ENVIRONMENTAL MANAGEMENT PLAN MIDSTREAM OPERATIONS LNGOP QL00 ENV PLN

ENVIRONMENTAL MANAGEMENT PLAN  – MIDSTREAM OPERATIONS  LNGOP‐QL00‐ENV‐PLN‐000002     Revision 0  January, 2014    QGC Midstream Operations  Environ...
Author: Collin Owen
2 downloads 0 Views 9MB Size
ENVIRONMENTAL MANAGEMENT PLAN  – MIDSTREAM OPERATIONS  LNGOP‐QL00‐ENV‐PLN‐000002     Revision 0  January, 2014 

 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

MIDSTREAM OPERATIONS  

ENVIRONMENTAL MANAGEMENT PLAN  Scope and application  This Operational Environmental Management Plan (OEMP), along with Appended subsidiary Plans, addresses  environmental management, monitoring and reporting requirements for operation of the Queensland Curtis  Liquefied Natural Gas (QCLNG) Project LNG Facility on Curtis Island.    It has been prepared with reference to the requirement for:  

an Operations Environmental Management Plan specified in the Coordinator General’s Report for the  QCLNG Project (Appendix 4, Part 3, Condition 2); 



an Operational Environmental Management Plan specified in the approval for the LNG Plant and Onshore  Facilities made under Sections 130(1) and 133 of the Environment Protection and Biodiversity Conservation  Act 1999 (EPBC Act) (Cth) (Approval EPBC 2008/4402, Conditions 26 to 28 inclusive); 



an Operational Environmental Management Plan covering the LNG Jetty (Condition 23 of Gladstone Ports  Corporation Concurrence Agency Response to the Development Application for Operational Works ‐  Prescribed Tidal Works (including the Disturbance of Marine Plants) for the LNG Jetty ‐ DA/429/2011); 

Further, this OEMP, along with subsidiary referenced management plans and procedures, is intended to address all  applicable environmental management, monitoring and reporting requirements for the LNG Facility specified in:  

Environmental Authority for Petroleum Facility Licence PFL11 (EPPG00711513); 



Operational Works Permits for the LNG Jetty, Materials Offloading Facility (MOF), Construction Dock and  tidal works within the bounds of PFL11; and 



Approvals for the LNG Facility and associated marine facilities made under the EPBC Act (Marine Facilities  Approval – 2008/4401; and LNG Facility Approval – 2008/4402. 

 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 2 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

  Table of Contents  1.0 



INTRODUCTION 

1.1.  Scope of Document 



1.2.  Document Revisions and Approval 



1.3.  Distribution and Intended Audience 



1.4.  Definitions 



1.5.  Acronyms and Abbreviations 

10 

1.6.  Referenced / Associated Documents 

11 

1.7.  Organisation Structure and Responsibilities 

12 

2.0 

15 

OEMP STRUCTURE AND LNG FACILITY HSSE MANAGEMENT SYSTEM 

2.1.  HSSE Policy and EMS 

15 

2.2.  OEMP Outline 

15 

3.0 

16 

SITE LOCATION AND FACILITY DESCRIPTION 

3.1.  Project Scope 

16 

3.2.  Description of Petroleum Tenures 

16 

3.3.  QCLNG Curtis Island Site 

19 

3.3.1.  Location and Facilities  3.3.2.  Meteorological Conditions  3.3.2.1. Temperatures  3.3.2.2. Relative Humidity  3.3.2.3. Wind  3.3.2.4. Rainfall 

19  19  19  19  19  19 

3.4.  Description of Petroleum Activities 

20 

3.5.  Facility Description 

20 

3.5.1.  LNG Process  3.5.1.1. Gas Pre‐treatment  3.5.1.2. Gas Liquefaction  3.5.1.3. LNG Storage and loading facilities  3.5.2.  Utilities  3.5.2.1. Refrigerant and Diesel Storage  3.5.2.2. Power Generation  3.5.2.3. Hot Oil System  3.5.2.4. Fuel Gas System  3.5.2.5. Plant and Instrument Air  3.5.2.6. Nitrogen Storage and Distribution  3.5.2.7. Fire Protection  3.5.2.8. Flare and Vent System  3.5.2.9. Water Systems  3.5.3.  Associated Pipelines  3.5.4.  Site Buildings and Helipad 

21  22  23  25  28  28  29  30  30  30  31  31  32  33  34  34 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 3 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

3.6.  Project Life and Phases 

4.0 

35 

3.6.1.  Construction and Commissioning Interface  3.6.2.  Project Life 

35  35 

ENVIRONMENTAL CONTEXT 

36 

4.1.  Identification of environmental values and potential impacts on environmental values from the activities 

36 

4.2.  Environmental protection commitments 

36 

5.0 

37 

ENVIRONMENTAL VALUES, MANAGEMENT AND MONITORING STRATEGIES 

5.1.  Air Emissions 

37 

5.1.1.  Description of Environmental Values  37  5.1.2.  Site Emissions Sources  40  5.1.3.  Emissions Reduction through Application of Best Techniques in Design  45  5.1.4.  Potential adverse or beneficial impacts of the project activities on the identified environmental values49  5.1.4.1. EIS Summary of Impacts  49  5.1.4.2. Updated Assessment of Impacts  51  5.1.5.  Management, Monitoring and Corrective Action  52  5.2.  Visual Impact and Light 

52 

5.2.1.  Description of Environmental Values  5.2.2.  Potential Impacts  5.2.2.1. Visual Amenity  5.2.2.2. Night Lighting  5.2.3.  Potential Light Impacts – Impacts of Flaring on Marine Turtles  5.2.3.1. Post‐EIS Assessment of Flare Visibility from Nesting Sites and Impact on Marine Turtles  5.2.3.2. Potential Impacts from Light Below the Horizons  5.2.3.3. Conclusion  5.2.4.  Mitigation Measures in Design  5.2.5.  Management, Monitoring and Corrective Action  5.3.  Noise 

52  52  52  53  53  54  54  55  57  60  60 

5.3.1.  Description of Environmental Values  60  5.3.1.1. Background Noise Monitoring  61  5.3.1.2. Analysis and Summary of Results  62  5.3.2.  Potential adverse or beneficial impacts of the project activities on the identified environmental values63  5.3.2.1. Noise Criteria  63  5.3.2.2. Noise Modelling  63  5.3.2.3. Summary of Noise and Vibration Impacts  64  5.3.3.  Management, Monitoring and Corrective Action  64  5.4.  Surface Water 

64 

5.4.1.  Description of Environmental values – Surface Water  64  5.4.2.  Description of Environmental values – Receiving Environment  65  5.4.2.1. Rodds Bay Dugong Protection Area  66  5.4.2.2. Seagrass and other Benthic Habitat  66  5.4.2.3. Reef Habitat  70  5.4.3.  Potential adverse or beneficial impacts of the project activities on the identified environmental values72  5.4.4.  Description of Site Water Management  72  5.4.4.1. Stormwater Management  72  5.4.4.2. Inlet Air Chill Condensate  73  5.4.4.3. Process / Oily Water (Unit 29)  74 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 4 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.4.4.4. Reverse Osmosis / Electro‐deionisation (Unit 36)  5.4.5.  Management, Monitoring and Corrective Action 

78  83 

5.5.  Waste Management 

83 

5.6.  Biodiversity 

83 

5.7.  Weeds, Pests and Quarantine 

83 

6.0 

DECOMMISSIONING AND REHABILITATION 

83 

6.1.1.1. Overview  6.1.1.2. Contaminated land  6.1.1.3. Rehabilitation 

83  85  85 

7.0 

ENVIRONMENTAL CONTINGENCIES AND EMERGENCY RESPONSE 

85 

8.0 

COMPLAINTS AND INCIDENT MANAGEMENT 

86 

9.0 

AWARENESS, TRAINING AND COMPETENCY 

86 

10.0  PERIODIC REVIEWS, AUDITS AND CONTINUOUS IMPROVEMENT 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

87 

Revision: 0  Page 5 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Tables Table 1: Referenced / Associated Documents ................................................................................................................... 11  Table 2: Key Management Responsibilities ........................................................................................................................ 12  Table 3: OEMP Plans and Procedures ................................................................................................................................ 15  Table 4: EHP Monitoring Sites for Gladstone ..................................................................................................................... 37  Table 5: Maximum 1‐Hour Average And Annual Average Concentration Of Nitrogen Dioxide (µg/M3) .......................... 38  Table 6: Summary of Annual Measurements of Sulphur Dioxide from the DERM Targinie Monitoring Sites (µg/m3) ..... 39  Table 7: Summary of Emissions Sources ............................................................................................................................ 43  Table 8: Summary of Best Available Techniques Assessment Outcomes as Applicable to Air Quality (assessment per  LNG Train) ........................................................................................................................................................................... 47  Table 9: Indicative Site Slope Stabilisation Summary ......................................................................................................... 57  Table 10: Noise Assessment Locations ............................................................................................................................... 61  Table 11: Unattended Noise Monitoring Locations ........................................................................................................... 61  Table 12: Unattended Monitoring RBL Results dB(A) ........................................................................................................ 62  Table 13: Noise Criteria for Project Noise Assessment Locations ...................................................................................... 63  Table 14:  Description and areas of habitat, including seagrass meadows, in Port Curtis ................................................. 67  Table 15:  Indicative IAC condensate production ............................................................................................................... 73  Table 16: Oily Water Treatment ‐ Design Influent and Effluent Water Characteristics ..................................................... 76 

Figures Figure 1: Facility Location – GSDA ...................................................................................................................................... 17  Figure 2: Facility Layout – Two Train Complete ................................................................................................................. 18  Figure 3: Optimized Cascade Process ................................................................................................................................ 21  Figure 4: LNG Process Flow – Process Units ....................................................................................................................... 21  Figure 5:  LNG Storage Tanks ‐ Schematic .......................................................................................................................... 25  Figure 6: LNG Loading Layout ............................................................................................................................................ 27  Figure 7: Refrigerant Storage Location .............................................................................................................................. 29  Figure 8: Firewater Pumps and Fire Main .......................................................................................................................... 32  Figure 9: Locations of QCLNG Static Emissions Sources ..................................................................................................... 42  Figure 10: Port Curtis Turtle Nesting Beaches and Seagrass Distribution .......................................................................... 56  Figure 11: Indicative Site Slope Stabilisation Plan .............................................................................................................. 59  Figure 12: Rodds Bay Dugong Protection Area .................................................................................................................. 66  Figure 13: Port Curtis Seagrass Meadow and Mangrove Habitat 2002‐2010 .................................................................... 69  Figure 14: Deep water benthic macro‐invertebrate regions in Port Curtis and Rodds Bay, November/December 2002 . 71  Figure 15: CPI Schematic .................................................................................................................................................... 75  Figure 16: Oily Water Flow Diagram .................................................................................................................................. 77  Figure 17: Site Service/Potable Water Management and Distribution .............................................................................. 79  Figure 18: Filtered / Demineralised Water System Overview ............................................................................................ 80  Figure 19: RO Cutaway ....................................................................................................................................................... 82 

Appendices

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 6 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Appendix A – QGC HSSE Policy 

88 

Appendix B – Gladstone and QCLNG Site Wind Roses 

89 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 7 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

1.0

Issue date: September 2013   Review due: September 2014  

INTRODUCTION 

1.1. SCOPE OF DOCUMENT  This  Operational  Environmental  Management  Plan  (OEMP)  addresses  environmental  management  for  operation of the Queensland Curtis Liquefied Natural Gas (QCLNG) Project LNG Facility on Curtis Island (the  LNG Facility).    QCLNG  Operating  Company  (QCLNG  Op  Co)  will  be  the  Operator  of  the  LNG  plant  for  normal  operations.  Bechtel Corporation (Bechtel), as the Engineering Procurement Construction (EPC) contractor for the QCLNG  Project,  is  responsible  for  the  design,  installation,  construction,  commissioning,  start‐up,  performance  testing, operation and maintenance until handover of the QCLNG Facility to QCLNG Op Co.  This  document  is  applicable  to  LNG  Operations  undertaken  by  QCLNG  Op  Co  following  handover  from  Bechtel.  It  therefore  does  not  consider  environmental  management  associated  with  construction  or  commissioning  of  the  LNG  Facility  as  undertaken  by  Bechtel.    Environmental  management  of  construction  and  commissioning  activities  will  be  undertaken  under  Environmental  Management  Plan(s)  specific  to  the  relevant stage of the Project, including the Bechtel Construction Environmental Control Plan(s) (CECP) and/or  Commissioning and Start‐Up Environmental Management Plan(s), as applicable.    Dredging,  shipping  or  other  marine  activities  associated  with  the  QCLNG  Project,  either  in  the  Port  of  Gladstone  or  elsewhere  are  excluded  from  this  OEMP  except  to  the  extent  that  the  vessels  are  using  wharves, jetties or other LNG Facility infrastructure.  While the QCLNG Project Environmental Impact Statement (EIS) assessed environmental impacts for a three  train  LNG  Facility,  only  two  LNG  Trains  are  currently  under  construction.    This  OEMP  addresses  site  environmental management based on the two train LNG Facility layout, and will be amended as required to  address future LNG trains.     This OEMP has been prepared with consideration for the requirement for:  

an Operations Environmental Management Plan for the LNG Facility as specified in the Coordinator  General’s Report for the QCLNG Project (Appendix 4, Part 3, Condition 2); 



an  Operational  Environmental  Management  Plan  specified  in  the  approval  for  the  LNG  Plant  and  Onshore  Facilities  made  under  sections  130(1)  and  133  of  the  Environment  Protection  and  Biodiversity Conservation Act 1999 (EPBC Act) (Cth) (Approval EPBC No. 2008/4402, Conditions 26 to  28 inclusive); and 



an Operational Environmental Management Plan covering the LNG Jetty (Condition 23 of Gladstone  Ports  Corporation  Concurrence  Agency  Response  to  the  Development  Application  for  Operational  Works  ‐  Prescribed  Tidal  Works  (including  the  Disturbance  of  Marine  Plants)  for  the  LNG  Jetty  ‐  DA/429/2011). 

Further,  this  OEMP,  along  with  subsidiary  referenced  management  plans  and  procedures,  is  intended  to  address applicable environmental management, monitoring and reporting requirements for operation of the  LNG Facility specified in:  

Environmental Authority (EA) for Petroleum Facility Licence (PFL) 11 (EPPG00711513). 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 8 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  



The Material Change of Use approval for the QCLNG LNG Facility (DGBN11_389). 



Operational  Works  Permits  for  the    LNG  Jetty,  Materials  Offloading  Facility  (MOF),  Construction  Dock, and other tidal works, and specifically: 



-

DA/429/2011  ‐  Operational  Works  ‐  Prescribed  Tidal  Works  (including  the  Disturbance  of  Marine Plants) for the LNG Jetty. 

-

DA/120/2010  ‐  Operational  Works  ‐  Prescribed  Tidal  Works  for  Curtis  Island  Construction  Dock (including disturbance of marine plants). 

-

DA/239/2010  ‐  Operational  Works  ‐  Prescribed  Tidal  Works  (including  the  Disturbance  of  Marine Plants) for Tidal Area Infrastructure at Curtis Island. 

-

DA/190/2010  ‐  Prescribed  Tidal  Works  Marine  Offloading  Facility,  Lot  2,  SP228454  and  SP228185. 

Approvals for the LNG Facility and associated marine facilities made under the EPBC Act, specifically:  -

Approval  to  develop,  construct,  operate  and  decommissioning  the  marine  facilities  component  of  the  QCLNG  LNG  Project  as  described  in  referral  EPBC  2008/4401  (Marine  Facilities Approval – 2008/4401). 

-

Approval:  Queensland  Curtis  LNG  Project  –  LNG  Plant  and  Onshore  Facilities  –  EPBC  No  1008/4402 (LNG Facility Approval – 2008/4402). 

1.2. DOCUMENT REVISIONS AND APPROVAL  This document has been prepared by Don Stockton, LNG Operations Permits and Licensing Coordinator, and  shall be reviewed and endorsed in accordance with the RACIE Matrix.   This  document  bears  a  revision  status  identifier  which  will  change  with  each  revision.  All  revisions  to  this  document (after approval and distribution) will be subject to review and endorsement by the same functions  as the original. 

1.3. DISTRIBUTION AND INTENDED AUDIENCE  This document is intended for Midstream (LNG Operations) members as well as other QGC stakeholders. The  document  will  be  made available  on  the  Document  Control  System.  This  document  will  be  updated  during  subsequent lifecycle stages and changes communicated to the team as applicable.  

1.4. DEFINITIONS  In this document, the following definitions apply:  Term  

Meaning 

CG Report 

The Queensland Curtis LNG Project:  Coordinator‐General’s Report on the Environmental  Impact Statement (June 2010) 

LNG Facility 

The QCLNG Facility located on Curtis Island Site and including the LNG plant, LNG loading  facilities, utilities and associated infrastructure. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 9 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

1.5. ACRONYMS AND ABBREVIATIONS   In this document, the following acronyms and abbreviations apply:  Acronym/Abbreviation 

Meaning 

BWRO 

Brackish Water Reverse Osmosis Package 

CECP 

Construction Environmental Control Plan (Bechtel CECP, which forms a component  of the site Framework CEMP) 

CEMP 

Construction Environmental Management Plan   

CG 

Coordinator General (Queensland) 

CIIP 

Curtis Island Industry Precinct 

DA 

Development Application 

DCS 

Distributed Control System 

DGA 

Diglycolamine 

DPIF 

Department of Primary Industries and Fisheries 

EA 

Environmental Authority for Petroleum Facility Licence PFL11 (EPPG00711513) 

EDI 

Electro de‐ionization 

EHP 

Department of Environment and Heritage Protection (Queensland) 

EIS 

Environmental Impact Statement (consisting of both QCLNG Project Draft and  Supplementary) 

EMS 

Environmental Management System 

EP Act 

Environmental Protection Act 1994 (Qld) 

EPBC Act 

Environment Protection and Biodiversity Conservation Act 1999 (Cmwth) 

EPC 

Engineering Procurement Construction 

ERA 

Environmentally Relevant Activity (under the Queensland Environment Protection  Act 1994) 

ERP 

Emergency Response Plan 

ERS 

Emergency Release System 

ESD 

Emergency Shut Down (System) 

GAWB 

Gladstone Area Water Board 

GHG 

Greenhouse Gas 

GSDA 

Gladstone State Development Area 

HSSE 

Health, Safety, Security, Environment 

IAC 

Inlet air chilling 

ISBL 

Inside Battery Limits 

MCU 

Material Change of Use (Approval) for the LNG Facility (DGBN11_389) 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 10 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Acronym/Abbreviation 

Meaning 

MOF 

Materials Offloading Facility 

NAL 

Noise Assessment Location 

NOx 

Oxides of nitrogen 

OEMP 

Operations (Operational) Environmental Management Plan 

OMS 

Operations Management System 

OPW 

Operational Works – Prescribed Tidal Works (Approval) 

OSBL 

Outside Battery Limits 

PCIMP 

Port Curtis Integrated Monitoring Program  

PDS 

Pipeline Delivery Station 

PERC 

Powered Emergency Release Coupling 

PFD 

Process Flow Diagram 

PFL 

Petroleum Facility Licence 

PSV 

Pressure Safety Valve 

QCLNG 

Queensland Curtis Liquefied Natural Gas (Project) 

RO 

Reverse Osmosis 

ROC 

Reverse Osmosis Concentrate 

SEWPC 

Department of Sustainability, Environment, Water, Population and Communities  (Commonwealth) 

TWAF 

Temporary Workers Accommodation Facility 

UF 

Ultra‐filtration 

VOC 

Volatile Organic Compound 

WHR 

Waste Heat Recovery 

1.6. REFERENCED / ASSOCIATED DOCUMENTS  Documents  referenced  or  reviewed  in  development  of  this  OEMP  are  summarised  in  Table  1  below.    Note  that  the  referenced  documents  do  not  include  environmental  procedures  or  plans  which  are  prepared  as  subsidiary documents and included as attachments to this OEMP.  A list of applicable OEMP subsidiary plans  is provided in Section 0.  Table 1: Referenced / Associated Documents  Document Number 

Title/Description 

Standards and Guidelines  QCOPS‐OPS‐ENV‐PCE‐000020  

QGC Procedure for Environmental Operational Control 

QGC‐GPA‐STD‐000001 

Stakeholder Feedback Standard 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 11 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Document Number 

Title/Description 

Permits and Approvals  EPPG00711513 

Environmental Authority (EA) for Petroleum Facility Licence 11  

DGBN11_389 

Material Change of Use approval for the QCLNG LNG Facility 

Marine  Facilities  Approval  –  EPBC  Approval  to  develop,  construct,  operate  and  decommissioning  the  2008/4401  marine  facilities  component  of  the  QCLNG  LNG  Project  as  described  in  referral EPBC 2008/4401  LNG  Facility  Approval  –  EPBC  Approval:  Queensland  Curtis  LNG  Project  –  LNG  Plant  and  Onshore  2008/4402  Facilities – EPBC No 1008/4402  DA/429/2011 

Operational Works ‐ Prescribed Tidal Works (including the Disturbance of  Marine Plants) for the LNG Jetty 

DA/120/2010 

Operational Works ‐ Prescribed Tidal Works for Curtis Island Construction  Dock (including disturbance of marine plants) 

DA/239/2010 

Operational Works ‐ Prescribed Tidal Works (including the Disturbance of  Marine Plants) for Tidal Area Infrastructure at Curtis Island 

DA/190/2010 

Prescribed Tidal Works Marine Offloading Facility (MOF) Lot 2, SP228454  and SP228185 

QGC Management Plans, Processes and Procedures  QCLNG‐AUS‐PMT‐ENV‐PLN‐0675 

Environmental Management Plan:  Water Mouse (Xeromys myoides) 

QCLNG‐AUS‐PMT‐ENV‐PLN‐0793 

Environmental Authority Monitoring Program – Curtis Island 

QCLNG – AUS – PMT – ENV – PLN –  QCLNG Whole of Project Migratory Shorebird Management  0952 (Rev B, Sept. 2011)  Plan  QCLNG‐BX00‐ENV‐PLN‐000020 

Greenhouse Gas Emissions Strategy – Queensland Curtis LNG 

QCLNG‐AUS‐GEN‐GPA‐PLN‐0689 

Gladstone Stakeholder Engagement Plan 

QCLNG‐BX00‐ENV‐PLN‐000070 

Long‐Term  Turtle  Management  Plan  LNG  Facilities  –  Curtis  Island,  Gladstone 

Other Documents  Queensland  Curtis  LNG  Project  The  Queensland  Curtis  LNG  Project  Environmental  Impact  Statement  Environmental Impact Statement  (EIS), incorporating both the draft and supplementary EIS. 

1.7. ORGANISATION STRUCTURE AND RESPONSIBILITIES  QGC  accountabilities  applicable  to  this  OEMP  are  provided  in  Table  2  below,  with  more  detailed  responsibilities specific to various environmental aspects (monitoring, site management, corrective actions,  etc.) detailed in relevant management plans and procedures referenced in this OEMP.  Table 2: Key Management Responsibilities  Position 

Management Responsibilities 

General 

 All delivery functions on Curtis island (production, maintenance, engineering, marine). 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 12 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Position 

Management Responsibilities 

Manager, LNG 

 Establishment of required management and operating systems, processes and  procedures in line with company and regulatory obligations.   Ensure the QGC HSSE Policy is implemented for QCLNG.   All staff made aware of their General Environmental Duty under the EP Act. 

Production  Manager 

 LNG production and operation of the LNG facility.   Safe Delivery of  the Day/Control of Work/Permit to Work.   Timely, safe and effective delivery of operational processes, procedures and systems for  production. 

Maintenance  Manager 

   

Marine  Manager 

 Managing port and marine operations.   Marine assurance and regulatory compliance. 

LNG  Operations  HSSE Manager 

 Ensure compliance with environmental legislation and regulations, permits, licences and  approvals.   Ensure this OEMP and associated environmental plans and procedures are implemented  and updated, including training of site personnel in applicable aspects of environmental  compliance and this OEMP.    Oversee environmental incident investigations and implementation of corrective actions. 

QGC  Central  Environment  Team  /  QGC  Central  Compliance  Team 

 Manage and coordinate monitoring in response to a complaint or request from the  Administering Authority.   Undertake audits against the QGC Environmental Management System (EMS).   Manage third party auditing of the EA and Coordinator General (CG) Conditions.   Coordinate preparation and submission of Statutory Reporting including Annual  Environmental Return and Annual Monitoring Report.    Communicate non‐compliances with the EA to the Administering Authority. 

Business  Services  Manager 

 Day‐to‐day management of contracts and procurement activities, including ensuring that  environmental requirements are established in applicable contracts.   Gladstone Social Performance programs. 

Lead  Environmental  Advisor  (LEA)  /  Superintendent  Environment  (title  TBC  for  Ops) 

 Provide input into the Environmental Site Induction provided to all site staff and visitors.   Act as primary point of contact for site personnel environmental matters and any  associated environmental incidents.   Provide the Production Manager and Maintenance Manager with environmental  technical and regulatory compliance support with regard to site environmental  management.   Coordinate and undertake routine site environmental sampling and monitoring and  manage field and laboratory analytical data results.   Undertake any required reporting associated with site environmental monitoring and  report results to the QGC Central Environment Team/QGC Central Compliance Team.   Initiate and participate in environmental incident investigations in conjunction with and  as directed by the LNG Operations Compliance Manager.   Communicate incidences and non‐compliance to the QGC Central Environment Team/  QGC Central Compliance Team. 

All maintenance activities.  Recruitment and training of maintenance personnel.  Management of maintenance support contracts.  Planning, delivery and reporting of maintenance execution. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 13 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Position 

Issue date: September 2013   Review due: September 2014  

Management Responsibilities   Collate environmental incident reports and associated regulatory notifications for  submission to the QGC Central Environment Team/QGC Central Compliance Team for  review and transmission to the administering authority.   Monitor the implementation of the management measures and identify corrective  actions.   Communicate the need for corrective actions to the QGC Central Compliance Team/ QGC  Central Compliance Team, Production Manager and LNG Operations Compliance  Manager.   Interact with Administering Authority as directed by the QGC Central Environment Team/  QGC Central Compliance Team.   Participate in audits against the QGC EMS.   Facilitate site aspects of third party auditing of the EA and CG Conditions. 

 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 14 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

2.0

Issue date: September 2013   Review due: September 2014  

OEMP STRUCTURE AND LNG FACILITY HSSE MANAGEMENT SYSTEM 

2.1. HSSE POLICY AND EMS  QGC  has  in  place  a  Health,  Safety,  Security  and  Environment  (HSSE)  Policy  that  outlines  individual  accountabilities  for  all  QGC  employees  and  contractors.    A  copy  of  the  QGC  HSSE  Policy  is  included  as  Appendix A.  An Environmental Management System (EMS) is in place for QGC Upstream Activities, certified to ISO 14001,  which has also been developed with reference to the QGC HSSE Policy.    This  OEMP,  with  associated  sub‐plans,  is  prepared  as  a  site  environmental  operational  control  procedure  with reference to the QGC EMS.  The scope of the QGC EMS will be extended to cover operation of the LNG  Facility as described in this OEMP.       

2.2. OEMP OUTLINE  This OEMP includes:  1. A description of operational activities to be undertaken on the site;  2. Description  of  the  existing  environment,  and  environmental  Aspects  and  Impacts  associated  with  operation of the LNG Facility; and  3. An overview of management, monitoring, reporting and corrective actions for key identified Aspects  and Impacts.  Appended  to this  OEMP  are  sub‐plans  addressing  detailed  environmental  management  and monitoring  for  specific environmental aspects.  Appended plans and procedures include the following:   Table 3: OEMP Plans and Procedures  Document Number 

Title/Description 

LNGOP‐QL00‐ENV‐PLN‐000004 

Air Quality Management Plan  

LNGOP‐QL00‐ENV‐PLN‐000008 

Noise Management Plan 

LNGOP‐QL00‐ENV‐PLN‐000006 

Water Management Plan (incorporating stormwater and sediment  and erosion control, process waters and groundwater) 

LNGOP‐QL00‐ENV‐PLN‐000005 

Waste Management Plan  

LNGOP‐QL00‐ENV‐PLN‐000012 

Biodiversity Management Plan 

LNGOP‐QL00‐ENV‐PLN‐000007 

Weed Management Plan 

LNGOP‐QL00‐ENV‐PLN‐000011 

Mosquito, Pest and Quarantine Management Plan 

LNGOP‐QL00‐ENV‐PLN‐000013 

Environmental Contingency and Emergency Response Plan 

LNGOP‐QL00‐ENV‐PLN‐000010 

Environmental Incident Reporting Procedure 

LNGOP‐QL00‐ENV‐PLN‐000003 

Chemicals and Hazardous Substances Management Plan  

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 15 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

3.0

Issue date: September 2013   Review due: September 2014  

SITE LOCATION AND FACILITY DESCRIPTION 

3.1. PROJECT SCOPE  QGC Pty Limited (QGC) is developing an integrated liquefied natural gas (LNG) project in Queensland, known  as  the  QCLNG  Project.  The  QCLNG  Project  involves  expanding  QGC’s  existing  natural  gas  operations  in  the  Surat  Basin  of  southern  Queensland  and  transporting  the  gas  via  an  underground  pipeline  to  a  gas  liquefaction and export facility on Curtis Island, near Gladstone, where the gas will be converted to LNG for  export.  The general scope of the QCLNG Project includes:   

Upstream natural gas field development and facilities; 



Pipeline construction of one pipeline sized for two LNG trains free‐flow, with the possible capability  of adding compression to supply three LNG trains of feed gas capacity in the future; 



Construction of an LNG production and export facility (LNG Facility) on Curtis Island to facilitate the  export of liquefied natural gas. 

Project  design  life  is  20  years  for  each  LNG  train,  although  these  trains  will  likely  operate  for  significantly  longer periods provided additional gas reserves are available.  While  three  (3)  LNG  Trains  are  approved  under  the  QCLNG  EIS  and  subsidiary  approvals,  BG  has  taken  a  decision  to  initially  construct  a  two  (2)  train  LNG  facility  on  Curtis  Island,  with  pre‐investment  to  support  potential  addition  of  future  trains  in  the  most  economical  and  least  operationally  disruptive  manner.    This  OEMP has been prepared to address operations of the LNG Facility component of the Project.  The two train  site layout is shown in Figure 2.  LNG  Operations  also  utilises  facilities  on  the  Gladstone  mainland  including  a  Marine  Operations  Terminal  (MOT), office facilities, and a warehouse (the Gladstone Supply Base or GSB).  These mainland facilities are  not covered by this OEMP. 

3.2. DESCRIPTION OF PETROLEUM TENURES  The LNG Facility is located within the bounds of PFL11 under the Petroleum and Gas (Production and Safety)  Act 2004.   The site is located within the Curtis Island Industry Precinct of the Gladstone State Development Area (GSDA).   The Real Property Description (RPD) is Lot 2, on SP228454 (previously Lot 2 on SP225924) and SP228185 (wet  lease).  PFL11 covers both these lots and extends into the water covering marine infrastructure.  The site is not currently included on the Environmental Management Register (EMR).  Site location, and the surrounding GSDA, is shown in Figure 1.   

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 16 of 89 

# !,)   1 # $ # + 0 '+ # '&     !&

" ) ) '. *

Rail Road Principal Road Secondary Road

&!) ''  *$ &

Wet Lease Boundary

# )  '# &+

Export Pipeline QCLNG Site Boundary (PFL11)

) # & '# &+

Aldoga Precinct Clinton Precinct

,) + # *  *$ &

Corridor Buffer Area Precinct Curtis Island Industry Precinct # *") %&* &# &!

Environmental Management Precinct (Curtis Island)

"# & 0

Environmental Management Precinct (Kangaroo Island) Materials Transportation and Services Corridor

%# $ + '& '# &+

Stuart Oil Shale Reserve Preservation Area

') +  ' $ *+ '& ') +  ,) + # *

# !!# &*  *$ &

      



     

Targinnie Precinct Yarwun Precinct





   

$ *+ '&

  

    

  2/08/2013      

±

     0

1

2

3

4

hibberde M_30997_01

5

Kilometers

    





  

   

Map Projec tion: GDA 94

   

SCALE:

1:100,000

(A3)

Ima ger y - Ne arMa p Site La yout - Bech te l

'+  

-  ) 0  ') +  "*   & %  + ' &*,)  + "# * # &') %+ # '& # * * ( + # $ $ 0 ,)  +   " $ '+ # '& ' + "# * # &') %+ # '& *"',$  &'+   ) $ #  '& * + " / + #  $  $ ' + # '& "B as e d on o r c o nta i n s d a ta p ro v id e d b y th e Sta te o f Q u ee n s la n d (D e p a rtm en t o f En v ir on m e n t an d R e so u rc e Ma n a g e me n t) 2 0 11 . In co n si d er a tio n o f th e S ta te p e rm itti n g u s e o f th is d a ta y o u a c kn o w le d g e a nd ag r ee th a t the S ta te g i ve s n o w a rra n ty i n re la ti o n to th e da ta (i n cl u di n g ac cu r ac y, re li a b il ity, co m pl e te ne s s, c ur re n cy or su ita b i li ty) a n d a cc ep ts no l ia b i li ty (i n cl ud i n g w i th o ut l im i tati o n , li ab i li ty i n ne g l ig e n ce ) fo r a n y l o ss , d a m a g e o r co sts (in c lu d i ng c on s e qu e n tia l d a ma g e ) re l a tin g to an y us e o f th e d a ta. D a ta m us t n ot b e u se d fo r d ir ec t ma r ke tin g o r b e u se d in b re a ch o f th e p ri va c y l a w s."

 &#  

   % * *!&%  + (! #  !" %    Export P ipeline Wet Lease B oundary QCLNG Site B oundary (PFL11)

Workshop

Maintenance Building

Chemical Storage Building

Operations Building

Material Offloading Facility

Main Control Building

Refrigerant Storage

LNG Train 2

Utility Air, Nitorgen & Diesel Storage

LNG Train 1

LNG Tank B LNG Tank A

  2/08/2013     



Process Flares

±

Marine Flare

0

100

200

300

400

hibberde M_25517_01a

500

Meters Map Projec tion: GDA 94

   

SCALE:

1:10,000

(A3)

Ima ger y - Ne arMa p Site Bo un dar y - DME

!%   ' # *   !# %  $       % !  $&#  %  $  !# %  !   $ $ " %    * &#  %     !%  ! ! %  $  !# %  !  $!&  !%   #    !  $ %  ) %        ! %  !

LNG Loading Berth

Construction Dock

"B as e d on o r c o nta i n s d a ta p ro v id e d b y th e Sta te o f Q u ee n s la n d (D e p a rtm en t o f En v ir on m e n t an d R e so u rc e Ma n a g e me n t) 2 0 11 . In co n si d er a tio n o f th e S ta te p e rm itti n g u s e o f th is d a ta y o u a c kn o w le d g e a nd ag r ee th a t the S ta te g i ve s n o w a rra n ty i n re la ti o n to th e da ta (i n cl u di n g ac cu r ac y, re li a b il ity, co m pl e te ne s s, c ur re n cy or su ita b i li ty) a n d a cc ep ts no l ia b i li ty (i n cl ud i n g w i th o ut l im i tati o n , li ab i li ty i n ne g l ig e n ce ) fo r a n y l o ss , d a m a g e o r co sts (in c lu d i ng c on s e qu e n tia l d a ma g e ) re l a tin g to an y us e o f th e d a ta. D a ta m us t n ot b e u se d fo r d ir ec t ma r ke tin g o r b e u se d in b re a ch o f th e p ri va c y l a w s."

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

3.3. QCLNG CURTIS ISLAND SITE  3.3.1. Location and Facilities  The  LNG  Facility  is  located  approximately  8  km  northwest  of  Gladstone,  and  approximately  9km  from  the  community at South End on Curtis Island.    As  well  as  the  two  LNG  train  plant  and  ancillary  Curtis  Island  based  utilities  and  infrastructure,  marine  facilities associated with the QCLNG Facility covered by this OEMP include a jetty for loading LNG (LNG Jetty),  a  MOF,  and  a  Construction  Dock.    These  facilities,  and  associated  shipping  channels  and  swing  basin  are  within the Port of Gladstone as defined in Transport Infrastructure (Ports) Regulation 2005 (Qld).    

3.3.2. Meteorological Conditions  QGC  has  installed  a  meteorological  station  on  the  QCLNG  Facility  site  for  ongoing  measurement  of  site  specific meteorological conditions.  Longer term data for the Gladstone region sourced from the Australian  Bureau of Meteorology is summarised below.    

3.3.2.1.

Temperatures  

Average daily temperature is 23°C; 



Absolute minimum is 4.4°C; 



Absolute maximum is 42°C. 

3.3.2.2.

3.3.2.3.

Relative Humidity  

Mean Annual (9am) 67% @ 22.9°C  



Mean Annual (3pm) 59% @ 25.5°C 

Wind 

Meteorological data from the Australian Bureau of Meteorology at the Gladstone Airport indicates that winds  are predominantly from the north‐east to south‐southeast, with 62.2% of winds blowing from this direction.  These winds usually dominate day and early evening flows; with winds strongest between midday and 6pm.  Winds tend to be strongest in an easterly direction during summer. Wind roses for the Gladstone Airport are  presented in Appendix B. Gladstone airport is about 11 km SSE of the QCLNG Facility.  In  the  absence  of  long  term  site‐specific  meteorological  data  for  the  QCLNG  Facility  site,  wind  roses  were  developed for the QCLNG Facility using the meteorological modelling tool, CALMET, and were presented as  part of the QCLNG draft EIS. These wind roses are presented in Appendix B.  Review of the annual wind rose  for the QCLNG site generated by CALMET with the annual wind rose for Gladstone airport indicates that site  winds are expected to be slightly less than those measured at the airport, representing the buffering of the  site from prevailing winds by topography to the east and south. 

3.3.2.4.

Rainfall 

About 66% of rain falls during the November to March wet season.  

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 19 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  



Mean annual 

 

 

879 mm 



Maximum rainfall in 24 hours 

 

248 mm 



Mean number of days with rain 

 

97.2/year  

 

3.4. DESCRIPTION OF PETROLEUM ACTIVITIES  This OEMP covers operations of the LNG Facility on Curtis Island.  The petroleum activities to be undertaken  at the LNG Facility include the following (per Section 3(2) of the Petroleum and Gas (Production and Safety)  Act 2004):  

the distillation, production, processing, refining, storage and transport of fuel gas;  



authorised activities for petroleum authorities; and 



other activities authorised under this Act for petroleum authorities.  

3.5. FACILITY DESCRIPTION   The QCLNG export terminal will receive natural gas by pipeline, remove impurities from the gas, liquefy the  clean dry gas, store the resulting LNG in storage tanks, and load the LNG into LNG tank ships for export. The  LNG plant will include two (2) liquefaction trains, each having a nominal capacity of 4.23 mtpa. The trains will  utilise  the  ConocoPhillips Optimized Cascade® Process to  chill  and  liquefy  the  gas.  LNG  will  leave  the  QCLNG Facility in purpose‐built LNG ships.  The LNG Facility will operate 24 hours per day, 365 days per year, although each LNG train will be periodically  shut down for maintenance.  The average production capacity of each train is approximately 4.0 mtpa, taking  into  consideration  the  expected  average  feed  gas‐flow  rates  and  long‐term  availability  of  the  processing  equipment, although may be higher in any given year subject to optimisation of operations and maintenance  scheduling.  For the purposes of this OEMP, the QCLNG Facility comprises:  



LNG process systems, incorporating:  -

Gas  pre‐treatment:  including  inlet  receiving  and  metering,  gas  pre‐treatment  facilities  for  the removal of water and impurities from the feed gas. 

-

Gas liquefaction units: The process by which the gas is systematically cooled and liquefied  at approximately ‐160°C. 

-

LNG storage and loading facilities: LNG storage, including two full containment LNG storage  tanks. The LNG tanks will each have a capacity of 140,000 m³. Loading facilities include jetty  and docking facilities. 

Utilities:  including  refrigerant  storage,  power  generation,  hot  oil  system,  fuel  gas,  nitrogen,  air  systems,  water  systems,  fuel  and  chemical  storage,  fire  protection  and  safety  systems,  flare  and  vent systems. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 20 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  



Associated Pipelines: including the Pipeline Delivery Station and other pipelines located within the  boundary of the QCLNG Curtis Island Site. 



Supporting  services  and  ancillary  infrastructure:  including  a  Construction  Dock  and  Materials  Offloading Facility (MOF). 

3.5.1. LNG Process  A generalised process flow diagram (PFD) for the  ConocoPhillips Optimized Cascade® Process is shown in  Figure  3  below.    A  simplified  summary  of  the  process,  including  the  Unit  numbers  relevant  to  the  QCLNG  project, is included as Figure 4.  Figure 3: Optimized Cascade Process 

  Figure 4: LNG Process Flow – Process Units 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 21 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

3.5.1.1.

Issue date: September 2013   Review due: September 2014  

Gas Pre‐treatment 

Gas will be transported from the gas fields to the LNG plant through a 42” main export pipeline. The gas is  dehydrated  to  sales  gas  quality  at  processing  plants  in  the  field.  The  pre‐treatment  at  the  LNG  Facility  consists of:  

Inlet Gas Receiving and Metering; 



Acid Gas Removal / Amine Regeneration; and  



Dehydration and Mercury Removal. 

Feed  gas  pre‐treatment  is  important to  remove  impurities  (primarily  CO2  and  water)  from  the  feed  gas,  as  these  would  freeze  in  the  liquefaction  section  of  the  LNG  trains  if  not  removed  and  block  or  damage  equipment. Residual CO2 and water in the pre‐treated gas supply to the liquefaction section therefore need  to be extremely low.  Feedstock  is  processed  through  a  feed  gas  heater  for  hydrate  prevention  if  necessary,  and  then  a  diglycolamine (DGA) gas treating system removes CO2, potential trace levels of hydrogen sulphide (H2S), and  other sulphur components that may be in the gas. A rich amine regeneration system is included for recovery  and recirculation of lean amine.  Treated gas, with CO2 removed, is then chilled to a temperature sufficiently above the hydrate point (around  20°C) to allow for the removal of as much water as possible before drying in the molecular sieve dehydration  section. This reduces the loading and size of the molecular sieves (free water is removed in an inlet separator  and inlet filter coalescer, and is recycled back to the acid gas removal unit). 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 22 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Regeneration  of  the  molecular  sieve  in  the  dehydrator  vessels  is  achieved  by  using  dry  gas.  The  dry  gas  is  heated  and  passed  through  the  dehydrator  vessel.  The  gas  is  then  cooled,  dehydrated  (water  removal),  compressed and fed back to the inlet of the acid gas removal system.  The dried gas then passes through two mercury removal beds to remove any traces of mercury in the feed  gas. While mercury is not expected in QCLNG feed gas, mercury removal has been provided to ensure that  pre‐treated feed gas to the liquefaction section has no mercury. Any mercury would condense in the cooler  sections, and liquid mercury may attack aluminium equipment in the liquefaction section. 

3.5.1.2.

Gas Liquefaction 

The liquefaction section consists of:  

Propane Refrigeration; 



Ethylene Refrigeration; and  



Feed Gas Liquefaction, Methane Refrigeration and Nitrogen Rejection.  

These  three  refrigeration  units  are  optimally  cascaded  to  provide  maximum  LNG  production  by  efficiently  using the maximum available horsepower of the compressor /turbine sets.  The propane circuit is a closed loop refrigeration circuit which uses propane as the refrigerant. The propane  refrigeration unit has three main purposes:  

Chill the feed gas prior to liquefaction; 



Condense ethylene refrigerant; and 



De‐super‐heat methane gas. 

Anti‐surge protection is provided for each compressor on all stages. Gas from each compressor discharge is  recycled via the anti‐surge control valves. Suction pressure is controlled by varying the turbine speeds of the  compressor  gas  turbines.  The  Distributed  Control  System  (DCS)  has  the  capability  to  reset  the  pressure  controller according to the ambient temperature for maximizing plant capacity.  At  high‐high  liquid  level  in  a  suction  drum,  the  associated  compressor  will  be  shut  down  and  the  corresponding  suction  isolation  valves  located  upstream  of  the  drum  will  close,  thereby  protecting  the  propane compressor from liquid carry‐over.  The Ethylene Refrigeration unit is a closed loop refrigeration circuit which uses ethylene as the refrigerant.  The Ethylene Refrigeration Unit has two main purposes:  

Cool and condense the feed gas; and 



Cool and condense the methane gas. 

As  in  propane  refrigeration,  each  ethylene  machine  is  equipped  with  an  anti‐surge  control  system,  Either  machine may be started, shut down, or placed on recycle without significant upset to the system as a whole,  provided plant throughput is adjusted accordingly.   

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 23 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Methane  Refrigeration  provides  the  final  stage  of  feed  gas  liquefaction.  Condensed  feed  gas  from  the  Ethylene Refrigeration unit  is liquefied at atmospheric  pressure.  This produces LNG which is transferred to  the  LNG  Storage  Tanks  via  the  LNG  Transfer  Pumps.  The  methane  refrigeration  unit  is  different  from  the  Propane and Ethylene Refrigeration units in that the feed gas itself is used as the refrigerant, as opposed to  the closed‐loop propane and ethylene circuits.  Vapour  from  each  flash  is  re‐compressed  and  recycled  to  points  upstream  of  the  feed  gas  condensing  operations, which use propane and ethylene refrigeration. The methane flash vapours are warmed prior to  compression and provide efficient cooling for the methane compressor discharge.   A recycle methane gas stream is taken from the high stage compressor discharge to be used as either fuel gas  or recondensed in the upstream propane and ethylene units.  The  methane  refrigeration  and  liquefaction  circuit  is  equipped  with  a  Nitrogen  Rejection  Unit  thermally  linked to the methane cold box which rejects and vents excess nitrogen to the atmosphere. The system takes  its feed gas as a side stream from the open loop methane refrigeration circuit and rejects a nitrogen (N2) rich  vent stream while returning a methane rich stream to the methane system.   The Nitrogen Rejection Unit is provided to allow production of a high‐quality fuel gas that meets the heating  requirements of the gas turbines.   Anti‐surge  protection  is  provided  for  both  of  the  methane  compressor  on  all  stages.  Suction  pressure  is  controlled by varying the turbine speeds of the compressor gas turbines. Either machine may be started, shut  down, or placed on recycle without significant upset to the system as a whole, provided plant throughput is  adjusted  accordingly.  The  DCS  has  the  capability  to  reset  the  pressure  controller  according  to  the  ambient  temperature for maximising plant capacity.   Compressor Turbine Inlet Air Chilling  The Inlet Air Chilling (IAC) system packages are used to maintain a constant air temperature at the inlet of the  GE LM‐2500+G4 gas turbine drivers for the refrigeration compressors in the liquefaction units of the QCLNG  plant.  Gas  turbine  power  output  depends  on  the  mass  flow  of  inlet  air  and  the  ambient  air  dry  bulb  inlet  temperature.  The  IAC  will  help  maintain  a  steady  efficiency  for  the  gas  turbines  during  hot  weather  to  maximize LNG production by:  

Reducing the inlet air temperature and hence air flow via increased air density; and, 



Reducing the inlet air humidity. 

The IAC package has the following process configuration:  

Chilled water loop to cool  the air at inlet to the gas turbines; and 



Propane refrigeration cycle to remove heat from the chilled water. 

Chilled water at 5.4°C from the evaporators in the lAC package is sent to the propane‐ethylene‐methane gas  turbine IAC coil modules to cool the turbine inlet air in contact with the coils.  The warm return water flows  from the gas turbine coils are sent back to the lAC package for chilling. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 24 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Water  condensed  on  the  outside  surface  of  the  coil  modules  from  moisture  in  the  air  at  turbine  inlets  is  collected and sent to the storm water system for disposal. 

3.5.1.3.

LNG Storage and loading facilities 

The  LNG  Facility  has  two  double‐walled,  full  containment  LNG  storage  tanks  of  140,000  m3  capacity,  each  fitted with four ship loading pumps.  The tanks are fitted with level gauges, level transmitters, relief valves,  vents, temperature elements and other instrumentation.  Lightning protection is provided by roof design and  by roof‐wall‐floor electrical continuity to earth.  The tank design temperature is ‐168°C.  The  LNG  storage  tanks  are  full  containment  cryogenic  design,  consisting  of  a  primary  inner  tank  of  high  ductility 9% nickel steel surrounded by insulation with a secondary outer tank of reinforced and pre‐stressed  concrete. The roof over the complete tank is steel. The annulus between the two tanks is filled with perlite  insulation.  The  outer  containment  vessel  has  a  1m‐thick  concrete  external  wall  offering  protection  from  external spill fires, and the concrete foundation contains heaters to prevent the soil beneath the tank from  freezing.  Schematics of the LNG storage tanks are shown in Figure 5.  Figure 5: LNG Storage Tanks - Schematic

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 25 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

  From the LNG storage tanks, LNG is pumped to the jetty head for ship loading.  The ship loading pumps have  a  combined  pump  capacity  (eight  pumps  operating  in  parallel)  of  12,000 m3/hr.    At  the  jetty,  four  loading  arms connect to each ship, including:   

Two dedicated loading arms; 



One dedicated vapour return loading arm; and 



One loading arm that can be used either for loading or vapour return. 

The jetty is just over 250 m long with a Marine Terminal Building located on the jetty. Mooring is facilitated  via six mooring dolphins and four berthing dolphins over a fender line about 360 m long.  Boil‐Off Compressors  Three  Boil‐Off  Gas  (BOG)  compressors  remove  excess  vapour  from  the  tanks  and  return  the  vapour  for  liquefaction  in  the  trains.  Composite  gases  from  the  LNG  tanks  and  from  the  ship  loading  system  are  compressed by the BOG compressors and returned to the open cycle methane LNG plant refrigerant system.  The BOG compressors are electric motor driven centrifugal compressors designed for the cryogenic service.   When no is ship loading, one BOG compressor is required for each train in operation to handle vapours from  the LNG storage tanks.   To  minimise  flaring  during  the  cool  down  of  a  warm  ship,  a  quench  system  reduces  the  temperature  of  relatively warm return vapours and to ensure cooled vapours can be processed by the BOG compressors and  returned to the liquefaction process.  Ship Loading  A  Navicom  Dynamics  “HarbourPilot”  berthing  aid  is  used  with  the  “Smartdock”  Docking  Aid  System  in  bringing  tankers  alongside.  A  Mooring  Load  Monitoring  System  will  guide  and  monitor  the  ships’  mooring.   When the ship is correctly secured, the gangway may be positioned. Earth and communications cables are  connected  and  tested.  Comprehensive  pre‐loading  procedures  are  undertaken  prior  to  connecting  the  loading arms, with the vapour arm connected first followed by the liquid arms. The arms are flushed with N2  and pressure tested.  The functionality of the ship and jetty shutdown valves is tested by a warm Shutdown  Loading (SDL) test, followed by cool down of the loading arms and ship manifold.  Following cool‐down is a  cold SDL test, after which the valves are reset and loading may start.  Vented  gas  from  the  ships’  holds  during  loading  that  meets  process  specifications  is  directed  back  to  the  vapour space of the LNG storage tanks and processed through the BOG compressors.  A gas‐chromatograph  measures N2, CO2, and oxyen (O2) to ensure they are at the required limits before directing vented gas to the  LNG tanks.  ‘Off’ spec vented gas from the ships’ holds during loading is directed to the Marine Flare.  On completion of loading, the loading arms are all drained of LNG to the collection drains header.  The arms  are  then  purged  of  LNG  using  N2  before  they  are  disconnected.  The  communications  and  earth  cables  are  disconnected, the gangway removed and the ship released in coordination with the harbour pilot.   Once two LNG trains are operating under normal conditions, it is anticipated that LNG cargo frequency will be  approximately two to three per week (or one every three days).  Loading times of about 24 hours alongside 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 26 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

the berth are expected.  Both cargo frequency and vessel loading times will vary depending upon the size of  the LNG vessels.   An overview of the LNG loading layout is shown in Figure 6.    Figure 6: LNG Loading Layout

  Notes:     

Red: 9kg fire extinguisher     Purple: Audible alarms    Green dotted line: open path gas detectors  Also low temp spill detectors at the loading arms and open path gas detector across the rear of the loading arms. 

 

Powered Emergency Release Coupling   The  unloading  arms  use  a  hard  arm  connector  and  a  cantilever  design  to  cater  for  ship  movements.  In  addition, the loading arms have the following features:   

Each loading arm is of the single counterweight balance type, fitted with self‐ levelling triple swivel  assembly  joints  and  equipped  with  an  emergency  release  system  and  a  manual  quick  connect/disconnect coupling. 



To allow for thermal shrinkage in the product carrying pipe‐work, the structural part of the loading  arm is independent from the pipe‐work. 



In operation, the loading arms are limited to no more than 80% of the safe operating envelope. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 27 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

On the end of each arm is a Quick Connect Disconnect (QCDC) coupling. Upstream of the QCDC is a Powered  Emergency Release Coupling (PERC) for emergency disconnection from the ship. The PERC is a set of two ball  valves held together by a releasable hydraulic coupling. In an emergency, the two ball valves close and the  hydraulic  coupling  releases.  The  loading  arm  counter  weight  will  swing  the  loading  arm  to  a  safe  position  clear  of  the  ship.  Mechanical  linkage  ensures  that  the  PERC  cannot  separate  until  the  ball  valves  are  fully  closed.  The emergency release system (ERS) allows the unloading arm to be safely disconnected from the ship. The  ERS has several alarms so the operator may correct the situation before disconnection occurs:  

Pre‐Alarm Warning ‐ A visible and audible signal to warn the operator to adjust the mooring lines. 



First Step Alarm ‐ An intermittent and audible signal is initiated at the jetty display panel and Central  Control Room (CCR) when the unloading arm crosses its working range limit. 



Second Step Alarm (Action) ‐ A continuous visible and audible signal to warn the operator that the  PERC will be opened and the loading arms hydraulically blocked. 



Automatic Emergency Release ‐ The ERS of all arms will be automatically activated when any arm  travels beyond its working range limit.  

On  arrival  of  the  ship  and  before  unloading  starts,  the  ship's  control  system  is  connected  to  the  onshore  emergency  shut  down  (ESD)  system  allowing  communication,  alarm  and  shutdown  signals  to  be  passed  between ship and shore. This allows the ship’s pumps to be shut down either directly or through a process  cascade leading to high discharge pressure at the pumps. 

3.5.2. Utilities  3.5.2.1.

Refrigerant and Diesel Storage 

Refrigerant  Refrigerant  storage  is  provided  for  ethylene  and  propane  systems,  allowing  for  periodic  make‐up  to  each  refrigerant circuit, as well as refrigerant storage during maintenance. These systems (Ethylene and Propane  Storage) are common for Trains 1 and 2.  The refrigerant storage location is shown in Figure 7.  Ethylene  is  stored  in  pressurised,  double‐walled,  vacuum  jacketed  horizontal  bullets,  with  a  capacity  of  approximately 255 m3 each, with inventory being a maximum of:  

Three (3) process inventories, shared between two trains; or 



Two (2) process inventories plus three month supply for two trains based on estimated losses. 

Propane  storage  is  in  three  pressurized  horizontal  bullets,  with  maximum  inventory  being  two  process  inventories minus the inventory of the propane accumulators plus three months’ supply for two trains based  on estimated losses.  Each pressurised vessel has a net capacity of 686 m3 at ambient temperatures. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 28 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Figure 7: Refrigerant Storage Location

 

Diesel Fuel  Diesel fuel is used for firewater pumps, back‐up air compressors and black start generators. Located in the  refrigerant storage area, the Diesel Oil Storage Tank is an API 650 atmospheric tank. The Diesel Oil Transfer  Pump  is  designed  to  transfer  diesel  oil  to  the  day  tanks  of  the  Stand‐by  Diesel  Generators,  the  Firewater  Pump Packages and the Start‐up/Back‐up Air Compressor Packages. This pump can also be used for filling the  storage tank.  

3.5.2.2.

Power Generation 

Electrical  demands  for  Trains  1  and  2  are  provided  by  three  gas  turbine  generators,  with  two  normally  operating  and  one  on  stand‐by.  The  normal  electrical  load  of  the  plant  with  all  equipment  operating  is  around 48,000 kW. Each individual generator (Gas Turbine Generator, GTG) is ISO rated at about 33,000 kW.  This may drop to around 26,000 kW under certain conditions.  Diesel emergency generators provide backup power for critical services and “black start‐up” power for power  generators. The standby generator system consists of three Diesel Generator Packages, which supply power  to  standby  loads  during  power  system  outages  and  serve  as  a  black  start  generator  for  the  gas  turbine  generators when required. Day tanks for the Standby Diesel Generator sets are sized for a minimum of 12  hours of operation at full load. Facilities are provided to top up the day tanks. Top up of diesel day tanks is via  a hard piped diesel distribution system.   An  automatic  load  shedding  system  ensures  power  supply  to  critical  services  if  one  of  the  gas  turbine  generators fails. The load shedding system also reduces power demand when the electrical system is heavily  loaded (possible during hot weather). The load shedding system is totally separate from the standby Diesel  Generators (which supply power to the site’s essential services). 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 29 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

3.5.2.3.

Issue date: September 2013   Review due: September 2014  

Hot Oil System 

The  hot  oil  system  is  a  closed  loop  re‐circulation  system  provided  to  service  the  process  heating  requirements.  “Therminol  55”  is  the  heating  medium  selected  due  to  its  properties  in  the  required  temperature range.  The Hot Oil Surge Drum (V‐3401) is sized for hot oil volume expansion up to temperature of 246°C. The Hot  Oil  Storage  Tank  (T‐3401)  is  common  for  two  trains  and  designed  to  hold  one  train  system  inventory  plus  volume expansion up to the average hot oil return temperature of 142°C.  Two (2) parallel Waste Heat Recovery (WHR) Units heat oil from an average inlet temperature of 142°C to an  outlet temperature of around 250°C by waste heat recovered from the Methane Gas Compressor Turbines  exhaust.  A back‐up, direct fired heater is provided for standby/start‐up purposes. The Standby/Start‐Up Hot Oil Heater  is common for the two trains. 

3.5.2.4.

Fuel Gas System 

Natura gas will be used as fuel for major equipment during plant operations. A fuel gas system is provided to  supply  gas  to  high‐use  components  such  as  refrigerant  turbines  and  power  generation  prime  movers,  and  low‐level  users  such  as  the heaters  and  flare  systems.  The  primary  source  of  high  pressure  fuel  gas  comes  from the plant methane refrigerant system with back‐up supply coming from the front end of the LNG plant.   The  High  Pressure  fuel  gas  system  is  designed  to  ensure  continuity  of  supply  to  the  power  generation  turbines  in  the  event  of  plant  upset  conditions.  Low  pressure  fuel  gas  is  pressure  let  down  from  the  high  pressure  system  downstream  of  the  fuel  gas  heater  which  is  used  to  dry  the  gas  stream  for  downstream  users.   Defrost gas is supplied by pressure control to the Defrost Heater from the make‐up fuel gas line on the front  end of the LNG plant. The defrost gas system is used to supply low pressure defrost gas to portions of the  refrigeration  units  and  feed  gas  stream  to  defrost  the  possible  build‐up  of  CO2  and  water  within  the  equipment in the cold sections of the plant (should it occur). Defrost gas at approximately 54°C is made from  mixing hot regeneration gas from the waste heat recovery or from the regeneration gas heater with dry, cool  gas from downstream of the mercury removal after filters.   A water‐bath heater is provided to heat the pipeline gas to operate the gas turbines when the LNG trains may  not be operating (i.e. initial start‐up and subsequent two‐train shutdowns). 

3.5.2.5.

Plant and Instrument Air 

The  plant  and  instrument  air  system  supplies  all  instrument  air  for  plant  start‐up,  including  Nitrogen  Generation System requirements.  Plant air, instrument air, and feed air to the Nitrogen Generator Package is supplied by the motor‐driven Air  Compressor  Packages,  complete  with  discharge  coolers  and  controls.  The  diesel  Start‐up/Back‐up  Air  Compressor Packages with discharge coolers and controls are provided for each train. Each Air Compressor  Package has 50% capacity of 2,950 normal cubic meters per hour (ncmh).  Two normally running compressors and two diesel driven back‐ups are dedicated for each LNG train. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 30 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Low pressure at either the Train 1 or 2 Plant Air Receiver activates a low pressure switch, which automatically  starts the Start‐Up/Back‐Up Air Compressor Package. Continuing low pressure cuts off air flow primarily to  the plant air system and secondarily to the nitrogen generation system. 

3.5.2.6.

Nitrogen Storage and Distribution 

Gaseous nitrogen is generated by membrane Nitrogen Generator Packages (one package for each train and a  common  back‐up).  The  nitrogen  is  then  fed  to  a  Nitrogen  Receiver  to  provide  surge  capacity  to  the  users  within the train.  Nitrogen is also supplied to Outside Battery Limits (OSBL).  Nitrogen is used as a blanket gas for various tanks, drum and sumps, purge gas for the cold boxes, back‐up  purge  gas  to  the  blowdown  headers,  loading  arm  swivel  point  purge,  compressor  gas  seals  (start‐up  and  tertiary),  pump  seals,  and  as  a  general  inert  gas  for  purging  of  systems  before  maintenance  and  for  leak  testing and inerting equipment before recommissioning. 

3.5.2.7.

Fire Protection 

The LNG Plant has a philosophy that should fire be detected within the processing facilities, the immediate  area  will  be  automatically  isolated  and  depressured  to  minimise  the  risk  of  a  fire  escalating.  Isolation  and  depressurisation  will  continue  via  a  number  of  pre‐programmed  sequences  until  either  the  fire  has  been  extinguished or the whole LNG facility has been de‐pressured.  The Firewater system is common for both Train 1 and Train 2 facilities along with OSBL and the Jetty. The fire  protection system consists of:   

Fire  water  pumps  (diesel  firewater  pumps  normally  on  standby,  with  electrically  driven  jockey  pumps used to maintain the pressure of the firewater loop) 



Fire water storage tanks 



Deluge systems 



Fire monitors 



Wheeled dry chemical fire extinguishers 



Dry chemical extinguishers 



Hydrants 



Hose reels 



Fire hoses 



Emergency Tug boat connection at LNG Jetty 



Foam generators  



Fire and gas detection  

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 31 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

The firewater system source will be supplied from the utility water system and will be stored in two firewater  tanks  (T‐3302  A/B)  with  a  capacity  of  3300m3  each.  Both  tanks  are  sized  to  meet  the  largest  firewater  demand  in  the  event  of  single  largest  fire  in  the  facility  or  in  the  jetty  plus  50%  of  maximum  flow  rate  required.   A simplified schematic of the firewater pumps and fire main is provided in Figure 8 below.  Figure 8: Firewater Pumps and Fire Main

3.5.2.8.

Flare and Vent System 

The flare system and vent system is designed to protect the QCLNG Facility in the event of overpressure, fire  or hydrocarbon leaks.   Flare System  The flare system includes three separate flare systems common for both Train 1 and Train 2. One of these  flare stacks is designed to  handle warm hydrocarbon  streams that may be saturated with water vapour or  may contain free liquid hydrocarbons and water, or both. This is referred to as the Wet Gas Flare.  A second flare is designed to handle vapour and liquid cryogenic hydrocarbons. This flare stack is referred to  as the Dry Gas Flare.  The wet and dry gas flares are located side by side in a common derrick and are jointly  referred to as the Process Flares.   The third flare system handles vapour from the LNG Storage Tanks in the event of BOG compressor failure,  and any ship vapours not recovered during ship loading. This is referred to as the Marine Flare.  The  Wet  Gas  and  Dry  Gas  Flare  Systems  include  "knock  out  drums"  to  separate  any  liquids  from  the  gas  before  it  is  routed  to  the  flare  stack.  Any  liquids  separated  from  the  flared  gas  in  the  Wet  Gas  Flare  are 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 32 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

pumped to the Waste Water Tank (T‐2912) for disposal.   Connections are provided to dispose liquids from  Wet Gas and Dry Gas K.O. Drum via vacuum truck.  Each  flare  is  equipped  with  a  utility‐type  flare  tip  and  an  integral  purge  gas  reduction  seal.  Each  flare  is  provided  with  a  flame  front  generator  (FFG)  ignition  system.  The  material  of  construction  of  the  Wet  Gas  Flare is carbon steel and the Dry Gas Flare is constructed of stainless steel.  The flares are designed to be smokeless up to a certain capacity of methane relief although smoke may occur  during relief of the propane or ethylene systems.   Vents   Key vents include:  

Reject gases from the amine regeneration system continuously vented to atmosphere through the  CO2  vent  stack  within  each  LNG  train,  as  described  in  Section  3.5.1.1.  Dispersion  modelling  has  confirmed that the CO2 Vent Stack outlet is at a “safe location” under worst case conditions.   



The  reject  N2  stream  from  the  Nitrogen  Rejection  Unit  (NRU)  in  each  LNG  train  removes  non‐ condensable  N2  from  the  LNG  product  as  described  in  Section  3.5.1.1,  with  the  NRU  reject  gas  stream  continuously  vented  to  atmosphere  from  a  vent  located  around  40  m  above  ground  level.  The NRU reject gas contains a small concentration of methane. Dispersion modelling has confirmed  that the NRU Vent outlet is at a “safe location” under worst case conditions. 



A manual vent to atmosphere is provided at the Pipeline Delivery Station (PDS) to allow venting of  the  pig  receiver  and  filters.  In  the  event  of  an  emergency,  the  PDS  will  be  quickly  depressured  through the main LNG flare system. 

3.5.2.9.

Water Systems 

Potable  water  for  the  LNG  Facility  is  supplied  by  the  Gladstone  Area  Water  Board  (GAWB)  via  pipelines  constructed from the Gladstone mainland to Curtis Island.  Pipelines are constructed allowing sewage return  from the QCLNG Facility to GAWB facilities on the Gladstone mainland for treatment.   The water system has been designed to treat the water from GAWB to generate demineralized water, service  water,  potable  water,  and  fire  water.  This  overall  system  includes  a  hypochlorite  injection  package,  ultrafiltration package, brackish water reverse osmosis (BWRO) package, electro deionization (EDI) package,  potable water cartridge filter package and an ultraviolet (UV) disinfection package.  The wastewater and sanitary sewage collection systems are segregated in the LNG Facility. The process area  drains,  oily  water  from  knock‐out  drums,  and  potentially  contaminated  storm  water  from  the  process  and  utility areas are routed to effluent treatment unit (Unit 29).   Sanitary  waste  from  various  sources  within  the  Facility  are  routed  to  sanitary  lift  stations,  pumped  to  the  property boundary and then connected to the Gladstone Regional Council sewer line for treatment.   Further  description  of  the  site  water  management  system  is  provided  in  Section  5.4,  with  detailed   management,  monitoring  and  reporting  requirements  associated  with  site  water  provided  in  the  Water  Management Plan (LNGOP‐QL00‐ENV‐PLN‐000006).   

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 33 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

3.5.3. Associated Pipelines  The 42” feed gas pipeline from the gas fields crosses the mainland to Curtis Island just outside of the Great  Barrier Reef Marine Park. On Curtis Island, it passes behind the neighbouring APLNG site and to the east of  the QCLNG site along a Common Infrastructure Corridor (CIC‐GSDA) before it turns into the QCLNG Facility.  At the QCLNG site boundary, the pipeline is brought above ground and enters the PDS, which consists of:  

Pig Receiver ‐ this facility allows pigs, which are used to clean the pipeline and to conduct internal  inspections of the pipeline, to be either launched or recovered; 



Filter  Coalescers  ‐  this  facility  removes  dust  particles  and  liquid,  which  may  have  entered  the  gas  during  upstream  processing  equipment  and  ensures  that  the  gas  is  free  from  contaminants  when  transferred to the LNG facility; 



Metering ‐ this measures the gas flow rate into the LNG facility at the point of custody transfer; and 



Local Equipment Room ‐ Process Control & Instrumentation. 

After  exiting  the  metering  system  at  the  PDS,  the  gas  enters  the  850  m  underground  pipeline  to  the  LNG  Plant.   The PDS sits at the interface between the export pipeline and the LNG facility.  The PDS is authorised under  Petroleum  Pipeline  Licence  155  and  Environmental  Authority  (EA)  EPPG00945113,  and  will  be  owned  and  operated by QCLNG Pipeline Pty Ltd. The LNG facility will be owned and operated by QCLNG Op Co.   

3.5.4. Site Buildings and Helipad  In addition to the process, utilities, and marine facilities described, the site will contain other site buildings  and infrastructure including:  

Maintenance Building; 



Warehouse Building; 



Chemical Storage Building; 



Main Control Building; 



Operations Building (including office space); 



Marine Terminal Building 



Fire Aid / Fire Station Building; 



Various electrical substantion buildings and associated control rooms; and 



Helipad (for emergency use only). 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 34 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

3.6. PROJECT LIFE AND PHASES  3.6.1. Construction and Commissioning Interface  At  the  time  of  preparation  of  this  OEMP,  construction  of  LNG  Train  1  and  2,  along  with  all  ancillary  infrastructure on the QCLNG site, is being undertaken by the principal contractor (Bechtel) on behalf of QGC.     As  construction  moves  towards  completion,  commissioning  and  start‐up  of  the  LNG  Facility,  and  commencement of operations can be described as follows:  Phase 1 ‐ Commissioning Train 1 and Utilities:  This phase of operations will entail power generation, utility  and  initial  LNG  plant  commissioning.  This  phase  will  see  a  dedicated  crew  of  commissioning  personnel  operating  the  QCLNG  Facility  in  conjunction  with  the  principal  contractor  (Bechtel)  with  live  areas  and  systems positively isolated from construction areas where construction activities will be ongoing.     Phase 2 – SIMOPS:  This phase will be defined by Simultaneous Operation (SIMOPS) of the first LNG train and  utilities,  and  the  completion  of  construction,  commissioning  and  start‐up  of  the  second  LNG  train.  The  construction  and  commissioning  of  the  second  LNG  train  will  be  undertaken  by  the  principal  contractor  (Bechtel)  on  a  segregated  area  of  the  site.    The  LNG  train  (Train  1)  will  be  operated  by  QCLNG  personnel  under  the  direction  of  Bechtel  until  transfer  of  care,  custody  and  control.      During  this  period  LNG  will  be  produced  and  the  first  LNG  cargo  will  be  shipped  from  the  LNG  Facility.    QGC  take‐over  of  Train  1  from  Bechtel will occur during this period.   Phase  3  –  Beneficial  Operation  of  2  LNG  Trains:    The  final  and  ‘normal’  operating  phase  is  the  normal  continuous operation of two (2) LNG trains by QCLNG personnel.   During  construction  and  Phase  1  (Commissioning  Train  1  and  Utilities)  site  environmental  management,  monitoring  and  reporting  is  being  undertaken  in  accordance  with  the  Construction  Environmental  Control  Plan  (Bechtel)  and  Framework  Construction  Environmental  Management  Plan  (QGC)  and  other  applicable  plans, procedures and processes.    Environmental management for commissioning and start‐up of the LNG Facility is addressed in the Bechtel  Commissioning and Start‐up EMP.   This  OEMP  will  apply  only  to  operational  activities  undertaken  following  completion  of  commissioning  and  start‐up activities, and at take‐over of the facility by QGC from Bechtel.  It should be noted that take‐over will  occur  on  a  staged  basis,  with  areas  of  the  site  (e.g.  Train  1  and  process  control  areas)  handed  over,  while  construction / commissioning activities are ongoing in other areas of the site.  During this period of partial  handover, this OEMP will apply only to those portions of the site where take‐over has occurred. 

3.6.2. Project Life  Commercial operations are anticipated to start in 2014 for Train 1. The Project is anticipated to have a design  life of at least 20 years for each LNG train. However, trains will likely operate for significantly longer provided  additional gas reserves are available. The first train is scheduled to commence LNG commercial production in  2014 with commercial production from the second train planned six to 12 months after. The QCLNG Project  EIS  envisaged  construction  and  operation  of  up  to  three  LNG  trains,  and  additional  LNG  trains  will  be  constructed and commissioned as gas supply allows and subject to the commercial viability.  The timing of a decision on construction of any LNG trains beyond the two currently under construction will  be based on a number of commercial factors including the growth of the LNG market internationally.  This 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 35 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

OEMP  does  not  address  construction  or  operation  of  a  third  LNG  train,  and  any  such  activity  will  trigger  revision of this OEMP.  

4.0

ENVIRONMENTAL CONTEXT    

4.1. IDENTIFICATION OF ENVIRONMENTAL VALUES AND POTENTIAL IMPACTS ON ENVIRONMENTAL VALUES FROM THE ACTIVITIES  The environmental values of the LNG Facility location and the potential impacts of LNG Facility operation are  described in Section 5.0 below, with further detail provided in the QCLNG Project EIS.  A  process  for  identification  of  environmental  hazards  has  been  developed  as  part  of  the  QGC  EMS,  and  Aspects  and  Impacts  workshops  undertaken  addressing  potential  environmental  impacts  associated  specifically with LNG Operations.  The Aspects and Impacts Register is maintained within the QGC EMS and  will  be  reviewed  and  updated  in  accordance  with  relevant  procedures.    Applicable  environmental  Aspects  and  Impacts  identified  in  the  workshops  and  recorded  in  the  associated  register  are  addressed  within  this  OEMP.  

4.2. ENVIRONMENTAL PROTECTION COMMITMENTS  The environmental protection commitments associated with LNG Facility operations are described in Section  5.0 below, with further detail provided in the specific sub‐plans referenced in this OEMP.  

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 36 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.0

Issue date: September 2013   Review due: September 2014  

ENVIRONMENTAL VALUES, MANAGEMENT AND MONITORING STRATEGIES  A  description  of  environmental  values  and  summary  of  potential  impacts,  environmental  performance  objectives,  targets,  and  key  performance  indicators  for  specific  environmental  aspects  are  provided  below  and in referenced sub‐plans to this OEMP.  

5.1. AIR EMISSIONS  5.1.1. Description of Environmental Values  A  detailed  description  of  the  existing  Environmental  Values  for  air  quality  in  the  Gladstone  region,  and  detailed  assessment  of  potential  impacts,  have  been  described  in  the  QCLNG  Project  draft  EIS  (Volume  5  Chapter 12).  A summary of findings from the EIS is provided below.  The Gladstone region is highly industrialised, and EHP operates a network of ambient air quality monitoring  stations  in  the  city  and  surrounding  areas.    Table  4  summarises  monitoring  stations,  approximate  distance  from the proposed QCLNG Facility, pollutants measured and the recording period.  Table 4: EHP Monitoring Sites for Gladstone  Distance to  Project site  (km) 

Record Period 

Nitrogen  dioxide 

PM10 

Sulphur  dioxide 

Carbon  monoxide 

Aldoga 

17 

2002 – present 

No 

No 

No 

No 

Boat Creek 



2008 – present 

Yes 

Yes 

Yes 

No 

Clinton 

11 

2001 – present 

Yes 

Yes 

Yes 

No 

South Gladstone 

12 

2001 – present 

Yes 

Yes 

Yes 

No 

Targinie 



2001 – 2008 

Yes 

Yes 

Yes 

No 



1997 – present 

Yes 

No 

Yes 

No 

25 

2008 – present 

Yes 

No 

Yes 

No 

24 

2008 – present 

Yes 

No 

Yes 

Yes 

11 

1997 – 2003 

Yes 

No 

Yes 

No 

Site 

(Stupkin Lane)  Targinie  (Swans Road)  Boyne Island   (Environment  Centre)  Boyne Island   (Beacon Ave)  Barney Point 

The  closest  monitoring  stations  to  the  LNG  Facility  site  are  at  Boat  Creek  and  Targinie.  The  Swans  Road  station at Targinie has been operating since 1997 and monitors nitrogen dioxide (NO2) and sulphur dioxide  (SO2). The Stupkin Lane station at Targinie was operational between 2001 and 2008 and monitored NO2 (until  May  2006),  particulate  matter  (PM10)  (until June  2008)  and  SO2  (until  May  2006).  The  Targinie  sites  were  used to describe the background concentrations of NO2, PM10 and SO2 at the QCLNG site.  Nitrogen Dioxide 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 37 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

The Environmental Protection (Air) Policy 2008 (EPP (Air)) air quality objective of 250 µg/m3 for the 1‐hour  average concentrations was not exceeded at either of the Targinie monitoring stations for the years for which  NO2  data  is  available.  Additionally,  there  were  no  exceedances  of  the  EPP  (Air)  objective  of  62  µg/m3  for  annual average concentrations of NO2. The maximum 1‐hour average and annual average results are shown  in Table 5.  Table 5: Maximum 1‐Hour Average And Annual Average Concentration Of Nitrogen Dioxide (µg/M3)  Maximum 1‐hour average  Annual average  Year  Targinie  Targinie  Targinie  Targinie  (Stupkin Lane) 

(Swans Road) 

(Stupkin Lane) 

(Swans Road) 

1997 

‐ 

78.1 

‐ 

4.1 

1998 

‐ 

90.4 

‐ 

6.2 

1999 

‐ 

86.3 

‐ 

8.2 

2000 

‐ 

78.1 

‐ 

6.2 

2001 

96.5 

78.1 

10.3 

6.2 

2002 

98.6 

80.1 

16.4 

6.2 

2003 

84.2 

71.9 

8.2 

6.2 

2004 

90.4 

61.6 

8.2 

6.2 

2005 

96.5 

80.1 

8.2 

6.2 

2006 

‐ 

84.2 

‐ 

8.2 

2007 

‐ 

73.9 

‐ 

6.2 

2008 

‐ 

65.7 

‐ 

6.4 

EPP (Air) objective for 1‐hour average: 250 µg/m³  EPP (Air) objective for annual average: 62 µg/m³ 

Carbon Monoxide  A monitoring station at Beacon Avenue, Boyne Island, has been recording carbon monoxide (CO) levels in the  Gladstone region since October 1, 2008. The following 1‐hour average CO concentrations were recorded:  

Minimum: 

0.00 µg/m3 



Average:  

60.7 µg/m3 



Maximum: 

624.6 µg/m3 

The maximum 8‐hour average CO concentration during the monitoring period was 312.3 µg/m3, well below  the EPP (Air) goal of 11,000 µg/m3.   This  monitoring  station  is  predominantly  upwind  of  the  industrial  activity  in  the  Gladstone  region  and  is  therefore not representative of a background CO level for the location of the LNG Facility.   PM10  The EPP (Air) objective for the 24‐hour average concentrations of PM10 of 50 g/m3 was exceeded at Stupkin  Lane monitoring station on 23 occasions between 2001 and 2008 during the following periods:  

October – November 2001 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 38 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 



July, October and December 2002 



December 2004 



January – February 2005 



November 2006 



March and April 2008.  

Issue date: September 2013   Review due: September 2014  

Uncharacteristically  high  events  during  2002  were  attributed  to  bushfires  while  those  during  2005  were  attributed to dust storms that occurred for 2‐3 days over a significant portion of Queensland.  Sulphur Dioxide  The maximum 1‐hour average and annual average concentrations for SO2 at the Targinie Stupkin Lane and  Swans Road monitoring stations are presented in Table 6.  The EPP (Air) goal of 570 µg/m3 for the 1‐hour concentration has not been exceeded at either of the Targinie  monitoring stations for the years for which SO2 data is available. Additionally, there were no exceedances of  the 24‐hour average SO2 concentration EPP (Air) goal of 230 µg/m3 or the annual average EPP (Air) goal of 57  µg/m3.   Table 6: Summary of Annual Measurements of Sulphur Dioxide from the DERM Targinie Monitoring Sites  (µg/m3) 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 39 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Maximum  1‐hour average 

Maximum  24‐hour average 

Annual  Average 

Year 

Targinie  (Stupkin  Lane) 

Targinie  (Swans Road) 

Targinie  (Stupkin  Lane) 

Targinie  (Swans Road) 

Targinie  (Stupkin Lane) 

Targinie  (Swans Road) 

1997 

‐ 

118.7 

‐ 

51.2 

‐ 

10.3 

1998 

‐ 

92.9 

‐ 

24.7 

‐ 

4.8 

1999 

‐ 

118.7 

‐ 

21.7 

‐ 

6.0 

2000 

‐ 

143.0 

‐ 

23.0 

‐ 

4.7 

2001 

19.5 

266.0 

2.4 

25.4 

0.6 

3.7 

2002 

201.6 

147.3 

33.5 

32.8 

6.3 

5.9 

2003 

235.9 

291.7 

44.9 

48.0 

6.7 

6.3 

2004 

316.0 

348.9 

34.3 

23.9 

6.8 

4.6 

2005 

147.3 

121.5 

36.2 

32.6 

6.7 

4.4 

2006 

150.1 

130.1 

35.7 

31.4 

9.1 

6.2 

2007 

‐ 

204.5 

‐ 

24.3 

‐ 

4.7 

2008 

‐ 

138.7 

‐ 

20.5 

‐ 

3.5 

EPP (Air)  objective 

570 

230 

57 

 

5.1.2. Site Emissions Sources  Emissions sources addressed in this plan include the following:  1. Point Sources under Normal Operations  Sources with continuous emissions under normal operations, including emissions generated by the  combustion of gas and the processing of feed gas for liquefaction.  2. Point Sources under Start‐up, Shutdown or Upset Conditions  Non‐normal operations refer to conditions at the LNG Facility that are outside the general operating  parameters  of  the  plant  and  occur  intermittently  for  a  short  duration.  Emission  rates  for  these  activities may also be variable and, consequently, do not impact air quality on a continual basis.  3. Fugitive Emissions and Other Sources  There may also be minor emissions from vehicles and occasional use of mobile plant and equipment  (for example, mobile pumps to manage stormwater, mobile generators for maintenance works, etc.).  These  emissions  will  be  transient,  intermittent  and  spatially  variable.  Vehicles  may  also  generate  dust if driven on unsurfaced roadways. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 40 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

Fugitive emissions may arise due to trace leakage of gas through flanges, valves or other equipment,  and  from  vents  and  pressure  safety  valves  (PSVs).    PSVs  and  vents  are  installed  on  a  range  of  equipment across the site.    Locations of key site static emissions sources during LNG operations are shown in Figure 9, and a summary  provided in Table 7 below.    

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 41 of 89 

Train 2

Nitrogen Rejection Unit

Acid Gas Removal Unit

( !

( ! Compressor Gas Turbines (x6)

! ( ( !

Regeneration Gas Heater Hot Oil Heater

Figure 11: Locations of QCLNG Static Emissions Sources Legend

( !

Static Emission Source

Gas Turbine Generator (x3)

QCLNG Site Boundary (PFL11)

Train 1 Acid Gas Removal Unit

( !

( !

Compressor Gas Turbines (x6)

Static Emission Source

Wet Lease Boundary

Nitrogen Rejection Unit

Export P ipeline

Emergency & Back-Up Diesel Generators Fire Water Pum ps (x3)

Process Flares (Wet and Dry Gas)

( !

Marine Flare

( !

DATE: 2/08/2013 CREATED BY: MAP NO:

hibberde M_25547_01c

±

Standby Diesel Generator (Marine Terminal Building)

0

50

100

150

200

250

Meters Map Projec tion: GDA 94

DATA SOURCE:

SCALE:

1:5,000

(A3)

Site La yout - Bech te l Site Bo un dar y - DME Aer ial Imag ery - Near Map

N ote : E v er y e ffo rt ha s b ee n m ad e t o e ns ur e this infor m a t io n is sp at ia lly a c c ur at e . T he loc a tion of this infor m a tio n s hould n ot be r e lie d o n a s t he e xa c t f ield lo c at ion. "B as e d on o r c o nta i n s d a ta p ro v id e d b y th e Sta te o f Q u ee n s la n d (D e p a rtm en t o f En v ir on m e n t an d R e so u rc e Ma n a g e me n t) 2 0 11 . In co n si d er a tio n o f th e S ta te p e rm itti n g u s e o f th is d a ta y o u a c kn o w le d g e a nd ag r ee th a t the S ta te g i ve s n o w a rra n ty i n re la ti o n to th e da ta (i n cl u di n g ac cu r ac y, re li a b il ity, co m pl e te ne s s, c ur re n cy or su ita b i li ty) a n d a cc ep ts no l ia b i li ty (i n cl ud i n g w i th o ut l im i tati o n , li ab i li ty i n ne g l ig e n ce ) fo r a n y l o ss , d a m a g e o r co sts (in c lu d i ng c on s e qu e n tia l d a ma g e ) re l a tin g to an y us e o f th e d a ta. D a ta m us t n ot b e u se d fo r d ir ec t ma r ke tin g o r b e u se d in b re a ch o f th e p ri va c y l a w s."

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Table 7: Summary of Emissions Sources  Location  Aspect 

Point Sources  ‐ Normal  Operations   

Issue date: September 2013  Review due: September 2014 

Emission Source 

Number 

Compressor Gas Turbines 

12 (6 per train) 

NOx (minor / trace CO, PM10, CO2, CH4) 

Trains 1 and 2 

Acid Gas Removal Unit (CO2 vent) 

2 (1 per train) 

CO2 (minor CH4) 

2 (1 per train) 

N2 (minor CH4) 

Power Generation 

Nitrogen Rejection Unit (NRU  vent)  Gas Turbine Generators 

3  

NOx (minor / trace CO, PM10, CO2, CH4) 

2 operational, 1 standby  

Wet & Dry Gas Flares  

  

NOx, CO (minor/trace PM10, CO2) 

Pilot light only during normal ops 

Marine Flares  

 

Dependent upon vessel 

Pilot light

Wet and dry gas flares 

 

Flaring due to purging, dryout,  cooldown, trips or upset 

Marine flare  

 

Hot Oil Heater  



NOx, CO, (minor / trace PM10,  hydrocarbons)  NOx, CO, (minor / trace PM10,  hydrocarbons)  NOx (minor / trace CO, PM10, CO2, CH4) 

Regeneration Gas Heater  



NOx (minor / trace CO, PM10, CO2, CH4) 

Start‐up only (not monitored) 

Power generation (diesel) 



Diesel emissions 

Start‐up / back‐up only (not  monitored) 

Fire Water Pumps (diesel)  



Diesel emissions 

Intermittent – emergency (not  monitored) 

Standby Diesel Generator Marine  Terminal Building  



Diesel emissions 

Emergency air compressor –  (diesel)  Vehicles 



Diesel emissions 

 

Diesel emissions 

Mobile Plant and Equipment  PSVs ‐ Amine Units and Tanks

 

PSVs ‐ LNG Tanks 

 

Diesel emissions  N2 Blanket CH4 

Vent ‐ Hot Oil Storage Tank 

 

N2 Blanket

Flares 

Flares 

Point Sources  ‐ Start‐up,  Shutdown or  Upset  Conditions 

Fugitive  Emissions and  Other Sources   

Comments 

Key Emissions 

Utilities and  Back‐up 

Mobile 

PSVs and vents 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Trips or upset Start‐up only (not monitored) 

Intermittent – (not monitored)  Intermittent –back‐up (not  monitored) 

Intermittent for pressure relief 

Revision: 0  Page 43 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Location 

Aspect 

Issue date: September 2013  Review due: September 2014 

Emission Source 

Number 

Comments 

Key Emissions 

Miscellaneous Atmospheric Vents  (e.g. water tanks, plant and  instrument air receivers) 

 

Air 

Demineralised Water Storage  Tanks 

 

N2 Blanket 

Nitrogen Receivers 

 

N2 Service

Gas Analysers 

 

CH4 

PSVs on Hydrocarbon Absorbers 

 

Air, N2

PSVs ‐ Refrigerant Isotainers 

 

Ethylene, propane

 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 44 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.1.3. Emissions Reduction through Application of Best Techniques in Design  A  part  of  Project  development,  a  Best  Available  Techniques  (BAT)  assessment  was  undertaken.  BAT  is  essentially  an  assessment  of  techniques  that  minimise  the  environmental  impact,  without  entailing  disproportionate cost. Techniques refer to both technology and the way the process is operated.  For the QCLNG Project, a BAT assessment undertaken by QGC during the design stage focussed on reducing a  range of atmospheric emissions, principally:  

GHG emissions (primarily CO2 and CH4) 



Emissions with potential impacts on local air quality (primarily nitrous oxides (NOx)) 



Emissions from H2S (not anticipated from the LNG Facility) 



Volatile Organic Compounds (VOCs)  (not anticipated from the LNG Facility) 

As a result of the BAT assessment process undertaken, the following emissions mitigations were incorporated  into the design of LNG Facility:  

Adoption  of  waste  heat  recovery  (WHR)  to  reduce  requirement  for  use  of  fuel  gas  burners  associated with the dehydration and CO2 removal components of the LNG process. Use of fuel gas  burners  is  estimated  to  result  in  emission  of  approximately  10,800  tonnes  of  CO2  per  annum  per  LNG train, with WHR to reduce this to approximately 365 tonnes CO2 per annum 



A  variety  of  refrigeration  compressor  drivers  were  considered  for  the  Project.  The  aero‐derivative  LM2500+G4s  with  Dry  Low  Emissions  (DLE)  were  selected  in  a  2+2+2  configuration  for  each  LNG  process  train  (a  total  of  six  compressor  drivers  per  train).  Design  NOx  emissions  from  this  configuration of LM2500+G4s + DLE are as low as or lower than any of the other options considered  in  detail  (although  electric  motor  drives  were  not  considered  in  detail  due  to  being  unproven  technology for the required drive size and electrical stability analysis). The initial template design of  the facility assumed use of 2+2+2 (per LNG train) Frame 5D Gas Turbine Drivers, and selection of the  LM2500+G4s will result in a reduction of:  -

annual NOX emissions from approximately 975 tpa per LNG train (for the Base Case of the  Frame 5D) to approximately 580 tpa per LNG train and 

-

annual CO2 emissions from approximately 1,020 Mtpa per LNG train (for the Base Case of  the Frame 5D) to approximately 730 Mtpa per LNG train. 



Optimisation  of  power  generation,  with  a  range  of  turbine  configurations  assessed  for  1,  2  and  3  train  operation.  Aero‐derivative  LM2500+G4s  with  DLE  were  also  selected  for  power  generation,  with 2 operating + 1 spare (for 2 Train operation). For the third train it was assumed that IAC has  been applied (see below), allowing two operating LM2500+G4 units to run all three trains. Use of  the  LM2500+G4  is  calculated  to  result  in  the  lowest  NOX  and  CO2  emissions  of  all  the  options  considered. 



Inlet  air  chilling  on  the  main  refrigeration  turbines  optimises  the  efficiency  of  the  turbines  over  a  range of ambient temperatures and humidity, improving annual LNG production. The use of IAC can  provide additional power per train to the liquefaction refrigeration compressors on a warm day for  an investment of less power to the IAC utility plant. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 45 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

IAC  provides  an  operational  benefit  for  upstream  operations,  as  it  can  provide  a  stable  feed  demand  throughout  daily  temperature  swings,  thus  improving  the  efficiency  of  upstream  operations  by  reducing  personnel  and  transportation  resources  through  steady  operations  rather  than continually cycling the production flow rates.       

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 46 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013  Review due: September 2014 

Table 8: Summary of Best Available Techniques Assessment Outcomes as Applicable to Air Quality (assessment per LNG Train)  Component  Environmental Issue / Constraint  Base Case  BAT Assessment Summary  Acid Gas Removal

H2S

BAT Outcome 

Venting off acid gas: ‐ no incinerator. 

Negligible H2S present in feed gas.  Also, given concentration of CO2, additional hydrocarbons would  need to be added to incinerator to make it burn, resulting in  increased emissions. 

Base case retained. 

Dehydration and  TOC/CH4 emissions arising from  Mercury Removal  operation of fuel gas burner 

Fuel gas burner (H‐1301).  3 beds, 2 beds on 24 hr  adsorption, 1 bed on 12  hrs regeneration/standby  with 3.5 hours heating.  

WHR to reduce burner requirement.  ‐ 3 beds, burner only required on restart. Assume WHR reduces  requirement to 5 per cent of year (ie, 95 per cent reduction  emissions from base case) 

WHR  adopted.  

Refrigeration gas  turbines 

2+2+2 Frame 5D Gas  Turbine Drivers 

Options considered:

NOx 

LM2500+G4 aero‐ derivative refrigeration   Option 1 2+2+2 Frame 5D Gas Turbine Drivers  driver with Dry Low   Option 2 2+2+2 LM2500+G4 Gas Turbine Drivers  Emissions (DLE)   Option  3  2+2+2  Electric  Motor  Drives  with  LMS100  combustion system  Power Station Drivers (Simple Cycle)  selected for the Project,   Option  4  2+2+2  Electric  Motor  Drives  with  LMS100  utilising 6 x LM2500+G4s,  Power Station Drivers (CCGT)  in 2:2:2 configuration for  NOx discharges of each turbine: Aero derivative engines will be  each 3.8 mtpa LNG train.  guaranteed at around 25 ppmv NOx. The Frame 5D LHE    combustor will operate at around 121 ppm NOx, and the Frame  Estimated reduction in  5D with a DLN1 combustor will produce 42 ppmv NOx.  annual NOx emissions    from approximately 975  Electric drives partially rejected due to limited reliability and  tpa per LNG train (for the  proven technology data.  Base Case of the Frame  5D) to approximately 580  tpa per LNG train. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 47 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013  Review due: September 2014 

Component 

Environmental Issue / Constraint 

Base Case 

BAT Assessment Summary 

Electric Power 

NOx

Power generation using  Solar Taurus 70's with  Solonox. Five operational  generators required for  Train 1 (plus one spare, for  a 5+1 configuration), with  an additional three  operational generators  required per additional  LNG train 

Options considered on a 2 train basis with Inlet Air Chilling.  ‐ Option 1: LM2500+ G4s ‐ 2 Units Online  ‐ Option 2: Taurus 70 ‐ 8 Units Online  ‐ Option 3: Mars 100: ‐ 6 Units Online  ‐ Option 4: Titan 130 ‐ 4 Units Online    LM2500+G4 option results in the lowest NOx emissions.   

Hot Oil System 

CO2, TOC/CH4 and NOx  

Heater 3401 ‐ 2 per train.  Estimated emissions per  train: 83,000 tpa CO2, 7  tpa TOC/CH4, 64 tpa NOx. 

WHR would allow reduction of heaters to 1 heater per train, with  Waste Heat Recovery  operation required only on start‐up.  adopted.     Assume WHR reduces requirement to 5 per cent of year, this  would indicate 95 per cent reduction in emissions from base  case. 

Inlet Air Chilling  (IAC) 

No inlet air chilling IAC on refrigeration turbines  reduces power requirements and  potentially allows for increase in  LNG production without an  increase in the PFD flow rates.  However, reduced power  requirement on the refrigeration  turbines and increased LNG  production is offset by increased  demand in electric power. Hence,  IAC has the potential to increase  emissions (primarily NOx and  CO2) associated with turbine  operation 

Estimates indicate that IAC potentially provides a marginal  increase (3.8 per cent) in LNG production per total unit of power  generation for the 1 train case, and a slightly greater increase  (5.1 per cent) in LNG production per total unit power generation  for the 2 train case. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 48 of 89 

BAT Outcome  LM2500+g4s: 2 operating 1  spare (for 2 Trains or 3  Trains with IAC).    Estimated reduction in  annual NOx emissions for 2  trains from approximately  145 tpa (for the base case)  to approximately 124 tpa  (for the LM2500+G4  option).  

IAC adopted. 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.1.4. Potential adverse or beneficial impacts of the project activities on the identified environmental values  5.1.4.1.

EIS Summary of Impacts 

Detailed  assessment  of  the  potential  impacts  of  LNG  operations  on  the  existing  air  quality  values  of  the  Gladstone region are described in Volume 5 Chapter 12 of the QCLNG Project draft EIS.  The assessment was  undertaken on the basis of a three train LNG Facility, so represents a higher emissions scenario than would  be  applicable  to  this  OEMP,  and  considered  both  the  QCLNG  Facility  in  isolation  and  cumulative  impacts  arising from other emissions sources in the Gladstone air shed.  A summary of outcomes is provided below.  For normal operation of the LNG Facility, the air quality assessment indicates the following:  

The  predicted  maximum  1‐hour  and  annual  average  ground‐level  concentrations  of  NO2  at  any  sensitive  place  during  normal  operating  conditions,  and  including  background,  are below  the  EPP  (Air) air quality objectives. 



The  maximum  concentrations  of  CO  are  below  air  quality  objectives  across  the  modelling  domain  under normal operation conditions including background. 



The predicted maximum 24‐hour average ground‐level concentration of PM10 at any location within  the  modelling  domain,  under  normal  operating  conditions,  in  isolation  is  1.8  μg/m3.    With  the  inclusion of the background (i.e. air quality resulting from existing industrial activities in Gladstone  region) the maximum is 30.8 μg/m3, which is 61.6 per cent of the EPP (Air) air quality objective of 50  µg/m3. 



None  of  the  hydrocarbon  species  associated  with  emissions  from  the  LNG  Facility  exceed  the  ambient air quality objectives at the most sensitive receptor. 



The  contribution  from  operations  to  photochemical  activity  in  the  Gladstone  region  is,  at  worst,  minor and unlikely to be of any concern. 



Predicted maximum 1‐hour average concentration of odorous compounds, from the LNG Facility in  isolation,  at  the  most  affected  sensitive  receptor  is  well  below  both  the  odour  threshold  and  the  ambient air quality objective. 

Non‐normal operations were assessed on the basis of three scenarios, including:  

normal plant operations plus LNG carrier at wharf. 



non‐normal plant operations with dry gas flare upset conditions. 



non‐normal plant operations with marine flare upset conditions. 

Under the normal plant operations plus LNG carrier at wharf scenario, the air quality assessment indicates  the following:  

The  predicted  maximum  1‐hour  and  annual  average  ground‐level  concentrations  of  NO2  at  any  sensitive place, including background, are below the EPP (Air) air quality objectives; 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 49 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  



There are no exceedances predicted of the EPP (Air) air quality objective for the 1‐hour, 24‐hour and  annual  average  ground‐level  concentrations  of  SO2,  due  to  the  proposed  shipping  activity,  when  assessed in isolation.  Predicted ground‐level concentrations in exceedance of the 1‐hour, 24‐hour  and  annual  average  air  quality  objectives  are  located  in  close  proximity  to  the  existing  Gladstone  power  station  and  due  to  power  station  emissions,  with  predicted  ground‐level  concentrations  of  SO2 in the vicinity of the QCLNG Project, well below the air quality objectives; 



The predicted maximum 1‐hour, 24‐hour and annual average ground‐level concentrations of SO2 at  any  sensitive  place  for  the  shipping  activities,  including  background,  are  below  the  EPP  (Air)  air  quality objectives. 

Under  the  non‐normal  plant  operations  with  dry  gas  flare  upset  conditions  scenario,  the  air  quality  assessment indicates the following:  

There  are  no  exceedances  predicted  of  the  EPP  (Air)  air  quality  objective  for  the  1‐hour  average  ground‐level  concentration  of  NO2  due  to  a  dry  gas  flare  event,  when  assessed  in  isolation.  Predicted  exceedances  of  the  1‐hour  average  ground‐level  concentration  EPP  (Air)  air  quality  objective are located in close proximity to the existing Gladstone power station and due to power  station emissions.  Predicted ground‐level concentrations of NO2 in the vicinity of the LNG Facility  are well below the EPP (Air) air quality objectives. 



The  maximum  concentrations  of  CO  are  below  air  quality  objectives  across  the  modelling  domain  including background. 



Predicted  ground  level  concentrations  of  hydrocarbons  are  very  low  and  none  are  likely  to  be  present in sufficient quantities to cause asphyxiation. 

Under  the  non‐normal  plant  operations  with  marine  flare  upset  conditions  scenario,  the  air  quality  assessment indicates the following:  

There  are  no  exceedances  predicted  of  the  EPP  (Air)  air  quality  objective  for  the  1‐hour  average  ground‐level concentration of NO2 at any sensitive receptor location when assessed in isolation and  with  background.    An exceedance  of  the  1‐hour  average  ground‐level  concentration  EPP  (Air)  air  quality objective for NO2 is predicted in the proximity of the marine flare and wharf facilities, with  predicted ground‐level concentrations of NO2 beyond the QCLNG Project operations area below the  EPP (Air) air quality objectives. 



Maximum  predicted  concentrations  of  CO  are  below  air  quality  objectives  across  the  modelling  domain including background. 



Predicted  ground  level  concentrations  of  hydrocarbons  are  very  low  and  none  are  likely  to  be  present in sufficient quantities to cause asphyxiation. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 50 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.1.4.2.

Issue date: September 2013   Review due: September 2014  

Updated Assessment of Impacts 

A  more  recent  assessment  has  been  undertaken1  to  validate  the  findings  of  the  QCLNG  Project  EIS,  addressing some minor changes from the assessment undertaken for the EIS due to:  

Minor modification to the site layout from what was previously assessed; 



The  inclusion  of  waste  heat  recovery  (WHR)  on  two  of  the  six  compressor  turbines  per  LNG  processing train; 



Changes in the source characteristics of the gas compressor turbine drivers and power generation  turbines. 

Given  that  NO2  was  identified  in  the  QCLNG  Project  EIS  as  the  air  pollutant  which  resulted  in  the  highest  ground‐level  concentrations  during  normal  operations  compared  to  the  air  quality  objectives,  the  revised  assessment considered only NO2 emissions.  The EIS modelling included compressor turbine drivers, power generation turbines, regeneration oil heaters,  hot oil heaters, and flares as NO2 sources. The revised QCLNG facility plans incorporate waste heat recovery  (WHR) on two of the six compressor turbines per LNG processing train. A consequence of the use of WHR is  that  the  regeneration  gas  heater  and  the  hot  oil  heater  will  be  required  for  start‐up  and  back‐up  only.  Because of this change and since the emissions contribution of flares during normal operations is negligible,  this  revised  assessment  considers  only  the  compressor  turbine  drivers  and  the  power  generation  turbines.  These two types of sources were together responsible for more than 90% of the NO2 emissions for normal  operations in the EIS modelling.  The assessment considered both the two LNG train case (which is the focus of this OEMP) and the three train  case assessed in the EIS, with key conclusions summarised below: 

1



The  predicted  1‐hour  average  and  annual  average  ground‐level  concentrations  of  NO2  for  the  QCLNG  Facility  in  isolation  are  well  below  the  relevant  Air  EPP  objectives  at  all  locations  in  the  modelling domain, including all of the sensitive receptors.  



The  highest  short‐term  concentrations  (1‐hour  average)  of  NO2  due  to  the  plant  in  isolation  are  predicted to occur on site and on elevated terrain to the north and at Mount Larcom. However, the  NO2 concentrations predicted in these areas are less than 20% of the Air EPP objective of 250μg/m³.  



The highest annual average concentrations of NO2 are predicted to occur to the northwest of the  site due to the dominance of winds from the southeast. The highest predicted annual average NO2  concentration in this area is less than 3% of the Air EPP objective of 62μg/m³  



Background ground‐level concentrations of NO2 in the Gladstone region are significantly higher than  the  contributions  by  the  QCLNG  Facility,  a  conclusion  of  the  QCLNG  Project  EIS  air  quality  assessment. As a consequence of the minor differences in predicted NO2 concentrations from the  QCLNG facility in both the QCLNG Project EIS and this air quality assessment, the cumulative impacts  predicted in the EIS remain valid. 

Katestone, 2013. Air Quality Impact Assessment for the QCLNG Facility. Unpublished report D12070-6, June 2013.

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 51 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.1.5. Management, Monitoring and Corrective Action  Specific  management  and  monitoring  measures  for  air  emissions  are  addressed  in  the  Air  Quality  Management Plan (LNGOP‐QL00‐ENV‐PLN‐000004). 

5.2. VISUAL IMPACT AND LIGHT  5.2.1. Description of Environmental Values  The QCLNG Project EIS considered the existing visual amenity of the Gladstone region and key impact issues  associated with the LNG Facility and associated lighting, with a summary of findings provided below.  The LNG Facility falls within the Great Barrier Reef World Heritage Area (GBRWHA), which is World Heritage  listed for Outstanding Universal Values including aesthetics and natural beauty.   However, in the Gladstone  region  the  visual  amenity  of  the  GBRWHA  is  already  attenuated  by  the  presence  of  Port  of  Gladstone  industrial  elements  in  the  viewshed.  Therefore,  this  area  is  not  ‘‘pristine’’  or  representative  of  the  “exceptional natural beauty” assigned to the World Heritage and National Heritage values.   The Narrows is listed on the Australian Heritage Commission Register of National Estate. The Statement of  Significance  as  detailed  on  the  Heritage  database  includes  the  fact  that  “The  Narrows  represent  an  uncommon  passage  landscape  and  are  one  of  only  five  narrow  tidal  passages  separating  large  continental  islands  from  the  mainland  in  Australia”.    The  significant  aesthetic  values  of  this  “uncommon”  passage  landscape are not, however, limited to this administrative area but are continuous with the natural coastal  landscape of Curtis Island fringing the northern extent of the Port of Gladstone. Management of scenic values  across this interface is detailed in the Curtis Coast Regional Coastal Management Plan.  The Curtis Coast Regional Coastal Management Plan also identified Areas of State Significance (Scenic Coastal  Landscape),  with  areas  of  scenic  coastal  landscapes  in  the  Gladstone  region  including  islands  and  offshore  features, coastal wetlands, estuaries and inlets.   In  addition  to  visual  amenity,  a  number  of  fauna  species  are  expected  to  inhabit  or  migrate  through  Port  Curtis, with consideration given to impacts associated with lighting of the LNG Facility.  Species considered as  having potential to be impacted included reptiles (including marine turtles), birds, amphibians, terrestrial and  marine mammals and fish.  Visual impacts associated with lighting for residents of Gladstone city were also considered.  

5.2.2. Potential Impacts  5.2.2.1.

Visual Amenity 

Taking  into  account  visual  impact  mitigation  measures  incorporated  into  LNG  Facility  design  (refer  Section  5.2.4), the QCLNG EIS considered the visual impact of the LNG Facility on landscape character from a range of  viewpoints  in  the  Gladstone  region,  with  impacts  ranging  from  major  (from  viewpoints  located  from  the  waters of Port Curtis immediately in front of the LNG Facility),  to low to negligible from residential dwellings  in the Gladstone region.  The  EIS  concluded  that  the  impact  on  the  “aesthetics  and  natural  beauty”  of  the  GBRWHA  area  is  already  attenuated by the presence of Port of Gladstone industrial elements in the viewshed. Therefore, this area is  not  ‘‘pristine’’  or  representative  of  the  “exceptional  natural  beauty”  assigned  to  the  World  Heritage  and  National Heritage values. In addition, the GSDA designation of Curtis Island indicates a planning intention to 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 52 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

develop the area into an industrial precinct. In these circumstances, the landscape and visual impact of the  proposed  LNG  Plant  Facility  and  associated  onshore  mainland  facilities  would  be  consistent  with  the  proposed expansion of industry around the Port of Gladstone, and therefore does not result in a significant  impact to World Heritage Area values. 

5.2.2.2.

Night Lighting 

For residents of Gladstone, high levels of existing industrial lighting in and surrounding the Port of Gladstone  reduce the significance of night lighting impact when viewed from the mainland areas.  Light impacts on other fauna were considered, with reptiles (except marine turtles), amphibians, terrestrial  and  marine  mammals  and  fish  rated  as  having  low  potential  susceptibility  to  impacts  caused  by  light  pollution.  Birds  and  marine  turtles  were  rated  as  having  high  potential  susceptibility  to  impacts  caused  by  light pollution.  Impacts on birds were considered unlikely to increase the extent of any roosting and/or nesting displacement  above  that  caused  by  vegetation  clearing  for  construction  of  the  LNG  Facility.  Foraging  and  roosting  sites  within adjacent habitat areas, particularly those located to the south and west of the LNG Facility site, are  expected  to  be  subjected  to  light  spill.  Potential  impacts  on  these  locations  are  expected  to  be  low  to  moderate, and generally within natural fluctuations and trends.  

5.2.3. Potential Light Impacts – Impacts of Flaring on Marine Turtles  The issue of potential impact of lighting (including light associated with flaring) from the QCLNG LNG facility  on  turtle  nesting  was  considered  in  the  QCLNG  EIS  which  noted  that  the  Green  turtle  (Chelonia  mydas);  Loggerhead  turtle  (Caretta  caretta);  and  Flatback  turtle  (Natator  depressus)  are  known  to  occur  in  Port  Curtis.  These turtles nest occasionally on the ocean side beaches of Curtis Island and Facing Island, but no  known turtle‐nesting beaches were identified within close proximity to the proposed QCLNG Project.  Based  on the LNG Facility layout and flare height described, it was concluded that  nesting beaches on the ocean  side of Curtis and Facing Islands would not be subject to direct light spill from the Facility (refer draft EIS Vol  5, Chapter 8 Section 8.4.1.4 and Chapter 16).    Known turtle nesting beaches are shown in Figure 10.  Green  turtles  have  been  regularly  observed  within  local  seagrass  meadows,  particularly  those  on  Pelican  Banks  (eastern  side  of  Curtis  Island).  Leatherback  turtles  Dermochelys  coriacea),  Hawksbill  turtles  (Eretmochelys imbricata) and Olive Ridley turtles (Lepidochelys olivacea) are not known to nest in the Port  Curtis  area.  Individuals  may  migrate  through  the  area,  but  significant  numbers  of  them  are  unlikely  in  the  vicinity of the LNG Facility.  The  assessment  of  flaring  impacts  described  in  the  QCLNG  EIS  was  based  on  a  flare  stack  height  of  approximately  60  m  above  ground  level.    Subsequent  refinement  in  design  and  safety  considerations  has  resulted in an amended flare stack height of approximately 95 m, which combined with the revision to the  flare  location  described  in  the  QCLNG  EIS  required  a  re‐visit  of  this  assessment2.    A  summary  of  issues  considered and conclusions is provided below. 

2

QGC, 2010. Potential Visibility of QCLNG Flares from Turtle Nesting Beaches. Unpublished report, August 2010, Doc No. QCLNG-BX00ENV-RPT-000016

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 53 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.2.3.1.

Issue date: September 2013   Review due: September 2014  

Post‐EIS Assessment of Flare Visibility from Nesting Sites and Impact on Marine Turtles 

A  preliminary  indication  of  flare  visibility  from  known  turtle  nesting  beaches  was  undertaken  based  on  sightlines from the QCLNG flare locations to a total of eight viewpoint (8) locations along approximately 23  km of coastline along Curtis and Facing Island.  The viewpoints were selected along known nesting beaches  for Green and Flatback turtles.    All  viewpoints  are  more  than  10  km  away  from  the  LNG  Facility,  with  the  closest  viewpoint  being  approximately 11.1 km from the nearest flare.  Intervening  topography  was  assessed  along  each  of  these  sightlines  to  determine  whether  the  top  of  the  flares (including flame) would be visible as a direct line of site from the beach.  Lines of sight were run to each  of the two process flares, with flare stack height assumed as follows:  

Stack height : 114 m (note that refinement of flare design has subsequently reduced the flare height  to 95 m above ground level) 



Flame  height:  40‐60  m  above  stack  (indicative  height  of  flame,  based  on  non‐emergency  flaring  scenarios – e.g. commissioning, start‐up, and process control).   

This  assessment  indicated  that  intervening  topography  will  result  in  no  direct  line‐of‐sight  visibility  of  the  flares  (flare  stacks  or  flame)  from  the  viewpoints  considered,  with  the  viewpoint  based  on  an  estimated  elevation of 1 m at the beach.  

5.2.3.2.

Potential Impacts from Light Below the Horizons 

Given  that  direct  visibility  of  the  flare  flames  is  not  anticipated  from  the  viewpoints  considered  along  the  turtle  nesting  beaches  on  Curtis  and  Facing  Islands,  further  consideration  was  given  to  whether  impacts  arising from light below the horizon may have a significant impact on turtle nesting behaviour.    Turtle  hatchlings  respond  not  only  to  nearby  light  sources  but  also  show  aversion  behaviour  to  tall  dark  horizons,  such  as  the  hills  on  Curtis  Island  behind  the  eastern  beaches3.  This  type  of  behaviour  is  likely  to  occur  despite  the  constant  night  sky  glow  from  Gladstone  city  and  existing  industrial  construction  areas  around  the  western  side  of  Port  Curtis.  This  would  be  particularly  relevant  to  the  turtles  nesting  on  the  eastern  beaches  of  Curtis  Island  where  proximity  to  the  Curtis  Island  range  (up  to  164m)  would  generally  allow for significant effects from background silhouetting on turtle behaviour.  Further, while artificial lighting has been linked to disorientation in marine turtles (particularly during periods  of nesting and hatching), the most disruptive wavelengths for hatchlings is relatively low wavelengths of 300  to  500  nanometres  (nm)4  (with  some  data  suggesting  that  Flatback  turtles  may  cue  off  slightly  higher  wavelengths).  Light emitted from a natural gas flare has peak spectral intensity in the 750 to 900 nm range5.     In addition, the distances from the QCLNG Facility to the nesting beaches are such that levels of luminosity  from LNG Facility flaring would be very low, with the distances involved greater than anything that had been  observed as being an influence to turtle behaviour. 

3

Pendoley, K, 2000. The Influence of Gas Flare on the Orientation of Green Turtle Hatchlings at Thevenard Island, Western Australia.

4

Shell Development (Australia) Proprietary Limited, 2009. Prelude Floating LNG Project Draft Environmental Impact Statement. pp131

5

Pendoley, K, 2000. The Influence of Gas Flare on the Orientation of Green Turtle Hatchlings at Thevenard Island, Western Australia

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 54 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.2.3.3.

Issue date: September 2013   Review due: September 2014  

Conclusion 

On the basis of the above, while recognising that light sources are a known potential cause of disorientation  for marine turtles, especially for hatchlings on beaches, assessment of the potential visibility and impact of  QCLNG’s flares indicates that:   

Light emitted from an LNG flare  flame is typically of higher wavelength than the wavelengths that  are most disruptive for marine turtles.  



Intervening topography means there will not be direct line of site to the QCLNG process flares (stack  or flame) from the eight viewpoints assessed along the nesting beaches on the eastern side of Curtis  and Facing Island.  

The distances involved (>10km) between the LNG Facility and the nesting beaches are greater than anything  that has been observed as being an influence to turtle behaviour.   

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 55 of 89 

Figure 13: Port Curtis Turtle Nesting Beaches and Seagrass Distribution

[ ¶

CURTIS ISLAND

Legend

/ " Temporary Marine Access

[ ¶

CURTIS ISLAND

Narrows Crossing Curtis Island Laydown

Flatback Turtle Green Turtle

Turtle Nesting Beaches

[ ¶

Proposed Export Pipeline Existing Export Pipeline

!

/ "

Existing Channels

MOF !

!

!

!

2001-2011 Seagrass Habitat

Coastal Seagrass, November 2011 !

!

!

!

! !

!

!

!

!

!

!

!

!

Coastal Seagrass, 2010 (November 2009)

Con Dock

!

!

!

!

/ "

Temporary Navigation Channel for MOF and CD

!

!

!

!

!

!

!

!

!

!

Coastal Seagrass, June 2010

[ ¶ !

/ "

!

/ "

[ ¶ [ ¶

Key Transport Nodes

[ ¶

!

FACING ISLAND

/ "

RG Tanna

/ "

Marina

/ "

Auckland Point 2

/ "

Auckland Point

[ ¶ [ ¶

DATE: 6/08/2013 CREATED BY: MAP NO:

±

0

1

2

3

hibberde M_30997_03

4

Kilometers QUEENSLAND MAINLAND

Map Projection: GDA 94

[ ¶

DATA SOURCE:

SCALE: 1:85,000

(A3)

Imagery - NearMap Site Layout - Bechtel

Note: Every effort has been made to ensure this information is spatially accurate. The location of this information should not be relied on as the exact field location.

"Based on or contains data provided by the State of Queensland (Department of Environment and Resource Management) 2011. In consideration of the State permitting use of this data you acknowledge and agree that the State gives no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accepts no liability (including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws."

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

 

5.2.4. Mitigation Measures in Design  Mitigation  measures  for  visual  impact  incorporated  into  the  site  location  and  design  of  the  LNG  Facility  include:  

Screening of the LNG Facility from the vast majority of Curtis Island and in particular the adjoining  Environmental Management Precinct through the location of the facility in relation to the Ship Hill  linear ridgeline located to the north.  



Retaining  the  vegetated  ridges  and  hills  on  the  skyline  to  assist  in  reducing  the  visual  impact  by  retaining the natural landscape horizon. 



The  landscape  values  of  Curtis  Island  as  viewed  from  Gladstone  are  largely  maintained  due  to  the  retention  of  the  minor  ridgeline  to  the  south‐east  of  the  site.  Vegetation  along  these  hills  and  ridgelines maintained to ensure their integrity as screening elements in the landscape. 



Views of Curtis Island from Targinie and the waters of the Port of Gladstone opposite the site do not  have the benefit of the screening potential of topography or vegetation. Retention of the mangroves  along  the  shoreline,  where  possible,  contribute  to  reducing  the  visual  impact  by  maintaining  a  continuity  of  the  natural  shoreline  on  Curtis  Island  and  softening  the  interface  between  the  constructed edge of the LNG Facility and the water’s edge. 

Based on the EIS assessment, State and Commonwealth Project Approvals imposed conditions on the Project  relating to minimisation of visual impact, primarily through measures undertaken during design, layout and  construction of the LNG Facility.  Management and mitigation measures for visual impact implemented (or  planned for completion during construction) include:  

Constructing  the  LNG  Facility  within  the  bounds  of  the  site  footprint  as  approved  in  the  Project  Material  Change  of  Use  approval  (permit  DGBN11_389),  the  EA  (EPPG00711513),  and  LNG  Facility  EPBC  Approval  (2008/4402)  with  clearing  of  vegetation  kept  to  the  minimum  required  for  construction works; 



Utilising  a  colour  scheme  for  the  LNG  facility  and  buildings,  other  than  the  LNG  storage  tanks  and  corrosion protected structures and pipe insulation, selected from the palette of predominant colours  found in the locality to minimise the visual intrusion of the structures except where health and safety  requirements dictate; 



Treating earthworks such as cuttings, batters and retaining walls, to minimise visual impacts.  Figure  11 below shows the planned completion status of site slopes and Table 9 summarises the areas to be  treated (noting that these are indicative subject to finalisation of slope treatment design), with the  majority  of  site  slopes  being  seeded  with  grass  (approximately  60%  of  site  slopes  being  lined  with  grass, either with or without underlying geoweb for stability), or rock.   



Physically shielding lights and directing the lights onto work areas, and keeping light heights as low as  practicable. 

Table 9: Indicative Site Slope Stabilisation Summary  Slope Treatment 

Treated Area 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 57 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

m2 

Area as % of all Site Slopes 

Rock lining 

1,272 

0.5% 

Grass lining 

151,257 

59.0% 

Geoweb with rock 

69,647 

27.2% 

No treatment 

7,703 

3.0% 

2.1 base course 

26,499 

10.3% 

240,642 

100.0% 

TOTAL 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 58 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013  Review due: September 2014 

Figure 11: Indicative Site Slope Stabilisation Plan   

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 59 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.2.5. Management, Monitoring and Corrective Action  As  outlined  above,  management  and  mitigation  measures  for  visual  impact  (including  light  impacts  on  nesting marine turtles) are addressed through:  

Location  of  the  QCLNG  Facility,  and  in  particular  the  topographic  barriers  between  the  facility  and  turtle nesting beaches in the Gladstone region; 



Minimisation of vegetation clearing during construction; 



Utilising  a  colour  scheme  for  the  LNG  Facility  and  buildings,  where  safe  and  practicable,  selected  from the palette of predominant colours found in the locality; 



Treatment  of  earthworks  such  as  cuttings,  batters  and  retaining  walls,  to  minimise  visual  impacts,  which will be completed during construction of the QCLNG Facility; and 



Lighting design. 

During Operations, measures applicable to management of visual impact will include:  

Maintenance  of  treated  earthworks  (i.e.  –  maintenance  of  re‐vegetated  slopes)  to  minimise  visual  impact 



Management  of  complaints  associated  with  visual  impact  in  accordance  with  the  QGC  Gladstone  Stakeholder Engagement Plan (QCLNG‐AUS‐GEN‐GPA‐PLN‐0689). 



Reporting  on  monitoring  undertaken  in  response  to  complaints  or  specific  direction  of  the  Administering Authority will be provided within fourteen (14) days of completion of the investigation  or receipt of monitoring results, whichever is the latter, in accordance with Schedule J of the EA.  



Additional management and monitoring requirements specific to marine turtles are included in the  Long‐Term Turtle Management Plan LNG Facilities – Curtis Island, Gladstone (QCLNG‐BX00‐ENV‐PLN‐ 000070), as referenced in the Biodiversity Management Plan. 

5.3. NOISE  A detailed description of the existing environmental values for noise in the Gladstone region, and a detailed  assessment  of  potential  impacts,  have  been  described  in  the  QCLNG  Project  EIS (Volume 5 Chapter 13).    A  summary is provided below. 

5.3.1. Description of Environmental Values  This  section  describes  potentially  sensitive  noise  receptors  in  the  vicinity  of  the  LNG  Facility  project  area  (which includes Curtis Island and the Gladstone mainland) and outlines the background noise monitoring that  was undertaken to establish the baseline noise environment. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 60 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.3.1.1.

Issue date: September 2013   Review due: September 2014  

Background Noise Monitoring 

Seven  residential  properties  were  identified  as  representative  of  the  nearest  sensitive  receptors  for  noise  from the proposed LNG Facility and were designated as noise assessment locations (NALs) for the purposes  of the assessment.  These NALs are summarised in Table 10 below.  Table 10: Noise Assessment Locations  Noise Assessment  Address  Location  NAL 1  Jetty G/H, Gladstone Marina  NAL 2  Lot 2 Fisherman’s Road, Yarwun  NAL 3  Turtle Street, South End, Curtis Island  NAL 4  71 Flinders Parade, Gladstone  NAL 5  Tide Island  NAL 6  12 Lord St, Gladstone  NAL 7  Smith St, Targinie 

Approximate Distance from Curtis  Island LNG Site (km)  8.5  6.5  11.5  10  5  9.5  9 

Five  noise  loggers  (M1–M5)  were  used  to  monitor  background  noise  levels  at  locations  that  were  conservatively selected as having an acoustic climate representative of the NALs.  The loggers continuously  recorded  and  logged  noise  statistics  every  hour  for  the  duration  of  logging.    Additional  data  from  prior  studies were obtained for locations M6 and M7. Noise monitoring locations and durations are summarised in  Table 11.  Table 11: Unattended Noise Monitoring Locations  Monitorin Address  Start‐Finish Date (Duration)  g Location 

Logging Representative of: 

M1 

Jetty G/H, Gladstone Marina 

9 ‐ 25 Sept 08  (17 days) 

Permanent residents living  on boats in the marina 

M2 

Lot 2 Fisherman’s Road, Yarwun 

9 ‐ 25 Sept 08  (17 days) 

Resident 

M3 

Turtle Street, South End, Curtis  Island 

10 ‐ 26 Sept 08  (17 days) 

Resident 

M4 

71 Flinders Parade, Gladstone 

10 ‐ 26 Sept 08  (17 days) 

Resident 

M51 

Hamilton Point, Curtis Island 

10 ‐ 26 Sept 08  (17 days) 

Tide Island resident 

M6 

12 Lord St, Gladstone 

5 ‐19 April 06  (15 days) 

Resident 

M7a2 

Forest Road, Targinie 

12‐19 Apr 08  (8 days) 

Smith St, Targinie Resident 

Notes:  1

 Monitoring undertaken at Hamilton Point proxy for Tide Island.  

2

 Monitoring was undertaken at a location representative of the Targinie area. 

 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 61 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

For periods  where wind speeds exceeded 5 m/s, or while raining, noise data from the affected period was  disregarded, using data from the Gladstone Airport and Gladstone Radar weather stations operated by the  Bureau of Meteorology (BOM).  Day  (7am‐6pm),  evening  (6pm‐10pm)  and  night‐time  (10pm‐7am)  attended  monitoring  was  conducted  to  supplement the unattended noise monitoring surveys and to quantify the contribution from existing industry,  road  and  other  sources  at  the  NALs.    The  attended monitoring  indicated  that  industrial,  road  traffic  or  rail  noise was audible at all locations at various times of the day, with the exception of NAL 3 (South End, Curtis  Island).  Seasonal  variations  in  ambient  noise  levels  were  also  factored  into  the  assessment.  These  variations  are  typically the result of an increase in insect activity, which usually occurs in the warmer months of the year.  Spectral unattended noise monitoring data was analysed for NAL’s 2, 3 and 5 as insects were audible at these  locations during attended monitoring.   Analysis showed a significant contribution from insect noise during  the evening at the three locations but the night‐time contribution was negligible and as such does not affect  monitored Rating Background Levels (RBL) at these three locations.  Evening RBL levels will be increased by  insect noise in some cases, however, this does not have a significant effect on the noise criteria. 

5.3.1.2.

Analysis and Summary of Results  

Analysis  of  logger  data  was  conducted  in  accordance  with  the  EcoAccess  guideline6.    The methodology  is  prescribed  in  terms  of  the  measured  Assessment  Background  Level  (ABL)  and  RBL  or  minLA90,1hour.    In  accordance with the EcoAccess guideline, a minimum of one week of representative data was then selected  for analysis to determine the RBL.  Table 12 provides a summary of RBL values for each NAL.  In addition to the day, evening, and night periods,  a RBL value was calculated for the 6 am to 7 am period.  Table 12: Unattended Monitoring RBL Results dB(A)  Rating Background Level (RBL)1 – dB(A)  Monitoring  Day   Night  Evening   Location  (6pm‐10pm)  (7am‐6pm)  (10pm‐7am) 

  6am–7am 

M1 

45 

47 

43 

43 

M2 

36 

36 

37 

39 

M3 

32 

35 

27 

29 

M4 

40 

36 

36 

40 

M5 

30 

31 

29 

37 

M6 

42 

45 

36 

–2 

M7a 

30 

32 

31 

38 

Notes:   1  RBL or min L90 is an overall single figure representing each assessment period over the whole monitoring period   2  Data not available. 

 

6

Queensland Environmental Protection Agency (now EHP). Guideline – Noise: Planning for Noise Control

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 62 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.3.2. Potential adverse or beneficial impacts of the project activities on the identified environmental values  5.3.2.1.

Noise Criteria 

During operations, the LNG Facility will contain various noise sources that may produce low‐frequency tonal  noise including gas turbines, compressors, flare, pumps and fin‐fan air coolers. Given the large distances to  the  nearest  noise sensitive  receptors  and  the  large  number  of  individual  noise  sources  emitting  noise  at  different  frequencies  at  the  LNG  Facility,  it  is  expected  that  the  industry  noise  may  be  heard  as  a  low  frequency source, with no distinguishable tonal components.  Hence, no adjustment for tonal characteristics  has  been  made  to  the  criteria.    However,  the  predicted  noise  levels  will  be  assessed  against  the  low‐ frequency guideline to determine the acceptability of the LNG Facility noise.  Table 13 provides the Operational noise criteria based on noise monitoring results applied for each NAL, as  specified in the EA (Schedule D).  Table 13: Noise Criteria for Project Noise Assessment Locations  Noise Assessment Location  Period  NAL1  NAL 2  NAL 3  NAL 4  NAL 5  Operations Noise Criteria dB(A) (LAeq, 1 hour) Monday –  7am – 6pm  48 39 35 43 33  Sunday /  6pm – 10pm  47  39  25  33  34  Public  10pm – 7am  40  40  27  39  32  Holidays 

5.3.2.2.

NAL 6 

NAL 7 

45 35  38 

33 35  33 

Noise Modelling 

Modelling  for  the  construction  and  operational  noise  impact  assessment  was  undertaken,  with  the  model  allowing for incorporation of meteorological and topographical effects into noise calculations.  Modelling  incorporated  topographic  data  including  LNG  Facility  site  benching  levels.    Areas  of  open  water  (i.e. Gladstone Harbour) were modelled as areas with very low absorption, while land areas were modelled as  absorptive.  The natural terrain (ridge running north to south) provides shielding for the eastern site of Curtis  Island.   Where modelling was undertaken, consideration was given to “neutral” and “adverse” weather conditions.   Due to the flat topography between the LNG Facility site and the sensitive receptors, no drainage flow7 was  assessed.    Due  to  the  prevalence  of  the  east–south‐easterly  (ESE)  sea  breezes  which  occur  in  Gladstone,  a “typical” weather condition was also modelled, with an east–south‐easterly breeze. 

7

Drainage flows can occur where cooler air flows down a hill or ridge into the valley creating an air movement that can influence sound propagation in a similar way to a light wind.

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 63 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.3.2.3.

Issue date: September 2013   Review due: September 2014  

Summary of Noise and Vibration Impacts 

Noise contour maps representing the various scenarios modelled for the LNG Facility can be found in Volume  5  Chapter  13  of  the  QCLNG  Project  draft  EIS.    A  high‐level  summary  of  predicted  operational  noise  and  vibration impacts is presented below.  The site selected for the LNG Facility is appropriate from a noise perspective as it is located well away from  residential receptors and the natural terrain (a ridge running north ‐ south) provides shielding to the eastern  side of Curtis Island.  This results in negligible impacts for the nearest noise sensitive receptors.  Predicted operational noise levels are below the relevant Queensland criteria for all sensitive locations under  neutral and typical weather conditions.   Under  adverse  conditions  (temperature  inversion  and  calm  winds),  predicted  operational  noise  levels  are  below the relevant criteria for all locations except Tide Island, the closest sensitive receptor to the proposed  LNG Facility.  The exceedance of 5dB(A) under adverse conditions is expected to occur only occasionally as  temperature inversions infrequently form over water, and winds are calm for only 14 per cent of the time.   This exceedance is not expected to be significant.  In  future,  noise  from  the  proposed  LNG  Facility  may  well  be  masked  on  Tide  Island  by  noise  from  other  industry, including the proposed Wiggins Island coal terminal.  The  nature  of  the  noise  generated  by  the  LNG  Facility  is  a  continuous  noise,  with  no  significant  impulsive  characteristics.    Predicted worst‐case noise levels (based on noise levels for ships under full power) for LNG vessels indicate  noise will not impact on sensitive receptors other than Tide Island.  Impact on Tide Island will be transient  and hence shipping traffic is not expected to have a significant direct noise impact on the residence at Tide  Island.  The LNG plant and equipment primarily involves rotating machinery, which will transfer relatively low levels  of vibration to the ground.  Hence operation of the LNG plant will not produce significant levels of ground  vibration.  In summary, noise and vibration are not predicted to impact on sensitive receptors under most conditions. 

5.3.3. Management, Monitoring and Corrective Action  Specific management, monitoring and correction action measures for noise, over and above those related to  design, location and layout of the LNG Facility which formed the basis of the modelling undertaken for the  QCLNG  Project  EIS  and  summarised  above,  is  provided  in  the  Noise  Management  Plan  (LNGOP‐QL00‐ENV‐ PLN‐000008). 

5.4. SURFACE WATER  5.4.1. Description of Environmental values – Surface Water  Volume 5 Chapter 9 of QCLNG Project draft EIS for the QCLNG Project describes “surface waters” and “water  resources,”  as  terrestrial  lakes  and  ponds,  streams,  riverine  and  non‐riverine  wetlands,  and  localised  watersheds in the vicinity of the LNG Facility. 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 64 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

The streams within the Curtis Island Surface Water Management Area (SWMA)8 are unregulated. No data is  available  in  relation  to  the  monitoring  of  Curtis  Island  water  bodies  including  wetlands,  vernal  pools,  lakes  and ponds, rivers and streams (ephemeral or intermittent).  The local catchment area on Curtis Island drains  into Port Curtis, which is within the Great Barrier Reef Marine Park World Heritage Area.  The Directory of Important Wetlands in Australia (DIWA) lists Port Curtis, The Narrows and Northeast Curtis  Island as Nationally Important Wetlands.  However, these are not Ramsar sites.  The Queensland Wetlands  Program database indicates there are riverine9 wetlands containing periodic or moving water in the vicinity of  the LNG Facility site.  Estuarine10 wetlands are the predominant system within and adjoining the LNG Facility  site and the indicative wet lease area.  These wetlands consist of mangroves, salt flats and estuaries. 

5.4.2. Description of Environmental values – Receiving Environment  The  QCLNG  Facility  is  located  on  western  side  of  Curtis  Island  within  Port  Curtis.    Port  Curtis  is  a  major  industrial centre that supports aluminium refineries/smelters, cement production works, chemical plants and  Queensland's  largest  power  station.  The  Port  facilities  provide  for  commercial  shipping  activities  for  a  number of commodities with international destinations. Environmental issues in the region include harbour  dredging,  port  infrastructure  development,  industrial  development,  discharge  of  effluent,  and  extensive  reclamation of intertidal wetlands, including mudflats, mangroves, salt flats and marshes. Intertidal wetlands  occur on the Port Curtis coastline, and some of these areas have been extensively cleared, filled or modified  in areas surrounding Gladstone City and Auckland Creek. Intertidal areas along the south‐west coastline of  Curtis Island in the vicinity of the proposed LNG site are largely undisturbed.  A number of sensitive habitats, including seagrass meadows, are represented across Port Curtis (as well as  broader  regional  areas).  The  key  habitats  found  in  Port  Curtis  are  upper  intertidal  salt  flats,  mid  intertidal  mangroves and rocky shores, and low intertidal mudflats. These habitats are all widespread in the region, and  are not unique to the area of the QCLNG Facility. The upper intertidal salt flats are areas of elevated salinity,  too high for mangroves to survive. These are low productivity areas virtually devoid of invertebrates, except  for small populations in the small tidal waterways.  The coastal area of  Port Curtis is  subject to a strong  tidal influence with up to  5m difference involving the  waters of the interconnected Port Curtis and Fitzroy River estuaries. The Port is well protected from the open  ocean by Curtis and Facing Islands. The area comprises a complex of inlets, channels, shoals, seagrass beds,  tidal  marshes,  river  and  stream  mouths  small  islands  and  shorelines11.  The  Boyne  and  Calliope  rivers,  Auckland  Creek  and  several  smaller  creeks  drain  the  upper  catchment  and  enter  the  estuary  through  its  south‐western coast near Gladstone Harbour.   Within the area of Port Curtis are several key ecosystem areas or habitats, described further below. 

8

As defined in the Australian Water Resources Assessment Database, 2000

9

Riverine wetlands describe all wetlands and deepwater habitats within a channel. These channels can be naturally or artificially created, periodically or continuously contain moving water, or form a connecting link between two bodies of standing water.

10

Estuarine wetlands are those with oceanic water sometimes diluted with freshwater run-off from the land.

11

Conaghan, P.J. 1966. Sediments and Sedimentary Processes in Gladstone Harbour, Queensland. Pap. Dep. Geol. Univ. Qld 6, 1-52

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 65 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.4.2.1.

Issue date: September 2013   Review due: September 2014  

Rodds Bay Dugong Protection Area 

Port Curtis, including the QCLNG Facility, is located within the Rodds Bay Dugong Protection Area (DPA), with  this area covering the entire coastal zone between Rodds Bay and the Narrows. The extent of the Rodds Bay  DPA is shown in Figure 12 below.  Figure 12: Rodds Bay Dugong Protection Area12 

 

5.4.2.2.

Seagrass and other Benthic Habitat 

Seagrasses are true flowering plants found between intertidal and subtidal habitats. Seagrasses play a major  role in marine ecosystem functioning including as a substrate, nursery area and providing shelter and food  for organisms as well as physical stability of the coastline and seafloor. They are essential food sources for a  variety of marine and estuarine organisms including dugongs, turtles, fish and macro invertebrates.   Within the Port Curtis region, seagrass has been regularly monitored by the Department of Primary Industries  and  Fisheries  (DPIF)  Marine  Ecology  Group  in  collaboration  with  the  Port  Curtis  Integrated  Monitoring  Program (PCIMP) which is funded by local industry. Within the Port of Gladstone, the following six seagrass  species have been identified:  

12



Halodule uninervis  



Halophila ovalis  

From Great Barrier Reef Marine Park Authority - http://www.gbrmpa.gov.au/__data/assets/image/0019/6157/gbrmpa_RoddsBay.gif

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 66 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 



Halophila decipens  



Halophila minor  



Halophila spinulosa  



Zostera capricorni.  

Issue date: September 2013   Review due: September 2014  

A total of 7,246 ha of intertidal (coastal) seagrass beds have been identified within the Port of Gladstone –  Rodds Bay Dugong  Protection Area (DPA), with an additional 6,332 ha in deepwater areas (>5m Mean Sea  Level)  identified  to  the  east  and  south  of  Facing  Island13.  No  deepwater  seagrass  communities  have  been  reported within the inner‐port area.   A summary of marine habitat within Port Curtis are summarised in Table 14 below14.

Table 14:  Description and areas of habitat, including seagrass meadows, in Port Curtis  Habitat Type 

Area (Ha) 

% Area of  Total 

Prominent Location(s) 

Exposed mud and sandbanks 

5,144 



Eastern side of Curtis Island,  Western side of  Facing Island 

Exposed rocky substrate 

297 

0.52 

Curtis, Facing, Tide and Picnic Islands 

Seagrass (coastal) 

7,246 

12.7 

Pelican Banks, Quoin Island, Fisherman’s Landing  area  

Seagrass (deepwater) 

6,332 

11.1 

Facing Island, Seal Rocks, West and East Banks 

Benthic  macro‐ invertebrate  communities  (including  coral) 

Open  substrate,  occasional  individual 

9,876 

17.3 

Outside Facing Island from Curtis Island to East  Bank 

Low Density 

8,606 

15 

Throughout the Port of Gladstone / Rodds Bay area 

Medium  Density 

4,099 

7.2 

Southern and northern side of Seal Rocks 

High 

4,189 

7.3 

Narrow strip in channel form 

North‐west of Seal Rocks  Entrance to Rodds Bay 

  The maximum ranges of seagrass communities in Port Curtis from surveys between 2002‐2010 are shown in  Figure 13. It should be noted that more recent surveys (February, March and November 2011) indicate low  seagrass  cover  at  all  permanent  Port  Curtis  transect  sites,  with  the  lowest  seagrass  cover  and  biomass  recorded  at  all  permanent  transect  sites  since  monitoring  began  in  November  2009  and  very  low  levels  of 

13

Data taken from QCLNG Draft EIS, Volume 5 Chapter 8 Marine Ecology, based on:  Rasheed M A, Thomas R, Roelofs,A J, Neil K M.and Kerville S P (2002) Port Curtis and Rodds Bay Seagrass and Benthic MacroInvertebrate Community Baseline Survey 

14

Danaher K, Rasheed M A and Thomas R (2005) The Intertidal Wetlands of Port Curtis

Data taken from QCLNG Draft EIS, Volume 5 Chapter 8 Marine Ecology

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 67 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

recovery during the 2011 growing season. All sites experienced a significant reduction in seagrass cover since  the previous quarterly survey in November 2010. Biomass estimates also showed a significant decline from  November  2010  for  Fisherman’s  Landing,  Pelican  Banks  North  and  Pelican  Banks  South  and  Rodds  Bay.  Seagrass  at  transects  at  Fisherman’s  Landing,  Wiggins  Island  and  Rodds  Bay  had  almost  disappeared  with  mean per cent covers of 0.03 ± 0.01%, 0.03 ± 0.03% and 0.008 ± 0.007% respectively15.  Surveys  in  November  2010,  over  the  Western  Basin  region  (during  the  seasonal  peak  for  seagrass  growth)  found no seagrass was present in the vicinity offshore from the QCLNG Facility site (Curtis Island), and only  one small isolated patch of Halophila ovalis was present in the entire investigation area616. Low cover patchy  meadows are known to vary considerably between years and seasonally. Although absent in 2009 and 2010,  the  presence  of  seagrass  in  2002  indicates  that  this  area  is  potential  seagrass  habitat  and  there  is  a  reasonable expectation that seagrass could occur in the area again given suitable environmental conditions.  Changes  observed  between  surveys  are  within  expected  natural  intra‐  and  inter  ‐annual  variability  for  seagrass along the tropical and sub‐tropical regions of the Queensland coast17.  The most recent monitoring reports of seagrass for the WBDDP project showed similar results in both July  and  August  (2013)  at  the  permanent  monitoring  sites.  Seagrass  was  present  at  all  sites  surveyed,  though  percent  cover  at  most  sites  remained  low,  as  expected  for  this  time  of    year.  The  seasonal  trends  are  generally  consistent  with  previous  years,  showing  smaller  seasonal  increases  in  cover  during  the  spring  months  of  August  or  September.  In  particular,  new  shoots  were  observed  at  inner  harbour  sites  where  seagrass has been absent since the beginning of the year. The return of seagrass meadows in these areas is a  sign of the commencement of the growing season. The trends observed at most inner harbour sites during  July are consistent with seasonal low percentages linked to recent flooding events observed in the past few  years.  It  is  expected  that  further  increases  in  seagrass  cover  should  continue  at  all  locations,  including  the  reference sites in Rodds bay, provided environmental conditions remain favourable and there is an adequate  seed bank18.   

15

Sankey, T. L. and Rasheed, M. A. (2011) Gladstone Permanent Transects Seagrass Monitoring Sites – February and March 2011 Update, DEEDI Publication. Fisheries Queensland, Cairns, 24pp

16

Vision Environment (2011) Marine Plant Surveys for Disturbance Areas – QCLNG Facility. Revised Report – April 2011. Pp.36

17

Unsworth, RKF, Rasheed MA, and HA Taylor (2009) Port of Townsville long term seagrass monitoring – October 2008. DEEDI, Cairns,30 pp

18

Amies RA, McCormack CV & Rasheed MA 2013. Gladstone Permanent Transect Seagrass Monitoring – July 2013 Update Report, Centre for Tropical Water & Aquatic Ecosystem Research Publication 13/36, James Cook University, Cairns, 19pp.

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 68 of 89 

Figure 15: Port Curtis Seagrass Meadow and Mangrove Habitat 2002-2010 Legend QCLNG Facility Layout Seagrass and Seagrass Habitat 2002-2010 Saltpan Mangrove Communities Closed Ceriops Closed Mixed Closed Rhizophora Open Avicennia / Ceriops Laird Point

Friend Point Nth Passage

China Bay

Sth Passage

Witt Island

DATE: 6/08/2013 CREATED BY: hibberde M_30997_02_B MAP NO:

±

0

1

2

3

4

5

Kilometers Map Projection: GDA 94

DATA SOURCE:

SCALE: 1:65,000

(A3)

Imagery - NearMap Site Layout - Bechtel

Note: Every effort has been made to ensure this information is spatially accurate. The location of this information should not be relied on as the exact field location.

"Based on or contains data provided by the State of Queensland (Department of Environment and Resource Management) 2011. In consideration of the State permitting use of this data you acknowledge and agree that the State gives no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accepts no liability (including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws."

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.4.2.3.

Issue date: September 2013   Review due: September 2014  

Reef Habitat 

Detailed  discussion  of  Port  Curtis  reef  habitats  is  provided  in  the  QCLNG  Supplementary  EIS  (Volume  5,  Chapter 8). In summary, Port Curtis is a depositional environment and consequently intertidal rocky shores  are generally restricted to areas that experience relatively strong tidal currents and wave action (i.e. in the  lower  intertidal  zone).  Overall,  exposed  intertidal  rocky  shores  within  Port  Curtis  cover  297  ha,  which  represents ~1.4% of the total intertidal wetland area of the Port Curtis region. Unvegetated mud and sand  banks (24 per cent), mangroves (~25 per cent), saltpan (18%) and seagrass meadows (~21%) form the largest  intertidal habitat areas in the Port Curtis area.   The water quality of Port Curtis is characterised by high suspended sediment loads at most times of the year  with a noticeable gradient in water clarity that improves towards the sea (South Channel and North Entrance)  and diminishes further into the harbour towards The Narrows.   The benthic reef fauna and flora assemblages of Port Curtis exist within the constraints imposed by variable  water (and air) temperature range, large tidal range, strong tidal currents and low light levels and associated  high  suspended  solid  concentrations.  Most  light‐dependent  reef‐building  corals,  seagrass  and  seaweed  (macroalgae)  species  therefore  occur  from  the  lower  intertidal  area  to  a  depth  not  usually  exceeding  2  m  below lowest astronomical tide (Port datum).   Many of the rocky shores extend into subtidal waters to form rocky reefs/rubble banks. Baseline deepwater  benthic habitat assessments in Port Curtis recorded nine reef habitat classes on the basis of density, diversity  and types of epifauna19. The dominant habitat classes found were:   

medium‐density  benthic  community  on  rubble  substrate,  dominated  by  bryozoans,  hard  coral,  hydroids, echinoids (1984 ± 1612 ha). This habitat class was recorded south of East Banks and Facing  Island.  



high‐density  benthic  community  –  scallop/rubble  substrate  dominated  by  a  bivalves  with  a  mix  of  reef  biota  (1456  ±  832  ha).  This  habitat  class  was  recorded  in  deepwater  areas  (coincident  with  navigation channels between Fisherman's Landing and west Facing Island, as well as a patch south of  Gatcombe Head (south of Facing Island).  



high‐density  benthic  community  on  rubble  substrate  dominated by  sponges,  soft  coral,  hard  coral,  hydroids, bryozoans, gorgonians and a mix of other benthic taxa (915 ± 352 ha).  



high‐density  benthic  community  on  rubble  substrate  dominated  by  bryozoans,  sponges,  low  numbers of other taxa (944 ± 337 ha). This habitat class occurred east of Boyne Island.  

Deep‐water macroinvertebrate distributions in Port Curtis are shown in Figure 14. No such communities are  shown  in  the  immediate  vicinity  of  the  jetty  outfall  outfall,  with  the  closest  identified  region  being  characterised as “dominated by open substrate with a low density of varied benthic taxa”. 

19

Rasheed MA, Thomas R, Roelofs, AJ Neil, KM and SP Kerville (2003). Port Curtis and Rodds Bay seagrass and benthic macro-invertebrate community baseline survey, November/December 2002. DPI Information Series QI03058 (DPI, Cairns), 47 pp.

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 70 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

  Figure 14: Deep water benthic macro‐invertebrate regions in Port Curtis and Rodds Bay,  November/December 200220 

 

20

Rasheed, M.A., Thomas, R, Roelofs, A.J. Neil, K.M. and Kerville, S.P. (2003). Port Curtis and Rodds Bay seagrass and benthic macroinvertebrate community baseline survey, November/December 2002. DPI Information Series QI03058 (DPI, Cairns), 47 pp.

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 71 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

5.4.3. Potential adverse or beneficial impacts of the project activities on the identified environmental values  Impacts  on  the  marine  environment  within  Port  Curtis  arising  from  site  water  discharges  may  potentially  occur  as  a  result  habitat  degradation  primarily  resulting  from  potentially  high  sediment  loads  in  the  discharged  waters  (with  sensitive  receptors  primarily  being  mangrove  and  seagrass),  or  from  other  contaminants in discharged waters.         

5.4.4. Description of Site Water Management  For  the  purposes  of  summarising  environmental  discharges  from  the  site,  with  consideration  for  potential  impacts on environmental values, site  surface water  management consists of the following key elements /  activities:  

Stormwater management, including sediment and erosion control; 



Management of atmospheric condensate from the IAC units on the LNG Trains; 



Management of site process / oily waters; and 



Management of waters arising from the site RO and EDI.  

5.4.4.1.

Stormwater Management 

At completion of construction and upon activation of this OEMP, site civil works will be complete and the site  will  have  in  place  an  engineered  stormwater  collection  and  control  system  designed  to  manage  site  stormwater and reduce suspended sediment solids from storm run‐off prior to discharge to Port Curtis.  Key design features of the stormwater management system include the following:  

runoff  from  outside  the  LNG  Facility  is  diverted  around  the  site  to  ensure  discharge  to  Port  Curtis  without coming into contact with site runoff; 



stormwater from within the site is segregated to allow runoff from process areas to be diverted to  for treatment to reduce possible concentrations of potential contaminants prior to discharge; 



permanent stormwater drainage channels are designed and constructed to convey up to a 1 in 25  year Average Recurrence Interval (ARI), one‐hour rainfall with intensity of 80 mm per hour; 



site slopes stabilised to minimise erosion; 



intermediate and shoreline sedimentation ponds, allowing sediment to settle prior to discharge. 

Figures  showing  site  road  surfaces  and  slope  stabilisation,  as  well  as  detailed  management  measures  for  stormwater management,  sediment  and  erosion  control,  are  provided  in  the  site  Water Management  Plan  (LNGOP‐QL00‐ENV‐PLN‐000006).  The Water Management Plan includes details of:  

design of stormwater drainage channels, sedimentation ponds, and discharge points; 



locations  of  key  sumps  and  diversion  drains  to  ensure  potentially  contaminated  stormwater  from  process areas is segregated from clean stormwater runoff; 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 72 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  



specific  site  management  measures  to  address  potential  impacts  arising  from  discharge  of  site  stormwater;  



discharge criteria and monitoring requirements; and 



additional sediment and erosion control measures, including corrective action measures.  

5.4.4.2.

Inlet Air Chill Condensate 

The IAC system packages are used to maintain a constant air temperature at the inlet of the compressor gas  turbine  drivers  for  the  refrigeration  compressors  in  the  liquefaction  units  of  the  QCLNG  plant.    This  helps  maintain  a  steady  efficiency  for  the  gas  turbines  during  periods  of  high  ambient  temperature  to  maximize  LNG production by:  1. Reducing the inlet air temperature via increased air density; and,  2. Reducing the inlet air humidity.  The IAC package includes:  

a chilled water loop to cool down the air at inlet to the gas turbines; and 



a propane refrigeration cycle to remove the heat from the chilled water. 

Water  is  chilled  to  approximately  5°C  in  evaporators  in  the  lAC  package,  and  sent  to  the  propane/ethylene/methane  gas  turbine  IAC  coil  modules  to  cool  the  turbine  inlet  air.    Warm  return  water  flows from the gas turbine coils back to the lAC package for chilling.  At the IAC package, water condenses on the outside surface of the coil modules from atmospheric moisture  at turbine inlets.  This atmospheric condensation on the cold carbon steel of the coil modules is referred to as  IAC condensate.  Rate of condensate production will vary significantly with ambient temperature and humidity. As an example  of  the  volume  of  IAC  condensate  that  could  be  generated  under  different  conditions,  indicative  rates  of  production  of  IAC  condensate  at  three  different  atmospheric  temperature  /  humidity  levels  is  provided  in  Table 15.  Table 15:  Indicative IAC condensate production  Air Temperature  

Relative Humidity  

Indicative IAC Condensate  

23°C 

100% 

21.6 m3/hr/LNG train 

31°C 

57% 

12.4 m3/hr/LNG train 

13.5°C 

80% 

1.6 m3/hr/LNG train 

  As atmospheric condensate without contamination by process chemicals, IAC condensate is diverted to the  stormwater management system for discharge through Sediment Pond 4.    

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 73 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

5.4.4.3.

Issue date: September 2013   Review due: September 2014  

Process / Oily Water (Unit 29) 

Oily water streams will be treated through Unit 29 (oily water treatment system), which will reduce oil and  suspended  solids  prior  to  discharge.  The  oily  water  treatment  system  can  effectively  be  divided  into  the  following sections:  

Corrugated plate interceptor (CPI) oil/water separator (1PK‐2905) 



Dissolved air flotation (DAF) unit (1PK‐2902); and 



DAF effluent filter package (1PK‐2910). 

The site water management system is designed to capture the following streams for treatment through Unit  29:  

Runoff  from  skids  and  drains  of  the  propane,  ethylene  and  methane  compressors,  and  oily  water  from  the  water  de‐gassing  drum.  Both  these  streams  are  captured  within  the  Compressor  Area  Collection Tank (T‐2902), and pumped to the CPI; 



Runoff  from  the  power  generation  turbines  skid  area,  which  is  collected  in  the  Power  Generation  Oily Water Sump (PK‐2918) prior to being pumped to the CPI; 



Oily waters from the Equipment Washdown Pad (Q‐2909), and from the laboratory,  both of which  are captured in the Lab/Wash Down Pad Oily Water Sump (PK‐2916) prior to being pumped to the  CPI; 



Runoff from within the process area within each LNG Train.  Runoff is collected within the Process  Area  Spill  Containment  Sump  (Q‐2908),  an  inground  sump  of  365m3  capacity  designed  to  capture  16mm of rain runoff and with a 100 mm thick perlite liner to also contain a LNG spill event of up to  10 minutes.  In periods of high rainfall the sump overflows to the clean stormwater drain.    Within the process area  spill containment sump, an oil skimmer package (PK‐2909) skims off any  free  oil  carried  into  the  spill  containment  sump.    This  package  has  two  100%  capacity  air  driven  diaphragm  pumps  with  pulsation  dampers  to  skim  the  oil/water  film  from  the  sump.  This  is  pumped to PK‐2905 CPI for oil separation.  Submerged pumps at the base of the sump will pump  clean water to the seawater outfall on the LNG jetty.  In the event of an LNG spill within the process area, temperature monitoring at the entrance to the  sump pumps will isolate power to prevent pumping of LNG to the stormwater system.  

A  summary  of  treatment  within  Unit  29  is  provided  below.    A  schematic  of  the  collection  and  treatment  process is included as Figure 16.  Corrugated plate interceptor  The CPI consists of inclined corrugated plates mounted parallel to each other at a spacing of 20 mm. Water  passes  between  the  plates  from  the  top,  with  laminar  flow  conditions  induced  for  the  effective  gravity  separation of water, oil and suspended contaminants.  This is shown in Figure 15 below.  In the course of passing from inlet to outlet, oil droplets that are sufficiently large float to the upper surface  of the plates, while solid particles denser than water pass to the lower surface of the plates.  The buoyant oil 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 74 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

then  floats  and  collects  on  the  surface  of  the  CPI  where  is  it  skimmed  from  the  CPI  tank  by  a  slotted  pipe  skimmer and collected in the oil reservoir for subsequent transfer to the waste oil tank. Solids (sludge) slide  down the plate for collection in the sludge hopper.   Figure 15: CPI Schematic   

    Dissolved Air Flotation  Clarified effluent from the CPI is stored in the DAF surge tank to feed to the DAF unit.  A polymer injection  system demulsifies the water before it fed to the DAF, and then mixed for effective flocculation.   Effluent  from DAF flocculation tank is then gravity fed to the DAF unit, where the emulsified oil and waste water is  destabilized by polyelectrolyte aiding in emulsified oil conversion into free floating oil of size more than 50  microns.  Following  demulsification,  finely  dispersed  air  micro  bubbles  are  passed  through  the  water,  attaching  to  flocculated  oil  and  imparting  strong  buoyancy.      The  DAF  package  unit  has  plate  packs  (with  35  mm  plate  spaces) to improve the quality of treated effluent. The flocs that rise rapidly, accumulate in a surface layer  while the flocs that rise slower are separated for collection in a float layer.  The  float  is  skimmed  by  a  Float  skimmer  removal  mechanism  and  is  collected  in  an  oil  chamber  that  is  an  integral  part  of  the  DAF  unit.  This  is  removed  under  level  control  intermittently  by  air  driven  diaphragm  pumps to the waste oil tank.  Sludge gravitates to the bottom of the DAF and is periodically removed with the help of a screw auger at the  bottom of the hopper. The sludge collected will be disposed off‐site.   Clarified effluent is collected in DAF Effluent tank. This has a level transmitter, which is used to control the  pump flow of effluent to DAF Effluent Filters.  Part of the treated effluent is recycled back for saturation with  air. Air is injected in the saturated vessel and mixed with the water. The DAF recycle pump pressurizes the 

  

UNCONTROLLED WHEN PRINTED 

  

© QGC 2013 

Revision: 0  Page 75 of 89 

QGC Midstream Operations  Environmental Management Plan  LNGOP‐QL00‐ENV‐PLN‐000002 

Issue date: September 2013   Review due: September 2014  

air‐water mixture to 5 bar g so that the air will dissolve into the water. The air‐water mixture is discharged  through a set of distributors on the inlet to the DAF.  DAF Effluent filters  DAF  Effluent  filters  are  designed  to  remove  suspended  particles  from  DAF  effluent.  The  filters  can  be  operated either in Auto mode, Semi Auto mode or Manual mode. The filtration media consist of a layer of  anthracite on top of a layer of sand.   As  the  trapped  particles  begin  to  fill  the  pores  of  the  filter  media,  it  becomes  increasingly  difficult  to  pass  feed water through the filters, and the filters must be “backwashed” to clean the trapped particles out of the  media. Backwash is the process to reverse the flow of water through the media.   Backwash will occur when  based on pressure differential or after a fixed period of time (every 24 hours).  Once filtered, the effluent is transferred to the Treated Effluent Tank (TK‐2903), and pumped from there to  outfall on the LNG jetty. Discharge is sampled online.  Detailed  management  and  monitoring  measures  associated  with  the  oily  water  treatment  system  are  included in the Water Management Plan (LNGOP‐QL00‐ENV‐PLN‐000006).   Further detail on management of wastes associated with the oily water treatment system, including sludge,  waste oil and waste water, are addressed in the Waste Management Plan (LNGOP‐QL00‐ENV‐PLN‐000005).  The  oily  water  treatment  system  is  designed  to  treat  inflow  waters  to  achieve  discharge  concentrations  as  specified in Table 16 below.    Table 16: Oily Water Treatment ‐ Design Influent and Effluent Water Characteristics  Flow (m3/hr)  Free Oil (mg/L)  TSS (mg/L)  pH  Influent Water   85 

100 

100 

6 ‐ 8 

GH? *'&,IJKD

L7 359 MN@/GG0B@

 4P2 4T9 'K%;E=S@@

62349 ,/B;E 

 -/0