Managing Large Scale Network Model

Building the Energy Markets of Tomorrow . . . Today Managing Large Scale Network Model for Energy Management System & Business Management System De ...
Author: Harvey Thornton
0 downloads 1 Views 156KB Size
Building the Energy Markets of Tomorrow . . . Today

Managing Large Scale Network Model for

Energy Management System & Business Management System De D. Tran Tampa, Florida IEEE Power Engineering Society June 27, 2007

New York Control Area Š Š Š Š Š Š Š Š

19.2 million people

Serving New York City 2006 load of 162,265 GWH

324 active Market Participants

Record peak of 33,939 MW (8/2/06)

Over 485 generating units modeled

10,775 miles of high voltage transmission

2007 required Installed Capacity 38,966 MW

2

Building the Energy Markets of Tomorrow . . . Today

NYISO Revenue by Market 12000

10000

Million

8000

6000

4000

2000

0 1999

2000

2001

2002

2003

2004

2005

2006

Year Energy

ICAP

TCC

Total

3

Building the Energy Markets of Tomorrow . . . Today

Background: 9 Backbone transmission: 230KV, 345KV and critical 138KV facilities in New York City. 9 ICCP: 11 Redundant data links (6-12 sec scan) 9 RTU: Continuous Telemetry – about 100 points (Tie line MW, Large Units MW). 9 40 AGC Tie lines to PJM, New England ISO, Ontario Hydro (IMO), Hydro Quebec (HQ). 9 About 3100 buses, 30/70 split between internal/external. 4

Building the Energy Markets of Tomorrow . . . Today

Network System Representation Host Control Area Load Area Substation Generator Breaker Transformer Phase Shifter Compensator Energy Consumer SVC

Total 11 21 2240 1511 13150 1110 50 1000 2490 7

Internal 1 11 400 485 5379 498 33 173 1000 5

External 10 10 1840 1026 7771 612 17 827 1490 2 5

Building the Energy Markets of Tomorrow . . . Today

Single Model For EMS, BMS & Other Applications:

9 Energy Management System Applications: ƒ SCADA: There are 20000 of analog points and 12000 of status points. Data is being processed on a 6 sec and 5 min basis. ƒ State Estimator (SE) ƒ Area Generation Control (AGC) ƒ Contingency Analysis (CA) ƒ Dispatcher Load Flow (DLF) ƒ Security Monitor (SM). ƒ Topology Confirmation (TC). ƒ Outage Scheduler (OS). ƒ CIM One-Line Station Diagrams. 6

Building the Energy Markets of Tomorrow . . . Today

Single Model For EMS, BMS & Other Applications:

9 Business Management System Applications: ƒ Security Constrained Unit Commitment (SCUC) for Day-Ahead-Market. ƒ Real Time Scheduling (RTS) for Real Time Market. ƒ Transmission Congestion Contract Market (TCC).

9 Other Related Applications: ƒ Training Simulator System for System Operators (DTS). ƒ PI Historian. ƒ Map board Data – Drive the Control Center map board. 7

Building the Energy Markets of Tomorrow . . . Today

Special Generator Model: EMS vs. BMS Energy Management System: 9 Model all physical units for EMS and pseudo units for BMS. 9 Open breakers for all BMS pseudo units within the EMS. 9 Total individual EMS units measurements and allocate to the BMS pseudo units measurements based on AGC 6 second base points (BMS units) Business Management System: 9 Generator status is based on the Bid data. 9 Thus, generator that has no bid would be out of service. 9 BMS pseudo units measurements are being used for Performance Tracking. 8

Building the Energy Markets of Tomorrow . . . Today

Demand Respond Program (DRP) Model large industrial loads as pseudo DRP generators for BMS. Business Management System (DAM): 9 Award Day Ahead contracts based on Bids.

Energy Management System: 9 Open breakers for all pseudo DRP generators. 9 Industrial loads would be disconnected from the grid in real-time.

9

Building the Energy Markets of Tomorrow . . . Today

Key ID for Data Exchange Between Applications 9 Equipment PTID: The key that allows all data being exchanged among applications on different platforms is the equipment PTID number. 9 PTID number: a unique ID that was assigned to each piece of the network model facility and Control Area related definitions.

10

Building the Energy Markets of Tomorrow . . . Today

EMS To BMS Data Exchange in Real-Time 9 EMS to BMS Applications: ƒ Contingency Definitions; Contingency Group. ƒ Security & Monitor flags. ƒ Transmission facility dynamic ratings (RTS only). ƒ Internal generators current loading. ƒ External generators schedules. ƒ Load pattern for all loads. ƒ Outage Schedule data. ƒ Regulation & Spinning,10 & 30 Min reserve requirements. 11

Building the Energy Markets of Tomorrow . . . Today

BMS To EMS Data Exchange in Real-Time 9 For AGC: ƒ 5 min generator base points from Real-time Dispatch (RTD). ƒ Normal low, high & Emergency high generator operating limits. ƒ Regulating and emergency response ramp rate. ƒ Generator regulation flag. ƒ 10-Min and 30-Min for spinning and non spinning control flag.

9 For Contingency Analysis & Security Monitor: ƒ Contingency violations identified by the Real-Time Dispatch application (RTD). 12

Building the Energy Markets of Tomorrow . . . Today

Data Source for Model Update 9 Generator: ƒ MPs request directly through NYISO Customer Relation department

9 Other Equipments: ƒ Internal Control Area: Transmission Owner’s Data Coordinator Þ Power System facility to be changed Þ One-line diagrams Þ Metering information Þ Equipment related data such as ratings, impedances. Þ The effective date of the changes.

ƒ External Control Area: Þ Contact the External Control Areas directly. 13

Building the Energy Markets of Tomorrow . . . Today

Network Model Exchange: CIM XML File 9 Provided the standard CIM-XML to other ISOs for reliability purposes only. 9 Provided the standard CIM-XML to other TOs. 9 CIM-XML extension is being used for the BMS application. 9 The NYISO has not yet to import data to CIM data base from CIM-XML file. 9 External Control Area network model updates are being requested on an as needed basis. 14

Building the Energy Markets of Tomorrow . . . Today

Network Model Exchange: CIM XML File 9 To support the BMS applications such as RTS & SCUC. 9 Following items are part of the CIM Extension. ƒ Interface (Branch Group) definition. ƒ Interface incremental limits for outage conditions. ƒ Special flags for monitoring and securing for different types of facilities. ƒ Limit logic types. ƒ Equipment outage priority for different applications. ƒ Phase shifter optimization flags.

15

Building the Energy Markets of Tomorrow . . . Today

ABB’s CIM Data Engineering Toolkit 9 To maintain & Update network model for all applications. 9 Oracle based program. 9 Graphical editing environment to manage data in CIMbased format. 9 Automatic diagram generation, multi-users and versioned editing. 9 Import and Export full & incremental CIM/XML data. 9 Support SCADA data definitions. 9 Seasonal and dynamic ratings. 9 PI historian definitions. 9 Data for Control Center Map Board. 16

Building the Energy Markets of Tomorrow . . . Today

Network Model Data Update 9 Update all network model data directly in CIM database. 9 Standard data for EMS applications. 9 Special data for BMS applications. 9 Data for DTS system – Simulator. 9 Data for SCADA system. 9 Transmission Owner Ratings – Define/update equipment seasonal ratings. 9 Definition for PI historian.

17

Building the Energy Markets of Tomorrow . . . Today

Ranger Run-Time Generation 9 Export data for EMS system - It takes about 4 and ½ hours. 9 Export data for BMS (XML file) - 1 hour. 9 Database generation – 3 hours. 9 Review database generation log file. 9 Correct all identified errors in CIM and re-start the entire process again. 9 Load database to Development System for unit testing. 9 Development system has live-data identical to Production System. 18

Building the Energy Markets of Tomorrow . . . Today

Database Validation & Verification 9 SCADA data - verify and validate all newly defined measurements. 9 AGC - Area Generation Control. 9 SE - State Estimator 9 DLF - Dispatcher Load Flow 9 CA - Contingency analysis 9 SM - Security Monitor. 9 RTS - Real-Time Scheduling Systems. 9 SCUC – Security Constrained Unit Commitment. 9 All zonal ties and zonal generators for load Forecast 9 PI – Verify and validate all new PI tags. 9 Verify to ensure that TCC receive the latest model. 9 CIM and Station one-line diagrams. 19

Building the Energy Markets of Tomorrow . . . Today

Additional Database Validation & Verification 9 Move new database to QA for System Integration testing (Bid-to-Bill). 9 Inform other departments being impacted by the new database. 9 Obtain approval permission for deployment to Production System. 9 Network Model is being updated on a monthly basis.

20

Building the Energy Markets of Tomorrow . . . Today

Any Questions? De D. Tran [email protected] 518-356-6115 www.nyiso.com

21

Building the Energy Markets of Tomorrow . . . Today