02Oview.ppt (1)
Performance Management in the Construction Industry
Ralph Kay Bechtel Savannah River
Management Influence on Project Cost and Schedule High 02Oview.ppt (2)
Conceptual Plan Engineering
Management Ability to Influence Cost/ Schedule
Procurement Construction/Installation Startup
Low
Start
Project Life
Complete
Management Influence on Project Cost and Schedule High 02Oview.ppt (3)
Conceptual Plan
Possibility for cost overruns & schedule delays
Engineering
Management Ability to Influence Cost/ Schedule
Procurement Construction/Installation Startup
Low
Start
Project Life
Complete
Objectives n
Address critical project control tools and their use on construction projects
02Oview.ppt (4)
—
Estimating
—
Planning & Scheduling
—
Performance Analysis
—
Progress Reporting
—
Baseline Control / Trending
—
Forecasting
The Control Cycle ESTIMATE 02Oview.ppt (5)
Project Plan Corrective Action
Contractor Project Control Customer
Identifying & Reporting Deviations
Monitoring the Plan
Project Controls Process
Scope and Organization
Planning
Monitoring
Analysis
n Scope of Work
n Estimates
n Physical Progress
n Critical Items
n Accomplishments
n Design
n
n Expenditures
n Planned
n Actions
and Other
Criteria n Work
Breakdown Structure
Project Schedules
n Time Phased
Budgets
and Commitments and Schedule Trends
n Cost
n Organizational
Breakdown Structure n Code
of Accounts
vs. Actual Performance & Productivity
Reporting and Milestones Achieved for Critical
Items n Cost
n Schedule Updates
and Schedule Performance
n Forecasts n Risk
Analysis
n Project Changes
n Plan n Funding and Cash
Flows
Forward
Construction Controls System Finance & Accounting
02Oview.ppt (7)
Estimate
Scope
Planning
Schedule
Working Schedules
Cost Processor
Progress & Performance
Quantity Tracking
Change Mngt. & Forecasting
Execution
Monitoring
Analysis
Reporting
Types of Estimates
02Oview.ppt (8)
n
Conceptual (Order of Magnitude)
n
Preliminary
n
Definitive
n
Others: —
Alternatives/”What-if’s”
—
Field estimates (change orders & trends)
Estimate Type Comparison Order of Magnitude 02Oview.ppt (9)
+/- 30% accuracy Engr 0% - 10% Plant cost/ capacity Ratio method Similar work
Preliminary +/- 25% accuracy Engr >10% cpt Site specific Major equip known Bulks factored
Definitive +/- 10 to 25% accuracy Engr >40% cpt Major equip qty Qty takeoffs Site specific labor Detailed Constr. Plan
Definitive Estimate Methodology
02Oview.ppt (10)
n
Major equipment pricing based on committed cost or firm quotations
n
Materials and Subcontracts based on detail quantity take-offs; firm unit cost or fixed price quotes or current billing costs
n
Labor estimated from man-hour unit rates per quantity incorporating crew and craft mix
n
Construction indirects detailed by major account and non-manual staffing plan
n
Home office support costs based on man-hour by department or function
Definitive Estimate General Requirements
02Oview.ppt (11)
n
Complete Process Design
n
Mechanical Equipment List and Data Sheets
n
P & ID’s
n
Critical Instrument Schedule and Data Sheets
n
Electrical Single Lines
n
Project Execution Plan
n
Project Intermediate Schedule
Quantification
02Oview.ppt (12)
n
Driver of an Estimate
n
Means of Developing Quantities — — — — — —
n
actual takeoffs estimates from P&IDs, single lines, etc. estimates to go allowances reference projects
Basis of Quantities Reflect the Estimate Level of Confidence
Materials and Subcontracts - Pricing
02Oview.ppt (13)
n
Bid Evaluation
n
Phone Quotes
n
Previous Projects
n
Industry Sources
Manual Labor
n
Unit Rates
02Oview.ppt (14)
—
n
Productivity Factors —
n
Based on corporate and / or industry standards
Developed by construction/estimating and using reference projects or regional standards
Wage Rates —
Buildup of wage (payroll costs plus fringes, additives by craft)
—
Craft mix (mix of craft workers per work operation)
Estimating Resources
02Oview.ppt (15)
n
Historical
n
Reference Standards
n
Reference Project/Plant
n
Industry Data —
Means
—
Richardson’s
n
Budgetary Quotes
n
Trade Journals
n
Who are the Guru’s???
Planning & Scheduling n
A Plan is a logical sequence of events
02Oview.ppt (16)
—
Identifies the Project GOALS
—
Encompasses the Scope of Work
—
Defines the Project Execution Plan
—
Identifies the required resources
Planning & Scheduling n
A Schedule incorporates durations and dates into the sequence of events necessary to accomplish the Plan
02Oview.ppt (17)
—
Used to establish project baseline
—
Prime tool to communicate project status
—
Serves as the basis for resources
—
Used to monitor and analyze progress
—
Must have proper level of detail
Types of Schedules n
Bar Chart / Graph - Only provides a pictorial representation of the project
02Oview.ppt (18)
—
n
Used for simple projects or for presentation purposes on complex projects
Critical Path Method (CPM) - Provides a true picture of the schedule for the project. It provides the critical path and allows various analyses to be done. The schedule is logically driven.
CPM Scheduling n Critical
02Oview.ppt (19)
Path Method - the calculation of the earliest and latest start and finish dates of activities based on their durations and relationships to other activities
n Critical
Path - one or more continuous chains of zero or negative float activities running from the start event to the finish event in the schedule. Normally the longest path in the schedule
n Critical
path
Activity - any activity on the critical
CPM Calculation
02Oview.ppt (20)
n
The determination of the earliest start and finish dates, and the latest start and finish dates of every activity in the network
n
Early dates indicate the earliest start and finish dates when an activity can be performed if all preceding activities have been completed
n
Late start and finish dates are the latest dates an activity can be performed without delaying the project
n
A computer is best suited to handle the numerous calculations of a forward pass and backward pass
Resource Scheduling n
People, equipment, costs, space, bulks...
02Oview.ppt (21)
n n
It defines which resources should be utilized on specific tasks - between which dates Good resource scheduling is the basis for maximizing the productivity of people and equipment while minimizing their cost
Why use Resource Scheduling? n
Optimizes resource use
02Oview.ppt (22)
—
Analyze staffing requirements
—
Evaluate effects of limited staffing
—
Avoid wide fluctuations in daily need for various resources
n
Analytically manage and use schedule float
n
Produce more realistic schedules
n
Produce progress & performance curves
n
Comply with client requirements
Common Scheduling Failures
02Oview.ppt (23)
n
Lack of buy-in by all project team members
n
Lack of PLANNING
n
Poorly defined activities
n
Inappropriate scheduling detail
n
Inadequate logic ties
n
Poor estimating of durations
n
Failure to effectively manage float
n
Failure to disseminate the proper information to all parties
Primavera Schedule ACTIVITY ACTIVITY DESCRIPTION DESCRIPTION
ACTIVITY ACTIVITY IDID
ORIG ORIG DUR DUR
-2-2
-1-1
11
22
33
44
55
66
77
88
99
MONTHS MONTHS 1111 1212
1010
1313
1414
1515
1616
1717
1818
1919
20 20
2121
22 22
23 23
24 24
PF PF -- FIRE FIRE PROTECTION PROTECTION EG EG -- ENGINEERING ENGINEERING ZEPFEG-100 ZEPFEG-100
PF: PF:FIRE FIREPROTECTION PROTECTIONENGINEERING ENGINEERINGSUMMARY SUMMARY
PF: PF:FIRE FIREPROTECTION PROTECTIONENGINEERING ENGINEERINGSUMMARY SUMMARY
198 198 EM EM--ENG. ENG.MECHANICAL MECHANICAL
02Oview.ppt (24)
ZEPFEM-500 ZEPFEM-500
PF-01: PF-01:FIRE FIREHYDRANTS HYDRANTS&&PIV'S PIV'S--PREP PREPSPEC SPEC
20 20
ZEPFEM-100 ZEPFEM-100
PF: PF:DESIGN DESIGN&&ISSUE ISSUEP&ID P&IDREV REV00
20 20
ZEPFEP-100 ZEPFEP-100
PF: PF:LB LBPIPE PIPEDESIGN DESIGN
20 20
ZEPFEP-500 ZEPFEP-500
SC-G02: SC-G02:U/G U/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--PREP PREPSS
20 20
ZEPFEM-110 ZEPFEM-110
PF: PF:LB LBHANGER HANGERDESIGN DESIGN
20 20
PF-01: PF-01:FIRE FIREHYDRANTS HYDRANTS&&PIV'S PIV'S--PREP PREPSPEC SPEC PF: PF:DESIGN DESIGN&&ISSUE ISSUEP&ID P&IDREV REV00 EP EP--ENG. ENG.PLANT PLANTDESIGN DESIGN PF: PF:LB LBPIPE PIPEDESIGN DESIGN SC-G02: SC-G02:U/G U/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--PREP PREPSS PF: PF:LB LBHANGER HANGERDESIGN DESIGN EEEE -- ENG. ENG. ELECTRICAL ELECTRICAL
ZEPFEE-350 ZEPFEE-350
PF: PF:ROUTE ROUTECABLE CABLE(SETROUTE) (SETROUTE)
30 30
ZEPFEE-100 ZEPFEE-100
PF: PF:CABLE CABLEDESIGN DESIGN
20 20
ZEPFEE-450 ZEPFEE-450
PF: PF:TERMINATION TERMINATIONDESIGN DESIGN(SETROUTE) (SETROUTE)
1515
PF: PF:ROUTE ROUTECABLE CABLE(SETROUTE) (SETROUTE) PF: PF:CABLE CABLEDESIGN DESIGN PF: PF:TERMINATION TERMINATIONDESIGN DESIGN(SETROUTE) (SETROUTE) MG MG -- MPAG MPAG
ZMPFMG-500 ZMPFMG-500
PF-01: PF-01: FIRE FIRE HYDRANTS HYDRANTS && PIV'S PIV'S -- BEA BEA
30 30
ZMPFMG-501 ZMPFMG-501
SC-G02: SC-G02:U/G U/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--BEA BEA
20 20
PF-01: PF-01: FIRE FIRE HYDRANTS HYDRANTS && PIV'S PIV'S -- BEA BEA MPAG MPAGLead LeadTime Time==1212wk wk
SC-G02: SC-G02:U/G U/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--BEA BEA MPAG MPAGLead LeadTime Time==1212wk wk
CN CN -- CONSTRUCTION CONSTRUCTION ZC7550-100 ZC7550-100
PF: PF:A/G A/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--INSTAL INSTAL
60 60
ZC0054-510 ZC0054-510
PF-01: PF-01:FIRE FIREHYDRANTS HYDRANTS&&PIV'S PIV'S--INSTALL INSTALL
60 60
ZC0054-500 ZC0054-500
SC-G02: SC-G02:U/G U/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--INSTAL INSTAL
60 60
PF: PF:A/G A/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--INSTAL INSTAL PF-01: PF-01:FIRE FIREHYDRANTS HYDRANTS&&PIV'S PIV'S--INSTALL INSTALL SC-G02: SC-G02:U/G U/GFIRE FIREPIPE PIPEPROTECTION PROTECTION--INSTAL INSTAL WD WD -- WALKDOWN WALKDOWN
ZCPFWD-100 ZCPFWD-100
PF: PF:FIRE FIREPROTECTION PROTECTION--WALKDOWN WALKDOWN&&PUNCHLIST PUNCHLIST
PF: PF:FIRE FIREPROTECTION PROTECTION--WALKDOWN WALKDOWN&&PUNCHLIST PUNCHLIST
1515 SU SU--STARTUP STARTUP
ZSPF95-100 ZSPF95-100
Plot PlotDate Date Data DataDate Date Project ProjectStart Start Project ProjectFinish Finish
(c)(c)Primavera PrimaveraSystems, Systems,Inc. Inc.
PF: PF:FIRE FIREPROTECTION PROTECTION--CHECKOUT CHECKOUT
20AUG96 20AUG96 1JAN00 1JAN00 1JAN00 1JAN00 6AUG01 6AUG01
Activity ActivityBar/Early Bar/EarlyDates Dates Critical CriticalActivity Activity Progress ProgressBar Bar Milestone/Flag Milestone/FlagActivity Activity
PF: PF:FIRE FIREPROTECTION PROTECTION--CHECKOUT CHECKOUT
1515
1240 1240
BECHTEL BECHTELPOWER POWER POWERLINE POWERLINE CC1240 CC1240(TEMPLATE) (TEMPLATE) PF PF--FIRE FIREPROTECTION PROTECTIONSYSTEM SYSTEMDETAILS DETAILS
Sheet Sheet
11
ofof
11
MILESTONES MILESTONES HAHA- -HAMMOCK HAMMOCK
Date Date
-----Project -----ProjectSchedule----Schedule----Revision Revision
Checked Checked
Approved Approved
Staffing and Jobhour Curve
140
175,000
120
150,000
100
125,000
80
100,000
60
75,000
40
50,000
20
25,000
0
0 14-Sep 12-Oct 9-Nov 7-Dec 4-Jan 1-Feb 1-Mar 29-Mar 26-Apr 24-May 21-Jun 19-Jul 16-Aug 13-Sep 11-Oct Plan Staffing
Actual Staffing
Plan Jobhours
Actual Jobhours
JOBHOURS
02Oview.ppt (25)
Equivalent People
NON-MANUAL STAFFING and JOBHOURS
Field Non-Manual Staffing Plan FIELD NON-MANUAL STAFFING PLAN Job No. XXXXX-XXX Position Site Manager Site Superintendant
02Oview.ppt (26)
Mechanical Sup't Piping Sup't Civil/Structural Sup't Electrical/Instr Sup't Secretary
Field Engineering Sup'v Mechanical Field Engr Piping Field Engr Civil/Struct Field Engr Elect/Instr Field Engr
Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst S/T Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst Plan Actual/Fcst S/T Plan Actual/Fcst
Data Date 1994 1995 M A M J J A S O N D J F M A M J J A S O N 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 4 5 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 5 5 3 2 4 4 7 7 7 7 7 7 7 7 7 7 7 7 7 6 5 4 2 0 1 1 0.5 1
1 1 0.5 1
2 2 1 2
1 1 1 1 1 1 1 1 1 0.5 1 1 1 1 1 1 1 1 1 5 5 4 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1 1 1 1 5 5
1 1 1 1 1 1 1
1 1 1 1 1 1
1 1 5 4
1 1 4 4
1 1 1 1 1 1
1 1
1 1 1
Jobhours Plan To-Date To-go Forecast 3,612 1,376 2,064 3,440 3,440 1,204 1,892 3,096 2,666 860 1,548 2,408 2,924 860 1,892 2,752 2,580 1,118 1,290 2,408 2,924 774 1,720 2,494 3,612 1,376 2,064 3,440 21,758 7,568 12,470 20,038 3,612 1,290
2,064
3,354
860
1,720
2,580
946
1,892
2,838
1,290
1,204
2,494
1,032
2,064
3,096
5,418
8,944
14,362
2,752 1 1
1
3,096 2,752
1 1 4 4
1 1 3 3
1 1 1 3 2 2 0
3,268 15,480
Manual Labor Wage Rate Report
MANUAL LABOR WAGE RATE and CRAFT MIX Job No. XXXXX 02Oview.ppt (27)
Period Ending: 12-Oct-96 Craft ID BM CP EL IN IW LB MW PF PL TD
Description
Jobhours Budget To-Date This Wk
Boilermaker Carpenter Electrician Insulator Ironworker Laborer Millwright Pipefitter Plumber Teamster
5,743 6,588 18,756 1,322 5,676 8,457 4,345 26,345 4,335 3,445
3,245 4,876 5,678 0 4,976 5,548 2,854 5,633 978 1,543
TOTAL
85,012
35,331
327 434 387 0 466 512 287 445 175 166
Budget 179,986 160,286 685,907 32,164 169,599 114,677 141,864 988,991 148,387 78,029
Dollars To-Date
This Wk
Wage Rate Craft Mix Budget To-Date This Wk Budget To-Date This Wk
96,571 128,873 213,777 0 141,517 70,737 87,561 223,348 34,680 34,316
9,336 12,386 14,485 0 13,477 6,477 8,966 17,853 5,877 3,665
31.34 24.33 36.57 24.33 29.88 13.56 32.65 37.54 34.23 22.65
29.76 26.43 37.65 0.00 28.44 12.75 30.68 39.65 35.46 22.24
28.55 28.54 37.43 0.00 28.92 12.65 31.24 40.12 33.58 22.08
6.8% 7.7% 22.1% 1.6% 6.7% 9.9% 5.1% 31.0% 5.1% 4.1%
9.2% 13.8% 16.1% 0.0% 14.1% 15.7% 8.1% 15.9% 2.8% 4.4%
10.2% 13.6% 12.1% 0.0% 14.6% 16.0% 9.0% 13.9% 5.5% 5.2%
3,199 2,699,890 1,031,380
92,522
31.76
29.19
28.92
100.0%
100.0%
100.0%
Cash Flow Curve PROJECT XXXXX
CASH FLOW CURVE 80,000 70,000
50,000 40,000 30,000 20,000 10,000
Revenue Plan Expenditure Plan
Revenue Actual Expenditure Actual
Nov-98
Sep-98
Jul-98
May-98
Mar-98
Jan-98
Nov-97
Sep-97
Jul-97
May-97
Mar-97
Jan-97
Nov-96
Sep-96
Jul-96
May-96
0 Mar-96
02Oview.ppt (28)
Dollars x 1,000
60,000
Cost and Commitment Curve MATERIAL AND SUBCONTRACT COST AND COMMITMENT CURVE
12,000
8,000
6,000
4,000
2,000
Commit - Plan Cost - Actual
Commit - Actual Cost - Forecast
Commit - Forecast
Dec-97
Nov-97
Oct-97
Sep-97
Aug-97
Jul-97
Jun-97
May-97
Apr-97
Mar-97
Feb-97
Jan-97
Dec-96
Nov-96
Oct-96
0 Sep-96
02Oview.ppt (29)
Dollars (x 1,000)
10,000
Progress and Performance Objectives
02Oview.ppt (30)
n
Compare Actual Project Progress against Planned Progress
n
Measure the Performance of Work being Executed
n
Identify Deviations to the Plan (Trends)
n
Implement Corrective Actions (Mitigate)
n
Forecasting Tool
Physical Progress
02Oview.ppt (31)
n
Physical Progress is represented by Percent Complete
n
Percent Complete is based on Earned Value
n
Earned Value (EV) is a direct measurement of quantity of work completed expressed in terms of the budget assigned to the work —
EV should be quantity based whenever possible (minimize LOE)
—
EV is a value added tool, but it should be used in conjunction with the other control tools
Construction Performance Measurement n
Calculations:
02Oview.ppt (32)
Detail level % Complete
= Installed Quantity Forecast Quantity
Summary level % Complete
= Earned Man-hours Forecast Man-hours
Earned Man-hours = (Quantity Installed) X (Budget Unit Rate) Man-hour PF
= Earned Man-hours Actual Man-hours
Progress and Performance Reporting Tools
02Oview.ppt (33)
n
Quantity Unit Rate Reports
n
Progress and Performance Reports
n
Progress and Performance Curves
n
Material & S/C Cost & Commitment Curves
n
Quantity Installation Curves
Quantity Unit Rate Reports
02Oview.ppt (34)
n
A Quantity Unit Rate Report is a integral part of a construction control system to monitor and control direct hire labor performance
n
The QURR also provides: —
Early indication of problem areas that need corrective action
—
Comparison between actual, budget and forecast labor performance
QURR Report
02Oview.ppt (35)
Construction Direct Hire Progress and Performance Curve Progress & Performance Curves Total Manual Construction 2.5
100
90
Performance Factor (PF)
02Oview.ppt (36)
2.0
80
70
1.5
60
50
1.0
40
30
0.5
20
10
0.0
0
Jul-96 Aug-96 Sep-96 O c t - 9 6 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 O c t - 9 7 Nov-97 Dec-97 Jan-98 2/15/98
Budget PF
Fcst PF
Actual PF
Budget % Complete
Fcst % Complete
Actual % Complete
Plan Forecast Actual
26-Apr
19-Apr
12-Apr
5-Apr
29-Mar
22-Mar
15-Mar
8-Mar
1-Mar
22-Feb
15-Feb
8-Feb
1-Feb
25-Jan
18-Jan
11-Jan
4-Jan
28-Dec
21-Dec
14-Dec
7-Dec
30-Nov
23-Nov
16-Nov
9-Nov
2-Nov
26-Oct
19-Oct
12-Oct
5-Oct
28-Sep
02Oview.ppt (37) Pipe (LM)
Quantity Installation Curve PIPING INSTALLATION CURVE
25000
20000
15000
10000
5000
0
Trending and Change Control
02Oview.ppt (38)
n
Change Control - formal process of modifying the project cost & schedule baseline and/or contract
n
Trend Program - a precursor to the formal change control process that that identifies the potential for change to occur to the scope, cost and/or schedule baseline
Trend Definitions n
Scope Change Trend —
02Oview.ppt (39)
n
An item of change to the project scope, schedule, or plant quality requested by the Client, recommended by the contractor or required by Regulatory Agencies
Other Trends —
Items that cannot be classified as scope changes, but are attributable to project evolution, such as: pricing, quantity fluctuations, design changes, productivity
Key Trend Program Attributes
02Oview.ppt (40)
n
Early Identification
n
Informed Decision Making
n
Timely Decision Making
n
NO SURPRISES
Trend Impact Assessment n
Why do we need to change?
n
Who or what is impacted by the change?
02Oview.ppt (41)
n
—
Project functions
—
Cost elements
—
Schedule
The objective is? —
n
Only change for the better
The Action is? —
If you can’t avoid it... minimize or work around it
Forecast Objectives
02Oview.ppt (42)
n
Evaluate current status of project cost and schedule
n
Determine critical items for management review and action
n
Provide a sound basis for future project control
Forecast Elements
02Oview.ppt (43)
n
Quantity Development & Review
n
Material & Subcontract Pricing Review
n
Manual Labor Productivity Analysis
n
Manual Labor Pricing Analysis
n
Construction Indirect Cost Analysis
n
Home Office Cost Analysis
n
Schedule Analysis
n
Escalation Analysis
n
Contingency Analysis
Forecast Elements n
Quantity Development & Review
02Oview.ppt (44)
—
To-Date Installed Quantities
—
Total Forecast Quantities •
Budget Quantities
•
Detailed Take-offs
•
Scope Growth Allowance
Summary These are just some of the tools that can be used to manage construction projects
n
Utilize the “graded approach” based on project complexity, size and risk
n
If/when a construction project gets into trouble, DON’T eliminate your controls tools to try to save money
02Oview.ppt (45)
n