

2,175

353

403

33,855

5,575

5,292

3,364

742

759

1,22,776

20,524

20,919

10,989

1,777

2,112

2,150

590

709

2,75,000

45,000

46,938

Rural Development

Industry and Minerals Transport General Economic Services Social and Community Services General Services Other Programmes Total

Link

Revised outlay Rs 48,500 cr. Additional 1,199 cr. for Gosikhurd National Irrigation Project Proportionate increase in SCSP / TSP Link

48,500 43

Outlays : SCSP and TSP (Rs. crore)

Year

Total Plan

SCSP

TSP

2009-10

35,958

2,652

2,314

2010-11

37,916

3,461

3,020

2011-12

42,000

4,284

3,738

2012-13

45,000

4,590

4,005

2013-14

48,500

4,947

4,316

44

Annual Plan 2013-14 : PSUs (Rs. Crore)

PSU

Annual Plan outlay 2012-13

2013-14

CIDCO

2,656

2,286

MHADA

2,884

2,905

MMRDA

4,663

3,917

MSRDC

280

900

MSRTC

575

476

1,692

2,140

8

18

MSEB (Generation, Transmission, Distribution)

13,321

18,529

Total

26,079

31,171

MIDC MAIDC

45

Thank You

46 / N N

Growth Rates : GSDP and GDP (2012-13) (Per Cent) Sector

GSDP

GDP

(-) 2.1

1.8

Industry

7.0

3.1

Services

8.5

6.6

Total

7.1

5.0

Agriculture & Allied

Back

47

GSDP & GDP : Sectoral Contribution Sector

(Rs. crore) 2011-12 2012-13

2008-09

2009-10

2010-11

Agriculture & allied activities

10.1 (15.8)

10.4 (14.7)

12.3 (14.5)

12.4 (13.9)

11.5 (13.7)

Industry

31.3 (28.1)

29.8 (28.1)

28.5 (27.8)

28.0 (27.1)

27.8 (27.0)

Services

58.6 (56.1)

59.8 (57.2)

59.1 (57.7)

59.5 (59.0)

60.7 (59.3)

100

100

100

100

100

All

Note : Figures in bracket indicate percentage contribution to GDP

Back

48 / NN 48

Growth Rate, Share in GDP, Per Capita Income : Major States & India (Per Cent) Share in GDP (2011-12)

Growth Rate (XI FYP)

Per capita income (Rs.) (2011-12)

Andhra Pradesh

8.2

68,970

7.8

Gujarat*

9.5

89,668

7.3

Haryana

9.0

1,09,064

3.7

Karnataka

7.2

69,051

5.5

Kerala

8.2

80,924

3.8

Maharashtra

8.1

95,339

14.4

Punjab

6.7

78,594

3.1

Tamil Nadu

7.7

84,496

7.6

West Bengal

7.3

55,222

6.5

India

8.0

61,564

-

State

* 2010-11

Note : In 2006-07, Maharashtra’s share in GDP was 15%

Back

49 / NN 49

Own Tax Revenue : Share of Major Taxes (Per cent) Particulars

2011-12

2012-13 (RE)

Sales Tax

57.7

59.1

Stamps and Registration Fees

16.5

16.4

State Excise Duty

9.8

9.5

Electricity Duty

5.5

5.3

Tax on Vehicles

4.7

4.4

Other Taxes on Income & Expenditure *

2.1

1.9

Other Taxes

3.7

3.4

100.0

100.0

Total Own Tax Revenue * Includes taxes on profession, trades, callings & employment

Back

50 / NN 50

Own Tax Revenue & Tax Revenue to GSDP

8.4

8.4

8.4

Tax/GSDP 8.0

Per cent

8.0 7.6 7.2

7.3

7.3 OTR/GSDP

6.9

6.8 6.4 2008 -09

2009 -10

2010 -11

2011 -12

2012 -13 (RE)

Back

51 / NN 51

State’s Debt Stock Year

GSDP (at current prices) (Rs. Lakh Crore)

Interest Interest Payments Payments to (Rs. Lakh Revenue Crore) Receipts (%)

Fiscal deficit to GSDP (%)

Debt stock (Rs. Lakh Crore)

Debt stock to GSDP (%)

0.18

14.4

1.7 (3.0)

2011-12

12.0

2.3

18.8 (26.1)

2012-13 (RE)

13.7*

2.5

18.0 (25.5)

0.19

13.3

1.4 (3.0)

2013-14 (BE)

15.4**

2.7

17.6 (24.8)

0.21

13.5

1.6 (3.0)

Note : Figures in brackets indicate CFRP (13th F.C).

* Advance estimates **Projected

Back

52 / NN 52

Consolidated Fiscal Reform Path (13th FC) Percentage of fiscal deficit to GSDP Consolidated Fiscal Reform Path 4 3.0

3.0

3.0

2

2.0

1.7

1.6 per cent of GSDP (Margin) 1.4

1

2012-13(RE)

2011-12

20010-11

2009-10

2008-09

-1

2007-08

0 2006-07

Per cent

3

Back

53 / NN 53

Financing : XII FYP & Annual Plans (Rs. Crore)

XII FYP

State’s Own Resources

1,03,260 (38%)

14,102 (32%)

15,435 (32%)

State’s Borrowings

1,21,425 (44%)

22,651 (50%)

25,350 (52%)

Central Assistance

50,315 (18%)

8,247 (18%)

7,715 (16%)

2,75,000

45,000

48,500

Total

AP 2012-13

AP 2013-14 (Proposed)

Sources of Fund

Back

54

Sectoral Share : XII FYP and Annual Plan 2013-14 Annual Plan 2013-14 (Proposed) Sector

State Level

District Level

Total

(Per Cent) XII FYP

Agriculture and Allied Services

6.1

13.1

7.5

8.0

Rural Development

2.9

4.1

3.1

3.3

21.1

4.6

17.9

17.5

Energy

8.3

2.5

7.2

7.5

Industry and Minerals

1.0

0.5

0.9

0.8

10.8

13.1

11.3

12.3

1.5

2.1

1.6

1.2

41.8

55.7

44.6

44.6

General Services

4.5

4.3

4.5

4.0

Other Programmes

2.0

0.0

1.4

0.8

100.0

100.0

100.0

100.055

Irrigation and Flood Control

Transport General Economic Services Social and Community Services

Total

55 / NN

Back

Agriculture : Area, Production & Yield Crop

Item

Cotton

Sugarcane

2011-12

2012-13

36

38

38

1,392

1,236

1,350

Production (lakh Tonne)

51

46

52

Area (lakh ha.)

39

42

42

Yield (kg./ha.)

322

278

284

Production (lakh Bales*)

75

68

69

Area (lakh ha.)

10

10

9

Yield (MT/ha.)

89

88

64

857

895

597

Area (lakh ha.) Oilseeds

2010-11

Yield (kg./ha.)

Production (lakh Tonne) Source : Commissionerate of Agriculture, GoM

* One bale of 170 kg.

Back

56 / NN 56

Sikka Committee recommendations y Special drought mitigation package for 7 districts – Pune

(1,830 cr.), Satara (2,318 cr.), Sangli (2,658 cr.), Solapur (1,625 cr.), Ahmadnagar (1,641 cr.), Beed (1,159 cr.) and Osmanabad (552 cr.) y Total 11,783 cr. y Cluster of area and watershed management 1078 cr. y Water resources augmentation 8,331 cr. y Water use management 1,521 cr. y Agriculture and diversification to horticulture 456 cr. y Drinking water 184 cr. y Livestock and fodder development 131 cr. y Fringe forest management

Back

57

Agriculture : Irrigation Status of Major States 97.6

100

National Average – 45.30% 85.3

90

76.4

80 61

70

58.3

56.2

60

48.7

%

50

45.6 35

40

34.7

32.5

31.9

30

17.7

17

20 10

Back

Kerala

Maharashtra

Karn.

M. P.

Raj.

Odisha

Guj.

A. P.

W. B.

T. N.

Bihar

U. P.

Harayana

Punjab

0

58

Agriculture : Irrigation Status Surface Irrigation Surface Irrigation

Well Irrigation

• •

Flow Wells

-

20.13 19.40

lakh Ha. lakh Ha.



Total

-

39.53

lakh Ha.



Percent -

17.70

%

59 / NN 59

MGNREGA : Performance Particulars Expenditure (Rs. crore)

2010-11

2011-12

2012-13

325

1,568

2,230

1,820

61,786

94,068

Person Days (crore)

1.9

7.7

8.3

Average Employment per household (days)

40

51

53

Share of SCs in Employment (%)

6.9

7.8

7.0*

Share of STs in Employment (%)

15.6

19.7

14.5*

Share of women in Employment ( %)

48.5

46.0

44.5

Employment generating Cost per day (Rs.)

172

203

268

Works Completed (Cumulative)

Source – EGS & Water Conservation Dept., GOM

*Data under updation

60 / 52 60

Power : R-APDRP y Part-A : y Rs. 324 crore estimated cost for 130 towns y 61 towns completed y Current Network Digitized

y Part-B : y Rs. 2,927 crore estimated cost for 120 Towns y 20% work completed

y Aim to : y Reduce loss y Improve Reliability y Release Connections Back

61

Power : Coal issue y Coal linkage from MCL 15.56 MMTPA y Coal linkage materialization @ 48% y Intervention of MoC/Railways required to step up

the supply from MCL to supply sufficient rakes as per linkage y Thermal power stations facing problems of low coal

stocks due to shortage of coal rakes/inadequate coal rake movements y Consistently raising this issue with MCL, Railways,

CEA

Back

Contd..

62 / NN 62

Power : Coal issue y New

up-comming projects Chandrapur 2x500MW,Koradi 3X660MW, Parli 1x250MW linked with Machhakata coal block, allocated jointly to Mahagenco & GSECL

y Facing hurdles in starting coal production from

Machhakata

Back

63 / NN 63

Power : Gas Issues y Uran Gas Station y GTPS Uran plant 672 MW capacity requires 3.5 mmscmd

gas y Average gas supply from M/s Gail @ 1.9 to 2.3 mmscmd y Not receiving gas from M/s RIL due to drop in production y Present Generation dropped to 400 MW

y RGPPL Gas issues y Installed Capacity - 1967 MW y Gas allocated from GoI

KG06 from RIL – 7.6mmscmd y ONGC C -series from Gail - 0.9 mmscmd y Total Gas allocated – 8.5 mmscmd y

y Generation availability vary from 0 to 600 MW y Plant completely shut down due to non availability of Gas 64 / NN Back

64

Power : Renewable Energy Installed Capacity Source Wind

Installed Capacity as on March 31 2009

2010

2011

2012

2013

1932

2071

2310

2717

3006

Bagasse

393

422

620

893

1088

Biomass

95

115

155

155

170

Solid waste

11

11

16

20

24

0

0

1

20

175

214

230

247

265

271

2634

2838

3348

4070

4734

Solar Small Hydro Project Total

Back

65 / NN 65

Power : Infrastructure y Infra-I : y Total cost Rs. 9,014 crore y 596 Substations added y 67,418 Distribution transformer added

y Distribution Transformer Failure rate reduced from 16.1% in

FY 2005-06 to 5.7% in FY 2012-13

y Infra-II : y Total Cost Rs. 6,500 crore, next 3 years y 31.6 Lakhs connections to release in next 3 years y Agriculture – 4.8 Lakh y Residential – 24.6 Lakh y Commercial – 1.8 Lakh y Industrial - 0.4 Lakh Back

66 / NN 66

Power : Per Capita Consumption (Units) Type

India

Maharashtra

2010-11

2010-11

2011-12

Industrial

190

307

321

Domestic

131

175

185

Agriculture

107

145

191

Source: Economic Survey of Maharashtra 2012-13

Back

67 / NN 67

Power : Renewal energy y 125 MWP Sakri, Dhule

Back

68 / NN 68

Power : Transmission and Distribution losses Transmission Loss

Dist. Loss

AT & C loss

30 25.8

Losses (per cent)

25

22.3

20

21.3

20.7

20.6 17.3

15

16.0

14.5

10 5 4.6

4.3

4.2

4.2

0 2009-10

2010-11

2011-12

2012-13 (Provisional)

Source : Energy Dept.

Back

69 / NN 69

Consumer Focus Centralized call center (Bhandup)

ATP Machine

Consumer Facilitation Center (Thane)

Automatic Meter Reading (AMR)

Back 70

Roads : Road Length in selected States As on 31st March, 2011 State

Area Road Length Road Length per 100 Sq. Km. (Lakh sq.km.) (Lakh km.) area (Km.)

Andhra Pradesh

2.75

2.38

87

Gujarat

1.96

1.56

80

Haryana

0.44

0.42

94

Karnataka

1.92

2.82

147

Kerala

0.39

2.01

518

Maharashtra

3.08

2.43

79

Punjab

0.50

0.84

167

Tamil Nadu

1.30

1.92

148

Uttar Pradesh

2.41

3.90

162

Back

71 / NN 71

Roads : Status Category of Road

Status as on Today (In Kms)

National Highway

5,616

State Highway/Expressway

32,910

Major District Road

50,256

Other District Road

47,529

Village Road

1,06,601 Total

2,42,912

Back

72 / NN 72

Ports y Development of ports on “BOOST” basis y Agreement

signed

for

greenfield

port

development: y Ratnagiri District : Dhamankhol -Jaigad & Angre y Raigad District : Rewas-Aware & Dighi y Sindhudurg District : Vijaydurg & Redi

y Proposed investment of Rs.15,000 crore; already

invested Rs. 4,000 crore y Dhamankhol-Jaigad,

operational

Angre

&

Dighi Back

ports 73 / NN 73

Civil Aviation : Navi Mumbai International Airport y Approvals / Clearances awaited from MoEF y Forest Clearance & Wild Life (ESZ) Clearance for Karnala

Bird Sanctuary y Forest Clearance appraised by Forest Advisory Committee

(FAC) for 250 ha. forest land

y Permission from Mumbai High Court for removal

of Mangroves Back

74 / NN 74

Civil Aviation : Navi Mumbai International Airport y Estimated Base Cost

: Rs.14,573 Crore

y Phase 1 Base Cost

: Rs.5,250 Crore

y Project Period

: 30 year

y Project Phases

:4

y D/E Ratio

: 70 : 30

y Equity IRR (Hybrid till)

: 20% approx.

Back

75 / 52 75

Civil Aviation : Airport Development y A greenfield international airport with two parallel

runways 4 km long planned at Pune y Work of 2500 metre runway at Shirdi near completion y Clerance from MoEF to Navi Mumbai International Greenfield Airport awaited. y Started work of Greenfield Airport at Chippiparule in Sindhudurg by MIDC. y Land acquired for development of new airport at Boramani, Solapur y Airports at Amravati, Kolhapur and Karad taken 76 / NN 76 for upgradation and expansion

Housing : JNNURM DUs SubApproved Project ACA cost (Rs. (Rs. Mission DUs In Crore) Crore) Completed (lakh) 2012-13 in XI FYP progress BSUP

1.4

5,838

2,819

54,295

2,551

25,469

IHSDP

1.1

2,559

1,604

16,762

5,779

20,897

Total

2.5

8,397

4,423

71,057

8,330

46,366

Back

77 / 52 77

Health : IMR and MMR 40 150 35

34 33

130 31

130 28 110

104

MMR

25 25

90

76

70

19

20

70 14

15

62 44

50

2017

2014-15

2013-14

2012-13

2007-09

2017

2012

2011

2010

2009

2008

2004-06

30

10 2007

IMR

30

Source : Public Health Department, GoM

Back

78

Health : MDG No.

Goal

Eradicate extreme poverty 1 and hunger

Target To halve the percentage of population below the National Poverty Line between 1990 and 2015 To halve the proportion of people suffering from hunger between 1990 and 2015.

Achieve universal primary 2 education

To ensure that all the children will be able to complete a full course of primary education by 2015.

3 Promote gender equality and empower women

To eliminate gender disparity in primary and secondary education preferably by 2005, and in all levels of education by 2015.

4 Reduce child mortality

To reduce the Under-five mortality rate by two-thirds between 1990 and 2015.

5 Improve maternal health

To reduce the Maternal Mortality Ratio by three quarters between 1990 and 2015.

Contd..

79 / NN 79

Health : MDG No. Goal Target 6 Combat HIV / AIDS, To halt the spread by 2015 and reverse the Malaria and other diseases spread of HIV/AIDS. To halt the spread by 2015 and reverse the spread of Malaria and other major diseases. 7 Ensure environmental To integrate the principles of sustainable sustainability development into country policies & programmes and reverse the loss of environmental resources. To halve the proportion of population without sustainable access to safe drinking water and basic sanitation by 2015. To achieve significant improvement in the lives of atleast 100 million slum dwellers by 2020. 8 Develop a global To make available the benefits of new partnership for technologies to the people, especially development information and communication, in cooperation with the private sector. Back

80

Water Supply & Sanitation: NRDWP No. of habitations Year Target

Achievement

Percentage

2009-10

11,639

7,465

64.1

2010-11

9,745

8,987

92.2

2011-12

6,502

6,364

97.9

2012-13

5,940

4,637

78.1

2013-15

14,030

-

-

81

Back

Water Supply & Sanitation: Nirmal Bharat Abhiyan Upto March, 2012 Component IHHL Community toilet (SCW)*

Target (‘000)

Achievement (‘000)

12,525

6,032

17

7

Source – Baseline survey conducted between 2nd October 2012 – 31st January, 2013 *100% target achieved for school and Aanganwadi toilets

Back

82

Education : RTE Compliance As on September, 2012 School Type

Number of Schools

(Lakh) Enrolment

No. of Teachers

Pupil Teacher Ratio

Government including local authority

0.7

62.5

2.8

22

Private aided

0.2

65.8

2.6

25

Private un-aided

0.1

33.0

1.2

27

1.0

161.3

6.6

24

Total

• •

Primary schools within 1 km., upper primary schools within 3 km. and secondary schools within 5 km. Back Literacy Rate : 82.9% (Second in India)

83

Education : Infrastructure As on 31st March, 2013 Item

Performance (%)

Girls toilet

98.3

Boys toilet

94.3

Water facility

98.0

Ramps

70.1

Boundary walls

68.8

Play ground

75.8

School Building

99.7

Electricity

88.6

Back 84

Education : Challanges y Out of School Children

: 86,856 y Gender Gap : 12.6% y Educationally Backward Blocks : 43 y High early primary drop out rate : Ahmadnagar, Jalna & Beed y Learning outcomes : Low (As per ASER) y Shifting from y ZP to Private Schools y Local Languages to English Medium School

y Poor capacity of Teachers & Supervisory officers

Back

y Private Schools / D.Ed. Colleges with poor

infrastructure

85

Education : Higher & Technical Stream General Education

Enrollment (Lakhs) 2011-12

2012-13

17.69

18.29

Technical Education

9.09

9.28

Medical Education

0.20

0.20

Veterinary and Fishery Science

0.02

0.02

Agriculture

0.11

0.12

27.08

27.89

Total

86

Mumbai Infrastructure Metro- I : Versova-Andheri-Ghatkopar

Project Scope

11.4-km fully elevated

Project Significance

Connectivity to eastern and western suburbs Reduction in travel time by 70 minutes

Commencement

March, 2008

Project Completion December, 2013 Project Cost

Rs. 2,356 crore

Financial Structure VGF Rs.650 crore. GoI Contribution : Rs.471 crore ; Received Rs.310.50 crore Present Status

Phase I commissioning in Sept.,13 from Versova to Airport Phase II commissioning in Dec.,13 from Airport to Ghatkopar Back Ten Metro Rakes arrived

87 / NN 87

Mumbai Infrastructure Metro- III : Colaba-Bandra-Seepz

Project Scope

Fully underground - 33.50 km.

Project Significance

Will provide connectivity to areas not having rail based transport. Four-coach Metro with capacity of 1178 passengers

Project Implementation Project Cost

2013 – 2019

Present status

Rs.23136 crore : Equity by GoI Rs. 2403 crore, GOM Rs. 2403 crore Process to secure JICA loan complete 88 / NN Back 88 GoI cabinet approval awaited

Mumbai infrastructure Mumbai Trans Harbour Link

Project Scope

Sewri - Nhava Sheva 6-Lane 22 km Link Road 16.5 Km Sea Bridge

Project Significance

Decongestion of island city. Development of main land. Connectivity with ports. Faster access to Navi Mumbai International Airport, Pune Expressway and to Southern India 5 years (2013 to 2018) Rs.9630 crore (VGF of Rs.1920 crore) RFP issued – January, 2013 Receipt of proposals – 24 May 2013 Award of Work – 24 June 2013 Financial Closure and project commencement 89 / NN Back 89 – Dec., 2013

Project Period Project Cost Present status

Mumbai Infrastructure Mumbai Urban Transport Project - I

Project Scope

Project Cost Financial Structure Present status

Providing additional 5th and 6th lines from Kurla to Thane and 101 new rail rakes Develope 12-km Jogeshwari-Vikhroli Link Road and 3.5-km Santacruz-Chembur Link Road Procuring 644 environment friendly buses Rs.5127 crore 40% World Bank contribution, 60% Counter Part Fund, GoI (Indian Railways) fund contribution Rs.2,055 cr. 12-km JVLR completed SCLR to be completed in DecemberBack 90 / NN 90

Mumbai Infrastructure Mumbai Urban Transport Project - II

Project Scope

Conversion of DC to AC 95 rail rakes Additional railway tracks

Project Significance Improvement of suburban rail system Project Cost

Rs.5,300 crore

Financial Structure

World Bank assistance - Rs.1910 crore

Back

91 / NN 91

GSDP & GDP : Sectoral Growth Rates (XI FYP) (Per cent) Sector

2007-08

2008-09 2009-10 2010-11 2011-12

XI FYP

Agriculture & allied activities

13.8 (5.8)

-15.5 ( 0.1)

1.0 (0.8)

17.8 (7.9)

4.6 (3.7)

4.3 (3.7)

Industry

11.7 (9.7)

-1.1 (4.4)

6.9 (9.2)

8.8 (9.2)

5.2 (3.5)

6.3 (7.2)

Services

10.5 (10.3)

8.0 (10.0)

11.7 (10.5)

10.0 (9.8)

8.4 (8.2)

9.7 (9.7)

GSDP (GDP)

11.3 (9.3)

2.6 (6.7)

9.3 (8.6)

10.2 (9.3)

7.1 (6.2)

8.1 (8.0)

Figures in bracket indicate growth rates in respect of GDP

Back

92 / NN 92

Leadership in eGovernance y More than 35,000 Common Service Centers established y State Data Centre set up to act as a common depository of Government

Data and applications, with focus on cloud computing y Signed MoU with Bharat Broad Band Network Limited (BBNL) for

implementing National Optical Fibre Network (NOFN) to facilitate connectivity to rural areas y e-Tendering made compulsory for all tenders above Rs. 10 lakh y e-Office, a Mission Mode Project aimed at bringing in paperless office,

being rolled out at State Head Quarters and a few districts

93 / NN 93

Pioneers in Aadhaar y Nearly 6 crore residents enrolled, of which 5.43 crore UIDs

generated y 12 districts selected for Aadhaar linked Financial Inclusion and

DBT y Introduced an innovative mechanism of testing the accuracy of

UID and linked account by pushing Re. 1 into each of the seeded account, appreciated by Hon. Chairman of UIDAI y First State to establish State Resident Data (SRDH) y Introduced the concept of USRDH (Usable SRDH) wherein the

data is being cleaned and standardized and also introduced the concept of Self Seeding

94 / NN 94

Receipts and Expenditure (Rs. crore) Particulars

X FYP

XI FYP

2012-13 (RE)

Revenue Receipts

2,17,120

4,74,918 (119)

1,44,623

Capital Receipts

1,41,693

1,03,243 (-27)

27,557

Revenue Expenditure

2,47,866

4,65,404 (88)

1,44,598

Capital Expenditure

1,10,780

1,14,778 (4)

27,423

Note : Figures in brackets indicate percentage increase over previous FYP

95 / NN 95

Civil Aviation : New Plans y All 6 Divisional HQ will be air-connected with y y

y

y

Boeing/Airbus landing with Night Landing facility State Government will link up all District HQ with airconnectivity during 12th FYP State Government planning to construct Heliport with Night Landing facility at important places in the State including Mumbai Allocation for Airport Development/Air connectivity has increased from Rs. 760 crores in 11th FYP to Rs. 1350 crores in 12th FYP The Budget Allocation has been increased from Rs.240 crores (2012-13) to Rs. 440 crores during 2013-14 96 / NN 96

OTR- Growth Rates

(Rs. crore)

X Plan Particulars

2002-03

2006-07

OTR

22,814

40,098

Sales Tax

13,488

Stamps & Registration Fees

XI Plan 2007-08

2011-12

15.1

47,528

87,648

16.5

24,131

15.7

26,753

50,596

17.3

2,823

6,416

22.8

8,550

14,407

13.9

State Excise Duty

1,939

3,301

14.2

3,963

8,605

21.4

Electricity duties

1,149

1,577

8.2

2,688

4,431

15.8

941

1,841

18.3

2,143

4,137

17.9

1,032

1,246

4.8

1,488

1,830

5.3

Taxes on Vehicles Other taxes on income & expenditure

Growth rate

Growth rate

97 / NN 97

Agriculture : Operational Holdings (201011) Holding Size (Ha.)

No. of Operational Holdings (‘000)

Percentage to total

Area of operational holdings (‘000 Ha.)

Percentage to total

Marginal (Up to 1.0)

6,709

49.0

3,186

16.1

Small (1.0 - 2.0)

4,049

29.6

5,734

28.9

Semi-medium (2.0 - 5.0)

2,158

15.8

5,761

29.0

Medium (5.0 - 10.0)

710

5.2

3,989

20.1

Large (10.0 and above)

73

0.4

1,171

5.9

13,699

100.0

19,842

100.0

Total

Back

98 / NN 98

Yield Rates of Some Major States (2011-12) Yield Rate (kg./ha.) State Andhra Pradesh

646

Total Foodgrains 2,525

Gujarat

823

1,961

Karnataka

455

1,637

Madhya Pradesh

803

1,411

Maharashtra

695

1,150

Tamil Nadu

512

2,687

Uttar Pradesh

991

2,495

West Bengal

911

2,675

India

694

2,059

Cereals

Source : Commissionerate of Agriculture, GoM

Pulses

99 / NN 99

RAY- Issues y The Cut-Off Date for

eligibility of Slum-dwellers for rehabilitation (under State Legislation) is 1st January 1995 ; this issue is presently sub-judiced in Hon. Supreme Court of India y Un-availability of adequate land with State Government & ULBs for In-Situ Rehabilitation and service constraints in observing the viable density norms of 500 Tenements/Net Hectare y Finalisation of Policy Guidelines for In-Situ redevelopment of slums on lands belonging to various Ministries and Departments of GoI y Unlocking Potential of Salt Pan and NDZ lands of GoI for effective Slum Free City planning and for creation of large stocks of Affordable Housing in Mumbai Metropolitan 100 / NN 100 Back Region

Growth Rates: Selected States (XI FYP) (Per cent) State

Agriculture & allied activities

Industry

Services

Total

Andhra Pradesh

5.3

8.1

9.6

8.3

Gujarat*

4.1

10.3

10.8

9.6

Haryana

3.3

6.9

12.7

9.1

Karnataka

5.7

5.3

9.5

7.6

Kerala

0.0

5.9

10.3

8.0

Maharashtra

4.3

6.3

9.7

8.1

Punjab

1.7

9.0

8.3

6.7

Tamil Nadu

2.2

7.6

8.8

7.7

West Bengal

2.7

5.1

9.0

6.9

India

3.7

7.2

9.7

8.0

Note : Figures in bracket indicate rank among listed States

*(2007-08 to 2010-11) 101 / NN 101

Interest payments and average cost of borrowings Interest payments 19,205

18000

17,505

10.0

20000

9.4

16000

9.0 8.2

12,932

8.1

8.0

14000

12000

Interest Payment (Rs. Crore)

11.0

10000

Year

2012-13 (RE)

2011-12

2010-11

2009-10

2008-09

7.0 2007-08

Avergae cost of Borrowing (per cent)

Average cost of borrowing

102 / NN 102

State Finances : Fiscal & Revenue Deficit (Per cent)

4 3

1.7

2 1

0.2

1.4

0.0

0 2012-13 (RE)

2011-12

2010-11

-2

2009-10

-1

2008-09

2007-08

-0.4

-2.2

-3

103 / NN 103

Revenue Expenditure : Composition Others 30%

Salary & Wages 37%

Subsidies 9% Interest Payments 14%

2011-12

Pension 10%

Others 30%

Salary & Wages 38%

Subsidies 9% Interest Payments 13%

Pension 10%

2012-13 (RE)

104 / NN 104

Plan Expenditure (Rs. crore)

Total plan expenditure Plan capital expenditure Capital expenditure/Total plan expenditure (%)

60.0 48.6

25,692

37,507

0 2007-08

2008-09

2009-10

2010-11

Year Expenditure includes CSS

37.8

15,472

15,155

5,000

13,272

10,000

9,709

15,000

19,998

20,000

41.3

40.0 30.0

16,071

31,879

30,000 25,000

33,256

35,000

50.0 Percentage

Expenditure

40,000

17000

45,000

44943

50,000

20.0 10.0

0.0 2011-12 2012-13 (RE) 105 / NN 105

ADF

Milk (lakh MT) Year

Eggs (crore)

Target

Achievement

Target Achievement

2011-12

84.5

84.7

436

2012-13

85.4

85.4

438

Meat (lakh MT) Target

Achievement

439

5.8

5.9

438

5.9

5.9

Source: ADF, GoM

106 / 52 106

Literacy Rates of Selected States (2011) 2001 State

Male Female Person

2011 Gender Gap

Male

Female Person

Gender Gap

Andhra Pradesh

70.3

50.4

60.5

19.9

75.6

59.7

67.7

15.9

Gujarat

79.7

57.8

69.1

21.9

87.2

70.7

79.3

16.5

Haryana

78.5

55.7

67.9

22.8

85.4

66.8

76.6

18.6

Karnataka

76.1

56.9

66.6

19.2

82.9

68.1

75.6

14.8

Kerala

94.2

87.7

90.9

6.5

96.0

92.0

93.9

4.0

Maharashtra

86.0

67.0

76.9

19.0

89.8

75.5

82.9

14.3

Punjab

75.2

63.4

69.7

11.8

81.5

71.3

76.7

10.2

Tamil Nadu

82.4

64.4

73.5

18.0

86.8

73.9

80.3

12.9

West Bengal

77.0

59.6

68.6

17.4

82.7

71.2

77.1

11.5

India

75.3

53.7

64.8

21.6

82.1

65.7

74.4

16.4

Source : Registrar General of India

Back

107 / NN 107

Literacy Rates : Rural, Urban, State (Per cent) Source

Rural

Urban

State

M

F

All

M

F

All

M

F

All

Population Census 2001

81.9

58.4

70.4

91.0

79.1

85.5

86.0

67.0

76.9

All (NSS 2007-08)

82.2

63.3

73.0

93.0

82.8

88.2

86.6

71.0

79.1

Population Census 2011

86.4

67.4

77.1

93.8

85.4

89.8

89.8

75.5

82.9

Back

108 / NN 108

Power : Non-Conventional Energy 5 , 000 4 ,546 4,

4 ,198 500

MW

4 , 000 3 ,408 3 , 500 3 , 000

2 ,807

2 , 500

2012-13*

2011-12

2010-11

2009-10

2 , 000

* - Upto Dec., 2012.

109 / NN 109

Industry: Mega Projects 2011-12

2012-13

Investme nt (Rs. Crore)

Employme nt

No .

Investme nt (Rs. Crore)

Employme nt

Mega Projects 82 Offer Letters (Since 2005)

87,741

56,307

56

40,912

31,244

13

7,970

7,153

31

16,975

17,848

No Particulars .

MOUs signed

11 0 / N N

110 / NN

Industry: MSME 2011-12 MSME

No.

Investment (Rs. Crore)

2012-13 Employme nt (Lakh)

No.

Investment (Rs. Crore)

Employmen t (Lakh)

Proposed

44,452

7,193

3.5

13,007

3,905

1.5

Functioning

15,606

4,443

2.1

14,738

4,331

1.6

11 1/ N N

111 / NN

Industry: FDI & Export 2011-12

11 2 / N N

Particulars

No.

FDI

-

Export from the State

-

Investment (Rs. Crore)

2012-13 Employment

No.

Investment (Rs. Crore)

Employment

44,664

-

-

40,909

-

3,94,005

-

-

3,54,582

-

112 / NN

Housing : JNNURM (Rs. crore) Sub Mission

Project Cost

Fund Released 2011-12

DUs completed

2012-13

2011-12

2012-13

Cumulative till March 2013

BSUP

6,241

442.6

115.5

22,636

2,551

55,747

IHSDP

2,672

208.2

261.7

7,894

5,793

19,435

Total

8,913

650.8

377.2

30,530

8,344

75,182

11 3 / N N

Status of Irrigation Potential ¾ Geographical Area (GA)

- 307 Lac ha

¾ Cultivable Area (CA)

- 225 Lac ha(73% GA)

¾ Annual Rainfall

- 400 to 6000 mm

¾ Ultimate Potential ƒ Through Surface Water

- 85 Lac ha (38% CA)

ƒ Through Surface & G.W.

- 126 Lac ha (56% CA)

¾ Potential created 06/2012

- 49.26 Lac ha

¾ Percentage of IP wrt. CA

- 21.89 %

¾ Percentage of IP wrt. ultimate potential

- 58%

114 / NN 114

O&M Cost and Recovery 900

803

Amount Rs. in Crores

800 700

673 627

600

709

746 765 762 627 632

555 500

490

450

400 300

252 200

494

466 448 453 413 416 377 370 378 376 333

O&M cost (Establishment+ M&R) Total Recovery

195

100 0

Back

115 / NN 115

On-going projects ¾ There are 589 projects under construction through five Irrigation Development Corporations. ¾ investment of about Rs.57,850 crore is made on these projects ¾ Balance estimated cost of works of these projects is about Rs.72,000 crore. ¾ Allocation for the irrigation sector increased from Rs. 1600 crore in 2003-04, to Rs.7,500 crore in 2013-14. ¾ this increased allocation can only cater the price escalation.

116 / NN 116

AIBP y So far received Rs. 11069 Crore y Till now 69 projects/ project components of Major and

Medium y Projects and 186 MI schemes included in this Programme y 39 Major and Medium projects and 100 MI schemes

completed y Created 6.43 lakh ha. irrigation potential under AIBP

117 / NN 117

Strategy for completion of ongoing projects y It is utmost important to give early benefits to the farmers, Due

to large balance cost and limited budgetary provisions, it becomes difficult to complete the project or project components y A Committee has been appointed by the Government of

Maharashtra consisting of Principal Secretary Planning, Finance and Water Resources to decide the priority of projects y Emphasis is given for creation of irrigation potential / storages

and completion of project / project component accruing early benefits. y This has resulted in reduction in number of on-going projects

from 1092 in 2010-11 to 589 in 2013-14. It is planned complete 140 projects during 2013-14.

118 / NN 118

Permanent measures for mitigation of drought y State traditionally remained drought prone State y Almost 70% of the State’s Geographical Area lies in semi-

aired region rendering it vulnerable to water scarcity. y Every year, some or other part of the State affected by

drought or drought like condition y To ameliorate the situation arising out of such drought

conditions, relief measures planned & State Government spends huge sum of money on relief measures y Taking permanent drought proofing measures is need of

the hour 119 / NN 119

Permanent measures for mitigation of drought y A Central team under the chairmanship of Shri Alok Sikka,

Technical expert, National Rainfed Area Authority, Planning Commission, Government of India visited the scarcity area of Pune division and Beed, Osmanabad Districts of Marathwada division in June 2012 y The Committee recommended Special Drought Mitigation

Package of Rs.11783.6 crore for seven Districts of the State, namely Pune, Satara, Sangli, Ahmednagar, Solapur, Beed and Osmanabad y The Committee recommended completion of

27 projects (9 Major, 7 Medium and 11 Lift Irrigation Schemes). Fast track completion of these projects at a total cost of Rs. 6615.72 120 120 crore will bring 3.17 lakh under irrigation.

Permanent measures for mitigation of drought y Abstract of proposed Central assistance under the drought

mitigation programme :.

1

Maharashtra Krishna Valley Development Corporation

26

Proposed funds requirement (Rs. Cr.) 8680.21

2

Godavari Marathwada Irrigation Development Corporation (RoM)

6

878.92

73272

3

Tapi Irrigation Development Corporation

26

1450.18

137198

58 1

11009.31 160.13

640475 7955

Sr No.

No of Projects

Name of Corporation

Total (RoM)

Irrigation Area to be created (In Ha.) 430005

4

Maharashtra Krishna Valley Development Corporation (Marathwada)

5

Godavari Marathwada Irrigation Development Corporation (Marathwada)

10

2878.43

86364

Total (Marthawada)

11 69

3038.56 14047.87

94319 734794

TOTAL

121

121

Permanent measures for mitigation of drought ¾ The funds allocated for the Irrigation Sector in Maharashtra State are distributed as per the formula prescribed by Hon’ble Governor of Maharashtra issued in the form of Directives. As per the directives the distribution of normal funds amongst the development boards is as below % of Distribution of funds

Total Funds required as per fomula (Rs. in crore)

Rest of Maharashtra

51.81

11009

Marathwada

22.54

4790

Vidarbha

25.65

5451

Total

100.00

21250

Development Board

¾ Additional projects from Vidarbha and Marathwada to keep the proposal in consonance with the Hon’ble Governor’s directives. The estimated cost of these projects is Rs.5353 Cr. and Rs.1589 Cr. respectivly. The total cost of all the project is 14208 + 5453 122 + 1589 = Rs.21250 Cr. 122

123 / NN 123

Minority Development y Scholarship - Rs25,000 to 72,900 students y Second shift in 42 ITI and 2 new it is – covering 7099 students y Second shift in 12 Polytechnics – covering 2316 students y Assistance to average 179 local bodies for infrastructure development y 20 girls hostel construction started y Around 1800 schools given infrastructure development Grants y 636 Anganwadis and 1500 Indira Awaj Houses taken up under GOI MSDP y Share Capital of Maulana Azad Minorities Financial Development Corp

i\enhanced from Rs 50 Cr to Rs .250 Cr and Rs. 139.78 Cr released under the Plan period. y Police pre-recruitment Training and UPSC exam training programmes y Haj House constructed at Nagpur and sanctioned for Auranagbad y Scheme for setting up 2600 Self Help Groups of Minority women with SHG

federation structure sanctioned in 11 towns.

124

Minority Development y Proposals under the XII FYP y Infrastructure development grant of Rs 10 lac for minority

concentrated villages approved – 440 villages in 2013-14 y Scope and ambit of skilled dev to be expanded to 3 lac

beneficiaries y Training for UPSC, MPSC, Banking, profession studies –

CET to be expanded. y Madrassa Modernisation programme proposed y Financial limit of grants to municipal corporations for

infrastructure development to be enhanced substantially. 125

Law and Judiciary y Cases instituted and disposed (Cases in lakhs) 30

Institution 26.2

Disposal

25 23.1

20

20.1

20.4

20.5

20.0

18.5 17.5

15

10

5

0 2009

2010

2011

2012

126

Substantial reduction in pendency 45

41.35 40

(Figures in lakhs)

39.04 32.76

35

29.77

30

25

20

15

10

5

0

30.06.2010

31.12.2010

31.12.2011

31.12.2012

127

Reduced pendency of 5/10 year old cases in last 2 years. 10 8.73

9

(Figures in lakhs) 10 Years old

8

Between 5 to 10 years old 7 6 5

4.67

4.43

4 2.84

3 2 1 0 30.06.2010

12 8 / N N

31.12.2012

Cases under Section 138 of N.I. Act, 1881 (1 July 2010 to 31 December 2012) (Figures in Lacs)

Courts

Pendency on Institution Disposal 1 July 2010

Pendency on 31 December 2012

Courts of Metropolitan Magistrate, Mumbai

3.27

2.26

4.46

1.08

Other Courts in the State

3.77

2.59

4.04

2.32

7.04

4.85

8.50

3.40

Total

129

Lok Adalats held & matters disposed of during last 3 years

Years

Lok Adalats held (All Categories)

Total Setteled Cases

No. of Beneficiaries

Jan. 2010 – Dec. 2010

3,470

1,19,958

2,45,174

3,454

4,57,425

8,34,414

2,887

5,97,123

10,11,565

9,811

11,74,506

20,91,153

Jan. 2011 – Dec. 2011

Jan. 2012 – Dec. 2012

13 0 / N N

Total

Judge- Population Ratio

(as on 05.03.2013)

Case load per Judge

2027

28.27

1424

Number of Judges

Population

Judge Population Ratio per million

2027

11.24 Crores Or 112.4 million

18 : 1

Number of Judges Number of Cases

131

Court Buildings in the State

Total Buildings

In own premises

In rented premises

District Court s

34

32

2

Taluka Courts

339

256

83

Family Courts

10

6

4

383

294

89

Particulars

Total

132

Infrastructure Development in last 2 years Court Buildings completed

Situated in no. of Districts

Total Cost (In Crores)

49 (171 Court Halls)

22

164.46

Residential quarters completed

Situated in no. of Districts

Total Cost (In Crores)

33 (75 Res. Qtrs.)

16

14.15

133

Ongoing Projects No. of Court Buildings

Situated in no. of Districts

Total Cost (In Crores)

74

28

430.78

No. of Residential quarters

Situated in no. of Districts

Total Cost (In Crores)

68 (144 Res. Qtrs.)

26

35.24

(420 Court Halls)

134

Ongoing Projects of Court C omplex and Residential quarters (Expected period of completion)

Total Court Buildings

Till June 2013

Till December 2013

Till June 2014

74

30

30

14

Total Residential quarters

Till June 2013

Till December 2013

148

70

78

135

Proposals under consideration for administrative sanction No. of Court Buildings

Situated in no. of Districts

Estimated Cost

37

19

293.14

No. of Residential quarters

Situated in no. of Districts

Estimated Cost

76

25

95.62

Other works of Court Buildings & Residential qutrs.

Situated in no. of Districts

Estimated Cost

87

32

(In Crores)

(150 Court Halls)

(In Crores)

(337 Res. Qtrs)

(In Crores)

26.90 136

Utilization of Central & State Share No. of Court No. of Residential buildings Buildings constructed in the constructed in the State * State **

Central Share Utilized (Rs.in Lacs)

State Share Utilized (Rs.in Lacs)

Sr. No.

Financial Year

1

2007-08

66

40

1330.00

2670.00

2008-09

68

30

1517.00

4983.00

2009-10

64

15

1890.00

9677.00

4

2010-11

98

21

1458.52

10577.48

5

2011-12

105

42

5421.60***

12034.06

6

2012-13

114

97

9862.85****

11516.04

2 3

* It covers the court buildings of which work completed as well as the work in progress. ** It covers the residential quarters of which work completed as well as the work in progress. *** Actually received Rs. 129.15 lacs from Central Government in this financial year 2011-12. **** Actually received Rs. 5920.24 lacs from Central Government in this financial year 2012-13. 137

Allocation proposed by Central Government (vide its letter No. J-1107/6/2010-JR, Dtd. 04/01/2012)

Name of the States/UT

No. of court Compl exes

Maharashtra

Gujarat Karnataka Andhra Pradesh

Proposed allocation of funds year wise

Rs. In Crores

2011-12 2012-13

2013-14

2014-15

2015-16

Total estimated cost

375

131.89

131.89

131.89

131.89

131.89

659.43

280

596.12

470.42

222.54

30.00

0.00

1319.08

32

143.19

143.19

143.19

143.19

143.19

715.93

145

169.72

169.72

179.39

179.39

179.39

877.62

It is necessary that the Central Government should increase its share for the State of

Maharashtra and at least Rs.375 to 2006-17.

crore be allocated per year for next 5 years i.e. up 138

Social Justice y e-Scholarship y Being implemented since 2011 y Maintenance allowance credited to student’s account y Tuition and other fees credited to the accounts of the concerned colleges y Received e-Award for the years 2011-12 & 2012-13 from Computer Society of India

139

E-Scholarship Expenditure (Rs. Crore)

Beneficiaries (‘000)

Scheme

2010-11 2011-12 2012-13 2010-11

2011-12

2012-13

SC Scholarship

469

616

597

443

429

359

SC Free ship

71

152

77

32

60

29

VJNT Scholarship

283

239

265

233

202

198

OBC Scholarship

341

415

543

365

607

534

SBC Scholarship

106

76

80

89

69

41

VJNT Freeship

100

62

75

44

25

25

OBC Freeship

210

159

195

87

79

95

140

Social Justice (Rs. Crore) Year 2009-10 2010-11 2011-12 2012-13 Since Inception Upto March 2013

Central Beneficieries Balance Central Total Expdt. Assistance Assistance ('000) Received 786 274.9 25.9 244.7 686 0 56.8 0 878 137.7 61.2 72.1 773 354 90.7 191.5

5182

1721.2

282.2

1387.1

141

Social Justice y

Balance Central Assistance for OBC Scholarship from Government of India

y

The scheme was introduced for OBC students from the year 2001-2002.

y

The Income limit for scholarship is Rs. 1 lakh.

y

The Outstanding Central Assistance up to 2012-2013 is Rs.1387 crore (excluding State liability).

142

RAMAI AWAS YOJANA (GHARKUL) y

State level scheme for the BPL & APL Families of Schedule caste and Navbuddhas.

y

The construction cost for one House is – In Rural Area – 0.70 Lakhs In Municipal Council Area – 1.50 Lakhs In Municipal Corporation Area – 2.00 Lakhs

143 / NN

Social Justice y Ramai Awas Yojana (Gharkul) Target

Completed Houses

In progress Houses

Year Rural

Urban

Rural

Urban

Rural

Urban

2010-11

68.5

25.0

7.3

0.4

-

-

2011-12

121.6

64.3

73.2

9.3

-

-

2012-13

57.6

28.4

36.3

2.0

46.4

23.0

Total

247.7

117.7

116.8

11.7

46.4

23.0

144 / NN

Government Residential Schools for SC Boys and Girls

y Policy decision to open residential schools in each taluka y 100 residential schools were sanctioned in the first phase y 66 Residential schools started functioning from 2011-12.

145

Government Hostels for SC Boys and Girls

y The State Government is running 381 hostels for Boys and Girls y Intake capacity of these hostels per year is 33000 y Lodging and Boarding, Clothes, beddings, books etc., are provided y Maintenance allowance per student per month is of Rs.500 to Rs.800

146

Requests from Agriculture Sector y y y y y y y

Increased provision for micro-irrigation under NMMI. VIIDP to be included under NMSA and excluded from RKVY. Sikka Committee recommendations on drought proofing to be accepted. RKVY provision to be increased as MMA is discontinued. An outlay for promotion of FIG/CIG. A platform for PPP with convergence of GOI schemes be created. Agricultural marketing to be included for VGF by MoF

147 / NN

Micro-Irrigation in Maharashtra y y y y y y

50 lakh Ha under Micro-irrigation in the country. State’s share in area under micro-irrigation (15 lakh Ha) = 30% Support from GOI under NMMI for 1 lakh Ha / year. Current achievement by the State – 2.5 to 3 Lakh Ha / year. Special package requested to bring in 5 lakh Ha area per year. Support needed – Rs. 1500 Crore / year at least for remaining part of 12th Plan.

148 / NN

Environment

Delays in Environment Clearance due to • High Rise Office Memorandum • Action on violations • Moratorium in Ratnagiri and Sindhudurg • Kasturi Rangan Committee Report • Mines below 5 Hectares in Environment Clearance.

149 / NN

Achievements • Only State which has a RRZ River Regulatotion • Environment awareness- Environment Service Scheme in schoos - Call for Green Ideas – Environment protection with community participation. • Certificate Course in Waste Water Treatment Plant Operator • Environment Research sponsored in technical institutions • Environment Status Report in all districts – an inventory of natural resources • Environment Information Centers – in all districts 150 / NN

Expectations .

• • • • •

Environment ManagementNeed increased focus on Waste Water Treatment Larger outlay for Natural River Action Plan and National Lake Conservation Programme River Basin wise Action Plan need technical and financial support Environment Awareness – requires focus and funds Solid Waste Management

151 / NN

1

Power: Capacity Addition (MW) Total , 35363

20000

17500

Capacity (MW)

15000

29168

37000

32000

Thermal, 18836

26162

27000

24229

22000

12500

12446 10000

9665

17000

10366

7500

5376 5000

3408 2500

3066 2714

6307

5792

4609

4198

Central Sector Allocation, 6627

12000

Renewable 5164 7000

3066

3066

Hydro 3066

2740

2740

Natural Gas , 2740

2000

-3000

0

2010-11

2011-12

2012-13

2013-14

Financial Year 152 152 / NN

Transmission and Distribution Losses AT & C Loss 35.00

30.97

29.64 25.85

AT & C Loss

30.00

22.33

21.31

20.71

2010-11

2011-12

2012-13

25.00 20.00 15.00 10.00 5.00 0.00 2007-08

2008-09

2009-10

Financial Year

Collection FY 2010-11

FY 2011-12

FY 2012-13

Category

Demand (Rs.Crs.)

Collection (Rs.Crs.)

Residential

5976

5896

99

6650

6469

97

Commercial

4630

4637

100

4952

4917

Industrial

2221

2292

103

18484

AG

865

571

66

1297

% Collection Demand Efficiency (Rs.Crs.)

Collection (Rs.Crs.)

% Collection Demand Efficiency (Rs.Crs.)

Collection (Rs.Crs.)

% Collection Efficiency

8516

8249

97

99

6448

6247

97

18497

100

20931

21075

101

751

58

1865

410

22

153 153 / NN

Power Availability Energy Shortage in 2005 – 18% Energy Shortage in 2013 – 3% 24 x 7 Power to industry Agriculture - 8 hrs/10hrs Targeted Load shedding - Out of 7,754 feeders, 6,339 feeders are load shedding free. y 82% Maharashtra no load shedding. y Load shedding only on feeders where Distribution and Commercial loss is above 42%. y Average revenue up by around 10-20% in high loss areas. y y y y y

154 154 / NN

Targeted Load Shedding Total feeders - 7754 6600 6339

6400 6200 5922

Feeders

6000

5994

5932

5991

6111

5800 5600 5400

5496 5502 5515 5444 5401

5200 5000 4800 Month 155 155 / NN

Electricity Tariffs (2012-13) y

Average Power Purchase Cost - 3.39 Rs./unit

y

Cost of Supply

- 5.56 Rs./Unit DETAILS OF SUBSIDIZING CONSUMERS

Sr. No.

Category

1 2 3 4

Industrial (LT and HT) Commercial (LT and HT) Others * Total

No. of Consumer 2012-13 347,262 1,265,407 2,567,279 1,868,948

Amount Rs.Crs 2012-13 6,363 1,933 1,210 9,506

*Others include HT-Railway, LT Advertising, LT-Temporary and Standby charges DETAILS OF SUBSIDIZED CONSUMERS

Sr. No. 1 2 3 4

Category Domestic (LT) Agriculture (LT and HT) Others $ Total

No. of Consumer 2012-13 16,474,882 3,459,790 194,983 20,129,655

Amount Rs.Crs 2012-13 1,008 6,935 1,563 9,506

$ Others include HT-PWW, HT-Bulk Supply, LT-Street Light, LT-PWW, Mula Pravara and Bhivandi Franchisee

• •

Ag. Tariff raised from average of 50 paise per unit to Rs. 1 per unit in 2012-13 Ag. Consumers horse power (HP )on record increased by 34,39,790 HP (23%)over 156 156 / NN Three years

R-APDRP Part-A : y 130 Towns at estimated cost of Rs. 324 Crs y 61 Towns completed and energy audit done. y Current Network Digitized Part-B : y 120 Towns at estimated cost of Rs. 2,927 Crs. y Work Started, 20% completed. Aim : y Reduce loss y Improve Reliability y Release Connections

157 157 / NN

Infrastructure Infra-I y Total cost Rs. 9,014 Crs.

y 596 Substations added y 67,418 Distribution transformer added • Distribution Transformer Failure rate reduced from 16.14% in FY 2005-06

to 5.68% in FY 2012-13. Infra-II y Total Cost Rs. 6,500 Crs., To be completed in 3 years. y Connections to release in 3 years

y Total – 31.60 Lakhs y Agriculture – 4.80 Lakhs y Residential – 24.63 Lakhs y Commercial – 1.80 Lakhs y Industrial - 0.36 Lakhs

158 158 / NN

Consumer Focus 1. 2. 3. 4. 5. 6. 7.

Centralized Call Center Online connection release system Web based payment facility Automatic Teller Payment (ATP) Machines (101 nos. installed in FY 2012-13) Real Time Gross Settlement (RTGS) IR/RF Meters (Around 22% rise in revenue) Automatic Meter Reading (AMR) 1. 2.

8.

HT Consumers – 15,833 Meters LT Consumers – 4,102 Meters

Consumer Facilitation Center

159 159 / NN

Primary Fuel Issues yLinkage materialization overall only 71.61%, MCL is 44.5 % yImplementation Problems at Machakatta Odisha, Tapering linkage for 2 x

500 Chandrapur 3 x 660 Koradi, 1 x 250 Parali, needed. yImprove rail corridor to move Orissa Coal, availability. yDabhol 1967MW (7.6 MMSCMD, KG Basin & 0.9 MMSCMD, ONGC) not

available. yUran gas plant of 672 MW running at 400 MW. Average gas supply is 1.9 to

2.3 instead of 3.5 MMSCMD.

160 160 / NN

Highlights •Out of 100600 habitations, 89300 habitations have full coverage of drinking water supply as on 31.3.2013 •98% of the 40900 pipe water schemes are operated and maintained by PRIs •State has decided to link all habitations and drinking water sources with Census Code •State has 129 laboratories for testing of water sources and this will be enhanced to 169 in next couple of months. With this infrastructure, it will be possible to test all sources thrice a year •State has set up an autonomous body “ MEETRA” as centre for excellance for water supply and sanitation.

161 / NN

Demands y

To tackle recurrent problem of drought strengthening of water sources is important. For this purpose it is proposed to increase outlay for sustainability under National Rural Drinking Water Programme from 10% to 15%.

y

To rationalise water usage it is proposed to include metering as part of project cost under National Rural Drinking Water Programme with 100% grant from Government of India.

y

For better utilisation of assets created it is proposed to increase outlay for Operation and Maintainance from 15% to 20% under National Rural Drinking Water Programme.

y

100% saturation approach for Individual Household Latrines under “ Nirmal Bharat Abhiyan” has adversely affected the programme. It is proposed to allow Individual Household Latrines programme to be taken in all GPs.

162 / NN

Expectations from GoI y Norms for release of next ACA installments be relaxed from y y y

y

present 70 % expenditure of last installment to 50 % Cost Norms of Dwelling Units for in-progress IHSDP projects to be revised to Rs. 1.50 Lakhs. Special Criteria for Environmental Clearances of Slum Redevelopment Projects Un-utilised ACA with State Government be allowed to be reappropriated for construction of EWS/LIG Housing by State Housing Authority. Extension of Mission Period for IHSDP and BSUP projects up to 31st March 2015 on the backdrop of Severe Drought

163 / NN

High Early Primary Drop out Rate at Ahmadnagar , Beed & Jalana

164 / NN

DISE 2006-07

DISE 20011-12

Ahmadnagar - 2.9

Ahmadnagar - 0.3

Beed- 5.7

Beed- 4.9

Jalana- 6.3

Jalana- 3.3 Date: 164 / NN

Environment • Environment clearance required, if built-up area is more

than 20,000 sq. mt. • Problems of establishing industries in Western Ghats • Implementation of Dr. Kasturirangan Committee recommendations for industrial development of Western Ghats

165 / NN

National Highways in the State y

NH Length

y

Road length proposed for upgradation as NH

y

- 5616 km

Comparison of NH road length with other States :-

Name of the State

Area in sq.km.

- 6026 km* NH Length in kms

NH Length per 100 sq.km.area

94163

4,106

4.36

Uttar Pradesh

240928

7,818

3.24

Karnataka

191791

4,396

2.29

Gujarat

196024

4,032

2.06

Maharashtra

307713

5,616

1.83

Andhra Pradesh

275069

4,537

1.65

Madhya Pradesh

308144

5,064

1.64

Bihar

* • Request to notify proposed 6026 km as new NH in Maharashtra.

• National average of NH is 2.43 km per 100 sq.km. • Maharashtra state average will be 3.78 km per 100 sq.km. after declaration of proposed 6026 km as NH.

166 / NN

y Additional

167 / NN

Agenda y State Economy y State Public Finance y Annual Plan 2013-14 y Sectoral Issues y State’s expectations

168 / 52 168

State Economy y GSDP y GSDP & GDP : Growth Rates y Per Capita Income : Selected States

169 / 52 169

State Public Finance y Own Tax Revenue : Growth Rates y Taxation Measures y State’s Debt Stock

170 / 52 170

Taxation Measures y More efficient tax collection by automation of

Sales Tax Department y Establishment of cyber forensic laboratory to

detect tax evasion

Contd..

171 / 52 171

Annual Plan 2013-14 y Sectoral XII FYP and Annual Plans y Financing: XII FYP & Annual Plans

172 / 52 172

Sectoral Issues y Agriculture

y Textile

y ADF

y Housing

y Irrigation

y Health, Women &

y MGNREGA y Power y Roads / Rural Roads

Child Development y Water Supply &

Sanitation

y Railway, Ports & Airports y Education y Industries

y Urban Infrastructure

173 / 52 173