® Making the right things happen, at the right time
Brussel, 15 October 2015 Peter Overgoor
Curriculum vitae
Peter Overgoor University, Business Management Information Science 1987 ABP Automation of pension fund processing 1988 Coopers & Lybrand Audit practice 1993 Coopers & Lybrand MCS practice » FMBA (FCM) » Interim- and Project management (PBM) 1998 Consultant to the firm Accomplishments ─
Fully responsible for completed large (inter)national projects in the area of :information systems (RWS, AAI,Y2K) energy (ENW, EPON) retail banking (Rabo, AAI) telecommunication (KPN, Telfort)
─
Lecturer Hogeschool Brabant Project management
─
Lecturer Hogeschool Brabant Master of Project management (Methods and Techniques)
GDPM NEXT30 Brussel, 15 October 2015
2 | 39
Case: Hoog water beschermingsprogramma AGENDA 15 October 2015 1. Assignment 2. Scope assignment 3. Organisation HWBP 4. Results interviews 5. Recommendations
GDPM NEXT30 Brussel, 15 October 2015
3 | 39
1. Assignment(1/2)
• Prepare a scan/audit on the project tooling as is • Reason: after two years no workable project tooling available
GDPM NEXT30 Brussel, 15 October 2015
4 | 39
1.
Assignment (2/2)
Monthly reporting, Q-reporting and ad-hoc reporting board are still a problem and are cost consuming Result an audit report explaining improvement area’s on the short time and long time with a proposed time to get the project tooling operational
GDPM NEXT30 Brussel, 15 October 2015
5 | 39
2.
SCOPE (1/2)
Agreed with the board to interview 30 program employees on different The audit issues are noted based on the interviews and available reports and not available reports
GDPM NEXT30 Brussel, 15 October 2015
6 | 39
2.
SCOPE (2/2)
Set-up PS/SharePoint is discussed with the application manager Planning of the implementation of the approved recommendations
GDPM NEXT30 Brussel, 15 October 2015
7 | 39
3.
Organisation HWBP (1/2) Programmamanagement Programmamanager
Manager Program control
Markermeerdijken
Zwakke Schakels Kust
Environment manager Program
Wijd (Waddenzee en IJsselmeer)
Praktijkproef dijken op veen
Projectmanager Markermeerdijken
Projectmanager Zwakke Schakels Kust
Projectmanager Wijd
Projectmanager Praktijkproef
Project controller Technical manager Environment manager: Contract manager
Project controller Technical manager Environment manager: Contract manager
Project controller Technical manager Environment manager: Contract manager
Project controller Technical manager Environment manager: Contract manager
GDPM NEXT30 Brussel, 15 October 2015
8 | 39
3.
Organisation HWBP (2/2) Mgr. Progr. Control
Program control
Program Control management
Program controller
PT-manager
PS/SharePoint
Functioneel manager (PS/ SP)
Program planners
Program risk
SharePoint
GDPM NEXT30 Brussel, 15 October 2015
Information analist
9 | 39
4.
RESULTS INTERVIEWS (1/8)
Program require ments
Implementati on PS/ SharePoint
Processes, procedures and guidelines
Reporting
Program control Project leads ‘IPM-rolhouders’
GDPM NEXT30 Brussel, 15 October 2015
| 10
10 | 39
4. Program require ments
RESULTS INTERVIEWS (2/8) • Program requirements not finalised nor approved
• No functional design nor system
architecture with interrelationships
• Lack of communication concerning the program requirements
• Lack of framework and guidelines and process not taken into account
GDPM NEXT30 Brussel, 15 October 2015
11 | 39
4.
RESULTS INTERVIEWS (3/8) • PS did not contain the basic Implementation PS/ SharePoint
information: Time/Planning to many details for the responsible managers Money (not integrated) Capacity (not taken into account) Risk (not usable) Quality (not taken into account) Scope (not clear)
• No one way of working • Nobody is using the project tools! GDPM NEXT30 Brussel, 15 October 2015
12 | 39
4.
RESULTS INTERVIEWS (4/8) • Not the right people on the project Implementation PS/ SharePoint
No knowledge available for project control within the project tooling team No knowledge available over the business functionality within project tooling team Device not built on the customers requirements! Lack of project management Lack of business knowledge
GDPM NEXT30 Brussel, 15 October 2015
13 | 39
4.
RESULTS INTERVIEWS (5/8) Process, procedures and guidelines
• Lack of Process, procedures and
guidelines. When available they were not used
• Programme organogram not up-to-
date. Not clear who is responsible for updates
• Resources not up-to-date!
GDPM NEXT30 Brussel, 15 October 2015
14 | 39
4.
RESULTS INTERVIEWS (6/8) • Project tooling should take care off:Reporting
Monthly reporting not operational. No input from the managers project controlling. They have never been asked for their input Q-reports after 7 Quarters still not available Risks not up-to-date (PS less up-todate than the Excel sheets) No analyses possibilities Planning not up-to-date (validation phase)
GDPM NEXT30 Brussel, 15 October 2015
15 | 39
4.
RESULTS INTERVIEWS (7/8) Program control Project leads ‘IPM-rolhouders’
• Tasks, responsibilities and authority
not clear… • External resources with knowledge and experienced do not cooperate to implement a standard way of working • External consulting agencies did not make use of ‘ shadow’ management
GDPM NEXT30 Brussel, 15 October 2015
16 | 39
4.
RESULTS INTERVIEWS (8/8) Program control Project leads ‘IPM-rolhouders
• No HR policy for the program (knock out criteria is
an university degree instead of knowledge and skills (the right person on the job) • Contract hours are not respected (e.g. 36 hours per week per contract to ca. 50 Hour in real without approval). • External resources are approving the hour of other external resources (no segregation of duties) • Not the right balance between internal-/external resources at the moment 30/70) GDPM NEXT30 Brussel, 15 October 2015
17 | 39
5.
RECOMMENDATIONS (1/6)
Project plan short term Solutions
Take care of business logica
CHECK
Reimplement ation adjusting current system
GDPM NEXT30 Brussel, 15 October 2015
18 | 39
5. Project plan short term solutions
RECOMMENDATIONS (2/6) 1. Prepare project plan short term solutions 2. Set TASKFORCE Who is responsible for what and what is needed Which tasks by whom executed Who has which authority! Clear appointments with internal-/external resources which tasks will be executed and what has been realised GDPM NEXT30 Brussel, 15 October 2015
19 | 39
5. Take care of business logica
RECOMMENDATIONS (3/6)
– Implementation of processes, procedures and guidelines – Who is responsible for the follow-up of the implemented processes, procedures and guidelines? – Segregation of duties: Design implement and control for the managers project control
GDPM NEXT30 Brussel, 15 October 2015
20 | 39
5.
RECOMMENDATIONS (4/6) Draft ‘HANDBOOK’ projects
Take care of business logica
Resource applications , availability , check and pay
Planning (capacity, risk, responsibility) Risk and issues Prepare general ledger accounts Obligation administration Regular reporting (internal month, Q-reports, subsidizing, annual accounts, reporting government at project level) Purchase procedure Purchase plan GDPM NEXT30 Brussel, 15 October 2015
21 | 39
5.
RECOMMENDATIONS (5/6)
Reimplementation
adjusting current system
Develop and implement reporting script
Project plans needs to be rolled up at the right level and need to be reconciled to finance reports
GDPM NEXT30 Brussel, 15 October 2015
22 | 39
5.
RECOMMENDATIONS (6/6) ü Per delivered product is mandatory that the responsible users do the sign off
CHECK
ü Facilitator roll ü One way of working ü Basis (Scope, planning, money, quality, organisation, risk and capacity) operational ü Process, procedures and guidelines operational ü Resource request based on capacity needed ü Tasks, responsibilities and authority assigned ü Risk/Issues addressed ü Train employees in project work (PS/SharePoint) GDPM NEXT30 Brussel, 15 October 2015
23 | 39
GDPM contribution
1. Introduction 2. GDPM® 3. Why GDPM®? 4. How does GDPM® work? 5. What are the deliverables?
GDPM NEXT30 Brussel, 15 October 2015
24 | 39
1.
Introduction GDPM® Solving control and monitoring issues Transparency and audit trail Multi currency Easy to work with Making use of existing applications
GDPM NEXT30 Brussel, 15 October 2015
25 | 39
2.
GDPM® (1/5) Uniform framework for projects Standardisation method
Multi-projects Planning and progress reporting
GDPM NEXT30 Brussel, 15 October 2015
26 | 39
2.
Uniform framework
GDPM® (2/5)
Phase 1: Milestone plan
A T i m e
B B1
C B1 Project Charter approved
GDPM NEXT30 Brussel, 15 October 2015
27 | 39
Standardisation method
APMIS® (3/5)
2.
Phase 2: Allocation of responsibilities and resources per milestone PROJECT RESPONSIBILITY CHART
10
18/02/2002 Mar
Apr
-
May
Jun
Milestones:
Jul
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
No
OR01
Plan van aanpak goedgekeurd
P,X
OR02
Financiele organisatie structuur goedgekeurd
P,X
SY01 OR03 OR04
3
SY02 OR05 SY03 OR06 OR07 SY04
5
SY05 PE01 AO01 AO02 AO03 PE02
1
SY06 SY07
P
Aantal bedrijven (6) aangelegd
P
Management rapportage vastgesteld Maatwerk SAP terug naar standaard Autorisatie matrix opgesteld Herinrichting administratie gerealiseerd Management rapportage geimplementeerd Standaard grootboekschema incl. kostenplaatsen geimplementeerd Acceptatie testplan goedgekeurd Procedure aanleggen stamgegevens afgerond SAP opleiding medewerkers bepaald Proces factuurcontrole gerealiseerd Opleidingsplan incl. AO procedures goedgekeurd ICT herinrichting administratie gerealiseerd Autorisatie matrix geimplementeerd
X
P P
X
5
P P P P
P
P,X
1
P
P
Opleiding medewerkers SAP beschikbaar
P
OR08
Migratieplan goedgekeurd
P
PE03
Werkinstructies opgesteld
P
PE04
Opleidingsplan SAP uitgevoerd
P
PE05
Acceptatie testplan uitgevoerd Communicatie richting finance afgerond Migratieplan uitgevoerd Communicatie richting organisatie afgerond SAP FiCo Operationeel
P
TOTAL RESOURCES:
3
P
AO05
OR10
2 X
P
P
Overdracht project aan de beheerorganisatie afgerond
X
P
Documentatie goedgekeurd
OR09
2 X
P
Stambestanden geschoond
CM02
2 X
P
AO06
SY08
2 X
P
AO04
CM01
19
Pilot testomgeving ingericht Standaard grootboekschema incl. kostenplaatsen goedgekeurd Leveranciers afspraken en spelregels vastgelegd
2 X
Ellen Kalkh oven
Ellen Kalkhoven
8
Peter Huber ts
Peter Huberts
D
Pal Kanta s
Pal Kantas
Period:
Cont. Feb
Approved by: Peter Overgoor Target completion: 04/11/2002 11/08/2002
Peter Habra ken
Peter Habraken
week Work
Companies, Departments, Functions, Types of Resources Peter Overg oor X - executes the work D - takes decisions solely d - takes decisions jointly P - manages progress T - provides training C - must be consulted I - must be informed A - available for advise Q - quality assurance
Peter Overgoor
Project: HSFC (Herinrichting SAP FiCo) Chart issue/date 08/04/2003 Period length
P P P P P
3
2
5
7
2
GDPM NEXT30 Brussel, 15 October 2015
28 | 39
2.
Multi-projects
GDPM® (4/5)
Phase 3: Project portfolioSummation and clustering over projects Defined projects
2015
2016
2017
2018
Total
• Per period management can decide to stop the project or not • The costs or cost savings are transparent
Total projects GDPM NEXT30 Brussel, 15 October 2015
29 | 39
Planning and progress
GDPM® (5/5)
2.
Phase 4: Progress reporting Progress report
Project name
Legend: Blank:
not yet started
Issues
Green:
on track
!
Yellow:
risk that milestone will be delayed
Red:
milestone delayed
Gray:
milestone finished
Reason why the milestone is yellow/red
Risks
! What are the risks for the project for the yellow/red milestones
Management decisions
! What must be done for the yellow/red milestone to get it on track again
Note: Every project member must deliver his timesheet every Monday relating to the previous week
GDPM NEXT30 Brussel, 15 October 2015
30 | 39
3.
Why GDPM®? Account for projects in the same way for comparison and for summation over projects Monitoring running projects Transparency over running projects in case of:─ Milestone plan and/or costs ─ Resource allocation ─ Budget vs. actual Filtering same projects
GDPM NEXT30 Brussel, 15 October 2015
31 | 39
4.
How does GDPM® work? (1/6) Project level (per milestone) ─ People (internal/external) ─ Materials ─ ─
Risk analysis Budget in hours and costs
Program Consolidated Programs Reporting ─ Progress ─ ─
Time Costs
─
resources
GDPM NEXT30 Brussel, 15 October 2015
32 | 39
4.
How does GDPM® work? (2/6)
Consolidation Working areas P1
P n
Board 1. Progress reporting
Milestones
Program cons. Working areas C1
C n
Program office: 1. Defining cons. programs 2. Resource allocation 3. Cons. program budget 4. Cons. program risk 5. Progress reporting
Milestones
Program -1 Working areas P1
Pn
Milestones
Project-n Working Project-1 areas
Resource resp.
Working areas Resource resp.
Milestone s
Milestones
Program manager: 1. Defining projects per working area 2. Resource allocation (persons (int/ext) and materials) 3. Defining program budget vs. actuals 4. Defining program risk 5. Progress reporting at program level Project leader: 1. Defining milestones per working area 2. Resource allocation (persons (int/ext) and materials) 3. Defining project budget vs. actuals 4. Defining risks per milestone 5. Progress reporting at milestone level 6. Time registration
GDPM NEXT30 Brussel, 15 October 2015
33 | 39
2.
Introduction GDPM® (3/6) Set-up
Input
Project reports Progress reports
Team effort defining the individual project milestones
Milestone plan
Defining the working area's
Time spent per resource per milestone
Allocation of the resources to the milestones
Material deliveries
Critical path (milestone dependencies)
Issues, actions and decisions
Yellow/red issues Budget vs actual Reports Financial cash planning Forecast
Projectmanager
Risk
Risk per milestone
Resource allocation
GDPM NEXT30 Brussel, 15 October 2015
34 | 39
2. Introduction GDPM® (4/6) Set-up
Input
Program reports Progress reports Milestone plan
Allocation of the projects in a program Key milestones per project Critical path (key project milestone dependencies) Risk per key milestone
Yellow/red issues Progress reports of the individual projects Issues, actions and decisions (at program level)
Budget vs actual Reports Financial cash planning Forecast
Program manager
Risk Resource allocation
GDPM NEXT30 Brussel, 15 October 2015
35 | 39
2.
Introduction GDPM® (5/6) Set-up
Input
Consolidated program reports Progress reports
Allocation of the program milestones to consolidated program Key milestones per consolidated program Critical path (key program milestone dependencies) Risk per key milestone
Milestone plan Yellow/red issues Progress reports of the individual projects Issues, actions and decisions (at consolidated program level)
Budget vs actual Reports Financial cash planning
Program office
Forecast Risk Resource allocation
GDPM NEXT30 Brussel, 15 October 2015
36 | 39
2.
Introduction GDPM® (6/6) Set-up
Input
Consolidation reports Progress reports
Allocation of the consolidated program milestones to consolidation Key milestones for consolidation Critical path (key consolidated program milestone dependencies) Risk per key milestone
Milestone plan Yellow/red issues Progress reports of the individual projects Issues, actions and decisions (at consolidated program level)
Budget vs actual Reports Financial cash planning
Board
Forecast Risk Resource allocation
GDPM NEXT30 Brussel, 15 October 2015
37 | 39
5.
What are the deliverables? Budget vs. actual on milestone level, project and program Time registration for invoice checking Progress reports Resource allocation reports Financial cash planning