Major Tube Regeneration Simon Newton Head of Engineering, LU Stations & Crossrail Programme. 8 October 2015

Major Tube Regeneration Simon Newton Head of Engineering, LU Stations & Crossrail Programme 8 October 2015        1.3 billi...
Author: Terence Hunt
3 downloads 0 Views 3MB Size
Major Tube Regeneration Simon Newton Head of Engineering, LU Stations & Crossrail Programme

8 October 2015

       1.3 billion passengers

year

a

TfL Rail & Underground Network • 5 modes • 15 lines • Over 430 stations • Over 1300 km of track

Growth

Accelerating passenger growth

1,300,000,000 passenger journeys

?

By 2026, 30 Central London Stations will experience crowding greater than 4ppsm A rising proportion, currently 53% of journey time, is spent in stations rather than on trains

Peak Congestion (2031)

London Underground and Rail priorities 1. Reliability & Safety 2. Capacity from the current network 3. Capacity from growing the network 4. Transforming customer service Underpinned by:

Efficiency

People

Technology

Over the next 9 years:

Renew and replace core assets

c.280kms of track replaced & over 250 points and crossing units renewed

200 plus civils renewal projects

Station stabilisation works at c.150 LU stations

c.350 lift and escalators refurbishments / replacements

Reliability & Safety

Future Capital Programmes Line Modernisation

Station Upgrades

S-Stock Trains

World Class Capacity

Re-signalling the SSR

Northern line Upgrade

Line Upgrades Capacity from the current network

Capacity from the current network

Station Upgrades Bank

Bond Street

Victoria

Tottenham Court Rd

Vauxhall

Finsbury Park

Camden Town

Holborn

Elephant & Castle

Estimated Final Cost c£250m New station entrance, 3 new escalators to ticket hall, new interchange passageways Start on Site c2019 Completion c2024

Future Station Capacity New Entrance at Procter Street

Estimated Final Cost c£450m Up to 9 new Escalators, new lifts & Stepinterchange Free Access tunnels and Interchange

New passageways

Start on Site c2020 Completion c2026

New concourse area using disused Platform 5 (Aldwych Branch Line)

Additional escalator capacity to Piccadilly Line

Existing narrow passageways widened

Engineering Challenges •  Working on an Operational Railway: - Limited Engineering Hours/Possessions - Need for Staging & Temporary Works -  Sub Surface Railway Regulations (Fire Precautions) -  Safeguarding operational resilience during construction •  Working with 3rd Parties: -  Utilities/Ground conditions (Tunnelling) •  Site Logistics -  Traffic Management, Spoil removal & Plant set up •  Design Management & Co-ordination

16 October 2006

15

15

BOND STREET STATION

Crossrail 2

West Anglia

Northern line extension

Crossrail

Growing the Network Capacity from growing the network

Customer expectations are rising Value for money

Transforming Customer Service

Fewer closures, more services and greater efficiency Large capital programme

Fewer closures

Reducing £ unit rates

1.6 BN More service

Transforming Customer Service

Less engineering time

Station Upgrades utilises “Stake” to engage directly at trade contractor level avoiding the need for tier 1 and 2 contractors.

CLIENT Contract

PPP Contract

TIER 1 Contract

TIER 2 Contract

WORKFORCE

‘       

Technology & Innovation WIR TEC ELESS Build Off-site HNO LOG Y Sustainab ility t n BIM e re u g t i l c l u r e t t s In Infra t r g a n i m S d n d Wayfi Variable Spee Low s r o t Product Standardisation la a c er Ca Es rbon N O I T I D N O C E LED REMOT LU Design Idiom G N Ligh MONITORI ting Digit al Ra ilwa y Modular Design Innovative Contractor Engagement Future Concept of Operation

“Create and Deliver Value ”

Offsite Opportunities •  More Prescriptive Approach –  Common architectural products and finishes –  Mock Up facility –  LU Product Register & Category Management

•  Review of LU Station Design Standards –  “Fit for the Future” –  LU Design Idiom

Innovative Contractor Engagement (ICE) •  •  •  • 

Pre-qualify innovators A structured, but protected, dialogue phase LU acknowledge the cost of dialogue Requirements statement and bid evaluated against business output •  Orthodox ITT/ Target cost Contract •  LU share value of innovative ideas from unsuccessful bidders

You don’t winning ideas Ideas may get be more valuable until ideas canpost win contract bids to the Contractor,

Excellent Outcome

Collaborate to Innovate (C2i)         •  The Integrator works with the Owner: – to innovate around requirements to develop the operational solution – to ensure benefits realisation •  Value is maximised through early engagement in solution development and the consents process •  The Integrator is directly rewarded on these outcomes •  We’ve seen such relationships work as DELIVERY PARTNERS

Owner Operator

Operational Solution

Resource Integration

Benefits Realisation

 

R&U Business Plan

2013/14

4 new trams, platform/ track works

Vauxhall station upgrade

Northern Line Upgrade

Victoria line capacity enhancement

2014/15

Paddington (H&C) upgrade

2015/16

2016/17

Overground fifth car

DLR Double Tracking Phase 1

Victoria station upgrade

Gospel Oak – Barking electrification

Bank (W&C) entrance

PLUS...Constant programme of stable investment for core asset renewal...

DLR Station Capacity

Bond St upgrade

2017/18

Jubilee line capacity enhancement

2018/19

Tottenham Court Road upgrade

Elephant & Castle upgrade

2019/20

Finsbury Park upgrade

Sub-surface railway upgrade

Croxley Rail Link

Northern Line Upgrade 2

Holborn station upgrade

Bank station upgrade

2020/21

2021/22

Northern line extension

Crossrail full service

DLR Additional Vehicles

2022/23

Start work on Camden Town

Deep Tube upgrades begin (approx)

Track

Escalators

Trains

Replacing c. 40km p.a.

Replacing and renewing c. 25 p.a.

Replacing c. 20 p.a.

TfL Rail & Underground Network by 2021 (including Crossrail and Emirates Airline)

• 6 modes • 16 lines • Over 440 stations • Over 1300 km of track

THANK YOU