Moderator: Michael Kenig, Holder Construction • Paul “Butch” Kuester, The University of Texas MD Anderson Cancer Center, Executive Director, Facilities Planning Design and Construction
• Mark Kohl, Walt Disney Imagineering, Executive, Project Management
2014 AGC Building Contractors Conference #FALLBCC
Procurement Types 1. Low Bid 2. Best Value: Total Cost 3. Best Value: Fees 4. Qualifications Bases Selection (QBS)
2014 AGC Building Contractors Conference #FALLBCC
Procurement Types 1. Low Bid • Total Construction Cost, is the only final selection criteria (Total Construction Cost weighted 100% )
2. Best Value: Total Cost • Total Construction Cost is a weighted final selection criteria (Total Construction Cost weighted between 0% & 100% )
3. Best Value: Fees • Validation (pre-con), Fees and/or General Conditions are weighted but Total Construction Cost is not a weighted final selection criteria (Fees and/or General Conditions weighted between 0% & 100%)
4. Qualifications Bases Selection (QBS) • Price is not a final selection criteria (Price weighted 0% )
2014 AGC Building Contractors Conference #FALLBCC DELIVERY METHOD