HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM This exhibit provides the distinction between the Executive Program Manager (EPM) and the P...
Author: Neal Hopkins
10 downloads 0 Views 447KB Size
HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM This exhibit provides the distinction between the Executive Program Manager (EPM) and the Project Management Support Systems (PMSS) roles and responsibilities. GENERAL SCOPE General Scope Client and Stakeholder Coordination

Executive PM (EPM) Gain the “buy in” of HAS executive management team to lead the ITRP

Client and Stakeholder Coordination

Coordinate with the HAS Infrastructure Division, various HAS and City of Houston departments, airlines, concessionaires, consultants retained by HAS and airlines, and other stakeholders of the ITRP as necessary for the timely and quality execution of the program. Gain the buy-in of United Airlines’ project team to cooperate in all efforts to complete the ITRP

Client and Stakeholder Coordination Continuity of Airport Operations

Program Scope

Program Proposals

Program Organization

Program Organization

Engage and collaborate with airlines and airport stakeholders to minimize disruption of operations and services throughout the duration of the ITRP. Develop and recommend program execution plan complete with program level scope, schedule, budget and level of quality expected. Draft the scopes of work to be incorporated in requests for qualifications/proposals for all design and construction packages forward of notice to proceed (NTP). Develop and recommend the organization structure as an integrated team to manage the ITRP. Thoroughly vet and recommend each and every manager to join the ITRP team.

PM Support Services (PMSS) Support the EPM as requested to gain the “buy in” of HAS executive management team to lead the ITRP. Support Program Level activities and lead the project level stakeholder engagement activities.

Support the EPM as requested to gain the buy-in of United Airlines’ project team to cooperate in all efforts to complete the ITRP. Support Program or Project Level activities and lead project level stakeholder coordination for continuity of Airport operations throughout the ITRP. Support the development of the program execution plan with supporting project level scope, schedule, budget and level of quality expected. Support the development of scopes of work to be included in design and construction packages forward of notice to proceed dates as requested by the EPM. Support the development of the organization structure as requested by the EPM. Support the development of the ITRP team by proposing only qualified and experienced individuals for the role being proposed.

September 17, 2014 Page 1 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM GENERAL SCOPE (continued) Performance Management

Create a Gantt chart of sufficient detail to explain overall sequence of Program elements and timing to completion of each element and the overall ITRP.

Performance Management

Develop the appropriate program and project performance and management metrics to successfully lead the ITRP. Meet or exceed Program performance metrics. Develop and recommend the ITRP budget with design-to-budget estimates for each design package. Review and recommend any changes to systems and processes need to execute the ITRP. Implement any change and any new systems/processes required. Develop, for HAS approval, recommended information management, public relations, and media strategies for the ITRP. Develop and recommend a set of ITRP controls, performance and management metrics, and related reports to assure all activities proceed on schedule, within scope, within budget, and at quality levels agreed to.

Financial Management

Program Policies and Procedures

Strategic Communications

Program Controls

ITRP PMO Building

Diversity Participation

Complete the design and construction of the ITRP PMO Building to accommodate the ITRP management team. Develop and recommend strategy for M/WBE participation in all contracting opportunities.

Support the development of a Gantt chart with sufficient detail to explain the overall sequence of project elements and timing to completion of each element and the overall project. Support the development of Program level, and develop Project level performance metrics. Meet or exceed Project performance metrics. Support the development of project budgets with design-to-budget estimates for each design package. Support the development of revised systems and processes as requested by the EPM. Implement changes and new systems/ processes as requested by the EPM. Support the development of media and PR documents, websites and events. Support the development of project controls, performance and management metrics and related reports to assure all activities proceed on schedule, within scope, within budget, and at quality levels agreed to and as requested by the EPM. Support the completion of design and construction of the ITRP PMO Building as may be requested by the EPM. Support the achievement of M/WBE participation in all contracting opportunities.

September 17, 2014 Page 2 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM GENERAL SCOPE (continued) Presentation and Briefings

Meetings

Additional Duties

Prepare and/or provide presentations or briefings to City officials, City Council, airlines, other City departments, industry groups or other constituents that may be required in support of the HAS. Lead Program level consultations, meetings, presentations, related remote site visits and other duties as may be assigned. Perform any additional duties as directed by HAS for overall success of the ITRP.

Support the preparation, and deliver, presentations and briefings as may be requested.

Lead Project level consultations, meetings, presentations, related remote site visits and other duties as may be assigned. Perform any additional duties as directed by the EPM for the overall success of the ITRP.

SPECIFIC SCOPE Program Initiation Phase Specific Scope Program Scope

Work Breakdown Structure (WBS)

Organizational Structure

Roles and Responsibilities

Executive PM (EPM) Successfully manage the ITRP by providing effective leadership, oversight, strategic evaluation and direction to achieve successful execution as measured by completion on time, within scope, within budget and with the anticipated level of quality. Validate the program scope and identify gaps and overlaps. Develop and maintain the primary breakdown of work into a comprehensive and consistent structure for the program. Develop and recommend the organization structure, processes, and roles and responsibilities of the various entities for the successful implementation of the ITRP for approval by HAS. Define and develop the roles and responsibilities for all members of the ITRP.

PM Support Services (PMSS) Support the development and validation of Program Scope. Provide effective management of ITRP projects to ensure successful completion as measured by completion on time, within scope, within budget and with the anticipated level of quality. Support in the maintenance of the WBS. Develop project level detail of the WBS. Support in the development and maintenance of the project level Organization Structure.

Support the development of project level roles and responsibilities.

September 17, 2014 Page 3 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Program Initiation Phase (continued) Objectives and Benchmarking

Develop benchmarking and guidance to achieve the ITRP program and project objectives.

Program Governance and Management Procedures

1. Develop decision and authority matrix for approval by HAS. Develop program and project level responsibility and assignment matrices. Review and recommend all systems, services and staff. Develop the framework for the Program Procedures including the coordination of functional roles and responsibilities. Establish ITRP communications and media protocols as approved by HAS. Develop and implement ITRP program controls processes and systems to ensure overall success of the ITRP as measured by completion on time, within scope, within budget and delivering the quality levels anticipated. Develop strategy for utilizing effective technology in all aspects of the ITRP program management to meet highest customer satisfaction, achieve cost efficiencies and achieve best practices. Support HAS by establishing ITRP design and construction sustainability protocols and practices. Facilitate program level recurring meetings and engagement with both internal and external ITRP stakeholders, managing and coordinating input and make program recommendations to HAS as appropriate. Provide leadership and manage the establishment of a training and development program for the ITRP processes, systems, procedures and projects.

Communication and Media Protocols Program Controls

Technology

Sustainability

Stakeholder Management

Training and Development

Develop specific project goals and objectives, and assist in developing relevant benchmarking data. Draft all ITRP Procedures for project level governance and management for approval by the EPM.

Provide support services as required. Provide systems, services and staff to implement and manage program and project controls.

Manage the design and implementation of technology throughout the ITRP in accordance with the Technology Strategy. Provide support services as required.

Facilitate project level recurring meetings and engagement with both internal and external ITRP stakeholders, managing and coordinating input and make program recommendations to HAS as appropriate. Support the development and implementation of the ITRP training program.

September 17, 2014 Page 4 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Program Definition Phase Specific Scope Partnering and Chartering Master Schedule

Budget, Cash Flow and Finance Work Plan

Implementation Planning

Program Definition Documents

Cost Estimating, Life Cycle and Market Analysis

Configuration and Change Management

Executive PM (EPM) Establish the overall guidelines for program level partnering.

PM Support Services (PMSS) Participate in program level partnering and lead project level partnering. Develop the ITRP Master Develop and maintain the Master Schedule, sequencing, interface Schedule at the project level. milestones and critical path Develop sequencing, interface and elements. interim milestones, and critical path elements for the ITRP. Develop the Program budget, cash Maintain the ITRP budget, cash flow and financial plan for approval flow, and financial plan. by HAS. Develop the work plan that forms Support in the development of the the Program Management Plan PMP and develop the project (PMP) for the ITRP. execution plans. Review, critique and submit for Review implementation plans as approval all ITRP implementation developed by sub consultant team plans as developed by the PMSS members. teams. Provide overall direction for Develop and maintain all project development of ITRP Program and definition documents. Design Definition Documents. Review, critique and submit for approval all ITRP Project Definition Documents. Manage ITRP estimating and life Develop and maintain project cost cycle (total cost of ownership) estimates. Review and reconcile asset costing, including estimates from all service contingency methodology and providers. estimate evolution through the program lifecycle. Develop and submit for approval Manage change for all projects and change management and impact contracts. Maintain the mitigation strategies throughout configuration control in all systems. the life of the ITRP. This includes, but is not limited to scope, cost, schedule control, and cost reduction initiatives. Establish protocols for Configuration Management.

September 17, 2014 Page 5 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Program Definition Phase (continued) Risk and Opportunity Management

Quality and Safety Management

Documentation and Records Management

Program Baseline Management

Manage ITRP risk and opportunity identification, assessment, and mitigation for the ITRP. Develop the policy and procedure for Management of Risk and Opportunities. Incorporate into the Change Management process as required. Develop the Program Quality Plan. Develop the Program Safety Plan. Establish an overall quality and safety culture for the ITRP. Develop Document Management Plan, and overall Program Information Management Plan, for all phases and entities within the ITRP. Develop the set of controls to assure team performance against the Program baseline metrics.

Diversity Compliance, Monitoring and Reporting

Develop protocols and guidelines for ITRP Diversity Compliance, Monitoring and Reporting.

Reporting

Establish the metrics and basis for progress reporting against the Program, Projects, and Contracts. Reporting shall include Performance Measurement, Forecasting, Trending, Issues, Actions, Progress and Overall Status.

Lead the team in project risk and opportunity identification, assessment, and mitigation for the ITRP.

Establish and maintain quality plans and safety plans for all projects. Establish and maintain ITRP documentation and accuracy of records.

Support the development and maintain the baseline for all projects and meet or exceed the performance metrics. Implement the contract compliance, monitoring and reporting in accordance with HAS Diversity requirements and as requested by the EPM. Develop all project reports in accordance with program requirements.

Procurement Phase Develop Procurement plans and strategies, and review ITRP Procurement documents. Specific Scope Procurement Plans

Executive PM (EPM) Develop the program procurement strategy to achieve program objectives. Coordinate with HAS Supply Chain Management to develop the procurement plan.

PM Support Services (PMSS) Support HAS on the implementation of the procurement strategy and plan.

September 17, 2014 Page 6 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Procurement Phase (continued) Contract Packaging

Project Delivery Methods

Design Procurements

Develop the program phasing and execution strategy to achieve program objectives for packaging of all ITRP contracts. Coordinate with HAS Supply Chain Management. Confirm the program delivery methods to achieve program objectives for packaging of all ITRP contracts. Coordinate with HAS Supply Chain Management. Review the design procurement documents as developed by the PMSS.

Construction Procurements

Review the Construction procurement documents as developed by the PMSS.

Other Procurements

Review other services, systems, materials and equipment procurement documents as required.

Support EPM in the implementation of the contract strategy.

Support EPM in the implementation of the delivery strategy.

Develop the scope and selection criteria. Support HAS Supply Chain Management in procurement processes as required. Develop the scope and selection criteria. Support HAS Supply Chain Management in procurement processes as required. Develop the scope and selection criteria. Support HAS Supply Chain Management in procurement processes as required.

Design Phase Specific Scope Design Management

Design Management Codes and Standards CADD and BIM Management

Constructability Review

Executive PM (EPM) Manage design assignments for every design package, whether performed in-house or contracted out, holding to approved scope, budget, schedule and quality. Develop the Design Management guidelines, policy and procedures. Manage and ensure compliance with all applicable codes and standards for the ITRP. Establish CADD and BIM framework, environment, policy and procedures. Establish constructability review guidelines and protocols. Approve constructability review recommendations.

PM Support Services (PMSS) Support the achievement of design management standards through the development of designs that hold to approved scope, budget, schedule and quality anticipated. Implement Design Management Procedures for the ITRP. Verify all project level designs are in compliance with codes and standards. Establish, implement and maintain the CADD and BIM framework, environment, policy and procedures. Perform constructability review and provide recommendations for all ITRP projects.

September 17, 2014 Page 7 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Design Phase (continued) Cost Reduction Initiatives

Sustainability Planning and Management

Operability and Maintainability Diversity Compliance, Monitoring and Reporting

Progress Reporting

Develop program guidelines and protocols for cost reduction initiatives. Review project level cost reduction recommendations. Develop ITRP sustainability program guidelines, practices and protocols for sustainability. Approve project level sustainability recommendations. Approve project level operability and maintainability recommendations. Review project level diversity recommendations.

Review design progress and approve recovery plans.

Develop and recommending cost reduction initiatives.

Develop and recommend project level sustainability plans for implementation during design and construction. Perform and recommend Operability and Maintainability Reviews for all ITRP projects. Review design diversity plans for all ITRP projects / contracts in accordance with Diversity Policy and Procedures. Perform diversity compliance, monitoring and reporting. Respond to diversity issues and recommend corrective actions. Review and analyze design progress reports and incorporate into project level status reports. Develop recovery plans as necessary.

Construction Phase Specific Scope Construction Management

Safety

Quality Control

Executive PM (EPM) Manage construction assignments for every construction project, holding to approved scope, budget, schedule and quality. Approve project level safety recommendations and corrective actions.

Establish the program level framework for Construction Quality Control

PM Support Services (PMSS) Achieve on budget, on scope, on schedule and quality standards of all construction assignments at the project level. Review safety programs and procedures developed by the various contractors. Review safety reports and practices of the contractors. Respond to safety issues and recommend corrective actions. Review the Quality Control programs and procedures developed by the various contractors.

September 17, 2014 Page 8 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Construction Phase (continued) Quality Assurance Approve quality recommendations and corrective actions. Approve project level Quality Assurance plans. Permitting Coordinate at a program level with authorizing agencies regarding required ITRP permitting. Monitor application and receipt of permits as submitted by the PMSS to ensure support of project and Program milestones.

Logistics and Phasing

Develop overall Program Site Logistics and Phasing Strategy. Approve Logistics and Phasing recommendations.

Construction Management

Develop the Construction Management guidelines, policy and procedures. Review project level diversity recommendations.

Diversity Compliance, Monitoring and Reporting

Progress Reporting

Review construction progress and approve recovery plans.

Claims Management

Review the claims resolutions recommendations.

Develop all relevant procedures required to provide Quality Assurance for the ITRP at the individual project level. Review all project permitting efforts and documentation developed by the various contractors for compliance and completeness. Establish tracking program to monitor permit application and receipt processes for each individual project to ensure timeliness of permitting to support project milestones. Implement the Logistics and Phasing Strategy. Review and recommend all project Logistics and Phasing plans and documents developed by the various contractors. Collaborate with all appropriate stakeholders and services providers to minimize impacts to operations. Implement the Construction Management guidelines, policy and procedures for the ITRP. Review construction diversity plans for all ITRP projects / contracts in accordance with Diversity Policy and Procedures. Perform diversity compliance, monitoring and reporting. Respond to diversity issues and recommend corrective actions. Review and analyze construction progress reports and incorporate into project level status reports. Requesting recovery plans as necessary. Lead the Claims Management process for all ITRP projects and make recommendations on the resolution of claims.

September 17, 2014 Page 9 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Construction Phase (continued) Beneficial Use

Collaborate with appropriate internal and external stakeholders to achieve consent to achieve “Beneficial Occupancy” (Use). Review all Beneficial Use recommendations as submitted by the PMSS.

Review and recommend all “Beneficial Occupancy” (Use) documents. Facilitate obtaining Beneficial Occupancy (Use) for all projects of the ITRP through liaison with the EPM.

Commissioning and Activation Phase Review all commissioning and activation activities of the ITRP prior to the opening of the new facilities. Ensure independent third party commissioning plans are developed and executed prior to requesting a Certificate of Occupancy (COO). Working with the HAS Operations, Readiness, Activation and Transition (ORAT) Team, identify, schedule and support ORAT activities in the integrated program schedules. Specific Scope

Executive PM (EPM)

Transition Planning

Review all ITRP project transition plans and recommendations.

Operational Readiness, Activation and Transition (ORAT)

Review all ORAT recommendations.

Component Testing and System Commissioning Operations and Maintenance (O&M) Manuals and Training

Review and establish Component Testing and System Commissioning guidelines for the ITRP.

Certificate of Occupancy

Review all Certificate of Occupancy recommendations; collaborate with appropriate internal and external stakeholders to achieve consent to gain occupancy.

Review delivery schedules for Operations and Maintenance (O&M) Manuals and Training for the ITRP, ensuring receipt of all deliverables prior to scheduled ORAT activities.

PM Support Services (PMSS)

Develop and recommend Transition Plans for all ITRP projects. Facilitate the ORAT process through active liaison with the EPM and the HAS ORAT Team. Resolve any issues that may occur during the construction phase and make recommendations. Implement the Commissioning guidelines for the ITRP. Provide support services as required. Implement the O&M guidelines for the ITRP. Review and record the receipt of all O&M manuals and training plans, ensuring compliance with ORAT guidelines and objectives. Review and recommend all Certificate of Occupancy documents. Facilitate obtaining Certificate of Occupancy for all facilities of the ITRP through liaison with the EPM.

September 17, 2014 Page 10 of 11

HOUSTON AIRPORT SYSTEMS IAH TERMINAL REDEVELOPMENT PROGRAM Commissioning and Activation Phase (continued) Final Acceptance

Review and recommend to HAS the establishment of Final Acceptance guidelines for the ITRP.

Warranty Management

Review and recommend to HAS the establishment of Warranty Management guidelines for the ITRP. Develop and implement ITRP Asset Management protocols and practices that support HAS guidelines.

Asset Management

Implement the Final Acceptance guidelines for the ITRP. Facilitate obtaining Final Acceptance for all projects of the ITRP through liaison with the EPM. Implement the Warranty Management guidelines for the ITRP. Review and record all warranties. Provide support services as required.

Contract Closeout Phase Review all closeout documents at the end of the assignment ensuring that all documentation has been submitted and approved. Specific Scope Records Management and Closure Records Management and Closure Project Closeout Report

Executive PM (EPM) Review all closeout documents at the end of the assignment ensuring that all documentation has been submitted and approved. Review for compliance with Policy and Procedures.

PM Support Services (PMSS) Manage the closure and conformance of all project record in accordance with ITRP Policy, Procedures and Guidelines. Support the review of records as requested by the EPM.

Establish the program level project Closeout Policy, Procedures and Guidelines for the ITRP.

Implement and manage the financial closeout of all ITRP projects and contracts in accordance with Policy, Procedures and Guidelines.

September 17, 2014 Page 11 of 11