Approved Project 150
Wednesday, July 01, 2015
Facilities Project Management Monthly Report by Building PM Status Accountable
ID
Project Code
PROJECT TITLE
Projects in Building
1 Leavitt Lane Houde
3‐ In Construction
2714
FCR
4
1 Leavitt Lane ‐ Fire Suppression Work is funded, FCT ordering material and setting up the work schedule. 6‐30‐15
Design Firm:
Woodcock
Contractor: FCT 3‐ In Construction
2319
FCR
Contractor Name:
1 Leavitt Lane ‐Warehouse Office, warehouse, and breakroom… 5/27/15_ In construction with carpet scheduled for June.
Design Firm:
Henry
Contractor: FCT/EH 3‐ In Construction
1542
RR
Contractor Name:
1 Leavitt Lane ‐ HVAC Investigation and Evaluation Scheduling re‐cap June 2015
Design Firm: Harriman
Woodcock
3‐ In Construction
Contractor: External 2372
FCR
Contractor Name:
TBD
1 Leavitt Lane ‐ SEED and DTZ Secure Storage Installations 6/29/2015_ Complete and waiting on prox card delivery.
Design Firm:
Contractor: FCT
Contractor Name:
Projects in Building
10 Pettee Brook Lane Cardoso
2‐ In Design
2624
FCR
1
10 Pettee Brook Lane ‐ Fit Out Lease Space Permit/Bid documents due by July 9 with budget to be established for approval by July 16.
Design Firm: Cowan‐Goudreau
Contractor: External
Contractor Name:
Landlord
Projects in Building
10 West Edge Henry
2‐ In Design
1292
FCR
1
10 West Edge Drive ‐ Printing Services Exhaust Vent Project has changed to a new printer type, Harriman working on estimate for new scope of work. 5‐27
Design Firm: Harriman
Contractor: External
Contractor Name:
Milestone
Projects in Building
10 West Edge Drive Henry
1.1‐ Plan/Est
2762
FCR
10 West Edge Drive ‐ Renovation to support new Fujifilm LED 1600 printer Sent FCR 6‐19‐15
Design Firm: Harriman
Contractor: External
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Milestone
Page 1 of 21
1
PM Status Accountable
ID
Project Code
PROJECT TITLE
10 West. Edge Woodcock
3‐ In Construction
2605
FCR
Projects in Building
1
Projects in Building
2
Projects in Building
3
10 West Edge Drive ‐ est to install dishwasher in 102 6/29/2015_FCT defining schedule.
Design Firm:
Contractor: FCT
Contractor Name:
121 TECHNOLOGY DRIVE Heckler
2‐ In Design
2518
FCR
Madbury Commons ‐ IOL Conceptual Design Review‐2 scheduled for 4/13/15.
Design Firm: Manypenny Murphy Archite
Heckler
2‐ In Design
2519
FCR
Contractor: External
Contractor Name:
Madbury Commons ‐ UNH Innovation Conceptual Design Review‐2 scheduled for 4/13/15.
Design Firm: Manypenny Murphy Archite
Contractor:
Contractor Name:
6 Leavitt Lane Healey
1.1‐ Plan/Est
2734
FCR
Design Firm:
Woodcock
Marine Lot at 6 Leavitt Lane Roof System
Contractor: FCT 2‐ In Design
2324
FCR
Contractor Name:
6 Leavitt Lane ‐ BSC Office Renovations 6/29/2015_ Re‐defining scopes associated with MEP, based on scope changes 6/2015.
Design Firm: Loureiro Engineering
Woodcock
3‐ In Construction
1567
Contractor: FCT FCR
Contractor Name:
6 Leavitt Lane ‐ Lock Shop and Facilities Office Renovation 6/29/2015_Punch list items, and controls being finalized.
Design Firm: Loureiro Engineering
Contractor: FCT
Contractor Name:
Projects in Building
88 Commercial Street Woodcock
3‐ In Construction
2583
FCR
1
UNH Manchester ‐ Installation of 5th Floor Science Labs 6/29/2015_ OCC granted for 1st phase of labs, with schedule on track for final OCC August 2015. Building signage is to be installed 6/30/2015 & 7/1/2015 400 Comm signage to be removed 6/29/2015
Design Firm:
Contractor:
Contractor Name:
Projects in Building
Adams Tower
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 2 of 21
1
PM Status Accountable
Cardoso
2.5‐ In Procurement
ID
Project Code
2737
RR
PROJECT TITLE
NEC ‐ Adams Tower Elevator Drive Repair Material on order as of June 23. Work to be scheduled for middle of July.
Emergency Repair Design Firm: NA
Contractor: External
Contractor Name:
Thyssen Krupp Elevator
Projects in Building
Barton and Cole Hall Henry
1.1‐ Plan/Est
2740
FCR
1
Cole Hall ‐ Carpeting & Electrical Rms 141 & 142 Waiting for Funding to be set up 6‐29
Design Firm:
Contractor: External
Contractor Name:
Sprague Flooring
Projects in Building
Barton Hall Houde
1.1‐ Plan/Est
1132
RR
1
Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications New, I will appropriate the aid of an engineer to provide a plan for this work.. Have to review Cole side again. 6‐25‐15
Design Firm:
Contractor:
Contractor Name:
BARTON HALL AND COLE HALL Healey
1.1‐ Plan/Est
2614
FCR
Projects in Building
1
Projects in Building
1
Barton Hall/Cole Hall ‐ Bottle Fill Stations 6/25/15 Estimate approved awaiting funding
Design Firm:
Contractor: FCT
Contractor Name:
Central Heat Plant Houde
3‐ In Construction
2582
SI
Combined Heat and Power Plant ‐ Boiler # 4 Replacement Boiler demolition is 90% complete. Ext, AST abatement and removal to begin soon. 6‐30‐15
Design Firm:
Contractor:
Contractor Name:
Projects in Building
CHASE OCEAN ENGINEERING LAB Cardoso
2‐ In Design
2668
FCR
1
Chase Ocean Engineering Building ‐ Sound Reduction HVAC‐1 and HVAC‐2 Purchase Order was sent to Harriman Associates on June 29 with design to start by July 17 and construction to take place in early fall 2015.
Design Firm: Harriman Associates
Contractor: TBD
Contractor Name:
Projects in Building
COLE HALL Houde
3‐ In Construction
TBD
2611
FCR
1
Barton Hall/Cole Hall ‐ Digital /Sign installation Thompson school has sent notice they will proceed with the funding of the Cole Hall digital sign only, at this time. . Per request of the customer, work has been delayed to after 7‐27‐15, . 6‐30‐15
Design Firm:
Contractor: FCT
Contractor Name:
Projects in Building
Conant Hall
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 3 of 21
2
PM Status Accountable
Jones
3‐ In Construction
ID
Project Code
2279
RR
PROJECT TITLE
Conant Hall ‐ Utility Pit Replacement 6/26/15: Onsite construction is continuing. Concrete walls to be poured and excavation backfilled by July 7. Work in tunnel in front of DeMeritt to begin on July 8. Anticipated completion is August 21.
Design Firm: Harriman
Woodcock
3‐ In Construction
Contractor: External 2551
FCR
Contractor Name:
RH White
Conant Hall ‐ Installation of Fume Hood Room 204 6/29/2015_FCT is currently working on scope outside of the fume hood. CDs fromt eh engineer are expected by 7/3/2015.
Design Firm: Harriman
Contractor: FCT
Contractor Name:
DEMERITT HALL Healey
1.1‐ Plan/Est
2657
FCR
Projects in Building
2
Projects in Building
10
Demerritt‐ 103 install 240V outlet 6/25 working with the customer to schedule.
Design Firm:
Woodcock
Contractor: FCT 3‐ In Construction
1995
FCR
Contractor Name:
Demeritt Safety Improvements 217 6/29/2015_FCT hired,and defining schedule with subcontractor.
Design Firm: Harriman Associates
Contractor: FCT
Contractor Name:
TBD
Dimond Library Woodcock
1.1‐ Plan/Est
2215
FCR
Dimond Library ‐ Ground Lvl compact shelving capacity study 6/29/2015_ Scope defined for engineering. FCR to client by 7/10/15
Design Firm: Loureiro Engineering
Henry
1.1‐ Plan/Est
806
Contractor: External SI
Contractor Name:
TBD
TEAL Classroom Submitted new budget to the Provost office, waiting for feed back. Still in holding 1‐7‐15
Design Firm:
Heckler
Contractor: 2‐ In Design
624
SI
Contractor Name:
Dimond Library Space Repurposing ‐ Phase 2 3/26/15: Per T. Lauder, internal Dimond group working on defining and/or redefining space uasge and needs. Outcome of those discussions will determine direction project will take.
Design Firm:
Cardoso
Contractor: 2.5‐ In Procurement
2064
RR
Contractor Name:
Dimond Library ‐ AHU‐ 1E Replacement Work is tenatively scheduled to begin July 13 with completion by August 28.
Design Firm: Oak Point
Contractor: FCT
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Palmer and Sicard
Page 4 of 21
PM Status Accountable
Houde
2.5‐ In Procurement
ID
Project Code
1833
FCR
PROJECT TITLE
Dimond Library‐Level III hall add lighting Client has a quote and FCR, we are waiting on funding. . 6‐26‐15
Design Firm:
Cardoso
Contractor: FCT 2.5‐ In Procurement
2154
RR
Contractor Name:
Dimond Library ‐ Heat Exchanger Replacement Working with Facilities Maintenance to schedule cleaning for July, 2015.
Design Firm: N/A
Cartabona
3‐ In Construction
Contractor: TBD 2325
RR
Contractor Name:
TBD
Dimond Library ‐ Stack Lighting Modifications 6/30/15 Yates has completed light sensor modifications on floor 1 with noticiable improvement. Proceeding to upper floors.
Design Firm: Rist Frost Shumway
Henry
3‐ In Construction
1711
Contractor: External FCR
Contractor Name:
Yates Electric
Dimond Library ‐ Level G UNH AV Space Renovation Project re‐opened for FCT to install new tables in Hub Rooms. 5‐20
Design Firm: Harriman
Heckler
3‐ In Construction
Contractor: FCT 1359
FCR
Contractor Name:
Shawmut
Dimond Library ‐ Room 301 Redesign and Relocation FCT scope expected complete by 6/19. Furniture install expected week of 6/22.
Design Firm:
Houde
Contractor: FCT 3‐ In Construction
2612
FCR
Contractor Name:
Dimond Library ‐ Digital Sign Upgrade This work has been funded. I met with Marshall White and FCT on Monday to go over details. I am expecting TV info from Marshall and a tentative start date from FCT. 6‐30‐15
Design Firm:
Contractor: FCT
Contractor Name:
Dunlap Center Healey
1.1‐ Plan/Est
2700
FCR
Projects in Building
1
Projects in Building
6
Dunlap‐ celing & wall repairs 6/25/15 Scheduled to begin week of 6/29
Design Firm:
Contractor: FCT
Contractor Name:
Field House Jones
1.1‐ Plan/Est
2469
FCR
Field House Space Reconfiguration/Remodelling rm 18 6/26/15: Architect has submitted 4 conceptual designs for the space reconfiguration. PM has sent conceptual designs to Athletics for review and comment.
Design Firm: Harriman
Contractor:
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 5 of 21
PM Status Accountable
Cartabona
2.5‐ In Procurement
ID
Project Code
2596
RR
Field House ‐ Heating Coil Replacements HV 25 6/30/15 Granite State Plumbing Heating provided proposal, project was funded. This work will be complete by August 2015.
Emergency Repair Design Firm:
Henry
PROJECT TITLE
Contractor: External 2.5‐ In Procurement
672
RR
Contractor Name:
Granite State Plumbing Heating
Driveway Repair Emergency Access‐ Field House Construction Started 6‐9‐15
Design Firm: Tighe& Bond
Cartabona
3‐ In Construction
Contractor: External 2342
RR
Contractor Name:
TBD
Field House ‐ Sprinkler Installation Phase IV Will report with 1159
Design Firm: SFC Engineering
Cartabona
3‐ In Construction
Contractor: External 1159
RR
Contractor Name:
TBD
Field House Sprinkler Installation ‐ PHASE III 6/30/15 Exterior water line has been installed with PC / Careno Construction. Transformer location has been confirmed near AV pad at West Stadium. Reviewing preliminary drawings from Careno / Carter and submit to FM Global for review comment.
Design Firm: SFC Engineering
Henry
3‐ In Construction
Contractor: External 177
SI
Contractor Name:
Careno Construction
Field House ‐ Asphalt parking lot Reconstruction ‐ Design and Improvements Construction Started 6‐9‐15
Design Firm: Tighe & Bond
Contractor: External
Contractor Name:
TBD
Projects in Building
Gregg Hall Cardoso
1.1‐ Plan/Est
Emergency Repair Design Firm: N/A
2575
RR
1
Gregg Hall ‐ Strobic Motor and Drive Replacements Basix scheduled to be complete by Friday, July 3.
Contractor: External
Contractor Name:
Palmer and Sicard
Projects in Building
Hamilton Smith Hall
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 6 of 21
1
PM Status Accountable
Rouleau
2‐ In Design
ID
Project Code
808
SI
PROJECT TITLE
Hamilton Smith Hall ‐ Major Renovation Project 7/1/2015 Update: Design development documents have been reviewed. DD estimate came in above budget; however VM efforts addressed this relatively easily. Design efforts on construction documents are ongoing. Occupants of the rear portion of the building have all been moved into swing space. Abatement is ongoing in the rear portion of the building and will be followed by demolition, which is expected to be complete prior to the fall semester. Installation of temporary services to the front of the building is an ongoing effort that will be complete prior to commencement of demolition of the rear portion. A temporary asphalt walkway has been constructed beyond the construction limits on the T‐Hall side of the building. Construction fencing around the summer/fall construction zone will be installed the first week in July. Foundation and steel work is to occur during the fall semester. The balance of Hamilton Smith will be vacated after finals in December 2015 and the contractor will fully mobilize in January 2016. Construction is expected to be complete such that we can re‐occupy the building in time for fall 2017 classes.
Design Firm: DiMella Shaffer Associates
Contractor: FCT
Contractor Name:
Skanska USA, Inc.
Projects in Building
Health Services Henry
3‐ In Construction
2647
FCR
1
Health Services Retro Commissioning RFS (Jerry Graybill) started project and will start looking closer at building systems on 5‐18.
Design Firm:
Contractor:
Contractor Name:
Projects in Building
Hewitt Annex Cartabona
2.5‐ In Procurement
2775
RR
2
Hewitt Annex ‐ Site Restoration and Utility Isolation 6/30/15 Site restoration and entrance to Hewitt basement to be provided.
Design Firm:
Cartabona
Contractor: External 2.5‐ In Procurement
2417
SI
Contractor Name:
TBD
Hewitt Annex ‐ Building Demolition 6/30/15 Building utilities have been isolated. All material has been removed from the building. DFD will begin training 7/6/15; demo to begin around 7/22.
Design Firm:
Contractor: FCT
Contractor Name:
Envirovantage
Projects in Building
Hewitt Hall Woodcock
1.1‐ Plan/Est
1964
RR
Hewitt Hall ‐ Carpet Investigation and Reinstallation 6/29/15_Estimating costs asoociated with broadloom or carpet square installation.
Design Firm:
Healey
Contractor: External 1.1‐ Plan/Est
2735
FCR
Contractor Name:
TBD
Hewitt Painting of rooms 125, 115 and 111 6/25/15 scheduled to begin the week of 7/6/15
Design Firm:
Contractor: FCT
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 7 of 21
4
PM Status Accountable
Woodcock
3‐ In Construction
ID
Project Code
2057
FCR
PROJECT TITLE
Hewitt Space Renovation 139 & 141 6/29/2015_Construction continues with completion by 8/15/15.
Design Firm: TBD
Healey
3‐ In Construction
Contractor: FCT 2738
FCR
Contractor Name:
Hewitt Painting rooms 183 & 187 Estimate submitted on 6/25/15
Design Firm:
Contractor: FCT
Contractor Name:
Projects in Building
Holloway Hall Cardoso
1.1‐ Plan/Est
2549
FCR
4
Holloway Commons Elevator Improvements Work was completed on March 18. Additional work to be performed during week of July 13.
Design Firm: N/A
Cartabona
3‐ In Construction
Contractor: External 2397
FCR
Contractor Name:
Stanley Elevator
Holloway Upgrade Digital Voice Evacuation System 6/30/15 Norris has recommended smoke detectors throughout the building be replaced as they currently perform weekly inspection of the smoke detector. This proposal will be submitted to OBA for review and approval.
Design Firm:
Cardoso
Contractor: External 3‐ In Construction
1835
FCR
Contractor Name:
Norris Inc.
Holloway Commons ‐ Iron Pipe Investigation As of June 29, pipe replacement is complete with new cleanout installation schedueld to be complete by July 3. Patching of finishes to be completed by July 17.
Design Firm: The Turner Group
Rouleau
3‐ In Construction
1657
Contractor: FCT CP
Contractor Name:
Palmer and Sicard
Holloway Commons ‐ Expansion Project 7/1/2015 Update: Demolition is nearly complete. Significant new construction activity is occurring throughout the existing building. Steel, concrete on deck and roofing have been completed on half of the third floor addition and will be commencing soon on the balance of the third floor addition. Foundation for the main entry/stair/elevator addition was placed yesterday. Related steel framing is to commence imminently. Construction is to continue through early‐February 2016. Dining will be up and running for the fall semester, although the additional seating will not be available until February.
Design Firm: Miller Dyer Spears
Contractor: FCT
Contractor Name:
Horton Hall Healey
3‐ In Construction
2623
FCR
North Branch Construction
Projects in Building
1
Projects in Building
3
Horton Misc work suite 128 6/25/15 Door camera complete
Design Firm:
Contractor: FCT
Contractor Name:
Horton Social Science Center
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 8 of 21
PM Status Accountable
Henry
1.1‐ Plan/Est
ID
Project Code
2552
FCR
PROJECT TITLE
Horton Hall ‐ Renovation of 1st Floor Deferred design until 4th floor work is under way 4‐14‐15
Design Firm: Harriman
Healey
3‐ In Construction
Contractor: External 2478
RR
Contractor Name:
TBD
Horton Hall ‐ Egress Door Hardware Installation 6/25 Removing the installed hardware. Returning partial hardware for credit.
Design Firm:
Henry
Contractor: FCT 3‐ In Construction
2475
FCR
Contractor Name:
Horton Hall ‐Renovation of 4th floor Project under partial Abatement, with Demo on remaining section. 5‐29
Design Firm: Harriman
Contractor: External
Contractor Name:
TBD
Projects in Building
Huddleston Hall Henry
3‐ In Construction
2670
RR
2
Huddleston Hall ‐ Interior Repairs Rooms G03A, G03B, G03E, and G03 Scheduling investigation work on floors and walls May 28/29
Design Firm:
Henry
Contractor: External 3‐ In Construction
2585
RR
Contractor Name:
Milestone
Huddleston Hall ‐ Mechanical Room Repairs DMA funding, will schedule work after May 1st when heating plant shuts down, Stakeholders requesting work start 5‐28/29
Design Firm:
Contractor: External
Contractor Name:
TBD
Projects in Building
Jackson Laboratory Woodcock
3‐ In Construction
2621
RR
Jackson Laboratory ‐ Greenhouse Repair and Restoration 6/29/2015 Repairs are complete to original standards. SFMO requires calculations for snow load. Securing a structural engineer to perform the task.
Emergency Repair Design Firm:
Contractor: External
Contractor Name:
Orlando Greenhouse Sales Inc
James Hall Houde
3‐ In Construction
1
1020
FCR
Projects in Building
1
Projects in Building
1
James, 80 below freezer to generator circuit. Project has been funded ,work is in progress. . 6‐26‐15
Design Firm:
Contractor: FCT
Contractor Name:
Jessie Doe Woodcock
2.5‐ In Procurement
2655
FCR
Jessie Doe ‐ Attic Insulation and Soffit Repairs 6/29/2015_ Renovations complete by FCT. Waiting till August to finalize roofing scope.
Design Firm:
Contractor: FCT
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 9 of 21
PM Status Accountable
ID
Project Code
PROJECT TITLE
Projects in Building
Kendall Hall Cardoso
1.1‐ Plan/Est
2360
RR
3
Kendall Hall ‐ Abatement and Planning Phase 1 work complete as of January 16, 2015. Phase 2 work on floors 2 and 5 was completed on March 25, 2015. Next round of abatement to be coordinated for Fall ʹ15.
Design Firm: TBD
Cardoso
1.1‐ Plan/Est
Contractor: FCT 1773
RR
Contractor Name:
Dec‐Tam
Kendall Hall ‐ Ceiling Tile Abatement Phase I of II Please refer to Project ID 2360 for the status of these activities.
Design Firm: N/A
Cartabona
Contractor: FCT
2‐ In Design
55
RR
Contractor Name:
Dec‐Tam
Kendall Hall Fire Alarm and Emergency Lighting Replacement 6/30/15 SFC Engineering finalizing design documents, expect this project will be issued to purchasing for RFB by 7/15.
Design Firm: SFC Engineering
Contractor: FCT
Contractor Name:
TBD
Projects in Building
Kingsbury Hall Jones
1.1‐ Plan/Est
33
RR
4
Kingsbury Hall ‐ VCT Flooring Repair Rooms N113 and N121 6/26/15: Patch repairs have been completed in N121. PM is developing scope with flooring contractor for repairs/replacement in N113. Construction to begin during week of July 6 and will work around nearby class and occupancy schedules.
Design Firm:
Woodcock
Contractor: External 2‐ In Design
2263
RR
Contractor Name:
Kingsbury Hall ‐ Roof Safety Restraint System Phase II of II 6/29/2015 Out for design with ARM & Safe Approach.
Design Firm: ARM
Woodcock
3‐ In Construction
Contractor: External 1933
FCR
Contractor Name:
TBD
Kingsbury Hall ‐ Area of Refuge Project 6/29/2015_ Scheduling work to start early July
Design Firm: HL Turner
Jones
3‐ In Construction
Contractor: FCT 934
RR
Contractor Name:
Site Stair Replacement ‐ Kingsbury Hall Entrance Stair STR_0141 6/26/15: Construction is continuing, remaining work includes installation of railings and site restoration. Completion date is anticipated July 3, 2015.
Design Firm: Hoyle Tanner
Contractor: External
Contractor Name:
Gauthier Bros.
Projects in Building
Library Storage Building
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 10 of 21
2
PM Status Accountable
Cartabona
2‐ In Design
ID
Project Code
1387
FCR
PROJECT TITLE
Library Storage Building ‐ Review of cooling system capacity 6/30/15 Harriman meeting with UNH to ensure all necessary components of the design are being addressed. New Dean has past experience with mold in storage facility and want to ensure our plan is appropriate.
Design Firm: Harriman Associates
Woodcock
3‐ In Construction
2012
Contractor: External FCR
Contractor Name:
TBD
Library Storage‐ Alarm System Relocation 6/29/2015_ Cleaning up punch list items related to the cameras with UNH IT.
Design Firm:
Contractor: External
Contractor Name:
Norris Inc
MacFarlane Greenhouse Healey
1.1‐ Plan/Est
2768
FCR
Projects in Building
1
Projects in Building
2
MacFarlane Greenhouse Rotten Corner Posts 6/25/15 Walkthrough 6/24 Writing estimate
Design Firm:
Contractor: FCT
Contractor Name:
MacFarlane Grnhse & Pesticide Lab Cardoso
3‐ In Construction
2468
FCR
Greenhouse Small Boiler Installation rm 117 Work is ongoing with completion scheduled by July 17.
Design Firm: TBD
Henry
3‐ In Construction
Contractor: FCT 2538
FCR
Contractor Name:
Palmer and Sicard
MacFarlane Greenhouse ‐ Fume Hood Alarm Upgrades Limited scope of work apporved and funded, scheduling 9‐11‐15
Design Firm:
Contractor: FCT
Contractor Name:
Memorial Union Bldg Henry
3‐ In Construction
2299
FCR
Projects in Building
1
Projects in Building
4
MUB ‐ New Deck Railings Project funded. PO in process, waiting for shop dwgs 6‐11‐15
Design Firm:
Contractor: External
Contractor Name:
Memorial Union Building Healey
1.1‐ Plan/Est
2607
FCR
Milestone
MUB‐ rm 18 est to replace lighting fixtures 6/25/15 Work has been approved & is scheduled for June 29‐ July4.
Design Firm:
Healey
Contractor: FCT 3‐ In Construction
2606
FCR
Contractor Name:
MUB‐ Refinish 45 Doors 6/25/15 Approved. Reviewing list of doors. Most to be done in August
Design Firm:
Contractor: FCT
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 11 of 21
PM Status Accountable
Cardoso
3‐ In Construction
ID
Project Code
1984
FCR
PROJECT TITLE
Memorial Union Bldg permanently divide rooms 158 & 158B Work is proceeding on schedule with completion expected by July 31.
Design Firm: Manypenny‐Murphy
Cartabona
3‐ In Construction
1475
Contractor: External FCR
Contractor Name:
Green Leaf Construction
Memorial Union Building ‐ Lactation Room Floor 3 6/30/15 Construction is complete. Awaiting door signage to arrive. FCT will install automatic opener on restroom.
Design Firm: Mannypenny Murphy
Contractor: FCT
Contractor Name:
Milestone
Projects in Building
Mills Hall Rouleau
1.1‐ Plan/Est
2225
FCR
2
Mills Hall ‐ Chiller Plant Retrocommissioning 7/1/2015 Update: Retrocommissioning is complete except for final verification, which cannot occur until a failed differential pressure sensor is corrected by UNH Zone 3 and there is sufficient load to verify chiller sequencing. As it stands now, only the 250‐ton chiller is operating due to the fact that Holloway Commons is mostly off‐line. It may not be until late‐August or early‐September when students return and Holloway is back on‐line that final verification can occur. Related Projects: Portal ID#s 1443 and 1657
Design Firm: RFS Commissioning
Jones
3‐ In Construction
2278
Contractor: FCT RR
Contractor Name:
Rist‐Frost‐Shumway Engineering (commissionin
Mills to Fairchild ‐ Steam Line Replacement 6/26/15: Onsite construction began on June 24. Anticipated project completion is August 21. Work blocking entrance of Mills will begin July 6 when building is mostly unoccupied.
Design Firm: Harriman
Contractor: External
Contractor Name:
RH White
Morrill Hall Woodcock
1.1‐ Plan/Est
2609
RR
Design Firm:
Projects in Building
4
Morrill Hall ‐ 1st Floor Window Replacement‐ Ice Damage
Contractor:
Contractor Name:
Morse Hall 1.1‐ Plan/Est
1
6/29/2015_Currently estimating repairs, building secure.
Emergency Repair
Healey
Projects in Building
2765
FCR
Morse 163 Build Crate Estimate submitted 6/23/15
Design Firm:
Henry
Contractor: FCT 2.5‐ In Procurement
2384
FCR
Contractor Name:
Morse Hall Renovations rm 345 Have revised drawings, Milestone, looking at cost and schedule 5‐27
Design Firm: Harriman
Contractor: External
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
TBD
Page 12 of 21
PM Status Accountable
Geuther
3‐ In Construction
ID
Project Code
2592
FCR
PROJECT TITLE
Morse Hall ‐ School of Marine Science Renovations 6‐24: Furniture installation scheduled for the week of July 13th. Move scheduled for the week of July 27.
Design Firm: Manypenny‐Murphy Archite Contractor: External
Cartabona
3‐ In Construction
1108
FCR
Contractor Name:
Build‐It Construction
Morse Hall ‐ Redundant Chiller Installation 6/30/15 This project is complete. UNH / Basix / RFS will commission the system 7/2/15.
Design Firm: Leading Edge Design
Contractor: External
Contractor Name:
Eckhardt & Johnson / Yates / Basix
Projects in Building
Nesmith Hall Woodcock
1.1‐ Plan/Est
1972
RR
2
Nesmith Hall ‐ Exterior Brick Wall and Parapet Repointing 6/29/2015_ Working with FCT to secure vendor and extend scope for project 1716.
Design Firm: TBD
Woodcock
3‐ In Construction
Contractor: External 1716
RR
Contractor Name:
TBD
Nesmith Hall ‐ Repair and Renovate 8 Classrooms 6/29/2015_ Under construction through FCT.
Design Firm:
Contractor: FCT
Contractor Name:
Projects in Building
New England Center Henry
3‐ In Construction
1683
FCR
1
New England Center ‐ Relocation of Photo Video Department Construction under way, looking at June completion date 5‐27, In addition working with group to re‐organize, moving 67 staff.
Design Firm: Harriman / Many Penny
Contractor: External
Contractor Name:
Milestone
New Hampshire Hall Woodcock
2.5‐ In Procurement
940
RR
Projects in Building
1
Projects in Building
2
New Hampshire Hall ‐ Major Roof Replacement 6/29/2015_ Project to be re‐bid in late fall for a May 2016 start.
Design Firm: TBD
Contractor: External
Contractor Name:
TBD
NHVDL Cartabona
3‐ In Construction
2053
RR
NHVDL ‐ Campus Deferred Repair Costs reported with ID 1537
Design Firm: Port City Architecture
Cartabona
3‐ In Construction
1537
Contractor: External SI
Contractor Name:
Allied Cook
NHVDL Relocation 6/30/15 Interior sheetrock is ongoing. Equipment / casework to begin arriving in July. Schedule completion / move in August 2015.
Design Firm: Port City Architecture
Contractor: External
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Allied Cook
Page 13 of 21
PM Status Accountable
ID
Project Code
PROJECT TITLE
Projects in Building
Parsons Hall Jones
1.1‐ Plan/Est
1030
RR
3
Parsons Hall ‐ Hallway Ductwork Insulation / Ceiling Repairs 6/26/15: PM has engaged services of term mechanical engineer to view sweating ductwork if it occurs and recommend possible solutions. PM has also been in contact with renovation architect to troubleshoot. Chemistry department is closing doors to stairwells. PM is working with FCT to seal doorways.
Design Firm:
Cartabona
Contractor: FCT 2‐ In Design
2626
RR
Design Firm: EYP 2‐ In Design
Parsons Hall ‐ Processed Chiller Modifications 6/30/15 EYP submitted suggetions for adjustment, however UNH cannot verify the sensors are installed. EYP will follow up with UNH week of 7/6.
Emergency Repair
Woodcock
Contractor Name:
Contractor: External 1704
RR
Contractor Name:
TBD
Parsons Hall ‐ Mechanical Penthouse Waterproofing DESIGN ONLY 6/29/2015_ Schematics in for review and estimating.
Design Firm: EYP/ARM
Contractor: TBD
Contractor Name:
Projects in Building
Paul Creative Arts Center Jones
2‐ In Design
2286
RR
4
PCAC ‐ Front Entrance and Foundation Drainage Repairs‐ DESIGN ONLY 6/26/15: design is complete (refer to project 2290 for construction updates)
Design Firm: Tighe & Bond
Cartabona
2.5‐ In Procurement
Contractor: 46
RR
Contractor Name:
PCAC Sprinkler Installation and Egress Modifications DESIGN 6/30/15: Awaiting confirmation from Port City Architecture, if less 20% wall coverage installed tack board solution may be modified.
Design Firm: Port City Architecture/ SFC E Contractor: FCT
Cartabona
2.5‐ In Procurement
1157
RR
Contractor Name:
PCAC ‐ Egress Modifications Phase 1 of 2 Please refer to ID 46 for ongoing updates ‐ All work will be reported and tracked ID 46.
Design Firm: Port City Architecture / SFC
Jones
3‐ In Construction
2290
RR
Contractor: FCT
Contractor Name:
TBD
PCAC ‐ Art Wing Foundation Drainage Repairs 6/26/15: Project is under construction and on schedule. Drain line installation is complete along the art wing of PCAC. Remaining work includes grass seed and sitting wall, to be completed by July 3.
Design Firm:
Contractor: External
Contractor Name:
T&S
Projects in Building
Pettee Hall
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 14 of 21
2
PM Status Accountable
Jones
1.1‐ Plan/Est
ID
Project Code
2317
RR
PROJECT TITLE
Site Stair Replacement and Pettee Hall Drainage Repairs 6/26/15: Design is complete. Funds for construction have been tentatively deferred to FY2016, but the project will be bid‐ready should funds become available for construction in summer 2015.
Design Firm: Hoyle Tanner
Cartabona
2‐ In Design
Contractor: 2631
RR
Contractor Name:
Pettee Hall ‐ Restoration and Recommissioning HV‐1 and HV‐2 6/30/15: RFS has identified areas to isolate and identify difficencies. Preparing a method to balance and retro commission the building. Also, emergency lighting inverter failed due to moisture in mechanical room, this work will be added to the scope as well as cleaning mechanical room, modifying drainage and epoxy floor.
Emergency Repair
Design Firm: RFS
Contractor: FCT
Contractor Name:
TBD
Philbrook Dining Hall Houde
3‐ In Construction
2686
FCR
Projects in Building
1
Projects in Building
1
Dining upgrading biometric readers and turnstiles Work is in progress. 6‐30‐15
Design Firm:
Contractor: FCT
Contractor Name:
Philbrook Hall Cartabona
2‐ In Design
2492
FCR
Philbrook Refrigeration Rack System 6/30/15 Harriman design proposal has been submitted to OBA for funding / approval.
Design Firm: Harriman Assoc.
Contractor: External
Contractor Name:
TBD
Projects in Building
Presidents House Geuther
2‐ In Design
2650
RR
1
Presidents House ‐ Porch Enclosure and ADA Modifications 6‐24: Construction Documents have been reviewed and are being completed. Waiting for confirmation on scheduled start date which is anticipated to be the week of July 6.
Design Firm: ManyPenny‐ Murphy Archit
Contractor: External
Contractor Name:
Milestone Construction
Projects in Building
Putnam Hall Houde
3‐ In Construction
2006
FCR
1
Putnam Hall ‐ Room Renumbering Welch sign would like to install on 7‐06015. Waiting on OK from dept. 6‐30‐15
Design Firm:
Contractor: FCT
Contractor Name:
Projects in Building
Ritzman Lab Cartabona
2.5‐ In Procurement
Welch sign
1794
FCR
1
Ritzman Lab ‐ Conference Room Technology 6/16/15: New monitor for floor 1 space as well as furniture for both rooms.
Design Firm:
Contractor: FCT
Contractor Name:
Adtech / Creative Office Pavillion
Projects in Building
Roads/Grounds
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 15 of 21
10
PM Status Accountable
Pesci
1.1‐ Plan/Est
ID
Project Code
295
SI
Design Firm:
Bencks
1.1‐ Plan/Est
184
SI
1.1‐ Plan/Est
2767
RR
Contractor Name:
Ravine Culvert Replacement 6/26/15: PM has reviewed project and tentatively plans to repair pavement by mid‐August. UNH Facilities to consider complete culvert re‐design and replacement project in summer 2016.
Design Firm:
Contractor: 2‐ In Design
Contractor Name:
Signs ‐ Campus wayfinding and University building sign improvements
Contractor:
Emergency Repair
Henry
Bike Rack Installations
Contractor:
Design Firm:
Jones
PROJECT TITLE
1115
SI
Contractor Name:
South Drive ‐ Design Advancement Permits approved, this phase of the design complete. CP looking for funding options, nothing scheduled for 2014.
Design Firm: Tigh & Bond
Henry
2‐ In Design
Contractor: External 1142
RR
Contractor Name:
MUB / Ravine Walkway Replacement ‐ DESIGN ONLY Heating Line SOW added to project, and now requires changes in building, Harriman added to design team, Design will resume this summer , construction Summer 2016. Design back on track 5‐27‐15
Design Firm: Tigh & Bond
Jones
2‐ In Design
Contractor: External 2692
RR
Contractor Name:
TBD
2016 Sidewalk and Walkway Repairs 6/26/15: POs have been issued for walkway repairs at corners of Edgewood & Main, Main Street near Scott Hall, Morrill, and Edgewood Road near McLaughlin. Schedule of repairs TBD. Smith parking lot repair is complete.
Design Firm:
Jones
Contractor: External 2‐ In Design
1728
RR
Contractor Name:
2016 Road Repairs and Crack Sealing 6/26/15: Project is in planning stage for construction in summer 2015. Areas to be crack sealed potentially include T‐Hall parking lot, College Road, and Ballard Street. PM has contacted crack sealing contractor to begin estimates and scheduling.
Design Firm:
Jones
Contractor: 2‐ In Design
1739
RR
Contractor Name:
2016 Site Stair Repairs 6/26/15: Pos have been issued for stair repairs at Dimond Library entrance, eastern side of Murkland, PCAC exit only doorway, and the wall between Fairchild and Huddleston. Specific dates have not been set, but work will be finished by August 21.
Design Firm:
Contractor:
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 16 of 21
PM Status Accountable
Houde
3‐ In Construction
ID
Project Code
75
SI
PROJECT TITLE
University Campus Exterior Lighting Improvements All the exterior lighting has been installed. It needs to be reviewed. , There is a small punch list. 6‐25‐15
Design Firm:
Henry
Contractor: 3‐ In Construction
1117
SI
Contractor Name:
Morce Circle Covered Bike Parking Bike Racks installed, waiting for closeout information 5‐27
Design Firm:
Contractor: External
Contractor Name:
TBD
Projects in Building
Rudman Hall Houde
1.1‐ Plan/Est
764
RR
5
Rudman/Spaulding Hall ‐ Replacement of built in Glass Washers Phase II of II The dept has to choose the product. . 6‐27‐15
Design Firm:
Cartabona
Contractor: 1.1‐ Plan/Est
2352
RR
Contractor Name:
Rudman Hall ‐ Fire Alarm Replacement Fire alarm installation will occur following design. Coordinate acitivity with building occupants prior to construction schedule.
Design Firm:
Cartabona
Contractor: 2‐ In Design
1149
RR
Contractor Name:
Rudman Hall ‐ Fire Alarm design 6/30/15 SFC to provide 50% drawings by end of July 2015
Design Firm: SFC Engineering
Cartabona
3‐ In Construction
Contractor: External 1787
RR
Contractor Name:
TBD
Rudman Hall ‐ Fume Hood / HVAC Modifications and Repairs 5/26/15 FCT sealed pipe penetrations in shaft 122 / 222 / 322 week of 5/18. Also assist with coordination steam insulation on pipe above 322 ceiling. Next step is to begin replacing all controls on floor 3 that are not Andover controls.
Design Firm: RFS
Henry
3‐ In Construction
Contractor: FCT 2591
FCR
Contractor Name:
TBD
Rudman G15 Office Space Configuration Project is almost finished, working on commissioning and close out. 6‐11‐15
Design Firm: Harriman
Contractor: External
Contractor Name:
Milestone
Projects in Building
Service Building Cardoso
1.1‐ Plan/Est
1465
RR
Service Building ‐ Replacement and Installation of Isolation valves Meeting to be scheduled with Zone Manager in July to review scope.
Design Firm: N/A
Contractor: External
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
TBD
Page 17 of 21
4
PM Status Accountable
Woodcock
2‐ In Design
ID
Project Code
2593
RR
PROJECT TITLE
Service Building ‐ Ice Melt System Fire Dept Roof 6/29/2015_ Ice melt in proposal phase.
Design Firm:
Cardoso
Contractor: FCT 2‐ In Design
2358
RR
Contractor Name:
Service Building ‐ Heating Line Replacement Design Harriman Associates has been selected as the design firm. Design began in June 2015. Construction anticipated for summer 2016.
Design Firm: Harriman Associates
Henry
3‐ In Construction
2331
Contractor: External FCR
Contractor Name:
TBD
Service Bldg DFD Kitchen new vent hood rm F214 Instillation under way, FCT has an issue with the Hood, bad electronics, part on order. 5‐27
Design Firm:
Contractor: FCT
Contractor Name:
Projects in Building
Spaulding Hall Henry
2.5‐ In Procurement
1000
RR
4
Spaulding Hall ‐ VAT Abatement Rooms G07, G11, and G27 Working on a flooring repair, schedule to be developed by FCT. 5‐27
Design Firm:
Cardoso
Contractor: FCT 3‐ In Construction
2745
RR
Contractor Name:
Spaulding Hall ‐ Sewer Vent and Mechanical System Replacements As of June 29, working with Shawmut Construction to complete work finalize costs being tracked on a time and material basis. Please see ID 2157 for additional updates.
Design Firm: HL Turner
Henry
3‐ In Construction
Contractor: External 2539
FCR
Contractor Name:
Shawmut Design and Construction
Spaulding Hall ‐ Fume Hood Alarm Upgrades Limited scope of work apporved and funded, scheduling 9‐11‐15
Design Firm:
Cardoso
Contractor: FCT 3‐ In Construction
2157
FCR
Contractor Name:
Spaulding Hall ‐ Instructional Improvements to Rooms 140, 150 and 160 As of June 29, MEP rough‐in is subtantially complete with drywall and masonry wall reinstallation ongoing. Overall progress currently on schedule for an August 7 completion.
Design Firm: The HL Turner Group
Contractor: FCT
Contractor Name:
Stoke Hall Healey
2.5‐ In Procurement
2619
FCR
Shawmut
Projects in Building
1
Projects in Building
1
Stoke Hall ‐ Water Meter Installation 6/25/15 Scheduled to begin June 27
Design Firm:
Contractor: FCT
Contractor Name:
TELECOMMUNICATIONS CENTER
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 18 of 21
PM Status Accountable
Cardoso
3‐ In Construction
ID
Project Code
1993
FCR
PROJECT TITLE
Telecom Air Conditioning Infrastructure As of June 29, the new cooling units at the Telecomm Building are operational with Gregg Hall scheduled to be completed by July 6.
Design Firm: WV Engineering
Contractor: FCT
Contractor Name:
Green Leaf Construction
Projects in Building
Thompson Hall Cartabona
2‐ In Design
2727
RR
1
Thompson Hall ‐ Presidents/Trustee Conference Rooms AC 6/30/15 Review short term / long term solution for AC at President Conference Room and Lubow conference room. Harriman will review chilled water capacity in the building to install ductless split system in both conference room.
Design Firm: Harriman
Contractor: FCT
Contractor Name:
Projects in Building
Utility Distribution Jones
1.1‐ Plan/Est
1750
RR
5
McDaniel Drive Steam Vault Repairs Phase II 5/26/15: Contractor has finished working in pits 3, 6, and 7. Repairs to steam line conduit near pit 2 were on hold as contractor waited for material delivery. Anticipated completion is May 29.
Design Firm: Harriman
Jones
2‐ In Design
Contractor: External 2362
RR
Contractor Name:
RH White
Quad Way ‐ Utility Line Replacement (Design Only) 6/26/15: Project is in planning stage for construction in summer 2016. Design is under contract and will be completed by October 31, 2015.
Design Firm: Tighe & Bond
Houde
3‐ In Construction
Contractor: 2555
FCR
Contractor Name:
Sub Station 3 ‐ Transformer Repairs/Replacement Work is in progress, The old equipment has been removed. The new transformer is in place. The new swithgear expected mid Aug. I expect completion before Sept 1 5‐26‐15
Design Firm:
Jones
Contractor: 3‐ In Construction
2058
RR
Contractor Name:
Main Street ‐ Structural Tunnel Concrete Repairs 6/26/15: Onsite construction is continuing on schedule. Steam shutdown to remove bypass is scheduled for July 7, 2015. Final completion is anticipated by July 31.
Design Firm: Hoyle Tanner
Houde
3‐ In Construction
Contractor: External 2658
SI
Contractor Name:
RH White
Ravine Electrical Circuit 11B Extension Project is funded. Contractor has PO. The temp power to the Hood hse, Ham‐Smith project is in place. On July 10th the front of H/S will be placed on temp cirt. #4. On July 11th cirt #2 will be disconnected in pit 8‐9 and H/S 1968 power will be connected to temp power circuit #4. , 6‐30‐15
Design Firm:
Contractor: External
Contractor Name:
IC Reed & Sons Inc.
Projects in Building
VISITORS INFORMATION CENTER
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 19 of 21
2
PM Status Accountable
Cartabona
2‐ In Design
ID
Project Code
2396
FCR
PROJECT TITLE
Visitors Information Center ‐ Fire Alarm System/Replacement 6/30/15 FCR submitted to OBA for approval. Review scope of work with Norris Inc to determine if this work could be completed with term agreement and installation complete summer 2015.
Design Firm: SFC Engineering
Houde
3‐ In Construction
Contractor: External 2379
FCR
Contractor Name:
Norris Inc.
Visitors Information Center ‐ Install & Activate CNG Refueling Equipment Project plan has been presented to the SFMO. Work will progress with the understanding engineering to back up any progress will be provided before final inspections.Work is progressing 6‐30‐15
Design Firm:
Contractor: FCT
Contractor Name:
Badger Rand / Yates & others
Projects in Building
Water Treatment Plant Hagstrom
2‐ In Design
38
SI
1
UNH R&R Water Treatment Plant Improvements spring pilot test complete. Wright Pierce to provide report. fall testing to start 10/15. will do subsurface investigation at waterworks site this summer
Design Firm: Wright‐Pierce
Contractor: External
Contractor Name:
Projects in Building
West Stadium Geuther
3‐ In Construction
1947
SI
1
West Stadium ‐ Design and Construction of New Facility 6‐24: Site work and site electrical is on going. Blasting complete. Piles being installed. Scheduled to start concrete foundations within two weeks. Finalizing 1B.
Design Firm: Populous/LaVallee Brensinge Contractor: External
Contractor Name:
PC Construction
Projects in Building
Whittemore Center Cartabona
1.1‐ Plan/Est
2720
FCR
2
Whittemore Center ‐ Arena Ice Making System Mechanical Replacements 6/30/15 FCT will relocate operations personnel 7/2; Milestone will begin preparation for chiller removal on 7/6 ‐ opening will be prepared no later than 7/17. American Refrigerations (ARC) will begin on site 8/10/15 following all summer hockey camps. This work is scheduled to be complete 8/27 to allow for UNH hockey team to begin using ice for practice.
Design Firm: Hoyle Tanner
Cartabona
3‐ In Construction
Contractor: FCT 2721
FCR
Contractor Name:
American Refrigeration Company, Inc. / Milesto
Whittemore Center ‐ Arena Block Wall Removal and Structural Support Installation 6/30/15 ‐‐ Please refer to 2721 for updates
Design Firm:
Contractor:
Contractor Name:
Projects in Building
WHITTEMORE CENTER ‐ ARENA Houde
2‐ In Design
2578
FCR
Whittemore Center ‐ Arena ‐ Generator Upgrade The study is in progress I expect OPA to supply results of the study in a week or so. . 6‐30‐15
Design Firm: OPA
Contractor:
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 20 of 21
2
PM Status Accountable
Houde
2‐ In Design
ID
Project Code
2581
FCR
PROJECT TITLE
Whittemore Center ‐ Arena Ice Sensor System Back Up Power The study is in progress I expect a report from OPA in a week or so. . 6‐30‐15
Design Firm: OPA
Contractor:
Contractor Name:
Projects in Building
WHITTEMORE CENTER ‐ HAMEL Hagstrom
3‐ In Construction
1176
CP
1
Hamel Recreation Center ‐ Renovation and Expansion Project CDʹs in. 2 addenda upcoming. GMP due 7/17. Piles complete. Pile caps starting.
Design Firm: HGA
Contractor: External
Contractor Name:
Shawmut
Whittemore Center Arena Woodcock
3‐ In Construction
2584
FCR
Projects in Building
1
Projects in Building
1
Whittemore Center ‐ Arena ‐ Videoboard 6/29/2015_Awarded project, and scheduling kick‐off meetings.
Design Firm: AJP
Contractor: External
Contractor Name:
Daktronics
Woodside Community Center Healey
1.1‐ Plan/Est
2708
FCR
WOODSIDE APTS COMMUNITY BUILDING ‐ Door Estimate submitted on 5/19/15
Design Firm:
Contractor: FCT
Contractor Name:
Brenda Whitmore, Director
Facilities Project Management
Wednesday, July 01, 2015
University of New Hampshire
Page 21 of 21