MONTHLY REPORT
Desember 2014 FC:Naqala barka 3
CONTENT 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18.
Summary report Working hour achievement Trendline HM crane achievement Schedule service Schedule replace wire Schedule replace pulley Accuracy service time 2014 Critical item pulley Performance life time wire & pulley Activity report service engineer Inventory spare parts Issued spare parts Average issued parts by month Total issiued wire & pulley 2014 Min max spare parts Check list service crane Photo report ( Replace pulley E1 E2 ) Photo report ( Service crane )
Pages - 01
Report to Cc. to
: Service dept head
SUMMARY MONTHLY REPORT
: ICDS Manager
Report by
MAINTENANCE ACTIVITY
: Maintenance Planner
SMR No.
: 001/SMR_Plant/09/2014
Periode
: DESEMBER 2014
Department
: Maintenance dept
FC : NAQALA BARKA 3 NO
UNIT
CARRIED OUT
NEXT PLANNING
REMARKS
Segera di lakukan penggantian pulley C4 C5 ( ROB NILL ) Sudah di lakukan penggantian pada pulley luffing E1 dan E2 pada tgl 20 Des 14 HM 3343
Prepare untuk pulley H1 ( Percentage 76% )
Segera di lengkapi stock wire grab 1
ROB NILL
CRANE Telah di lakukan service crane pada tgl 21Des-14 HM 3343
Next service HM3840
Plan akhir Jan 15 ( Create Telah di lakukan analisa oli hydraulic crane ( Plan pengganti oli hydraulic bersamaan MR oli hydraulic Tellus 68 6 Viscosity rendah ) dengan service crane drm ) Plan pengganti wire closing / holding ( End Feb 15 ) 2
AE
ROB 2 set ( 4 coil )
Telah di lakukan service pada generator AE 1 Next service HM 3149 tgl 10 Des 14 HM 2649
Approved by
Prepared by
Iskak Salahudin Arief Service Dept Head
Eko untung Planner
Pages - 02
HOUR METER ACHIEVEMENT FC NAME : NAQALA BARKA 3 Month of periode : December 2014 LAST DATE
CODE
EQUIPMENT NAME
WORKING HOURS
24-Dec-14
AE 1
AUXILIARY ENGINE 1
229
24-Dec-14
CRANE
CRANE
296
24-Dec-14
MGE 1
MAIN GENERATOR ENGINE 1
139
24-Dec-14
MGE 2
MAIN GENERATOR ENGINE 2
208
TREND CRANE UTILITY 2014 100.00%
Value
80.00% 55.42%
60.00%
55.97%
52.78%
49.72%
49.03%
41.11%
40.28% 40.00%
20.00%
10.97%
8.19%
0.00% 0.00% Mar
Apr
May
Jun
Jul
Aug Periode
Avg UA 36.3%
Sep
Oct
Nov
Dec
Day 0 0 0 0 0
20-Dec
21-Dec
22-Dec
23-Dec
24-Dec
0 19-Dec
0.00 18-Dec
17-Dec
18
16-Dec
22
15-Dec
22
14-Dec
13-Dec
22
12-Dec
11-Dec
15.00
10-Dec
7
09-Dec
08-Dec
23
07-Dec
06-Dec
05-Dec
04-Dec
20.00
03-Dec
24
02-Dec
25.00
01-Dec
Hours
TREND HM CRANE ACHIEVEMENT
Pages - 03
30.00
24 23 22
19 18
17
14 13
10.00
7
5.00
1 0
Pages - 04
MONITRING SCHEDULE SERVICE FC NAME : NAQALA BARKA 3 Up date :Thursday-25-December-2014 RUNNING CODE
LAST SERVICE
PLAN SERVICE
INTERVAL HM
DATE
HM
DATE
HM
Date
GROUP : CRANE CRANE
3343
24-Dec-14
500
3340
21-Dec-14
3840
10-Feb-15
GROUP : GENERATOR MGE 2
2054
24-Dec-14
1000
1541
29-Oct-14
2541
04-Mar-15
MGE 1
2048
24-Dec-14
1000
1742
29-Oct-14
2742
29-Mar-15
AE 1
2839
24-Dec-14
500
2649
10-Dec-14
3149
25-Jan-15
Remarks :
Warning
Action
CRANE = Cranes MGE = Main Generator Engine AE = Auxiliary Engine ME = Main Engine DZ = Bulldozer WA = Wheel loader
Pages - 05
MONITORING REPLACE WIRE FC NAME : NAQALA BARKA 3 Up date : Thursday-25-December-2014 RUNNING
LAST CHANGE
CODE
PLAN CHANGE
CHECKED HM
DATE
HM
DATE
HM
MEAS
LMT
%
LIFE TIME
ROB
DATE
GROUP : WIRE CLOSING C RHL
3,343
24-Dec-14
11-Nov-14
1,834
01-Aug-14
3,834
08-Mar-15
31.8
30.0
40%
1,509
1
C LHL
3,343
24-Dec-14
11-Nov-14
1,834
01-Aug-14
3,834
02-Mar-15
31.7
30.0
43%
1,509
1
GROUP : WIRE GRAB Grab RHL
3,343
24-Dec-14
11-Nov-14
2,391
14-Oct-14
4,391
23-Apr-15
32.5
30.0
17%
952
Grab LHL
3,343
24-Dec-14
11-Nov-14
2,391
14-Oct-14
4,391
30-Apr-15
32.6
30.0
13%
952
GROUP : WIRE HOLDING H RHL
3,343
24-Dec-14
11-Nov-14
1,834
01-Aug-14
3,834
08-Mar-15
31.8
30.0
40%
1,509
1
H LHL
3,343
24-Dec-14
11-Nov-14
1,834
01-Aug-14
3,834
08-Mar-15
31.8
30.0
40%
1,509
1
11-Nov-14
1,908
12-Aug-14
4,408
07-Apr-15
33.8
32.0
40%
1,435
1
GROUP : WIRE LUFFING LFF
Remarks :
3,343
Warning
24-Dec-14
Action
C RHL = Wire closing kanan / C LHL = Wire closing kiri H RHL = Wire holding kanan / H LHL = Wire holding kiri LFF = Wire luffing Grab RHL = Wire grab kanan / Grab LHL = Wire grab kiri
Pages - 06
MONITORING REPLACE PULLEY FC NAME : NAQALA BARKA 3 UPDATE : Thursday-25-December-2014 LAST REPLACE NO
CODE
SECTION
PLAN REPLACE
MEASUREMENT
LIMIT
ROB HM
DATE
HM
DATE
DATE
VALUE
%
LIFE TIME
IMPRINT
DEFLECT
1
C3
PULLEY CLOSING
60.0
0
21-Mar-14
3,343
20-Mar-15
11-Nov-14
56.7
34%
3343
NO
NO
2
C4
PULLEY CLOSING
160.0
0
21-Mar-14
3,343
12-Feb-14
11-Nov-14
166.9
238%
3343
NO
NO
3
C5
PULLEY CLOSING
160.0
0
21-Mar-14
3,343
16-Feb-14
11-Nov-14
166.8
236%
3343
NO
NO
4
C6
PULLEY CLOSING
60.0
0
21-Mar-14
3,343
25-Feb-15
11-Nov-14
57.3
46%
3343
NO
NO
5
CF 6
PULLEY CLOSING
60.0
0
21-Mar-14
3,343
12-Mar-15
11-Nov-14
56.9
38%
3343
NO
NO
6
CF 7
PULLEY CLOSING
60.0
0
21-Mar-14
3,343
05-Feb-15
11-Nov-14
57.8
56%
3343
NO
NO
7
CR 2
PULLEY CLOSING
60.0
0
21-Mar-14
3,343
01-Apr-15
11-Nov-14
56.4
28%
3343
NO
NO
8
CR 3
PULLEY CLOSING
60.0
0
21-Mar-14
3,343
24-Mar-15
11-Nov-14
56.6
32%
3343
NO
NO
9
E1
PULLEY LUFFING
60.0
3343
20-Dec-14
6,686
04-Jul-15
20-Dec-14
55.0
0%
0
NO
NO
10
E2
PULLEY LUFFING
60.0
3343
20-Dec-14
6,686
04-Jul-15
20-Dec-14
55.0
0%
0
NO
NO
11
EF 1
PULLEY LUFFING
60.0
2391
10-Oct-14
5,734
09-Feb-15
11-Nov-14
57.7
54%
952
NO
NO
12
EF 2
PULLEY LUFFING
60.0
2391
10-Oct-14
5,734
13-Feb-15
11-Nov-14
57.6
52%
952
NO
NO
13
ER 1
PULLEY LUFFING
60.0
2391
10-Oct-14
5,734
09-Apr-15
11-Nov-14
56.2
24%
952
NO
NO
14
H1
PULLEY HOLDING
100.0
0
21-Mar-14
3,343
28-Dec-14
11-Nov-14
98.8
76%
3343
NO
NO
15
H2
PULLEY HOLDING
60.0
0
21-Mar-14
3,343
05-Apr-15
11-Nov-14
56.3
26%
3343
NO
NO
16
H7
PULLEY HOLDING
60.0
0
21-Mar-14
3,343
16-Mar-15
11-Nov-14
56.8
36%
3343
NO
NO
17
H8
PULLEY HOLDING
100.0
0
21-Mar-14
3,343
17-Feb-15
11-Nov-14
97.5
50%
3343
NO
NO
18
HF 5
PULLEY HOLDING
60.0
0
21-Mar-14
3,343
01-Apr-15
11-Nov-14
56.4
28%
3343
NO
NO
19
HF 8
PULLEY HOLDING
60.0
0
21-Mar-14
3,343
12-Mar-15
11-Nov-14
56.9
38%
3343
NO
NO
20
HR 1
PULLEY HOLDING
60.0
0
21-Mar-14
3,343
20-Mar-15
11-Nov-14
56.7
34%
3343
NO
NO
21
HR 4
PULLEY HOLDING
60.0
0
21-Mar-14
3,343
17-Apr-15
11-Nov-14
56.0
20%
3343
NO
NO
Remarks :
= Warning
= Action
Pages - 07
Avg accuracy service time 160.00%
140.00%
120.00%
Percentage
100.00%
80.00%
133.60% 60.00% 105.96%
87.10% 40.00%
77.05%
20.00%
0.00% AE 1
Remarks : RED = Not good
CRANE
MGE 1
GREEN = Good Unit no
MGE 2
Pages - 08
MONITORING CRITICAL PULLEY FC NAME : NAQALA BARKA 3 UPDATE : Thursday 25 December 2014 NO
SECTION
CODE
LAST CHEKED
GROOVE
LIMIT
(%)
REASON FOR CHANGE
1
PULLEY CLOSING
C4
11-Nov-14
166.9
160.0
238%
DEPTH
2
PULLEY CLOSING
C5
11-Nov-14
166.8
160.0
236%
DEPTH
This item base on from last checking Remarks : Only for percentace 100% - up / Imprint / Deflection
ROB
Pages - 09
LIFE TIME WIRE & PULLEY FC NAME : NAQALA BARKA 3 START
FINISH
LIFE TIME
CODE
ACHIEVE DATE
HM
DATE
GROUP : PULLEY LUFFING
HM
DAY
HM
Average :
274
3,343
167%
TARGET
E1
21-Mar-14
0
20-Dec-14
3,343
274
3343
167%
2,000
E2
21-Mar-14
0
20-Dec-14
3,343
274
3343
167%
2,000
Average :
133
1,834
92%
GROUP : WIRE CLOSING C RHL
21-Mar-14
0
01-Aug-14
1,834
133
1834
92%
2,000
C LHL
21-Mar-14
0
01-Aug-14
1,834
133
1834
92%
2,000
Average :
194
2,285
114%
GROUP : WIRE GRAB Grab RHL
21-Mar-14
0
01-Oct-14
2,285
194
2285
114%
2,000
Grab LHL
21-Mar-14
0
01-Oct-14
2,285
194
2285
114%
2,000
Average :
133
1,834
92%
GROUP : WIRE HOLDING H RHL
21-Mar-14
0
01-Aug-14
1,834
133
1834
92%
2,000
H LHL
21-Mar-14
0
01-Aug-14
1,834
133
1834
92%
2,000
Average :
144
1,908
76%
1,908
144
1908
76%
Total average :
179
2,278
112%
GROUP : WIRE LUFFING LFF
21-Mar-14
0
12-Aug-14
Page 1 of 1
2,500
Pages - 10
ACTIVITY SERVICE ENGINEER FC NAME : NAQALA BARKA 3 PERIODE : Desember 2014 NO
DATE
RHM
START
END
TOTAL
JOB DESCRIPTION
NAME : Rustam effendi 1
16-Dec-14
3342
08.00
16.00
8.00
2
17-Dec-14
3343
08.00
17.00
9.00
3
18-Dec-14
3343
08.00
16.00
8.00
4
19-Dec-14
3343
08.00
16.00
8.00
5
20-Dec-14
3343
08.00
16.00
8.00
6
21-Dec-14
3343
08.00
12.00
4.00
Page 1 of 2
Prepared for replacement pulley E1& E2( Welding stand fram on jib top ) Welding plate for stand fram Moved stand fram to jib top and instal By pass limit boom parking and stoper wire luffing Removed and Instal pulley E1 E2 Service crane
NO
DATE
RHM
START
END
TOTAL
TOTAL :
NAME
TOTAL
PERCENTAGE
Rustam effendi
45.00
18.8%
Productivity = Jumlah mechanic x 8 jam x 30 hari / total jam kerja
Page 2 of 2
JOB DESCRIPTION
Pages - 11
INVENTORY SPARE PARTS FC NAME :NAQALA BARKA 3 Periode : December-2014 NO
CATEGORY
PARTS NUMBER
DESCRIPTION
QTY
UNIT
GROUP : Consumable 1
Oil & Grease
CAT DEO15W-40
Oil engine
522
Ltr
2
Oil & Grease
COOLANT
Radiator collant
20
Ltr
3
Oil & Grease
GANDUS
Grease
180
Kg
4
Oil & Grease
MALEUS GL500
Grease
380
Kg
5
Oil & Grease
RIMULA 15W-40
Oil engine
283
Ltr
6
Oil & Grease
SPIRAX-A90
Gearbox oil
50
Ltr
7
Oil & Grease
TELLUS-68
Hydraulic oil
558
Ltr
GROUP : Floating crane 1
Crane
10037623
Oil coller
6
Pcs
2
Crane
7373880
Filter hyd return flow
10
Pcs
3
Crane
Wire guard
Wire guard / safety wire
2
Pcs
4
Crane
Bushing wire grab
Bushing wire grab
4
Pcs
5
Crane
79364696
Filter breather
5
Pcs
6
Crane
1253106
Filter luffing
9
Pcs
7
Crane
10511555
Pin bolt
2
Pcs
8
Crane
10511548
Pin bolt
4
Pcs
9
Crane
510713841
Filter
4
Pcs
10
Crane
411516914
Nut
12
Pcs
11
Crane
10536582
Bolt nut
2
Pcs
12
Crane
10544155
Bolt
20
Pcs
13
Crane
490054603
Bolt
4
Pcs
14
Crane
75835
Pin
2
Pcs
15
Crane
SBE-10,9
Bolt slewing
16
Pcs
16
Wire rope
32mmx148mtr ( C LHL )
Wire closing
1
Coil
17
Wire rope
32mmx148mtr ( C RHL )
Wire closing
1
Coil
18
Wire rope
32mmx148mtr ( H LHL )
Wire holding
1
Coil
19
Wire rope
32mmx148mtr ( H RHL )
Wire holding
1
Coil
20
Wire rope
10596874 ( 34mmx210mtr )
Wire luffing
1
Coil
Page 1 of 2
NO
CATEGORY
PARTS NUMBER
DESCRIPTION
QTY
UNIT
GROUP : Generator 1
AE
233-5182
Air cleaner ( Primary )
4
Pcs
2
AE
233-5184
Air cleaner ( Secondary )
10
Pcs
3
AE
250-6527
Filter element
29
Pcs
4
AE
7W-2326
Filter oil
2
Pcs
5
AE
GTB-22
Filter fuel
16
Pcs
6
MGE
2040
Filter racor
21
Pcs
7
MGE
4P-0710
Air cleaner ( Primary )
6
Pcs
8
MGE
9M-2342
Filter fuel
7
Pcs
9
MGE
1R-0726
Filter oil
2
Pcs
10
MGE
1R-0756
Filter fuel
25
Pcs
11
MGE
G-1000
Filter racor
4
Pcs
12
MGE
141-7116
V Belt
4
Pcs
13
MGE
12V-200A
Battery
2
Pcs
Page 2 of 2
Pages - 12
ISSUED SPARE PARTS FC NAME :NAQALA BARKA 3 Periode : 01 December 2014 To : 31 December 2014 NO
DATE
CATEGORY
PARTS NUMBER
DESCRIPTION
QTY
UNIT
REMARKS
ISSUED GROUP : AE 1 1
11-Dec-14
AE
233-5182
Air cleaner ( Primary )
1
Pcs
2
11-Dec-14
AE
GTB-22
Filter fuel
1
Pcs
3
11-Dec-14
AE
7W-2326
Filter oil
1
Pcs
4
11-Dec-14
AE
250-6527
Filter element
1
Pcs
5
11-Dec-14
AE
233-5184
Air cleaner ( Secondary )
1
Pcs
6
11-Dec-14
Oil & Grease
RIMULA 15W-40
Oil engine
15
Ltr
ISSUED GROUP : CRANE 1
20-Dec-14
Pulley rope
929658114-E1
Pulley luffing
1
Pcs
2
20-Dec-14
Pulley rope
929658114-E2
Pulley luffing
1
Pcs
3
21-Dec-14
Crane
7373880
Filter hyd return flow
2
Pcs
4
21-Dec-14
Oil & Grease
SPIRAX-A90
Gearbox oil
4
Ltr
5
21-Dec-14
Crane
1253106
Filter luffing
2
Pcs
6
21-Dec-14
Oil & Grease
SPIRAX-A90
Gearbox oil
4
Ltr
Aggregate 1
7
21-Dec-14
Oil & Grease
SPIRAX-A90
Gearbox oil
14
Ltr
Closing gearbox
8
21-Dec-14
Oil & Grease
SPIRAX-A90
Gearbox oil
21
Ltr
Holding gearbox
9
21-Dec-14
Oil & Grease
SPIRAX-A90
Gearbox oil
15
Ltr
Luffing gearbox
10
21-Dec-14
Crane
10037623
Oil coller
2
Pcs
ISSUED GROUP : MGE 1 1
06-Dec-14
Oil & Grease
RIMULA 15W-40
Oil engine
20
Ltr
2
13-Dec-14
Oil & Grease
RIMULA 15W-40
Oil engine
20
Ltr
RIMULA 15W-40
Oil engine
10
Ltr
ISSUED GROUP : MGE 2 1
02-Dec-14
Oil & Grease
Page 1 of 2
Aggregate 2
NO
DATE
CATEGORY
PARTS NUMBER
DESCRIPTION
Page 2 of 2
QTY
UNIT
REMARKS
Pages - 13 AVERAGE USAGE PARTS PER MONTH FC NAME : NAQALA BARKA 3 PARTS NUMBER Part group :
DESCRIPTION
JAN
FEB
MAR
APR
MEI
JUN
JUL
AGUST
SEP
OKT
NOP
DES
TOTAL AVG
Consumable
GANDUS
Grease
100
35
68
MALEUS GL500
Grease
150
40
95
RIMULA 15W-40
Oil engine
16
624
SPIRAX-A90
Gearbox oil
45
39
TELLUS-68
Hydraulic oil
12
10037623
Oil coller
1
32mmx148mtr ( C LHL )
Wire closing
1
1
32mmx148mtr ( C RHL )
Wire closing
1
1
32mmx148mtr ( H LHL )
Wire holding
1
1
32mmx148mtr ( H RHL )
Wire holding
1
1
32mmx19mtr ( Grab LHL )
Wire grab
1
1
32mmx19mtr ( Grab RHL )
Wire grab
1
1
10596874 ( 34mmx210mtr )
Wire luffing
7373880
Filter hyd return flow
929658114-E1
Pulley luffing
929658114-EF2
Pulley luffing
929658114-E2
Pulley luffing
992091014-ER1
Pulley luffing
79364696
Filter breather
1
1253106
Filter luffing
1
10570793
Replacement joy stick
929658114-EF1
Pulley luffing
Part group :
Part group : 2040
15
17
25
395
170 30
50
7
16
95
150
12
54
30
24
Floating crane 2
2
1
2
1 2
2
2
1
2
2
2
2
1
1
1
1 1
1
1 1 1
2
2
2
1
2 1
1
1
Generator Filter racor
2 Page 1 of 2
2
2
2
PARTS NUMBER
DESCRIPTION
233-5182
JAN
FEB
MAR
APR
MEI
JUN
JUL
AGUST
SEP
OKT
DES
TOTAL AVG
Air cleaner ( Primary )
1
1
233-5184
Air cleaner ( Secondary )
1
1
250-6527
Filter element
1
1
4P-0710
Air cleaner ( Primary )
7W-2326
Filter oil
1
1
1
GTB-22
Filter fuel
1
1
1
1R-0726
Filter oil
1R-0756
Filter fuel
JABSCO 50444
Water pump assy
1
NOP
1
1
3 3
3
5
4 1
Page 2 of 2
3
1
Pages - 14
ISSUED WIRE AND PULLEY FC NAME : NAQALA BARKA 3
NO
DATE
PARTS NUMBER
DESCRIPTION
CODE
QTY
CATEGORY : Pulley rope 1
10-Oct-14
929658114-EF2
Pulley luffing
EF 2
1
2
10-Oct-14
929658114-EF1
Pulley luffing
EF 1
1
3
10-Oct-14
992091014-ER1
Pulley luffing
ER 1
1
4
20-Dec-14
929658114-E2
Pulley luffing
E2
1
5
20-Dec-14
929658114-E1
Pulley luffing
E1
1
CATEGORY : Wire rope 1
01-Aug-14
32mmx148mtr ( H RHL )
Wire holding
H RHL
1
2
01-Aug-14
32mmx148mtr ( H LHL )
Wire holding
H LHL
1
3
01-Aug-14
32mmx148mtr ( C RHL )
Wire closing
C RHL
1
4
01-Aug-14
32mmx148mtr ( C LHL )
Wire closing
C LHL
1
5
12-Aug-14
10596874 ( 34mmx210mtr )
Wire luffing
LFF
1
6
14-Oct-14
32mmx19mtr ( Grab RHL )
Wire grab
Grab RHL
1
7
14-Oct-14
32mmx19mtr ( Grab LHL )
Wire grab
Grab LHL
1
Page 1 of 1
Pages - 15
MIN - MAX SPARE PARTS FC NAME : NAQALA BARKA 3 PERIODE : December-2014 NO
PARTS NUMBER
AVG ISSUED
SAFETY STOCK
MIN
MAX
STOCK
ORDER
UNIT
Gearbox oil
54
16.2
70
125
50
75
Ltr
DESCRIPTION
GROUP : Consumable 1
SPIRAX-A90
GROUP : Floating crane 1
32mmx148mtr ( C LHL )
Wire closing
1
0.1
1
2
1
1
Coil
2
32mmx148mtr ( C RHL )
Wire closing
1
0.1
1
2
1
1
Coil
3
32mmx148mtr ( H LHL )
Wire holding
1
0.1
1
2
1
1
Coil
4
32mmx148mtr ( H RHL )
Wire holding
1
0.1
1
2
1
1
Coil
5
32mmx19mtr ( Grab LHL )
Wire grab
1
0.1
1
2
0
2
Pcs
6
32mmx19mtr ( Grab RHL )
Wire grab
1
0.1
1
2
0
2
Pcs
7
10596874 ( 34mmx210mtr )
Wire luffing
1
0.1
1
2
1
1
Coil
8
929658114-E1
Pulley luffing
1
0.1
1
2
0
2
Pcs
9
929658114-EF2
Pulley luffing
1
0.1
1
2
0
2
Pcs
10
929658114-E2
Pulley luffing
1
0.1
1
2
0
2
Pcs
11
992091014-ER1
Pulley luffing
1
0.1
1
2
0
2
Pcs
12
929658114-EF1
Pulley luffing
1
0.1
1
2
0
2
Pcs
GROUP : Generator 1
7W-2326
Filter oil
1
0.3
1
2
2
0
Pcs
2
1R-0726
Filter oil
3
0.9
4
7
2
5
Pcs
Remarks : Item wire & pulley safety stock 10% , item filter safety stock 30% , oil & grease 50%
Page 1 of 1
Pages - 16
Pages - 17
FHOTO REPORT PEKERJAAN FC.Naqala Barka III Tanjung Pemancingan, Kotabaru
Date : 20 Des 2014
Coment : Wire Luffing pada pick point sudah siap di Stopper
Comemt Pulley E2 yang Sudah di lepas dan siap proses Menaikan Pulley baru untuk di pasang di E2
Coment Pulley E1 dan E2 yang sudah selesai terpasang
Pages - 17
FHOTO REPORT PEKERJAAN FC.Naqala Barka III Tanjung Pemancingan, Kotabaru
Date : 20 Des 2014
COMENT : Persiapan pekerjaan untuk membuat tiang gawang dan melanjutkan pengelasan full welding
Coment : Pengelasan diatas jip top Crane untuk untuk pemasangan tiang gawang gantungan chain blok
Coment : Tiang Gawang dan Chain Blox yang sudah siap Terpasang untuk pekerjaan pengantian Pulley E1 Dan E2 Dan Menunggu Chain Blok lain nya dari Barqa 2
Pages - 18
FHOTO REPORT PEKERJAAN FC.Naqala Barka III Tanjung Pemancingan, Kotabaru
Date : 20 Des 2014 Cervicing Crane
Coment : Sedang Melakukan Darin Oli Luffing Gear box dan pengambilan oli sample
Coment Sedang melakukan Proses Draain Oli Holding dan Closing Winch
Coment Saat Pengisian oli gear box Closing winch
THANK YOU