R Value Calculation Method: Heat loss equation for less than or equal to 30% of total wall area - non-solid construction walls
WALL TYPE KEY:
Maximum A roof + A 70% of total wall area + A floor + A 30% of total wall area HL reference = 2.9 1.9 1.3 0.26
James Hardie Axon Panel
HL reference =
101.35 + 2.9
James Hardie Linea Weatherborad
FIRE CODE COMPLIANCE: Fire code compliance with NZBC sections C1/AS1, C2/AS1 C3/AS1 & C4/AS1. Purpose group SH in accordance with Table 2.1 Pg 43
75.10 + 101.35 + 32.18 1.9 1.3 0.26
HL reference = 34.95 + 39.52 + 77.96 + 123.78 = 276.22 Calcs provided based on R values supplied in this dwelling;
W11 1200x1600 L 190x90
HL proposed = 32.69 + 44.81 + 77.96 + 85.15 = 240.62 Heat loss value is LESS than the maximum heat loss value based on up to 30% glazing area.
fridge N.i.C
Therefore; COMPLIES
dw space under
WC
tub wm N.i.C LAUN.
KITCHEN
-Asht. 14
D/W
sink
All dimensions are CRITICAL to ensure neat and exact fitting of components/fixtures. Most important are Baths, Showers, Vanities and the like. Due to manufacturing processes these can vary in dimension + or - 5mm. Confirm ALL dimensions prior to placing Gib Board or before permanently fixing any items.
900 vanity
W4 600x1200 L 140x90
BED 3
900sq acrylic shower
linen
66
W12 1200x2400 L 190x90
2/610 sliders
KEY WALL FRAMING:
HALL
EXTERIOR WALLS Allow 90x45 MSG8 H1.2 KD studs @ 450mm ctrs with 2 rows of nogs.
46 0 66
860
71
0
860
0
LIVING
Note: - All joinery to have double glazing. FINDINGS: Insulation R values for dwelling provided: Roof = R3.2 ceiling insulation Wall = R2.2 wall insulation Floor = R1.3 floor insulation
wr
W3 600x1200 L 140x90
BED 2
BED 1
Ensure 'cabinatery and other components' backing nogs are placed prior to placing any wall linings. N.I.C. = Not in Contract.
860
71 WH
BATH.
710
1 ELEVATION KEY
GENERAL NOTES:
0
Glazing Area calculation: Wall Area = 107.28m² Glazing Area = 23.04 Calc. 23.04 / 107.28 x 100 = 21.47% Therfore Less than 30%
W5 1200x1800 L 190x90
2
4
Proposed dwelling compliant with C1/AS1 Detached Dwelling: Paragraphs 1.3.3 & 1.3.4 - Pg 36
1675x760 bath
pantry Hob, u/b oven & rangehood
W6 800x800 obscure safety glass L 90x90
710
101.35 + 85.14 + 101.35 + 22.14 3.1 1.9 1.3 0.26
0
INTERIOR WALLS; Load Bearing Walls - Allow 90x45 MSG8 UT KD studs @ 450mm ctrs with 2 rows of nogs. Non Load Bearing Walls - Allow 90x45 MSG8 UT KD studs @ 600mm ctrs with 2 rows of nogs. 90x45mm timber wall framing
wr
71
0
HL proposed =
D2 2000x880 trim 2015x895 Obsc. with Vision Rail W7 800x600 W10 W9 W8 L 90x90 obscure 900x300 900x300 800x500 L 90x90 L 90x90 L 90x90 L 90x90
3
Construction R values adjusted from the above values provided for the dwelling: Roof = R3.1 (Pitched profile steel using 90mm bottom chord trusses). Wall = R1.9 (Axon Panel & Bevelback weatherboard with 90mm frame). Floor = R1.3 (Enclosed timber subfloor 100mm max. sag sisalation foil) (Area/Perimeter ratio of 2.27) Construction values obtained from BRANZ House Insulation Guide.
D1 2000x2800 unit 2200 Slider + 600 Sidelight and Vision Rail L 290x90
W1 1200x1800 L 190x90
Allow 1 row of tiles (min. 150mm high) as bath splashback to walls around bath. Allow to rebate studs for recessing of bath. Allow 10mm Gib Aqualine on ceiling and walls for all bathrooms & laundry
W2 1200x1800 L 190x90
INSULATION: Allow wall insulation of R2.2 Allow ceiling insulation of R3.2
WET AREAS BATH / KITCHEN / WC / LDY (floor finishes) (NOTE: Non-slip vinyl to achieve a minimum slip resistance coefficient of 0.25 - 0.50) Non-slip vinyl lining over sealed floor. Waterproof seal vinyl to edge of painted skirting contractor to comply with NZBC : E3/AS1 internal moisture.
Lintels as shown from NZS:3604 A2 or similar approved system.
THE MATSON 102
BATH / LDY (Wall & ceiling finishes) 1/Coat GIB sealer with 2/coats GIB Aquaseal paint.
-alteredFloor Area = 101.35m² o/frame
All documentation prepared in accordance with NZS:3604 (Amendment No.2 May 2006)
*All timber stress grading to be a minimum MSG8 or VSG8 unless otherwise noted.
All dimensions & underground service locations to be checked prior to commencement of all works. DO NOT scale off drawings. Cross reference all drawings, confirm site levels, floor heights & restrictions prior to earthworks. If any descrepancies occur, contact Highmark Homes immediatley before commencing works or ordering. COPYRIGHT; These drawings remain the property of HIGHMARK HOMES ltd and are provided for use as described above and may not be used or re-produced in whole or part without written permission. Producer statements issued by all suppliers & tradesmen where applicable. Any site/construction works are not to commence until building permit becomes unconditional.
NEW HOME FOR:
Charitable Build
Wind:
THE MATSON 102 -alteredwww.highmarkhomes.co.nz
Date:
Very High EQ:
B Corrosion Zone: 1
FLOOR PLAN texts only
02 March 2010 Drawn:
CT
Sheet #
Set of
02
27
Scale:
Job # HM-1105
1 : 100
WALL TYPE KEY: James Hardie Linea Weatherborad James Hardie Axon Panel FIRE CODE COMPLIANCE: Fire code compliance with NZBC sections C1/AS1, C2/AS1 C3/AS1 & C4/AS1. Purpose group SH in accordance with Table 2.1 Pg 43
13 620 2 800 90
2 710
3 200 90
3 020
1 590 90
1 590
2 870 90
900
90
3 160
1 700
90
90
3 070
Proposed dwelling compliant with C1/AS1 Detached Dwelling: Paragraphs 1.3.3 & 1.3.4 - Pg 36
90 1 360
90
3 170
8 180
7 630
90 600 90
N.I.C. = Not in Contract. KEY WALL FRAMING: EXTERIOR WALLS Allow 90x45 MSG8 H1.2 KD studs @ 450mm ctrs with 2 rows of nogs.
3 500
BED 2
BED 1
Ensure 'cabinatery and other components' backing nogs are placed prior to placing any wall linings.
INTERIOR WALLS; Load Bearing Walls - Allow 90x45 MSG8 UT KD studs @ 450mm ctrs with 2 rows of nogs. Non Load Bearing Walls - Allow 90x45 MSG8 UT KD studs @ 600mm ctrs with 2 rows of nogs.
90
3 500
LIVING
90 1 360 600
300
90
HALL
90x45mm timber wall framing
600
90
1 000
2 730 900
300
90 90 600
300
2 570
90
BED 3
WH
6 450
7 000
LAUN.
90 90
5 820
90
3 655
5 910
90
600
90
945
90
945
1 ELEVATION KEY
All dimensions are CRITICAL to ensure neat and exact fitting of components/fixtures. Most important are Baths, Showers, Vanities and the like. Due to manufacturing processes these can vary in dimension + or - 5mm. Confirm ALL dimensions prior to placing Gib Board or before permanently fixing any items.
90
1 750
BATH.
2
4
GENERAL NOTES:
550
90
600
550
600
1 050
KITCHEN
2 180 90 90 900 600
300
WC
90
6 630
700
D/W
8 180
300
90
90
90
550
850
3
Allow 1 row of tiles (min. 150mm high) as bath splashback to walls around bath. Allow to rebate studs for recessing of bath. Allow 10mm Gib Aqualine on ceiling and walls for all bathrooms & laundry
90
INSULATION: Allow wall insulation of R2.2 Allow ceiling insulation of R3.2
3 095
7 710
Lintels as shown from NZS:3604 A2 or similar approved system.
13 620
THE MATSON 102 -alteredFloor Area = 101.35m² o/frame All documentation prepared in accordance with NZS:3604 (Amendment No.2 May 2006)
*All timber stress grading to be a minimum MSG8 or VSG8 unless otherwise noted.
All dimensions & underground service locations to be checked prior to commencement of all works. DO NOT scale off drawings. Cross reference all drawings, confirm site levels, floor heights & restrictions prior to earthworks. If any descrepancies occur, contact Highmark Homes immediatley before commencing works or ordering. COPYRIGHT; These drawings remain the property of HIGHMARK HOMES ltd and are provided for use as described above and may not be used or re-produced in whole or part without written permission. Producer statements issued by all suppliers & tradesmen where applicable. Any site/construction works are not to commence until building permit becomes unconditional.
NEW HOME FOR:
Charitable Build
Wind:
THE MATSON 102 -alteredwww.highmarkhomes.co.nz
Date:
Very High EQ:
B Corrosion Zone: 1
FLOOR PLAN dimensions only
02 March 2010 Drawn:
CT
Sheet #
Set of
03
27
Scale:
Job # HM-1105
1 : 100
10.1° pitch Dimond Corrugate 0.4 BMT Colorcote ZR8 Longrun Roofing
JH Linea weatherboad exterior cladding on 20x50 H3.1 cavity battens
NZBC:EXTERNAL MOISTURE Table 2:
Acceptable Solution E2/AS1
Building Envelope Risk Matrix Paragraph 3.1.2, Figure 1 RISK SEVERITY LOW
MEDIUM
HIGH
VERY HIGH
Subtotals for each Risk Factor
Wind zone (per NZS:3604)
0
0
1
2
2
Number of storeys
0
1
2
4
0
Roof/Wall intersection design
0
1
3
5
3
Eaves width
0
1
2
5
5
Envelope complexity
0
1
3
6
1
Deck design
0
2
4
6
0
Risk Factor
S
FFL D1
W1
H3.2 timber steps
ELEVATION 1.
W2
FGL
JH Axon Panel exterior cladding on 20x50 H3.1 cavity battens
powder coated aluminium joinery
NOTE: Risk score shown is the highest risk score for elevations.
JH Linea weatherboard exterior cladding on 20x50 H3.1 cavity battens
D2
S2
D1 = Hinged door with panels of area > 0.5m² = Grade 'A' Safety Glass. D2 = Hinged door with panels of area < 0.5m² = Annealed Glass. D3 = Hinged door with panels of area > 0.5m² = Grade 'A' Safety Glass. D4 = Hinged door with transom = Annealed Glass. > 20
< 1000
D4
D4
S5
S5
> 700
S3
< 1000
> 1000
< 500
S4
4 845
D1
10.1° pitch
approx. building height
> 1000 S1
S1 = Res. side panel of width > 500mm & lower edge < 500mm above highest abutting floor level = Grade 'A' Safety Glass. S2 = Res. side panel of width < 500mm = Annealed Glass. S3 = Res. side panel of width > 1000mm = Grade 'A' Safety Glass. S4 = Res. side panel of width < 1000mm = Annealed Glass. S5 = Res. side panel with transom = Annealed Glass.
S3
11
Note: Cavity battens to exterior claddings
GLAZING SCHEDULE: sg = safety glass.
D3
Total Risk score:
All glazing below 1000mm height in access routes (including stairwells) to be Grade 'A' Safety Glass.
FFL W3
FGL
W4
All glazing to be in accordance with NZS.4223.
ELEVATION 2.
ALL GLAZING TO BE DOUBLE GLAZED
10.1° pitch Dimond Corrugate 0.4 BMT Colorcote ZR8 Longrun Roofing
JH Axon Panel exterior cladding on 20x50 H3.1 cavity battens
JH Linea weatherboard exterior cladding on 20x50 H3.1 cavity battens
1x25mm roof strip brace & tensioner
10.1° pitch
JH Linea weatherboard exterior cladding on 20x50 H3.1 cavity battens
sg sg
FFL W5
ELEVATION 3. All documentation prepared in accordance with NZS:3604 (Amendment No.2 May 2006)
W6
W7
D2
W8
W9
W10
JH Linea weatherboard exterior cladding on 20x50 H3.1 cavity battens
W11
FGL FGL
W12
FFL
powder coated aluminium joinery
ELEVATION 4.
JH Axon Panel exterior cladding on 20x50 H3.1 cavity battens
*All timber stress grading to be a minimum MSG8 or VSG8 unless otherwise noted.
All dimensions & underground service locations to be checked prior to commencement of all works. DO NOT scale off drawings. Cross reference all drawings, confirm site levels, floor heights & restrictions prior to earthworks. If any descrepancies occur, contact Highmark Homes immediatley before commencing works or ordering. COPYRIGHT; These drawings remain the property of HIGHMARK HOMES ltd and are provided for use as described above and may not be used or re-produced in whole or part without written permission. Producer statements issued by all suppliers & tradesmen where applicable. Any site/construction works are not to commence until building permit becomes unconditional.
NEW HOME FOR:
Charitable Build
Wind:
THE MATSON 102 -alteredwww.highmarkhomes.co.nz
Date:
Very High EQ:
B Corrosion Zone: 1
ELEVATIONS
02 March 2010 Drawn:
CT
Sheet #
Set of
04
27
Scale:
Job # HM-1105
1 : 100
GENERAL NOTES: All electrical work & items to comply with; NZBC F7/AS1, AS/NZS 3000, AS/NZS 3008, AS 3786, NZS 6401
METER BOX
Confirm final positioning & fitting allowance with client contract specifications. SD - first alert or similar. Approved smoke alarms are required within 3.0m of any sleeping space door. Smoke alarms must be audible to sleeping occupants on the other side of closed doors. Smoke alarms shall also be located on escape routes within the household.
D/W
distribution board WH
All downlighting to be CA Rated to comply with NZBC: H1/AS1 energy efficiency.
SD
LEGEND: Power Points - All Doubles Lights SD
TV
Light Switches SD
TV
Smoke Detectors- Not in Contract Telephone Jack
TV
Television Jack
ELECTRICAL LAYOUT
All documentation prepared in accordance with NZS:3604 (Amendment No.2 May 2006)
*All timber stress grading to be a minimum MSG8 or VSG8 unless otherwise noted.
All dimensions & underground service locations to be checked prior to commencement of all works. DO NOT scale off drawings. Cross reference all drawings, confirm site levels, floor heights & restrictions prior to earthworks. If any descrepancies occur, contact Highmark Homes immediatley before commencing works or ordering. COPYRIGHT; These drawings remain the property of HIGHMARK HOMES ltd and are provided for use as described above and may not be used or re-produced in whole or part without written permission. Producer statements issued by all suppliers & tradesmen where applicable. Any site/construction works are not to commence until building permit becomes unconditional.
NEW HOME FOR:
Charitable Build
Wind:
THE MATSON 102 -alteredwww.highmarkhomes.co.nz
Date:
Very High EQ:
B Corrosion Zone: 1
ELECTRICAL LAYOUT
02 March 2010 Drawn:
CT
Sheet #
Set of
10
27
Scale:
Job # HM-1105
1 : 100
Note: This drawing is an artistic interpretation of the general appearance of the design. It is not meant to be an exact rendition.
Charity Build.kit
Designed :17/06/2011 Printed: 27/10/2011
Drawing 1
Drawing #: 1