Mifflin County School District New Indian Valley High School Project Summary ™ The project shall consist of a new 251,000 square foot high school capable of housing 1,150 students with core capacity to facilitate future expansion to 1,300. Amenities shall include an auditorium capable of seating the entire student body plus faculty, a 1,500 seat gymnasium, an auxiliary gym and a wrestling room. The cafeteria will be capable of serving as a pre-function space for events in the gymnasium and auditorium. ™ Site work shall include new access drives, parking lots and sidewalks to serve the new high school and all associated utilities, retaining walls and landscaping. ™ A new concrete retaining wall and concrete steps will be provided between the new High School and the existing track in preparation for future bleachers and a press box. An alternate bid shall provide the school district with the option to add the bleachers at this time if bid results are favorable and if so desired. ™ The building structure shall be a steel frame supported by conventional spread footings. ™ The exterior of the building shall be utility sized face brick over concrete block back-up, aluminum windows, storefronts and curtainwall, and EPDM and standing seem metal roofs. ™ Interior finishes shall consist of then set terrazzo floors in the first floor academic wing corridors and in the cafeteria, linoleum floors in the music department and second and third floor corridors, VCT floors in the classrooms and general spaces, ceramic tile floors and walls in the toilet rooms and showers, painted walls and acoustical tile ceilings throughout. ™ The building shall include a fully automatic sprinkler system throughout. ™ The HVAC system shall be a geo-thermal heat pump system. ™ Electrical systems shall include automatic fire alarm system, closed circuit television surveillance, card access, cable television and data cabling systems. ™ Off-site road improvements shall include a new traffic signal at the corner of Cedar Street & Logan Boulevard.

Reynolds Construction Management, Inc

1

February 21, 2008

Mifflin County School District New Indian Valley High School 90% Construction Document Estimate Summary

BUILDING AREA

251,100

sf

Cost

Cost /sf

New Construction Site Work

$ $

43,584,000 7,996,000

$ $

173.57 31.84

TOTAL CONSTRUCTION COST

$

51,580,000

$

205.42

Off-Site Road Improvements Construction Costs

$

300,000

Off-Site Road Improvements Design Costs Estimated Soft Costs

$ $

110,000 8,598,000

$

60,588,000

TOTAL PROJECT COST

Prepared by: Reynolds Construction Management, Inc. February 21, 2008

Mifflin County School District New Indian Valley High School Soft Costs Breakdown

Architectural/Engineering Fees Additional A/E Fees (including Site LDP approvals) Food Service Consultant Architectural Reimbursables Building Commissioning Geotechnical Investigations Surveying General Building Permit L&I Review Fees Zoning Fee Miscellaneous Site Work Permits & Fees Misc Review & Permit Fees Sewage Tap in Fee (Based on an estimated 92 EDUs) Water Tap in Fee Utility Company Charges Printing of Bidding Documents Cost Advertisement Cost Stenographer Cost For ACT 34 Hearing Builders Risk Insurance (Typically @ .22% of Building Construction) Construction Testing & Inspection Agency Fees Movable Furniture, Fixtures and Equipment (Allowance) Computer Technology Budget Construction Managers Fee & Reimbursables (Based on 28 months) Land Purchase & Easements (Including Legal Fees, Appraisals, etc) Project / Construction Contingency (3% of Construction Cost) Bond/ Financing Cost (Not Included) TOTAL SOFT COSTS

Reynolds Construction Management, Inc

$

$ $ $ $

3,230,300 Included Included Included 95,000 45,000 20,000 160,000 N/A 2,000 5,000 5,000 92,000 85,000 10,000 40,000 5,000 2,000 120,000 140,000 1,500,000 In Above 1,141,700 300,000 1,600,000 -

$

8,598,000

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

February 21, 2008

Mifflin County School District New Indian Valley High School Value Engineering Incorporated Into the Project

Included in Estimate

1.

Change Storm Water Detention Structure #2 from 12 ga 72” diameter corrugated metal pipe to 14 ga 96” diameter corrugated metal pipe and reduce the length accordingly.

2.

Delete plywood sheathing under standing seam metal roofs.

3.

Delete underground make-up air ductwork for generator room. Install louver in West exterior wall of Generator Room.

4.

Reduce number of linear slot diffusers to one per window in lieu of 2 per window as originally shown.

5.

Reduce number of runs of ductwork in Gymnasium from 6 to 4, in Auxiliary Gym from 6 to 4 and in Wrestling Room from 4 to 3. TOTAL SAVINGS REALIZED

Reynolds Construction Management, Inc





1

February 21, 2008

Indian Valley High School Project Summary of Value Engineering to Date Approximate Savings to School District Schematic Design 1. Adjust grading of site to balance cut to fill.



2. Delete canopy in front of locker rooms and fitness room.



Design Development 1. Analyze Various Roof Framing Options



2. Change flooring in corridors of non academic wings of first floor



nd

and throughout 2 & 3rd floors from terrazzo to linoleum. 3. Eliminate approximately 25% of site retaining walls. not including steep slope wall at rear of building. 4. Change stamped concrete at front entry and cafeteria plazas to standard concrete walks. 5. Current design indicates approximately 3 miles of concrete curbs in the driveways and parking lots. Eliminate curbs in front of parking spaces and use wheel stops. 6. Change doors from 7'-2" high with 2" frame head to 7'-0" with 4" head. 7. Change ceramic tile walls in bathrooms. kitchen and serving to epoxy painted CMU. 8.

Delete student cubbies in classrooms.



9.

Add 2 additional loops of geothermal wells and reduce the depth from 550' to 500'.

Construction Documents 1. Change Storm Water Detention Structure #2 from 12 ga 72" diameter corrugated metal pipe to 14 ga 96" diameter corrugated metal pipe and reduce the length accordingly. 2. Delete plywood sheathing under standing seam metal roofs.



3. Delete underground make-up air ductwork for generator room. Install louver in West exterior wall of Generator Room. 4. Reduce number of linear slot diffusers to one per window in lieu of2 per window as originally shown. 5. Reduce number of runs of ductwork in Gymnasium from 6 to 4. in Auxiliary Gym from 6 to 4 and in Wrestling Room from 4 to 3.

TOTAL SAVINGS TO DISTRICT TO DATE Reynolds Construction Management

February 21.2008

Mifflin County School District New Indian Valley High School Bid Alternates 1.

Alternate No. C-1 – Add grandstands and associated work at existing track.

2.

Alternate No. C-2 –Delete the concrete retaining wall, west steps and asphalt walk between the steps at the existing track and provide a reinforced earth slope.

3.

Alternate No. C-3 –Add the Plaza Retaining Wall and Steps at Southwest corner of track. +$ 72,000

4.

Alternate No. C-4 – Add the asphalt walk around South and West Sides of Existing Track. +$ 10,000

5.

Alternate No. C-5 –Add the concrete pad and retaining wall at baseball field and concrete walk from the existing high school parking lot to the concrete pad including associated retaining walls. +$120,000

6.

Alternate No. C-6 –Add concession stand / press box at the existing baseball field including the asphalt path from the concrete pad (included in Alternate No. C-5) to the concession stand. +$ 50,000

7.

Alternate No. C-7 –Eliminate the Architectural Finish on the Soil Nail retaining wall system and provide a screeded shot-crete finish.

8.

Alternate No. A-1 – Change corridor and stair flooring on the second and third floors in Units A & B from linoleum with rubber base to epoxy terrazzo with precast terrazzo base. Change stair treads and risers in Units A & B from rubber to precast terrazzo. +$327,000

9.

Alternate No. A-2 – Delete the wood wall panels in Library and Cafeteria and replace with painted walls to match adjacent walls and change linear wood ceilings Type C acoustical tile ceilings.

10.

Alternate No. A-3 – Change floor finish in rooms first floor corridors A102, A104, A109, A110, A118, A125, A129, B112 and B126 from terrazzo to linoleum. Precast terrazzo base shall be changed to rubber base.

11.

Alternate No. A-4 – Change Wood-Veneer Faced Casework as specified in section 12322 to Plastic Laminate Faced Casework similar to specified in section 12324. Countertops shall still remain as specified in section 12322.

12.

Alternate No. A-5 – Change interior ground face CMU to standard CMU painted to patch adjacent surfaces.

Reynolds Construction Management, Inc

1

+$203,000

February 21, 2008

13.

Alternate Bid No. HC-1 - Provide the Direct Digital Temperature Control System as manufactured by Automated Logic and supplied by Intercon Automation, in lieu of Invensys Building Systems Controls supplied by NRG Controls, as required by the Contract Documents. To Be Determined

14.

Alternate Bid No. HC-2 - Provide a waterside economizer package for the terminal heat pump units. This package shall include water coil, 3-way diverting valve, drain pan and strap on aquastat. +$125,000

15.

Alternate Bid No. HC-3 - Provide rooftop heat pump units as manufactured by Annex Air (listed under Part 2 of Specification Section 15722A) in lieu of Desert Aire & Semco (listed under Part 2 of Specification Section 15722). This shall also include the deletion of the refrigerant condensing units (listed on the schedule of drawing M4.1 as RHP-B2, RHP-C1, RHP-D1, CU-A1,CU-B1,CU-B2,CU-C1,CU-D1)) as required by the Contract Documents.

16.

Alternate Bid No. HC-4 - Provide exterior lighting control by the DDC system (thru the lighting control panel) as required by the Contract Documents. +$ 4,000

TOTAL SAVINGS OF ALL DEDUCT ALTERNATES



TOTAL COST OF ALL ADD ALTERNATES

+$911,000

Reynolds Construction Management, Inc

2

February 21, 2008

Mifflin County School District New Indian Valley High School Clarifications to Scope of Work

1.

Some storm water piping sizes have not yet been determined. For those pipe missing size designation, we have assumed 15” diameter for estimating purposes.

2.

The estimate includes resurfacing the existing parking lot of the McCardle property along Logan Blvd following installation of the new storm water piping. Resurfacing work shall be limited to the McCardle property and shall not extend into the public right of ways.

3.

Plantings within the Water Quality Islands of the parking lots have not yet been designed. For estimating purposes Reynolds has included an allowance of $20,000 for this work.

4.

Small retaining walls within the parking lot islands have not yet been designed. For estimating purposes Reynolds has assumed 2’ high segmental retaining walls.

5.

A paving section is not provided for the asphalt paths. For estimating purposes Reynolds has assumed 4” of crushed stone and 2” of asphalt paving.

6.

The baseball field is to be used as a stockpile area for topsoil and earth. Following removal of the stockpiled material the contractor shall regrade the outfield, Respread the topsoil and install new sod. The infield shall receive an additional 2” of infield mix and shall be regraded. The chain link fence shall be reinstalled where it was removed for access by earthmoving equipment.

7.

This estimate includes the architectural finish on the soil nail wall by Boulderscapes as approved by the School Board on December 20, 2007.

8.

Resealing and restriping of the existing parking lot on the Logan Associates property is to be performed by the school district under a separate contract and is not included in this estimate.

9.

This estimate includes the added cost of the proposed mezzanine above the cafeteria serving area as approved by the school board on December 20, 2007.