Performance Measurement of Mining Equipment Mousa Mohammadi1, Piyush Rai2, Suprakash Gupta3 1

Research Scholar, Department of Mining Engineering, Indian Institute of Technology (BHU), Varanasi, India & Faculty Member, Department of Mining Engineering, Sirjan Branch, Islamic Azad University, Sirjan, Iran. 2 Professor, 3Associate Professor, Department of Mining Engineering, Indian Institute of Technology (BHU), Varanasi, India In this light, various indicators such as cycle time, bucket-fill factor, material-swell factor, reliability, availability, maintainability, utilization, and production efficiency have been in vogue since long for evaluating the performance of BELT equipment. The present paper aims at reviewing the available pertinent literature in the subject field and deals with various aspects of performance measurement of BELT equipment in the mining industry. These indicators which are used for evaluating the performance of BELT equipment are described herewith. It is worthy to note that, the term of „BELT‟ has been introduced as acronym, in the present work, to cover the entire variety of equipment that have bucket, which is capable of excavating, loading, hauling and dumping or even for transporting the excavated material (as in trucks).

Abstract-- Achieving the high production and productivity target is one of the biggest challenges for mining companies, in order to remain competitive in the global market. As such, it entails proper performance measurement of huge and capital intensive equipment which are deployed in mining industries. The present paper aims at reviewing the available pertinent literature in the subject field and deals with various aspects of performance measurement of excavating, loading and transporting equipment in the mining industry. Keywords-- Availability, Dragline, Maintainability, Mining Equipment, Overall Equipment Effectiveness (OEE), Performance Measurement, Production Index, Reliability, Shovel, Utilization

I. INTRODUCTION Minerals are one of our basic needs as they are used in tools, machines and provide us power and energy. The ever increasing demand for minerals, owing to rapid industrialization and population explosion has forced the surface and underground mines to produce more of it. As such, a large number of Bucket based Excavating, Loading and Transporting (BELT) equipment such as dragline, shovel, dumper, Side- Discharge-Loader (SDL), LoadHaul-Dump (LHD) and Low-Profile-Dump-Truck (LPDT) are deployed to meet the demand. With deploying these huge and capital intensive equipment, improving their overall effectiveness and performance are absolutely important in order to achieve high production and productivity target. As such, it entails proper measurement of equipment efficiency.

II. AVAILABILITY AND UTILIZATION Availability and utilization are the key performance indicators of equipment and this is a usual tool for decision-making by management in the mine operation. Rate of production is highly sensitive to the equipments‟ availability and utilization [1,2,3,4]. Therefore, serious efforts should be made by the mining companies to achieve and maintain the level of higher availability and utilization for capital intensive equipment. By closely scrutinizing the pertinent literature, field visits and investigations in the case study mines, various events in the BELT equipment operation were identified, and classified which are used in definition of availability and utilization concept (see figure 1).

FIGURE 1: Breakup of total calendar time under different time head

240

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) Where, TT is total calendar time, PSDT is planned shutdown time or non-scheduled time for operation, POT is planned operating time or loading time, BDT is breakdown time, AT is available time, IT is idle time, S&A T is set-up and adjustment time and UT is utilization time. Various forms of availability are defined depending on its applicability and consideration of the time duration, such as operational availability and inherent availability.

Anvari et al. [15] consider routine maintenance activities (such as cleaning and lubrication) as Planned-Shut DownTime (PSDT), while CMPDI [11], considered them as preventive maintenance which comes under the Break Down Time (BDT). Shift changing, lunch break and non availability of operator are considered as idle time by Mirabediny [5], CMPDI [11] and Rai [16], while Zoltan [6], Anvari et al. [15] and Dal et al. [17] consider such activities as PSDT.

A. Operational Availability Operational availability is associated with the operation of an equipment or system. It can be represented by the total number of hours „within a period‟ that machinery is fit for work [5, 6, 7, 8, 9, 10]. However, there are a few inconsistencies in the definition and utility of the term „within a period‟, e.g. some researchers proposed calendar-time based approach which considers this period based on scheduled and nonscheduled time for operation [1,7,11]. Other researchers have propounded loading-time based approach which considers this period based on planned/scheduled operating time [12,13,14]. The main differences between the two approaches lie in the consideration of total accountable time for evaluating the operational availability. Mathematically, the difference between these two approaches can be understood by the equations 1 and 2.

B. Inherent Availability Inherent availability (Ai) is associated with the in-built characteristic of the equipment or its parts. It ignores the downtimes due to other sources which are not directly caused by the equipment design and are generally beyond the control of the designer. Hence, it is recommended to assess design characteristics during the design process that can be used as an important tool for framing preventive maintenance schedule, spare parts management and optimal replacement strategies [8,18,19,20]. Mathematically the Ai may be expressed as:

Where, Ai is inherent availability, MTTF is Mean Time To Failure, and MTTR is Mean Time To Repair. From the above definition, it is clear that the inherent availability is a function of reliability parameter (how often a unit fails) and maintainability parameter (how fast the unit can be restored after failure) [3,19,21, 22]. Hence, it can be expressed as:

Where, Ao is operational availability (calendar-time based),

Ai=f (MTTF, MTTR)

(4)

Ai = f (R,M)

(5)

or, Where, Ao' is operational availability (loading-time based), Loading-time based approach provides higher availability values than calendar-time based approach. Therefore, it is important to be very clear about the selection and application of one of these approaches before proceeding for evaluation of availability. Besides, while scrutinizing the review of literature, it is found that there are some inconsistencies in the definition and classification of events that affect the value of availability and ability to compare results. For instance, the term "maintenance" has been invariably used to depict routine maintenance, planned maintenance or even corrective maintenance. It is important to make an exact definition of each event.

Where, R is reliability characteristic of item or system measured in terms of MTTF, and M is maintainability characteristic of item or system measured in terms of MTTR. Reliability investigations are usually helpful in deciding the optimal maintenance intervals and the patterns of spare parts consumption. Therefore, one of the most effective ways of increasing equipment‟s inherent availability is to improve its reliability and maintainability, either by reducing the number of unplanned shutdowns, or by minimizing the length of scheduled turnarounds [19,23].

241

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) A lot of research related to Reliability, Availability and Maintainability (RAM) of mining equipment with the aim of improving inherent availability has already been reported. Tregelles and Worthington [24] pointed out the importance of reliability assessment of mining equipment throughout its life starting with specification and design, through manufacture and testing and finally during installation, commissioning and operation. Kumar [18] studied in detail, the Time To Failure (TTF) and Time To Repair (TTR) data for major subsystem for evaluating performance and effectiveness analysis of LoadHaul-Dump (LHD) machines. The data was collected from Kiruna mine, the largest and most modern underground iron ore mine in the world. Mean of TTF and TTR data was calculated for the best fit distribution, with the aim of analysis of inherent availability. Vagenas et al. [25] deployed graphical, analytical and statistical tools in RAM analysis to study the failure and repair characteristic of the system and its subsystems. They further used these tools for enhancing the availability of mine trucks. Nanda [26] estimated the availability of a drilling system using Markov model assuming failure and repair rates to be constant. Paraszczak [27] identified reliability and maintainability are the key constraints to improve the availability and hence productivity of LHDs. He proposed that MTTF can also serve for benchmarking of mining equipment performance. Hall et al. [28] stated that reliability and inherent availability are the design characteristic of an equipment and therefore much space is not available to improve them from users‟ viewpoint. As such, it should be taken care of during design and user should put reliability as a criterion in the selection and evaluation of surface mining equipment. Grujic et al. [29] pointed that operating environment has a significant role on the system‟s reliability and efficiency. Observing the dynamic nature of the operating environment and quality of repair, a genetic algorithm based reliability assessment has been proposed by Nuziale and Vagenas [30] for mining equipment. Hall and Daneshmand [31] used Pareto analysis to identify the principle subsystems of haul trucks, responsible for high maintenance and downtime cost. They performed a comparative study of the MTTF and MTTR of hydraulic and electrical shovels deployed in surface mines. Gupta et al. [32] discussed the methodologies to evaluate the effectiveness of the active maintenance polices to frame an importance measure based maintenance and replacement schedule for availability improvement of long-wall shearer.

Marquez [33] studied the critical failures of heavy duty earth moving machines to design maintenance policy. Barabady [2] analyzed TTF and TTR data for studying the reliability of crushing plant at Jajarm Bauxite mine. Elevli et al. [34] analyzed the maintainability of mechanical systems of electric cable shovel. On the basis of all these studies it may be appropriate to state that RAM approach has been effectively used for identifying the Ai of various equipment since last 40 years in mining industry. The idea has evolved over these years to improve the equipment performance by the proper investigation of reliability and maintainability aspects. C. Utilization Utilization signifies the productive use of available hours. A machine may be available but still may not be working during the available hours due to inordinate and idling conditions. Thus, utilization represents a loss in available hours [3,9,10,35]. Utilization of available hours can be expressed as the ratio of UT & AT. Mathematically, it can be expressed in equation 6.

It is also revealed by the review of literature [5,6,9,11,16,36] that there are some inconsistencies in the definition and classification of events that affect the value of utilization and ability to compare results. It is worthy to note that, the low utilization of excavating, loading and transport equipment operation in surface mines, is largely due to the problem in their control or management. This is particularly pronounced in large and deep open pits with large fleet of trucks and many dump points. Different methods of truck control and truck allocation have been classified as non-dispatching (lockedout or fixed-assignment mode) and dispatching mode by Pfleider [37] and Burton [38]. To optimize utilization of shovel and truck operation, dispatching system (manual, Semi-automatic and Automatic) is being effectively applied in mining industry [39,40, 41,42,43,44]. Trivedi et al. [45] in their study used the approach of queuing model to optimize the shovel truck operation. They critically analyzed the relation between the length of queues, waiting time in queue, utilization of shovel, approximate output from the shovel-truck combination and the cost involved in the system with respect to variation in the number of trucks. Rai et al. [46] evaluated Computerized Truck Dispatch System (CTDS) in order to improve utilization and performance of shovel-truck combination. 242

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) Benjamin et al. [47] conducted an investigation to improve the utilization time of trucks based on an operating mine in South-east Queensland using a commercially available GPS collision avoidance system. The approach was to use the GPS collision avoidance system to collect the truck positioning, speed, and timing data, which gets automatically recorded as part of its normal function in order to translate this information in a conventional time and motion study. Operation Research (O.R.) is another popular technique used widely in mining industry since 1960s in the areas of mine planning, design, production scheduling, equipment selection, and dispatching, etc. O.R. helps us in making a correct decision where a number of alternative solutions are available and is thus helpful in choosing the optimum policy. It is the application of mathematical methods for obtaining optimum and/or exact solution for the problems of economic, planning and management [48]. Burt and Caccetta [49] discussed the use of operational research to solve equipment selection problem in the context of surface mining. Fitspatrik [50] cited methods used by mining industry in the evaluation and selection of new haulage equipment and in increasing the utilization of existing fleet. White et al. [51] suggested an operational truck-dispatching system based on network models, linear programming, and dynamic programming. Dash [52] discussed a linear programming model for energy optimization. Brahma [53] studied application of operational research techniques in an open cast mining. Martinez and Newman [54] proposed a mixed-integer program to schedule long- and short-term production at LKAB‟s Kiruna mine, an underground sublevel caving mine. The proposed model minimizes deviations from monthly pre-planned production quantities while adhering to operational constraints.

Rai et al. [57] reported the cycle and idle time analysis for draglines operation in field. On the basis of image analysis, Osanloo and Hekmat [58] reported the influence of degree of fragmentation on the dig-ability of excavators. Influence of geometry and dimension of excavation face on the digging time of excavators operating in surface mines has been reported by Rai [16], Erdem and Pasamehmetoglu [59], Erdem and Baskan [60], Patnayak et al. [61], Erdem and korkmaz [62], Mohammadi et.al. [63]. Benjamin et al. [47] did investigation to optimize truckshovel fleet cycle using GPS collision avoidance system focused on the speed and timing data of a selected fleet of coal trucks at an open cast mine.

III. CYCLE TIME OF OPERATION

V. MATERIAL-SWELL FACTOR

It must be borne in mind that with the huge and capitalintensive BELT equipment, every second of its life time is very important from the production and productivity point of view. The BELT equipment performs tens of thousands of cycles daily. Therefore, a small improvement in its overall cycle time will definitely have a significant effect on its overall performance. In this line, Mirabediney [5] analyzed the cycle time data of dragline operation in open-cast coal mine in Australia. AbouRizk et al. [55] fitted Beta distribution to analyze the cycle time data for dozer and truck operation. Howard [56] suggested the use of automation and robots in deciding the bucket placement position during the digging operations for optimum filling and reduction of cycle time of operation.

Material once excavated becomes loose and its original volume increases. The material-swell factor is defined as the ratio of volume (m3) of equal weight of material before and after blasting/excavation as:

IV. BUCKET-FILL FACTOR Bucket-fill factor indicates how well the available room in the bucket is used. This is the percentage of the bucket capacity that is actually filled with material. Mathematically, it is expressed as:

The bucket-fill factor depends on bucket size & shape, dig-ability of material (dragging and filling the bucket), fragmentation (particle size, shape and distribution of material in the bucket), the angle of repose of the material on top of the bucket, operator skills, etc. [5,58,64]. Misra [65] stated that the Bucket-fill factor for dragline operation is 0.95-1.10 for easy digging conditions, 0.800.90 for medium digging conditions, 0.65-0.75 for medium-hard digging conditions and 0.40-0.65 for very hard digging conditions. Mirabediny [5] pointed out that bucket-fill factor may vary from 0.4-1.2 in practice

The swell factor may vary between 0.6-0.9, depending on the nature of material (stickiness, moisture content), fragmentation (shape, size and distribution of material), etc. [5,64].

243

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) Pundari [66] pointed that potential production per hour can be computed by equation 11 as:

VI. PRODUCTION INDEX Production index (PI) is another indicator in mining industry which serves to control day-to-day and shift-toshift operations. Rai [16] termed it, as Production Efficiency in respect of the studies performed by him on shovel-truck and dragline operations in surface mines. Production Index for any earthmoving equipment may be understood as the ratio between the actual production (output) and its potential production (rated output) of the equipment during the period of its operation [3,65]. However, PI does not indicate the reasons for low production. Mathematically, it can be expressed as:

Where, O' is rated output per hour (m3), d is depth of cut (m), a is factor of swing angle, and r is stripping ratio. Misra [67] proposed that output of shovel and dragline (m3) can be obtained from the equation 13.

Where, α is angle of swing factor, and D is depth of cut factor.

Misra [67] stated that production efficiency of any excavator has two components: machine operating efficiency and the job management efficiency. Operating efficiency of a machine depends on the condition of operation, environmental conditions, experience and ability of the operator, and the state of maintenance of the machine itself. But usually such machines operate in conjunction with other equipment. In such cases the output also depends on the job management efficiency that controls the extent of utilization of the machine in the system. Chironis [68] suggests that the efficiency of shovels should lie in the range of 85 to 90 percent. Misra [67] found that power shovels have a utilization of 31 to 77 percent with a production efficiency of 25-60 percent in Indian mines. Carter [69] pointed that the shovels in Lee Ranch mines, are operating at efficiencies of 80-85 percent. Rai [16] reported production efficiency of shovel in large surface mines, in the range of 58 and 66 percent. To compute potential production, CMPDI [11] proposed equation 10 for BELT equipment.

VII. PROBLEMS OF STATED INDICES AND SUGGESTED SOLUTION Although, many improvements have been reported by using these indices, but these concepts are capable of providing only a tunnel view to the scope of the problem by considering the equipment in isolation from the system and, as such, are unable to address the performance measurement in a holistic manner. In this light, the concept of Overall Equipment Effectiveness (OEE) seems to be contemporary and truly relevant to address the growing demands on production and productivity. In other words, the OEE concept can bring together all the aforesaid indices under the domain of a comprehensive index. Managers appreciate such an aggregated metric instead of many detailed indices [70]. VIII. BASIC CONCEPT OF OEE OEE is one of the most widely used performance indicator in production industries to assess how effectively the manufacturing operations utilize the facilities, time and material. It is a good indicator and compares the status of the performance with the designed capacity and the best practices in the industry. OEE analysis distinctly highlights the areas which need improvement, to optimize the manufacturing process. Nakajima [12] introduced the concept of OEE to measure the performance of machine/equipment in manufacturing industries which considers the various sources of production losses.

Where, O is potential production per period (m3), BC is bucket capacity (m3), f is bucket-fill factor, s is material-swell factor, TT is total calendar time (h), A is operational availability, U is utilization, CT is cycle time (s), and m is factor to be allowed for travelling, positioning, etc. (m=0.8 for dragline operation at Northern Coalfield Limited, India.) 244

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) This concept accounted „Six big losses‟ for computing availability, performance and quality rates which is illustrated in figure 2.

He expressed OEE as a function of availability, performance and quality rates as given in equation 14.

FIGURE 2: OEE components based on Nakajima’s concept [12].

From the figure 2, it is evident that the time component of any operating system suffers from three losses namely, downtime, speed and quality losses, which have been further divided on the basis of ascribing the reasons. Given this, „six big losses‟ are clearly described as: 1. Equipment failure losses refer to the breakdown of equipment. 2. Set-up and adjustment time losses, occur when the production of one item ends and the equipment needs to be adjusted to meet the requirements to produce another item. 3. Idling and minor stoppage losses occur when the production is interrupted by a temporary malfunction or when a machine is idle. 4. Reduced speed losses refer to the difference between the speed for which the equipment is designed (standard speed) and the actual operating speed. 5. Defect in process and rework are considered as losses in quality which are caused by the malfunction of production equipment. 6. Reduced yield occurs during the early stages of production as the machine takes time to stabilize after its start up. By closely scrutinizing in literature [7,14,15,17,71,72], it is clear that OEE has been used by various industries to provide meaningful solutions to real-time problems since 1988.

Emery [73] described the application of the Total Productive Management (TPM) technique, to improve OEE for a coal mining operation through loss analysis. Samanta and Banerjee [75] investigated the improvement in productivity of mining machinery through TPM and OEE. Based on Nakajima‟s concept, they proposed OEE as a function of availability (A), performance (P) and utilization (U) for mining equipment. They stated that Nakajima‟s concept have given equal weights to A, P and U for calculating OEE, whereas it is not applicable in mining industry. So they assume some weight for A, P and U as 0.3, 0.5 and 0.2 respectively, for computing the OEE of mining equipment as given in equation 15.

Dhillon [3] proposed that OEE is a function of availability, utilization and production index as equation 16. Elevli and Elevli [76] reported that, there was no study in literature regarding how to use OEE metric for mining equipment. They tried to identify causes of time losses for shovel and truck operations, and classified these losses into three categories i.e. availability, performance, and quality losses. X. CRITICAL EVALUATION OF THE LITRATURE AND RESEARCH ISSUES

IX. CONCEPT OF STATE OF ART „OEE‟ IN MINING INDUSTRY

Scrutiny of literature in performance evaluation of BELT equipment shows that all the indices (availability, utilization, cycle time, bucket-fill-factor, material-swellfactor, production index) have been in vogue since long in evaluation of equipment‟s performance in order to improve the same.

Unfortunately, the excavation and mining industry in general has lagged behind other industries in the adoption of OEE as a good performance measurement and only a few studies [3,73,74,75,76] have been reported. 245

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) [9]

Although, many improvements have been reported by using these indices, but traditional indices for measuring performance of BELT equipment are capable of providing a tunnel view to the scope of the problem by considering the equipment in isolation from the system. However, the concept of OEE holds promise in bringing together the aforesaid indices in a comprehensive index for its evaluation and further improvement. In other words, OEE is a simple and clear overall indicator, which managers appreciate such an aggregated metric instead of many detailed indices. Unfortunately, the excavation, construction and mining industry in general has lagged behind other industries in the adoption of OEE as a good performance measurement and only a few studies have been reported. Although, these studies are suggestive of improvement to the adoption of OEE‟s concept in performance evaluation of mining equipment, they do not address the need to standardize the concept of OEE and its applicability to the BELT equipment to indicate how well the equipment was run in a holistic manner. In other words, the true benefit of OEE concept and its application has not been fully realized in BELT equipment because of the absence of a standard methodology to estimate OEE for BELT equipment. Given the reasonably comprehensive (holistic) approach of the OEE and also keeping in mind its successful application in the manufacturing industry, the path forward is, to suitably translate the concept of OEE for BELT equipment by evolving appropriate methodologies and tools for the measurement of OEE in mining operations.

[10]

[11]

[12] [13]

[14]

[15]

[16]

[17]

[18]

[19]

REFERENCES [1]

[2] [3] [4] [5]

[6]

[7]

[8]

[20]

Rai P. “Performance assessment of draglines in open cast mines”, Indian journal of Engineering & Material Science, 11, 493-498, 2004. Barabady J., “Production Assurance, Concept, Implementation and Improvement”, Ph.D. diss., Lulea University of Technology, 2007. Dhillon B.S., “Mining Equipment Reliability, Maintainability, and Safety”, Springer-Verlag London Limited, London, 2008. Osanloo M., “Surface mining method”, (VOL.2), Amir Kabir University Press, Tehran, 2005. Mirabediny H., “A dragline simulation model for strip mine design and development”, Ph.D. diss., University of Wollongong, Australia, 1998. Zoltan W., “Standardization of Definitions for Benchmarking”, MTech. diss., Department of Mining and Petroleum Engineering, University of Alberta, 1999. Jeong K.Y. and Phillips D.T., “Operational efficiency and effectiveness measurement”, International Journal of Operations and Production Management, 21 (11), 1404-1416, 2001. Bhadury B. and Basu S.K., “Terotechnology; reliability engineering and maintenance management” Asian Books Private Limited, Delhi, 2003.

[21] [22] [23] [24]

[25]

[26] [27]

246

Rai P., Yadav U. and Kumar A., “Productivity analysis of draglines operating in horizontal tandem mode of operation in coal mine: A case study”, Journal of Geotech Geol Eng, 29, 493-504, 2011. Mohammadi M., Rai P., Oraee K., and Kumar M., “Analysis of availability and utilization of dragline for enhancement of productivity in surface mines-a case study”, Proceeding of 23rd World Mining Congress, Montreal, Paper 598, 2013. Central Mine Planning and Design (CMPDI), “Norms and methodology for the calculation of the productivity of excavators and dumpers”, Singrauli, India, 2000. Nakajima S., “Introduction to TPM: total productive maintenance”, Productivity Press, Cambridge, 1988. Jonsson P. and Lesshammar M., “Evaluation and improvement of manufacturing performance measurement system: the role of OEE”, International Journal of Operations & Production Management, 19 (1), 55–78, 1999. Wibowo H., “Analysis overall equipment effectiveness (OEE) in improving productivity in the machine processing creeper hammer mill crumb rubber”, International Journal of Engineering and Science, 3 (2), 52-60, 2012. Anvari F., Edwards R. and Starr A., “Methodology and theory evaluation of overall equipment effectiveness based on market”, Journal of Quality in Maintenance Engineering, 16 (3), 256-270, 2010. Rai P., “Dragline and shovel-dumper operations in opencast mines”, MTech. diss., Department of Mining Engineering, Banaras Hindu University, Varanasi, India, 1992. Dal B., Tugwell P., and Greatbanks R., “Overall equipment effectiveness as a measure of operational improvement: a practical analysis”, International Journal of Operations & Production Management, 20 (12), 1488–1502, 2000. Kumar U., “Availability studies of Load-Haul-Dump machines”, proceeding of 21st Application Operation Research and Computers in Mineral Industry, SME,AIME, Las Vegas, USA, 323-335, 1989. Sutton I.S., “Process Reliability and Risk Management”, Van Nostrand Reinhold, New York, 1992. Ebeling E.C., “An introduction to reliability and maintainability engineering”, McMraw Hill Education, Sixteen re-print 2013, New Delhi, India, 2000. Dhillon B.S. and Singh C., “Engineering Reliability”, John Wiley & Son, New York, 1981. Kumar U., “Reliability technique: A powerful tool for mine operators”, Mineral Resource Engineering, vol.1, 13-28, 1988. Kumar U., “Reliability analysis of Load-Haul-Dump machines”, Ph.D. diss., Lulea university of technology, Sweden, 1990. Tregelles P.G. and Worthington B., “Reliability assessment as an aid to the development of mining equipment”, The mining engineer, 142(250), 95-103, 1983. Vagenas N., Kumar U. and Ronnkvist E., “Analysis of truck maintenance characteristics in a Swedish open pit mine”, International Journal of Surface Mining, Reclamation and Environment, 8, 65-71, 1994. Nanda N.K., “The need of reliability analysis of drilling system”, The Indian Mining & Engineering Journal, 25-33, 1998. Paraszczak J., “Failure and downtime reporting -A key to improve mine equipment performance”, CIM Bulleting, 93(1044), 7377,2002.

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) [46] Rai P., Trivedi R., Nath R., “Computerized Truck Despatch”, Coal International, 97-100, 2000. [47] Benjamin D Knights B.D., Kizil M.S. and Seib W., “Truck-shovel fleet cycle optimization using GPS collision avoidance system”, Coal Operators‟ Conference, The University of Wollongong, 361370, 2012. [48] Pathak J.R., “Operations research applications to mining”, Journal of Mines, Metals & Fuels, 15(2), 7-11, 1967. [49] Burt C. and Caccetta L., “Equipment Selection for Surface Mining: A Review”, www.optimization-online.org, 2013. [50] Fitspatrik J.J., “Truck performance by computers”, C.I.M. Bull., 913, 1967. [51] White J.W., Arnold M.J. and Clevenger J.G., “Automated open pit truck dispatching at Tyrone”, Engg. Min. J., 183 (6), 76-84, 1982. [52] Dash A., “A linear programming model for energy optimization”, Report. Department of Mining Engineering, BHU, (Unpublished), 1990. [53] Brahma K.C., “A study on application of strategic planning models and operations research techniques in opencast mining”, Ph.D. diss., National Institute of Technology, Rourkela, 2007. [54] Martinez, M. and A. Newman, “A Solution Approach for Optimizing Long- and Short-term Production Scheduling at LKAB's Kiruna Mine” European Journal of Operational Research, 211(1): 184-197, 2011. [55] AbouRizk S. M., Halpin D.W. and Wilson J.R., “Fitting beta distributions based on sample data”, Journal of Construction Engineering and management, 120(2), 268-304, 1994. [56] Howard N.C., “Extended Earthmoving with an Autonomous Excavator”, MSc.diss. The Robotics Institute Carnegie Mellon University, Pittsburgh, 1999. [57] Rai P., Trivedi R. and Nath R. “Cycle time and idle time analysis of draglines for increased productivity- a case study”, Indian Journal of Engineering & Material Sciences, 7 (6), 77, 2000. [58] Osanloo, M., and Hekmat, A., Prediction of shovel productivity in the Gol-e-Gohar iron mine, Journal of Mining science, 41 (2), 177184, 2005. [59] Erdem B. and Paşamehmetoğlu A.G., “Dragline cycle time Analysis - case study”, International Mining Congress and Exhibition of Turkey-IMCET, Turkey, 2003. [60] Erdem B. and Baskan D.H.F., “Dragline cycle time Analysis”, Journal of scientific and Industrial Research, 64, 19-29, 2005. [61] Patnayak S., Tannant D., Parsons I., Del Valle V. and Wong J., “Operator and dipper tooth influence on electric shovel performance during oil sands mining”, International Journal of Mining, Reclamation and Environment, 22 (2), 120-145, 2008. [62] Erdem B. and korkmaz F., “Analysis of Dragline cycle time components”, Journal of Mining Science, 48, 545-558, 2012. [63] Mohammadi M., Rai, P., and Oraee K., “A Critical Investigation of Digging Time Segment of Draglines in a Large Surface Mine” Journal of Geotechnical and Geological Engineering”, 33, 763-771, 2015. [64] Doktan M., “Impact of Blast Fragmentation on Truck Shovel Fleet Performance”, 17th International Mining Congress and Exhibition of Turkey, 375-380, 2001. [65] Misra G.B., “Surface Mining”, Dhanbad publishers, Dhanbad, India, 1979. [66] Pundari N.B., “Selecting and using large walking draglines for deeper overburden stripping”, Mining Engineering, AIMMPE, 1981.

[28] Hall R.A., Daneshmend L.K., Lipsett M.G. and Wong J., “Reliability analysis as a tool for surface mining equipment evaluation and selection”, CIM Bulletin, 93(1044), 78 – 82, 2000. [29] Grujic M. Milos, Grujic M. Miodrag and Ivkovic D.M, “The impact of multi-element external Coal transportation on reliability of the system and on environment”, Mine Planning and Equipment Selection, Panagiotou & Michalakopoulos, Balkema, Rotterdam, 569 – 572, 2000. [30] Nuziale T. and Vagenas N., “Reliability assessment of mining equipment using genetic algorithms”, Mine Planning and Equipment Selection, Panagiotou & Michalakopoulos, Balkema, Rotterdam, 841 – 846, 2000. [31] Hall R.A. and Daneshmend L.K., “Evaluation of reliability and availability of surface mining equipment”, Journal of Mines, Metals & Fuels, 395-399, 2002. [32] Gupta S., Ramkrishna N. and Bhattacharya J., “Replacement and maintenance analysis of a Longwall Shearer using Fault Tree Technique”, Mining Technology, 2(115), 49-58, 2005. [33] Marquez C.A., “Applications and case studies modeling critical failures maintenance- A case study for mining”, Journal of Quality in Maintenance Engineering, 11( 4), 301-317, 2006. [34] Elevli S., Uzgoren N. and Taksuk M., “Maintainability analysis of mechanical systems of electric cable shovels”, Journal of Scientific and Industrial Research, 67, 267-271, 2008. [35] Vamshi K. K., “Standardizing Availability Definition”, M.Tech. diss. University Of New Orleans, USA, 2000. [36] Rai P. “A Critical Case Study on Draglines Operating in Vertical Tandem in a Coal Mine”, Journal of the institution of engineers (India), 87, 3-9, 2007. [37] Pfleider E.P., “Surface mining”, Mining Engineering, the American Institute of Mining Metallurgy and Petroleum Engineering (AIMMPE), New York, 1968. [38] Burton A.K., “Off-Highway Trucks: How to Calculate Truck Fleet Requirements”, Mining Engineering, the American Institute of Mining, Metallurgical, and Petroleum Engineers (AIMMPE), New York, 1975. [39] Lizotte Y., Bona Tes E. and Leclerc A., “Design and Implementation of a Semi-automated Truck/Shovel Dispatching System”, Proceedings of the Twentieth International Symposium on the Application of Computers and Mathematics in the Mineral Industries. Volume I: Mining. Johannesburg, SAIMM, pp. 377 - 387, 1987. [40] Victor A.T., “A computerize Model For Truck Dispatching In Open Pit Mines”, PhD diss., Michigan Technological University, 1997. [41] Alarie S. and Gamache M., “Overview of solution strategies used in truck dispatching systems for open pit mines”, Int. J. Surface Mining. 16, 59-76, 2002. [42] Xing J., Sun X.Y., “The open-pit truck dispatching method based on the completion of production target and the truck flow saturation”, J. China Coal Society. 977-980, 2007. [43] Blouin S., Guay M. and Rudie K., “An application of discrete-event theory to truck dispatching”, CEJOR, 15:369–391, 2007. [44] Kaveh Ahangaran D., Yasrebi A.B., Wetherelt A. and Foster P., “Real time dispatching modeling for trucks with different capacities in open pit mines”, Arch. Min. Sci., 57 (1), 39–52, 2012. [45] Trived, R., Rai, P. Nath, R., “ Shovel- truck optimization study in an open cast mine- A queuing approach” , Indian Journal of Engineering and Material Science, 6, 153-157, 1999.

247

International Journal of Emerging Technology and Advanced Engineering Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015) [67] Misra G.B., “Surface Mining”, Geominetech Publisher, Bhubaneswar, India, 2006. [68] Chironis N.P., “Smaller versatile dragline reach deep seems efficiency”, Coal Age, 91(12), 1986. [69] Carter R.A., “Lee Ranch turns to dragline for increase production”, Coal Age, 96 (6), 1991. [70] De Ron A.J. and Rooda J.E., “OEE and equipment effectiveness: an evaluation”, International Journal of Production Research, 44 (23), 4987–5003, 2006. [71] Zandieh S., Nilipuor Tabatabaei S.A. and Ghandehary M., “Evaluation of overall equipment effectiveness in a continuous process production system of condensate stabilization plant in Assalooyeh”, Interdisciplinary Journal of Contemporary Research in Business, 3 (10), 590-598, 2012.

[72] Tsarouhas P.H., “Evaluation of overall equipment effectiveness in the beverage industry: a case study”, International Journal of Production Research, 51 (2), 515-523, 2013. [73] Emery J.C., “Improving coal mining production performance through the application of Total Production Management”, Coal Operators' Conference, University of Wollongong, 71-80, 1998. [74] 73. Samanta B., Sarkar B., “TPM and Assessment of Overall Effectiveness for Mining Equipment”, Coal Mining Technology and Management, 8(2), 10-21, 2003. [75] 74. Samanta B., Banerjee J., “Improving Productivity of Mining machinery through Total Productive Management”, theammj.com/262pdf/tpmforproductivity.pd, 2004. [76] Elevli S. and Elevli B., “Performance Measurement of Mining Equipments by Utilizing OEE”, Acta Montanistica Slovaca Ročník, 15 (2), 95-101, 2010.

248