MAJOR PROJECTS AND NEWS ITEMS

P.O. Box 1099 Missouri City, Texas 77459-1099 3507 Plum Brook Ln., Missouri City, TX 77459 (281) 499-3131 FAX (281) 499-3223 E-mail: pipelineintellig...
Author: Guest
2 downloads 0 Views 7MB Size
P.O. Box 1099 Missouri City, Texas 77459-1099 3507 Plum Brook Ln., Missouri City, TX 77459

(281) 499-3131 FAX (281) 499-3223 E-mail: [email protected] www.pipelineintelligence.com

Volume XXVI, Number 26 September 15, 2015

MAJOR PROJECTS AND NEWS ITEMS INDUSTRY NEWS (Norman, OK) – Henkels & McCoy, Inc. (H&M) is pleased to announce the promotion of Richard Hill to Vice President, Major Pipelines. In his new role, Richard will be responsible for the operations management of H&M’s Major Pipelines division based in Norman, Oklahoma. Specifically, he will oversee the development, direction, and management of operational development plans, client development programs, labor and talent management initiatives, operations communications, and safety leadership. Richard has over 40 years of pipeline industry experience, with the vast majority of his career spent at Henkels & McCoy. Most recently, Richard served as H&M’s Pipeline Services Business Line Director overseeing the delivery of pipeline projects for customers in the Northeast. INDUSTRY NEWS (Houston, TX) – The Access Northeast pipeline project plans to add another 27-mile natural gas line that starts in Milford and heads northwest to the Worcester area. The new line, referred to as the West Boylston Lateral, would run through Milford, Upton, Grafton, Sutton, Shrewsbury, Boylston and West Boylston. The 16-inch pipeline would connect in Milford to a 21-mile line called the Q-1 Loop LINK, slated to run through Franklin, Medway, Bellingham, Norfolk, Millis, Walpole, Sharon, Canton and Stoughton. Access Northeast is backed by Spectra Energy, Eversource Energy, and National Grid. The two lines are significant pieces in Access Northeast’s overarching goal of adding 119 miles of gas pipeline infrastructure to existing Algonquin Gas Transmission and Maritime pipelines in New York, Connecticut, Rhode Island and Massachusetts. The estimated $3 billion project would allow

for roughly 1 billion cubic feet of natural gas per day. It would connect to up to 70 percent of New England’s power plants. It's billed as a way to lower electricity rates as early as winter 2018, according to a Spectra Energy fact sheet; that idea isn't without political contention. Industry News-The Woodlands, TX-Delaware Basin Express, LLC, a wholly owned subsidiary of Western Gas Partners, LP, is holding a non-binding Open Season to gauge interest in a new pipeline project serving portions of Reeves, Loving and Ward Counties, TX. The pipeline will provide transportation service from a new connection at the tailgate of the Ramsey Gas Processing Plant, located in Northern Reeves County, to new connections with intrastate pipelines located in the Waha area near Coyanosa, TX. Additional receipt connections at the tailgate of the MiVida Gas Processing Plant and Bone Spring Gas Processing Plant are also being contemplated. The initial capacity of the pipeline will be approximately 600,000 Dth/d of residue gas to the Waha Hub area, and could be increased up to 1,600,000 Dth/d with the addition of compression. The Open Season commenced on Tuesday September 1, 2015, and concludes at 4:00 PM CST on Wednesday September 30. The target in-service date for the project is the fourth quarter 2016. The target in-service date is an estimate and may change dependent upon the necessary facilities and regulatory requirements. The project is anticipated to include 53 miles of 36” and 26 miles of 42” pipe. Additionally, compression horsepower will be added to the extent needed to deliver gas in the Waha area at a maximum pressure of 1440 psig.

Continued on page 51

New Listings Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Algonquin Gas Transmission Houston, TX

27 mi.

16”

“Access Northeast Project” will run from Grafton, MA to near Boylston, MA.

In planning stages Construction could be 2018

Magellan Midstream Tulsa, OK

50 mi.

20”

“Jet Fuel” project will run from Fort Smith, AR to near North Little Rock, AR. Project will also use 159 mi. of existing pipe. “See Industry News.”

Southern Pipeline Construction Searcy, AR

Millennium Pipeline Pearl River, NY

7.8 mi.

16”

“Valley Lateral Project” to be located in Orange county, NY.

Construction Summer 2016

PG&E Portland, OR

3 mi.

24”

Take up & relay located near Lodi, CA.

Snelson Companies Sedro Wooley, CA

Western Gas Partners The Woodlands, TX (sub of Anadarko)

53 mi. 26 mi.

36” 42”

Project to be located in Reeves, Loving & Ward counties, TX. “See Industry News.”

Open Season ends 09/30/15 Construction planned for late 2016

Pipeline Intelligence Report, September 15, 2015 - 2

Updated Listings (A bold listing indicates a change) Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

AGL Resources Atlanta, GA Tallgrass Development Leawood, KS

140 mi.

36” or 42”

“Prairie State Pipeline” will run from Douglas county, IL to the “Chicago Market Center.”

Construction could be 2017

AGL Resources Atlanta, GA Williams-Transco Houston, TX

111 mi.

16”, 20”, 24” & 30”

The Dalton Expansion Project will begin at Station 115 in Murray county, GA and end near Holmesville, MS. Also includes new compressor facility in Carroll county, GA.

Filed w/FERC March 2015 Construction could be 3rd quarter 2016

Algonquin Gas Transmission Houston, TX

1.2 mi.

16”

“Salem Lateral” project to be located near Salem, MA.

Awaiting FERC approval Construction Summer 2015

Algonquin Gas Transmission Houston, TX

20.1 9.1 1.3 2.0 5.1

42” 16” 12” 36” 16” & 24”

“AIM” take up & relay & looping project would start north of Greeneville section of Norwich and continue SE to the RI border. Will include 1.2 mi. directional drill of Hudson River.

Henkels & McCoy Norman, OK Construction 2016

American Midstream Partners Denver, CO

50 mi.

Undet.

Crude oil gathering & transportation system located in McKenzie co., ND.

Open season ended June 22, 2015

Pipeline Intelligence Report, September 15, 2015 - 3

Pipeline Intelligence Report, May 1, 2015 - 4

INDUSTRY NEWS (Tulsa, OK) – A spokesman with Magellan Midstream Partners said the Tulsa-based pipeline company is in the final stages of permitting and acquiring easements for a distribution system that is expected to bring some 75,000 barrels of refined petroleum products from Fort Smith into the Little Rock market. This was announced after Houston-based Spectra Energy received approval from the Federal Energy Regulatory Commission (FERC) on June 1 to “abandon by sale” some 159 miles of a once thriving natural gas pipeline system that stretches across the Fayetteville Shale, overriding concerns from Conway Corp. and Central Arkansas landowners that the aging transmission line would later be used to transport petroleum products. After receiving strong interest in the project, the lynchpin of Magellan’s proposal was to significantly boost the level of gasoline, diesel fuel and jet fuel that enters the Little Rock market, providing access to refined products from MidContinent and Gulf Coast refineries via Magellan’s Fort Smith terminal and extensive refined petroleum products pipeline system. Magellan spokesman Bruce Heine recently said the project is scheduled to be complete and operational in mid-2016. “The project includes a combination of new pipeline and the utilization of an existing pipeline segment which is owned by an affiliate of Spectra Energy,” said Heine, director of government and media affairs for the Master Limited Partnership (MLP). “We will be constructing approximately 12 miles of new pipeline to connect our Fort Smith petroleum distribution terminal to the existing pipeline. In addition, we will add 38 miles of new pipeline to connect the existing pipeline (near Searcy) to distribution facilities in North Little Rock.” INDUSTRY NEWS (Tulsa, OK) – Sawyer Manufacturing Company is proud to introduce the Grinder Holder, the newest addition to an exceptional line of pipeline and welding products. The Grinder Holder keeps tools visible and conveniently within reach yet safely out of the way. It holds two grinders, a Rheostat box and additional tools in one compact, convenient location and incorporates durable steel construction with a corrosion-resistant powder coating. The Grinder Holder features two mounting options; it can easily mount to all major manufacturer’s pipe stands or be affixed to either flat surfaces or pipe 3 inches and larger with four powerful rotating magnets. An easy-carry handle provides the user extreme portability and an additional side-mounted magnet allows frequently used tools to be secured to the frame. Sawyer’s Grinder Holder keeps grinders and tools close at hand while being easily transferable to the next weld. It is now in full-scale production at Sawyer's Tulsa facility.

Pipeline Intelligence Report, September 15, 2015 - 5

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

American Midstream Partners Denver, CO

52 mi.

12”

“Midla-Natchez” take up & relay an old 8” line to run from near Winnsboro, LA to near Natchez, MS.

Will file w/FERC Summer 2015 Construction Spring/Summer 2016

Ascension Pipeline Company Dallas, TX (EnLink & Marathon)

30 mi.

Undet.

Project located near Garyville, LA.

Construction planned for late 2016

Atlanta Gas Light Atlanta, GA

17 mi.

16”

“Newman Bypass Project” will be located near Coweta, GA.

Construction Fall 2015

BakkenLink Pipeline Houston, TX

37 mi.

16”

Project runs from Dry Creek to Beaver Lodge near Tioga, ND.

Awaiting the BLM environmental assessment.

Blueknight Energy Partners Tulsa, OK

160 mi.

16”

“Knight Warrior Pipeline” project will run from Madisonville, TX to the Horton Ship Channel.

Construction late 2015 early 2016

Cheniere Energy Houston, TX

23 mi.

48”

Project located near Corpus Christi, TX.

Construction could be Summer 2016

Columbia Pipeline Group Houston, TX

150 mi.

36”

“Mountaineer XPress” will be located in the Appalachia with deliveries near Leach, KY.

Construction could be mid 2017

Pipeline Intelligence Report, September 15, 2015 - 6

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Columbia Pipeline Group Houston, TX

7 mi.

24”, 36”, 42”

“Gulf Xpress Project” to be located near Ceredo, WV.

Construction could be 1st or 2nd quarter 2017

Columbia Pipeline Group Houston, TX

34 mi.

30”, 36”

“Cameron Access Project” will be located in Cameron Parish, LA and will include a new compressor station.

Awaiting FERC approval Construction could be late 2016

Columbia Pipeline Group Houston, TX

5.1 mi.

24”

Utica Access” project will be located in Kanawha county, WV. Also will include upgrades to existing compressor stations.

Filed w/FERC January 2015 Construction could be late 2015

Denbury Resources Plano, TX

87 mi.

36”

“Conroe Lateral-Green Project” located near Conroe, TX.

Construction could be Summer 2016

Dominion Transmission Richmond, VA

39 mi.

30” & 36”

“Supply Header Project” consists of 2 loops located in Westmoreland county, PA & Harrison, Doddridge, Tyler & Wetzel counties WV.

Will file w/FERC Summer 2015 Construction could be 2016-17

Dominion Transmission Duke Energy Piedmont Natural Gas AGL Resources

560 mi.

20”, 36” & 42”

“Atlantic Coast Pipeline” would run from Harrison county, WV to near Lumberton, NC.

Will file w/FERC Summer 2015 Construction could be 2017-2018

Pipeline Intelligence Report, September 15, 2015 - 7

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Dominion Carolina Gas Richmond, VA

28 mi.

8”

Project will begin at the DAK Americas facility in Calhoun county, NC.

Construction Spring 2016

DTE Energy - Ann Arbor, MI Enbridge Energy - Houston, TX Spectra Energy - Houston, TX

250 mi.

36” or 42”

“Nexus Gas Transmission System” to run from the Utica Shale to markets in the Midwest & Eastern Canada.

Delayed construction could be 2017

Downeast Pipeline, LLC Robbinston, ME

30 mi.

30”

Project located near Baileyville, ME.

Still awaiting approval. Could be 2016 or 2017

Dow Pipeline Company Houston, TX

140 mi.

Undet.

Project would run from Freeport, TX to Mont Belvieu, TX.

Wood Group Mustang - engr. Houston, TX - Could be mid 2016

Eastern Shore Natural Gas Camden, DE

10 mi.

16”

“Reliability Project System” located in New Castle, Kent & Sussex co., DE.

Construction mid 2016

East Tennessee Natural Gas Houston, TX

10 mi.

12”

“Loudon Expansion Project” will be located in Bradley & Loudon co., TN.

Summer 2016 Construction

Enbridge Energy Houston, TX

338 mi.

36”

“Line 3” is a take up & relay that will run from Neche, ND to the Superior terminal.

Construction could be late 2016

Pipeline Intelligence Report, September 15, 2015 - 8

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Enbridge Energy Houston, TX

616 mi.

24”

“Sandpiper Pipeline” will run from near Beaver Lodge south of Tioga, ND to Superior, WI.

Construction will be 2016

Energy Transfer Houston, TX

342 mi.

42”

Two lines, one runs from near Pecos, TX to Presidio, TX. The other line runs from South of El Paso, TX to Pecos, TX. Project to begin in early 2016

Pumpco, Inc. Giddings, TX

Energy Transfer Houston, TX

100 mi.

24” & 30”

“The Revolution Pipeline” will begin in Butler county, PA and extend to the Revolution Plant in Western PA.

Construction could be 2017

Energy Transfer Houston, TX

143 mi.

42”

“Trans Pecos Pipeline” will run from the Permian Basin near Waha, TX to the border at Presidio, TX & Ojenaga, Mexico.

Construction could be late 2015 or early 2016

Energy Transfer Houston, TX

954 mi.

30”

“Dakota Access Pipeline” to run from the Bakken/3 Forks production area to Patoka, IL.

Spd. 1-3 Michels Corp. Brownsville, WI Spd. 4-6 Precision Pipeline Eau Claire, WI

Pipeline Intelligence Report, September 15, 2015 - 9

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Energy Transfer Houston, TX

180 mi.

30”

“Dakota Access Pipeline” Spds. 7 & 8 located on the Southern Part of the line. This is part of the 954 mi. already listed.

Awards pending

Enterprise Products Houston, TX

65 mi.

10”

RGP Pipeline and rail terminal expansion will begin near Sorrento, LA and end near Breaux Bridge, LA.

Construction late 2016 or early 2017

Enterprise Products Houston, TX

33 mi.

Undet.

“North Dean Pipeline” is 149 mi. conversion, 33 mi. expansion and will be located in Calhoun county, TX near Seadrift, TX.

Construction late 2016 or early 2017

Enterprise Products Houston, TX

75 mi.

12”

“South Eddy” project will run from near Hobbs, NM to near Seminole, TX.

Was rebid Bids due late September 2015

Enterprise Products Houston, TX

60 mi.

30” or 36”

“Panola Pipeline Project will run from near Carthage, TX to Mont Belvieu, TX.

Willbros Construction Houston, TX

Enterprise Products Houston, TX

416 mi.

24”

Pipeline will run from Midland, TX to Sealy, TX.

Construction to begin 2016

Enterprise Products - Houston, TX Plains All American - Houston, TX

55 mi.

Undet.

Gathering & trunkline systems to built in Karnes & Live Oak county, TX.

Construction Summer 2015

Pipeline Intelligence Report, September 15, 2015 - 10

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Enterprise Products Houston, TX Plains All American Houston, TX

70 mi.

20”

Project will run from Three Rivers, TX to Corpus Christi, TX.

Construction Summer 2015

EQT Midstream Pittsburgh, PA

49.5 mi.

24”, 30”

“Ohio Valley Connector” project will run from Southeastern OH to Northwestern WV. Also includes two compressor stations with a combined 36,000 of HP.

Filed w/FERC December 2014 Construction could be Summer 2015

EQT Midstream Pittsburgh PA

32 mi.

20” & 24”

“Maco Pipeline”Natural Gas Header System located in Southwestern PA.

Construction 3rd Quarter 2016

EQT Pittsburgh, PA NextEra Miami, FL

330 mi.

42”

“Mountain Valley Pipeline” will run from Equitrans transmission system inWV to delivery points in Pittslavania county, VA.

Construction mid 2018

EQT Midstream Pittsburgh, PA

4 mi. 5 mi.

30” 30”

Project located in Greene, Allegheny & Washington counties, PA.

Construction could be late 2016 or early 2017

ET Rover (Energy Transfer) Dallas, TX

25 mi. 5 mi.

42” 24”

“ET Rover Lateral” located along the mainline of the planned 710 mi.

Latex Construction Conyers, GA

Pipeline Intelligence Report, September 15, 2015 - 11

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

ET Rover (Energy Transfer) Dallas, TX

710 mi.

24”, 30”, 36” & 42”

“ET Rover Pipeline” will run from the Marcellus and Utica Shale gas formations in PA, WV, MI & OH to end at a terminal in Ontario, Can.

Sheehan Pipe Line - Tulsa, OK US Pipeline - Houston, TX Michels Corp.- Brownsville, WI Precision P/L - Eau Claire, WI

Fairway Energy Partners Houston, TX

21 mi.

24”

“Pierce Junction Crude Oil” storage facility will be located near Houston TX.

Construction late 2016

Fidelity Exploration & Production Co. Denver, CO

24 mi.

12”

“Paradox Basin Project” will be located near Moab, UT and will tie into the Dead Horse Lateral.

BLM approved Delayed due to an appeal

Florida Southeast Connection, LLC Juno Beach, FL

77 mi. 49 mi.

36” 30”

“Florida Southeast Connection Project” to be located in Osceola, Okeechobee, Polk, St. Lucie & Martin counties, FL in two phases.

Rockford Corp. Hillsboro, OR Construction will be 2016

Gulf South Houston, TX

64 mi.

36”

Coastal Bend Header Project” to be located in Wharton & Brazoria counties, TX. Will also include 3 compressor stations and 7 meter stations.

Construction could be early 2017

Howard Midstream San Antonio, TX

200 mi.

30”

“The Nueva Era Pipeline” will begin in Webb county, TX and run to Escobedo, Mexico.

Construction late 2016 or early 2017

Pipeline Intelligence Report, September 15, 2015 - 12

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Kinder Morgan Houston, TX

360 mi.

Undet.

“Palmetto Project” will begin near Belton, SC & end near Jacksonville, FL.

Construction could be early 2017

Kinder Morgan Houston, TX

240 mi.

12”

“UTOPIA West & East” pipelines would run from Harrison county, OH to near Riga, MI from there it would run to near Windsor, ON, Canada. Added another line of 240 mi. 12”.

Construction could be late 2016

Kinder Morgan Houston, TX

176 mi.

24”

The “Trans Pecos Pipeline” will run from Ward county, TX and end in Hudspeth county, TX.

Construction mid 2016

Magellan Midstream Houston, TX TransCanada Corp. Houston, TX

9 mi.

24”

Project located east of Houston, TX.

Construction late 2015

Magellan Midstream Partners Tulsa, OK Saddle Butte Pipeline Durango, CO

600 mi.

20”

“Saddlehorn Pipeline” will run from Niobrara Shale near Platteville, CO to near Cushing, OK.

MPG Pipeline Contractors Houston, TX Sterling Construction Rifle, CO Progressive Pipeline Meridian, MS

Pipeline Intelligence Report, September 15, 2015 - 13

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Marathon Petroleum Houston, TX

49 mi.

16”

“Cornerstone” will run from near Cadiz, OH to Leesville, OH. Located in the Utica Shale.

Construction could be 2016

Meadowlark Midstream, LLC Dallas, TX

47 mi.

Undet.

Pipeline to be located in Burke county, ND.

Construction could be late Summer 2015

Medallion Pipeline Company Irving, TX

55 mi.

Undet.

“The Santa Rita Lateral” will be located in Reagan county, TX.

Construction early 2016

Meritage Midstream Services Denver, CO

140 mi.

30” or 36”

Project located near Cheyenne, WY and will tie into the Overland Pass Pipeline.

Construction Summer 2015

National Fuel Gas Supply Williamsville, NY

97 mi.

24”

“Northern Access 2016 Project” will run from Sergant Township, PA to Elma, NY. Also will include 2,500 HP additional compression.

Construction to begin 1st quarter 2016

Navigator Energy Services Dallas, TX

34 mi.

16”

“Big Spring Gateway Project Phase II” to be located near Big Spring, TX.

Construction late Summer 2015

Net Midstream Houston, TX

25 mi.

12”

Project located near Corpus Christi, TX.

Sunland Construction Eunice, LA

Pipeline Intelligence Report, September 15, 2015 - 14

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

New Jersey Natural Gas Wall, NJ

28 mi.

30”

“Southern Reliability Line” would run from Chesterfield Township, NJ to near Manchester Township, NJ.

Construction to begin Fall 2015

NGL Energy - Tulsa, OK Rimrock Midstream - Plano, TX

550 mi.

20”

“Grand Mesa Pipeline Project” will run from Weld co, CO to Cushing, OK.

Construction 2nd Quarter 2016

Northern Border Pipeline Houston, TX

64 mi.

16”

“Bakken Header Supply Lateral” will be located in Northwestern ND.

Construction could be 2017

Northwest P/L - Salt Lake City, UT Veresen, Inc. - Calgary, Alberta

232 mi.

36”

“The Pacific Connector” project starts near Jordan Cove, OR & runs to Marling, OR SE of Klamath Falls, OR.

Construction late 2016

NRG Ohio Pipeline Co, LLC Princeton, NJ

20 mi.

24”

Converting the coal-fired Avon Lake power plant to natural gas. Will run from plant to a Dominion or Columbia gas line.

Construction will be late Summer 2015

Oneok Tulsa, OK

7.7 mi.

16”

Project located near Casper, WY.

Construction Summer 2015

Oregon Pipeline, LLC Warrenton, OR

85 mi.

36”

Would begin near Warrenton, OR and end near Woodland, WA and tie into an existing Williams line.

Delayed Could be 2017

Pipeline Intelligence Report, September 15, 2015 - 15

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Paiute Pipeline Co. Las Vegas, NV

35 mi.

8”

Project will be located near Elko, NV. This line will tie into the Ruby Pipeline.

BLM approved

Paradigm Midstream - Dallas TX Phillips 66 - Houston, TX

78 mi.

16” & 20”

“Sacagawea Pipeline” project would run from McKenzie co. to Mountrail co., ND.

Awarded in error Awards pending

Pembina Pipeline Calgary, Alberta

47 mi.

8”

Project located near Williston, ND.

Tomahawk Pipeline Sheridan, WY

Penn East Pipeline Co. Wyomissing, PA

105 mi.

36”

Project will run from Wilkes-Barre, PA to Trenton, NJ.

Construction could be 2017

Piedmont Natural Gas Charlotte, NC

9.5 mi.

30”

Project located near Charlotte, NC.

Awards pending

Pilgrim Pipeline Palm Coast, FL

122 mi.

Undet.

Line will run from near Albany, NY to the New York Harbour.

Petersen Engineering (engr.) Indianapolis, IN (Const. 2016)

Plains All American Houston, TX

60 mi.

16”

“State Line” will run from Culberson county to Wink, TX.

Construction early 2016

Plains All American Pipeline Houston, TX

9.5 mi.

8”

Project will be located near Lake Sakakawea, ND.

Awaiting Approval

Pipeline Intelligence Report, September 15, 2015 - 16

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Plains All American Houston, TX

32 mi.

12”

“The Avalon Extension” will be located in Loving & Culberson counties, TX.

Construction Summer 2015

Plains All American Pipeline Houston, TX Delek Logistics - Brentwood, TN

80 mi.

12”

“The Caddo Pipeline Project” will run from Longview, TX to near Shreveport, LA. 2016 start date.

Sunland Construction Eunice, LA

Plains All American Houston, TX

226 mi. 30 mi.

16” 12”

Pipeline will run from near Duncan, OK to Longview, TX.

Construction could be late 3rd quarter 2015

Plains All American Pipeline Houston, TX

440 mi.

20”

“Diamond Pipeline” will run from Cushing, OK to Memphis, TN.

Construction slated for early 2016

PSNC Raleigh, NC

25 mi.

Undet.

Pipeline would run from Franklin, NC to Wendell, NC.

Early stages Construction 2016 or 2017

Red Rock Gathering South Denver, CO

21.4 mi.

12” & 16”

“Winter Flats Pipeline Project” will be located near Grand Junction, CO.

Awaiting BLM approval Construction could be Fall 2015

Saddle Butte Pipeline, LCC Durango, CO

600 mi.

Undet.

“Rockies South Pipeline” will run from the DJ Basin in Colorado to Cushing, OK.

Construction could be mid 2016

Pipeline Intelligence Report, September 15, 2015 - 17

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Saddle Butte Pipeline LLC Durango, CO

140 mi.

Undet.

Project located in northwestern New Mexico in the San Juan Basin.

Awaiting BLM approval

Saddlehorn Pipeline Tulsa, OK

50 mi.

16”

“The Carr Extension Project” will run from Platteville, CO to Carr, CO. This is an extension of the 600 mi. 20” line to be built from Carr to Cushing.

Construction early 2016

SemGroup Tulsa, OK

34.2 mi. 35 mi. 34 mi.

24” 12” 6”

The “Maurepas Pipelines” will connect to refineries in Southern Louisiana.

Construction Sumer 2016

Sempra Energy San Diego, CA

90 mi.

36”

“North-South Project” will run from Adelanto, CA to Adelanto, CA then turn East to end near Whitewater, CA.

Construction 2016

SourceGas Golden, CO

4.6 mi.

Undet.

“Rocky Mountain Gas” take up & relay project located near Town of Eagle, CO.

Out for bids early 2016

Southern Star Central Gas P/L Owensboro, KY Next Era Energy Juno Beach, FL

250 mi.

24”

“Sooner Trails Project” will run from near Grady, OK to near Bryan, OK and will cross over into Lamar county, TX.

Will file w/FERC later Anticipate Construction 2018

Pipeline Intelligence Report, September 15, 2015 - 18

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

South Jersey Gas Folsom, NJ

22 mi.

24”

Project will run from Maurice River Township to Upper Township, NJ.

Awaiting permit approval

Spectra Energy Houston, TX NextEra Energy Juno Beach, FL

465 mi.

36”

“Sabal Trail” would run from mid Alabama thru Georgia & into Central Florida in Marion county. This would be part of the FP&L project.

Spd. 1, 4, 5 - Price Gregory Houston, TX Spd. 2 - MPG P/L - Houston, TX Spd. 3 - Troy Construction Houston, TX Spd. - 6, 7 Rockford Corp. Hillsboro, OR

Spectra Energy Houston, TX

10.9 10.4 2.6 10.1 2.2

42” 36” 36” 30” 12”

“Atlantic Bridge” will include take up & relays & new lays all located in Connecticut, New York & Massachusetts. Will also include compressor station work.

Filed w/FERC February 2015 Construction 2017

Summit Midstream, LLC The Woodlands, TX

115 mi.

Undet.

“Summit Utica” project will be located in Belmont and Monroe counties, OH. Also includes 4 compressor stations.

Construction 2015

Sunoco Logistic Partners Philadelphia, PA

40 mi.

20”

SunVit P/L will run from Midland, TX to Garden City, TX & will connect to the Express II line when built.

In early stages Could be mid 2015

Pipeline Intelligence Report, September 15, 2015 - 19

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Sunoco Logistics Philadelphia, PA

350 mi. 350 mi.

16” 20”

“The Mariner East 2” project will move propane, butane & ethane. Will run through Ohio, WV and western PA.

Awaiting approval Could be constructed in early 2016

Sunoco Logistics Philadelphia, PA

125 mi.

Undet.

Delaware Basin Extension will run from Loving, TX to Lee, NM turn & go east to near Midland, TX.

Construction could be late 2015 or early 2016

Tall Oak Midstream Oklahoma City, OK

20 mi.

Undet.

“Stack” system will be located east of Okarache, OK.

Construction late Summer 2015

Tennessee Gas Pipeline Co. Houston, TX

7 mi.

36”

“Triad Expansion Project” to be located near Lenox & Clifford Townships, PA.

Construction could be Spring 2017

Tennessee Gas Pipeline Houston, TX

30 mi.

30” or 36”

“Southern Indiana Market Lateral” will begin near Robards, KY and end near Mount Vernon, IN.

Construction could be late 2015 or early 2016

Tennessee Gas Pipeline Houston, TX

13.26 mi.

24” & 36”

“Connecticut Expansion Project” is a looping project located in Connecticut.

Awaiting FERC approval Construction 2015 or early 2016

Tennessee Gas Pipeline Co. Houston, TX

8.2 mi.

36”

“Susquehanna West Project” will be a looping project located in Tioga co., PA.

Filed w/FERC April 2015 Const. late 2016 or early 2017

Pipeline Intelligence Report, September 15, 2015 - 20

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Tennessee Gas Pipeline Houston, TX

7.6 mi.

30” or 36”

The Abandonment & Capacity Restoration Project (ACR) will be located in Carter & Lewis counties, KY. Also includes a new compressor station in Mahoning county. 4 new compressors in Ohio.

Early stages No timetable yet

Tennessee Gas Pipeline Houston, TX

167 mi.

36”

“Northeast Energy Direct Project” to upgrade its existing p/l system within NY, MA, CT & NH to run from Wright, NY to Dracut, MA.

Construction could be late 2016 or early 2017

Texas Eastern Transmission Houston, TX

35 mi.

20” & 24”

The SOLA project would be located near Assumption Parish, LA.

Construction late 2015 or early 2016

Texas Gas Transmission Owensboro, KY

225 mi.

24”

“The Western Kentucky Lateral Project” located in Muhlenberg co., KY.

Construction could be late 2015 or early 2016

Texas Gas Transmission Owensboro, KY

30 mi.

20”

“The Southern Indiana Market Lateral Project” will run through Henderson county, KY and Posey county, IN.

Construction could be late Summer or early Fall 2015

TexStar San Antonio, TX

120 mi.

16”

Project will run from the Eaglebine formation in Walker, Madison, Grimes & Montgomery co, TX to Houston’s ship channel.

Construction will be mid 2015

Pipeline Intelligence Report, September 15, 2015 - 21

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

TransCanada Corp. Calgary, Alberta Canada

200 mi.

Undet.

The Upland Pipeline will run from near Williston, ND and end across border in Saskatchewan, Canada.

Very early stages Could be 2020

UGI Wyomissing, PA

35 mi.

20”

“Sunberry Pipeline” to run from Lycoming county to a plant near Shamokin Dam, in Snyder county, PA.

Construction could be early 2016

WBI Energy Bismark, ND

95 mi.

16”

“Wind Ridge Pipeline” will run from Ashley, ND to near Spiritwood, ND. Will also include a meter station.

Filed w/FERC February 2015 Construction could be Summer 2016

WBI Energy Glendive, MT

95 mi.

16”

“Wind Ridge Pipeline” will run from near Zeeland, ND to Spiritwood, ND.

Construction planned for late 2015 or early 2016

Western Refining El Paso, TX

40 mi.

12”

“Delaware Basin” project to be located in Reeves & Winkler counties, TX.

Construction mid 2015

WGL Midstream - Washington DC Williams-Transco - Houston, TX

177 mi.

Undet.

“Central Penn Line” will run from Susquehanna co. to Lancaster co. PA.

Early stages Construction mid 2017

Williams - Transco Houston, TX

8 mi.

36”

“The Gulf Trace” project will tie into the new Sabine Pass LNG facility located near Cameron Parrish, LA.

Construction could be 2016

Pipeline Intelligence Report, September 15, 2015 - 22

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Williams - Transco Houston, TX

4.6 mi. 15.5 mi.

48” 42”

“Hillabee Expansion” Phase I will consist of 4 loops located in Autauga, Chilton, Coosa & Tallaposia co., AL. Starts early 2016

Price Gregory Houston, TX

Williams - Northwest Pipeline Salt Lake City, UT

136 mi.

36”

“The Washington Expansion Project” will begin in Whatcom co, WA & end near Woodland, WA.

Construction could be 2016 or 2017

Wolverine Pipe Line Co. Portage, MI

35 mi.

Undet.

“The Detroit Metro Access Project” will run from Freedom, MI to Romulus, MI.

Open Season Ended April 8, 2015

Pipeline Intelligence Report, September 15, 2015 - 23

FIRST CLASS

First Class Mail U.S. Postage PAID Sugarland, TX Permit No. 345

Order Form

Pipeline Intelligence Report – Master subscription $300 per year for 24 issues. Additional subscriptions for same Company available to any address $150 per year for 24 issues. 2013 2015 Pipeline Intelligence Directory $75 plus S & H $60 for each additional copy. 2015 Pipeline Intelligence Directory CD in Excel format: Pipeline Company, Contractor or Supplier Section – $150 per 2013 section or $400 for all three.

** Tax: All orders in Texas are subject to 8.25 % state sales tax. Method of payment: A check for the total amount is enclosed. Charge to my: MasterCard Visa Exp. Date: Mo.

Card Number

Yr.

Signature Bill me. Purchase Order No:

(if required) Title

Name Company Address City

State

Zip

Phone number (

)

----------------------------------------------------------------------------------------------------------------------------------------------------------------Pipeline Intelligence Report (PIR) is published 24 times per year by Pipeline Intelligence Company, PO Box 1099, Missouri City, TX 77459-1099, phone (281) 499-3131. Copyright 1990 by Pipeline Intelligence Co. All rights reserved. Subscription rate is $300 per year; mailed in U.S. Texas residents please add 8.25% sales tax. PIR reports on construction projects contemplated by hydrocarbon transporters. Since this information is received from others, PIR cannot guarantee the accuracy of any information. Postmaster: Please send address changes to Pipeline Intelligence Report, PO Box 1099, Missouri City, TX 77459-1099.

Pipeline Intelligence Report, May 15, 2013 – 24 Pipeline Intelligence Report, September 15, 2015 - 24