Polish NPP new build project Project Overview PGE and PGE EJ 1 February 2016
Polish NPP new build project Project Overview – February 2016
Disclaimer
This Presentation has been prepared by PGE S.A. (“ PGE”) and PGE EJ 1 Sp. z o.o. (“ PGE EJ 1”) (the “Company”) on the basis of information received from different sources, including not independently audited and publicly available information. The Company is not responsible for the accuracy, reliability and consistency of information contained in this Presentation (“ Presentation”). This Presentation includes results of preliminary analyses considered by PGE and PGE EJ 1. PGE and PGE EJ 1 reserve the right to introduce changes and modifications as well as to complement this information at any given stage and are not under obligation to explain reasons for these changes, modifications and complementation. The information included in this Presentation cannot form the basis for any claims or civil law suits against PGE, PGE EJ 1 or any other entity from within PGE Capital Group, in particular with regards to damages or indemnities to be paid in case of negligence in contracting. PGE and PGE EJ 1 wish to inform that all responsibilities and risks pertaining to and resulting from any decisions taken on the basis of or in relation to the information provided in the Presentation shall be borne by makers of these decisions. As a result, PGE and PGE EJ 1 on their own behalf and on behalf of all their directors, partners, employees and agents, declare that none of the entities listed herein will incur any liability towards any person in connection with any consequences of the decisions and/or actions taken in reliance on this Presentation and information provided. This Presentation reflects prevailing conditions, and PGE and PGE EJ 1’s understanding of the current situation, all of which are accordingly subject to change after this date upon obtaining new information or occurrence of new events.
For internal distribution only.
2
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
3
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
4
Polish NPP new build project Project Overview – February 2016
Business purpose of NPP new build project
NPP Project
Unchanged country imperatives driving nuclear power introduction to Poland – security of supply (aging generation fleet, EU climate change policies) – Electricity supply shortage (near blackout) in August 2015, State Grid Operator forced strong electricity supply reductions on large and industrial customers for the first time since 1989
Continued Polish government commitment to the implementation of the Polish Nuclear Power Programme
Nuclear power in future fuel mix according to the Polish Energy Policy until 2050 (each of three reference scenarios defined includes nuclear in the national energy fuel mix)
Increase of Poland’s industrial capabilities with a number of Polish companies having potential to join the nuclear supply chain
Diversification of Poland’s generation portfolio in order to lower CO2 emission (currently approx. 90% based on coal and lignite)
PGE as the leader continues NPP build project development activities with important milestones achieved
5
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing Stakeholder Management
6
Polish NPP new build project Project Overview – February 2016
PGE Polish Energy Group – Main Investor
•
2 open pit lignite mines (Bełchatów and Turów) Lignite output 50 million tons p.a.
•
Production net ca. 55 TWh
•
Installed capacity ca. 12.6 GW
•
Sales of heat ca. 18 million GJ
•
2 Lignite-fired power plants (Bełchatów and Turów)
•
2 Hard coal-fired power plants (Opole and Dolna Odra)
•
Combined heat and power plants – 8 sites (Szczecin, Pomorzany, Gorzów, Bydgoszcz, Zgierz, Kielce, Rzeszów and Lublin-Wrotków)
•
Hydroelectric power plants (Hydro ca. 97 MW, Pumped-storage ca. 1.5 GW), Wind farms 311 MW
•
Activity of PSE S.A.
•
Distribution of energy 32.54 TWh
•
Distribution grid: 281,290 km
•
Number of substations: 91,374
•
Final consumers 39.60 TWh
•
Wholesale market 62.44 TWh
•
Balancing market 1.10 TWh
•
Mining
Power generation
Transmission
Distribution
Nuclear potential locations
Wholesale & Supply
7
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
8
Preparation of the investment process and construction of Poland’s first nuclear power plant is divided into four key stages (in line with MAEA recommended approach)
MAEA (Phase 2)
MAEA (Phase 3)
Stage I
Stage II
Stage III
Pre-development
Development
Construction
Site selection – site investigation and environmental surveys – obtaining the decision on environmental conditions and site permit Development and execution of Integrated Proceedings (amongst others selection of technology) Business and financing model development (incl. support mechanisms) National and site infrastructure planning (incl. transmission system) Communication and Education (public support) Preparation and implementation of Integrated Management Systems Building nuclear and other specific competences (Capacity Building) Obtaining the Decision in Principle
Preparation of a detailed technical plan of a nuclear power plant (FEED) Prep. of a preliminary safety report Obtaining key decisions, permits and licences: – Licence issued by the PAA (Polish National Atomic Energy Agency) – Construction permit for NPP and environmental permit Signing a contract regarding the connection to the transmission grid Development of associated infrastructure for the NPP construction Communication (public support) Building of key competences and human resources development Financial close and Final Investment Decision
Decision in Principle Source: own materials
Stage IV Start-up and commissioning
Site preparation and initiation of the final stage of the process First concrete NPP construction process Delivery of long lead equipment System tests Development of national and site infrastructure for the NPP operations Connection to the transmission grid Simulator installation Further expertise development and building site operator structure Fuel Loading Permit
Final Investment Decision
Power tests Start-up Licence Integration of the NPP with the National Grid Operating licence Concession for power production Commercial operation (COD) Daily operations of the NPP Maintenance of the NPP Fuel management Waste management
Fuel Loading 9
Polish NPP new build project Project Overview – February 2016
National and site infrastructure planning and preparation
Stakeholder Management and Communication (local communities focus)
Integrated Proceedings
Feasibility Study
Support mechanisms and business model
Legislation and relations with European Commission
Decision in Principle
Implementation of Integrated Management Decision Systemin
Capacity Building
Site selection (EIA, Site Permit) based on site characterization
Organization of Polish Nuclear Program – 10 main projects
Principle
Source: own materials
10
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection
Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
11
Polish NPP new build project Project Overview – February 2016
Site selection
So far studies and analyses were conducted in three considered sites of a nuclear power plant: "Choczewo ", "Lubiatowo-Kopalino" (Choczewo) and "Żarnowiec" (Gniewino and Krokowa). Based on their results, in January 2016, two sites were selected for the full program of site characterization and the environmental impact assessment - "Lubiatowo-Kopalino" and "Żarnowiec".
Full environmental studies and site characterization works to be started in 2016 (seismic already ongoing, meteo equipment under installation) Preliminary national and site infrastructure plan developed in cooperation with local communities and Pomerania voivodeship First stage of transmission grid and transmission infrastructure analyses completed for candidate sites in cooperation with PSE – Polish National Grid 12
Polish NPP new build project Project Overview – February 2016
Site characterization and environmental assessment
Preparations are underway to launch full environmental assessment and site investigation by PGE EJ 1
The purpose of environmental assessment is to provide data necessary for a decision whether a given site is suitable for the construction of a nuclear power plant in terms of environmental protection.
Environmental assessment
Start – 2016 Duration – 12 months
The objective of site investigation is to confirm that a given site is suitable for a nuclear power plant in terms of nuclear safety.
Site investigation
Start –2016 Duration – 24 months
The Environmental Scoping Report (ESR) has been prepared and, on the 5th of August 2015, the first stage of the environmental impact assessment (EIA) procedure was launched. 13
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
14
Polish NPP new build project Project Overview – February 2016
Integrated Proceedings (IP) framework Under the Integrated Proceedings, potential bidders will be requested to include in their offers all of the following elements:
Plant Vendor
Provision of technologies for the NPP as well as the general implementation of the investment (EPC)
Proposed rules and conditions for the capital engagement by strategic investor/business partner Concept of how to finance the Investment, together with written confirmation of interest in supporting the project from relevant ECAs, financing institutions or commercial banks (at best offer(s) selection stage; these are construed as Letters of Intent and potentially also the preliminary proposed financing conditions)
Fuel supplier
O&M support provider
Equity investor / Strategic Partner
Integrated Proceedings Export Credit Agencies Commercial financing
Nuclear fuel supply and related services Provision of O&M support services for the NPP together with capacity building program for PGE EJ1
EPC Contractor
All elements of the IP scope are obtained in one procedure
The financing closure takes place after the above mentioned elements are obtained, but its initial terms and conditions are the subject of the IP scope
Integrated Proceedings are to be conducted as a competitive procedure based on the Contracting Authority’s Regulations, outside of the regime of the PPL
IP Participants Companies which have submitted declarations of participation and took part in preliminary dialogue between 2012 - 2015 15
Polish NPP new build project Project Overview – February 2016
Reactor Technology
Received declarations determine the potential reactor technologies for the first Polish NPP
EPR
ABWR
AREVA NP PWR 1650 MWe
GE-Hitachi BWR 1350 MWe
AP1000 Westinghouse / Toshiba PWR 1100 MWe
GE-Hitachi BWR 1535 MWe
APR1400
EC6
KEPCO PWR 1400 MWe
Candu Energy PHWR 700 MWe
ESBWR
16
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
17
Polish NPP new build project Project Overview – February 2016
Planning and development of site infrastructure
Define the scope of investments and the preliminary schedule for their preparation and implementation
Consultation and agreement with the municipalities and the Marshal Office of the Pomeranian Voivodeship
Finalization of the first stage of network analyses for specific sites and considered NPP reactor technologies in cooperation with PSE SA (Polish National Grid)
Development of the site development study, transport study, and permit plan
18
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
19
Polish NPP new build project Project Overview – February 2016
Business and Financing model development (incl. support mechanisms)
Business model, investment, support mechanisms, electricity market In April 2015, PGE and National Business Partners (KGHM Polska Miedź SA, Tauron Polska Energia SA and Enea SA ) signed a shareholding agreement giving each of the partners 10% share in PGE EJ 1
PGE EJ 1 shareholding structure (since April 2015)
Ongoing work on financing model for the investment. Involvement of Export Credit Agency considered. Need of support scheme to be established Necessary support system for the Project including Contract for Difference (CfD) and National Treasury guarantees 20
Polish NPP new build project Project Overview – February 2016
Agenda
Purpose of NPP new build project Main Investor NPP Project stages Site selection Integrated Proceedings Site infrastructure Business and financing models Stakeholder Management
21
Polish NPP new build project Project Overview – February 2016
Polish NPP new build project
STAKEHOLDER MANAGEMENT AND COMMUNICATION Activities on local level
Development of long-term cooperation program with the local communities 3 Local Information Centers – 1 in each of the 3 adjacent communities hosting 3 candidate sites Dedicated communication regarding site characterization activities – workshops, printed publications, public exhibitions Ongoing education for local schools – dedicated classes, trips to science centers Seasonal educational events on nuclear power during major local events Focused projects – study tours to European NPPs, conferences, seminars
Activities on national level Świadomieoatomie.pl – website presenting various information on nuclear power as well as news on the NPP project in Poland Atom dla Nauki (Atom for Science) – promoting nuclear-related knowledge among students and cooperation with universities (3rd edition) Pandora’s Promise – organization of the official premiere and several special screenings of the documentary by Robert Stone 22
Polish NPP new build project Project Overview – February 2016
Polish NPP new build project
HIGH LOCAL SUPPORT FOR NPP CONSTRUCTION IN THE NEIGHBORHOOD
KROKOWA
GNIEWINO
CHOCZEWO
% of supporters
Recent opinion polls (Autumn 2015) show strong support for the NPP in all three communities, with support levels ranging from 66% (Krokowa) up to 71-72% (Gniewino and Choczewo) Regular public opinion polls (every 6 months since 2011) to monitor local and national levels of support for the NPP. 23
Thank you