Implementation Status & Results Indonesia Indonesia Power Transmission Development Project (P117323)

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Report No: ISR8339 The World Bank Implementation Status & Results I...
Author: Derek Hall
2 downloads 3 Views 28KB Size
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy

Report No: ISR8339

The World Bank Implementation Status & Results Indonesia Indonesia Power Transmission Development Project (P117323) Operation Name: Indonesia Power Transmission Development Project

Project Stage:

Implementation

Seq.No: 3

Status: ARCHIVED

Archive Date:

01-Nov-2012

(P117323) Product Line: IBRD/IDA

Country: Indonesia

Approval FY:

Region: EAST ASIA AND PACIFIC

Lending Instrument: Specific Investment Loan

2011

Implementing Agency(ies):

Key Dates Board Approval Date

08-Jul-2010

Original Closing Date 31-Dec-2015

Planned Mid Term Review Date 02-Dec-2013

Effectiveness Date

30-May-2011

Revised Closing Date 31-Dec-2015

Actual Mid Term Review Date

Last Archived ISR Date 30-Jun-2012

Project Development Objectives Project Development Objective (from Project Appraisal Document)

The development objective of the project is to assist the Borrower to meet growing electricity demand and improve the reliability of electricity supply in Java and SouthCentral Sumatra by strengthening the power transmission system. Has the Project Development Objective been changed since Board Approval of the Project?

Yes

No

losure Authorized Public Disclosure Authorized Public Disclosure Copy

Component(s) Component Name

Component Cost

Java-Bali Transmission Substation Expansion and Construction.

103.50

South-Central Sumatra Transmission Substation Upgrading and Expansion

150.60

Overall Ratings Previous Rating

Current Rating

Progress towards achievement of PDO

Moderately Satisfactory

Satisfactory

Overall Implementation Progress (IP)

Moderately Unsatisfactory

Moderately Satisfactory

Overall Risk Rating

Implementation Status Overview The project has made a good progress. Although it has been behind the original schedule due to delay in procurement process, the progress toward the development objective has improved substantively with equipment manufacturing and physical construction for all project investments being launched. Locations

Page 1 of 5

Report No: ISR8339

Public Disclosure Copy

Public Disclosure Copy

The World Bank

Country

First Administrative Division

Location

Indonesia

Not Entered

Kotamadya Yogyakarta

Indonesia

Not Entered

Wonosobo

Indonesia

Not Entered

Ungaran

Indonesia

Not Entered

Kotamadya Surakarta

Indonesia

Not Entered

Provinsi Sumatera Barat

Indonesia

Not Entered

Semarang

Indonesia

Not Entered

Kabupaten Sawahlunto Sijunjung

Indonesia

Not Entered

Kota Prabumulih

Indonesia

Not Entered

Pekalongan

Indonesia

Not Entered

Pedan

Indonesia

Not Entered

Kotamadya Payakumbuh

Indonesia

Not Entered

Pati

Indonesia

Not Entered

Panongan

Indonesia

Not Entered

Kabupaten Musi Hulu Rawas

Indonesia

Not Entered

Kabupaten Merangin

Indonesia

Not Entered

Lubuklinggau

Indonesia

Not Entered

Lahat

Indonesia

Not Entered

Krian

Indonesia

Not Entered

Kabupaten Klaten

Indonesia

Not Entered

Provinsi Jawa Tengah

Indonesia

Not Entered

Gombong

Indonesia

Not Entered

Depok

Indonesia

Not Entered

Cilacap

Indonesia

Not Entered

Bumiayu

Indonesia

Not Entered

Blora

Planned

Actual

Page 2 of 5

Report No: ISR8339

Public Disclosure Copy

The World Bank

Country

First Administrative Division

Location

Indonesia

Not Entered

Baturaja

Indonesia

Not Entered

Bangko

Indonesia

Not Entered

Balaraja

Indonesia

Not Entered

Kabupaten Magelang

Indonesia

Not Entered

Secang

Indonesia

Not Entered

Kotamadya Salatiga

Indonesia

Not Entered

Desa Majenang

Indonesia

Not Entered

Bayeman

Indonesia

Not Entered

Desa Tenggeles

Indonesia

Not Entered

Bungo Regency

Indonesia

Not Entered

Kiliranjao

Indonesia

Not Entered

Kota Pagaralam

Actual

Planned

Results Project Development Objective Indicators Indicator Name

Public Disclosure Copy

Electricity sales in the project areas (Java)

Electricity sales in the project areas of southcentral Sumatra (GWh)

Core Unit of Measure

Number

Number

Baseline

Current

End Target

Value

50442.00

70952.00

Date

31-Dec-2009

31-Dec-2014

Comments

GWh

GWh

Value

4919.00

7770.00

Date

31-Dec-2009

31-Dec-2014

Value

2.09

2.03

Date

31-Dec-2009

31-Dec-2014

Value

3.47

2.95

Date

31-Dec-2009

31-Dec-2014

Comments

Transmission losses in Java-Bali system

Percentage

Comments

Transmission losses of the Sumatra system

Percentage

Comments

Page 3 of 5

Report No: ISR8339

The World Bank Intermediate Results Indicators

Public Disclosure Copy

Indicator Name

Core Unit of Measure

Incremental Capacity of 500/150 kV Substations in Java (MVA)

Number

Incremental Capacity of 275/150 kV Substations in Sumatra (MVA)

Number

Baseline

Current

End Target

Value

0.00

2000.00

Date

31-Dec-2009

31-Dec-2014

Value

0.00

2000.00

Date

31-Dec-2009

31-Dec-2014

Value

0.00

390.00

Date

31-Dec-2009

31-Dec-2014

Value

0.00

1350.00

Date

31-Dec-2009

31-Dec-2014

Comments

Comments

Incremental Capacity of 150/20 kV Substations in Sumatra (MVA)

Number

Comments

Incremental Capacity of 150/20 kV Substations in Java (MVA)

Number

Comments

Data on Financial Performance (as of 03-Oct-2011) Financial Agreement(s) Key Dates Project

Ln/Cr/Tf

Status

Approval Date

Signing Date

Effectiveness Date

Original Closing Date

Revised Closing Date

P117323

IBRD-79400

Effective

08-Jul-2010

18-Nov-2010

30-May-2011

31-Dec-2015

31-Dec-2015

Disbursements (in Millions) Project

Ln/Cr/Tf

Status

Currency

P117323

IBRD-79400

Effective

USD

Original

Revised

225.00

Cancelled

225.00

Disbursed

0.00

Undisbursed

0.00

225.00

% Disbursed

0.00

Public Disclosure Copy

Disbursement Graph

Page 4 of 5

Report No: ISR8339

Public Disclosure Copy

The World Bank

Key Decisions Regarding Implementation The borrower will develop a proposal for the use of saving resulting from lower than expected costs for the original project investments.

Restructuring History There has been no restructuring to date.