SECTION CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING

SECTION 01321 CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING PART 1 1.01 1.02 1.03 GENERAL SUMMARY A. Employ competent photographer to take constru...
1 downloads 1 Views 68KB Size
SECTION 01321 CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING PART 1 1.01

1.02

1.03

GENERAL

SUMMARY A.

Employ competent photographer to take construction record photographs for preconstruction conditions, periodically during course of Work, and post-construction.

B.

Employ competent video recording professional to take pre-construction, existing conditions video record.

C.

Employ competent video recording professional to perform gravity sanitary pipe inspection video recording.

RELATED SECTIONS A.

Application for Payment - Division 1.

B.

Project Record Documents - Division 1.

PHOTOGRAPHY REQUIRED A.

Provide photographs taken on cutoff date for each scheduled Application for Payment.

B.

View and Quantities Required:

C.

1.

Take a minimum of twelve (12) Site Level exposures of the site and adjacent property at pre-construction, monthly, and post-construction. Two (2) complete sets of prints must accompany the Contractor’s Monthly Payment Request. Failure to provide Site Level photos shall be grounds for withholding progress payments.

2.

(NOT APPLICABLE) Aerial photography shall be required. A minimum of six (6) views taken from an altitude of