MAJOR PROJECTS AND NEWS ITEMS

P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 2714 Cypress Point, Suite K, Missouri City, Texas 77459 E-mail: pipelinei...
Author: Amos Houston
4 downloads 2 Views 7MB Size
P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 2714 Cypress Point, Suite K, Missouri City, Texas 77459 E-mail: [email protected] www.pipelineintelligence.com

Volume XXIV, Number 5 November 1, 2012

MAJOR PROJECTS AND NEWS ITEMS INDUSTRY NEWS (Santa Fe, NM) – Officials with the Bureau of Land Management are seeking public input for an environmental assessment on a natural gas pipeline that would cross 12 New Mexico counties, including Lincoln.

Some Southern California refiners have said they are looking into transporting light-sweet crude by rail or pipeline to their plants to capitalize on cheap inland U.S. crude already processed by refiners in other regions to varying degrees.

They initiated a public scoping process to solicit public comments and identify issues for the EA being prepared for the Western Expansion Pipeline III Project proposal. The proposed project would consist of about 246 miles of 16-inch diameter pipeline with seven loop pipeline segments of 20-inch diameter. The line would cross land in the counties of San Juan, Rio Arriba, Sandoval, McKinley, Bernalillo, Santa Fe, Torrance, Guadalupe, Lincoln, De Baca, Chaves, and Lea. The proposed pipeline loop segments would transport increased natural gas liquids production to Hobbs and ultimately to markets in Mont Belvieu, Texas.

Tesoro Corp last month began receiving North Dakota Bakken crude oil via rail at its 120,000 bpd refinery in Anacortes, Washington.

This proposed plan of development, prepared by Enterprise MidAmerica Pipeline, and submitted to the BLM, proposes to construct, operate, and maintain about 246 miles of natural gas liquids pipeline, which would tie into and be installed adjacent to its existing system that runs through New Mexico. Construction is proposed to start April 2013. INDUSTRY NEWS (Houston, TX) – Kinder Morgan Chief Executive Richard Kinder told analysts that the company is considering a possible $2 billion project to convert part of its underused El Paso Natural Gas (EPNG) pipeline system to possibly transport up to 400,000 barrels per day of light Permian crude to Southern California. "That is very speculative at this point, but there are a lot of opportunities that could be very exciting there," Kinder said. "We have had some interesting conversations with potential shippers on that line who are very enthusiastic."

In August when the company announced its $2.5 billion purchase of BP Plc's 240,000 bpd Los Angeles-area refinery next to Tesoro's 103,800 bpd plant, Tesoro CEO Greg Goff told analysts that he expected to see more U.S. crude move west, "whether from North Dakota or West Texas." Also, Alon Energy USA Inc President Paul Eisman in August told analysts that the company was in advanced talks to move cheaper inland U.S. crude to its 84,500 bpd Southern California refining system via new rail facilities or existing pipelines. He declined to provide details, but said Alon would "more likely than not" start with Bakken crude as well. Credit Suisse analyst Ed Westlake said in a note to investors that key drivers of oversupply of crude in the Gulf Coast region -home to 44 percent of the nation's refining capacity -- is supply coming from the Permian as well as the Eagle Ford shale play in South Texas. Much of the Gulf Coast's refining capacity is designed to process heavy-sour crudes like that from Venezuela or Canada rather than the light-sweet variety that comes from the Permian and Eagle Ford. Such refineries can still process that light crude, but it makes less efficient use of heavy-oriented refineries because some units not needed to process light crude, like cokers, would not be needed.

Pipeline Intelligence Report, Novemberon 1, 2012 Continued page– 51

New Listings Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Antero Resources Denver, CO

70 mi.

20”

Project located near Pennsboro, WV.

Michels Pipeline Brownsville, WI

Mark West Energy Denver, CO

9.1 mi.

30”

Project located near Glen Dale, WV

Sheehan Pipeline Tulsa, OK

Mark West Energy Denver, CO

22.5 mi.

16” & 20”

Project located near Claysville, PA. This is a dual lay. 11.2 miles of ditch.

Price-Gregory Houston, TX

Nustar Energy San Antonio, TX

41 mi. 5 mi.

8” or 10” 8” or 10”

“Niobrara Falls Project” new lay portion of a line change and reversal that would originate near Platteville, CO. The second line would originate near Watkins, CO and both lines would end at the Niobrara oil operations near Denver, CO.

Construction to begin mid to late 2013

Xcel Energy Denver, CO

77 mi.

16”

“West Main Natural Gas Pipeline Replacement Project”. Take up and relay an existing 8” line. Will run from WY to near Westminster, CO.

Construction to begin Spring 2013

Pipeline Intelligence Report, November 1, 2012 – 3

Updated Listings (A bold listing indicates a change) Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Atlas Pipeline Eden Prairie, MN Pioneer Natural Resources Irving, TX

10.2 mi.

16”

“The Driver Residue Pipeline Project” will be located in Midland Co., TX.

Construction early 2013

Alliance Pipeline LP Valley City, ND (Enbridge/Veresen)

80 mi.

12”

“Tioga Lateral Project” would run from the Williston Basin, near Tioga , ND, to the Alliance mainline near Sherwood, ND.

Minnesota Limited Big Lake, MN

BakkenLink Pipeline LLC Houston, TX

128.1 mi. 4 mi.

12” 8”

Project located near Fryburg, ND. Delayed because of Keystone.

On Hold

Bargath, LLC (Williams Midstream) Tulsa, OK

22 mi.

16”

Project located near Parachute, CO.

Delayed until at least 2013

Blueknight Energy Partners Oklahoma City, OK

65 mi.

Undet.

Project will begin in Southern OK and end near Wynnewood, OK.

Construction early 2013

Pipeline Intelligence Report, November 1, 2012 – 4

"If there is no available light processing capacity in the Gulf, we believe it would make sense to push crude to the California market," Westlake said. VERY EARLY STAGES – Kinder stressed that Kinder Morgan's consideration of converting part of the EPNG system to transport crude is in "very early stages of our thoughts." He said Kinder Morgan would not convert the entire system and would still deliver gas to customers at whatever throughput levels they want. "We have multiple lines across there, and still could convert a line all the way from the Permian into Southern California," Kinder said. The 10,200-mile EPNG system now transports natural gas from the San Juan, Permian and Anadarko basins to California, Arizona, Nevada, New Mexico, Oklahoma, Texas and northern Mexico. The EPNG system connects with the company's 500-mile Mojave Pipeline near Cadiz, California, about 215 miles west of Los Angeles. Kinder Morgan spokesman Larry Pierce said that it was too premature to specify which lines would be involved in a crude conversion because it was "extremely early in the process." INDUSTRY NEWS (San Antonio, TX) – NuStar Energy LP is proposing to create a system of pipelines to carry crude oil from Colorado's Niobrara shale formation to refineries in Texas and elsewhere. The system seeks to address a shortage of ways to get oil from Colorado's promising Niobrara play to refineries with the capacity to handle it. The system proposed by San Antonio-based NuStar dubbed the Niobrara Falls Project would use an existing petroleum-products pipeline from Denver to McKee, Texas, that would be reversed and converted to crude oil. That line which has a capacity of 70,000 to 75,000 barrels a day would be connected to another existing pipeline between McKee and refineries in Wichita Falls, Texas. The system would include new pipelines running from Niobrara oil operations near Platteville and Watkins to the existing line in Denver. Niobrara Falls would be able to carry crude to other refineries as well, including Suncor Energy’s Denver facility as well as Valero Energy refineries in McKee, Texas and Ardmore, Okla., and a WRB refinery in Borger, Texas, NuStar said. In order to gauge support for the project, an affiliate of NuStar has launched what’s called a “binding open season” to find out which companies are willing to make long-term commitments to use the pipeline system. The open season will close at noon on Nov. 15. NuStar hopes to have Niobrara Falls running by the first quarter of 2014. Pipeline Intelligence Report, November 1, 2012 – 5

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Boardwalk Field Services Houston, TX

55 mi.

20” & 24”

Gathering Expansion located near Edna, TX.

Strike Construction The Woodlands, TX

Boardwalk Field Services, LLC Houston, TX

26 mi.

12”

Gathering system located in Susquehanna & Lackawanna counties, PA. Will be built out over several years.

Construction could be 2012 or 2013

Bridger Logistics LLC Dallas, TX Advantage Pipeline, LLC Midland, TX

75 miles

Undet.

The Pecos River Pipeline Project will run from Pecos, TX to Crane, TX. It will tie into the Longhorn pipeline in Crane.

Two Rivers Pipeline Odessa, TX

Buckeye Partners Breinigsville, PA

225 mi. or 275 mi.

12” & 16”

“The Marcellus Union Pipeline” will run from near Detroit, MI to near the West Virginia & PA border.

Still in planning stages Could be 2013 or 2014

Cabot Oil & Gas Houston, TX Williams-Transco Houston, TX

120 mi.

Undet.

“Constitution Pipeline”, Susquehanna county, PA to Schoharie county, NY.

Construction 2014 or 2015

Columbia Gas Transmission Houston, TX

21.3 mi.

26”

“Line MB Extension” project to be located in Baltimore and Harford counties, MD.

Will file w/FERC August 2012 Construction summer 2013

Pipeline Intelligence Report, November 1, 2012 – 6

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Columbia Gas Transmission Houston, TX

2.5 mi.

24”

“Warren County Expansion Project”. Project located in Warren county, VA.

Construction spring 2013

Copano Energy Houston, TX

5 mi.

16”

Project located in Nueces Bay near Corpus Christi, TX.

Sunland Construction Eunice, LA

Copano Energy Houston, TX

72 mi.

12”

“Double Eagle Project” located in Nueces Bay near Corpus Christi, TX.

Out for bids late October or early November 2012

Copano Energy Houston, TX Magellan Midstream Partners Tulsa, OK

50 mi. 50 mi.

12” 24”

“Double Eagle” project located in the Eagle Ford Shale and will run to near Corpus Christi, TX.

Sprint Pipeline Rosharon, TX

Crestwood Midstream Partners Houston, TX Mountaineer Keystone Pittsburg, PA

42 mi.

16”or 20”

“The Tygart Valley Pipeline” project to run through Barbour, Preston, and Taylor counties, WV.

Construction 2013

Crosstex Energy Dallas, TX

130 mi.

12”

“The Cajun Sibon Extension” will run from Louisiana to near Mont Belvieu, TX.

WHC, Inc. Broussard, LA

Pipeline Intelligence Report, November 1, 2012 – 7

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Denbury Resources Plano, TX

84 mi.

20”

Project located near Conroe, TX.

Construction 2014

Department of Energy Washington, DC

28.5 mi.

6”

Project located near Kennewich, WA. Line would tie into Hanford nuclear plant.

Construction could be 2013 or 2014

Downeast Pipeline, LLC Robbinston, ME

30 mi.

30”

Project located near Baileyville, ME.

Could be late 2013

DTE Energy Ann Arbor, MI Enbridge Energy Houston, TX Spectra Energy Houston, TX

250 mi.

Undet.

The Nexus Gas Transmission system would run from the Utica Shale to markets in the Midwest & eastern Canada. They will have an open season in the 4th Quarter 2012

Construction could be 2014 or 2015

Eagle Ford Midstream, LLP Houston, TX

105 mi.

30”

Project will run from Brasada natural gas processing plant in LaSalle county, TX to pipelines at the Agua Dulce Hub in Nueces county, TX.

Strike Construction The Woodlands, TX

El Paso Corp. Houston, TX

114 mi.

36”

Project located in Susquehanna county, PA and Broone, Delaware & Schoharie county, NY.

Construction late 2013 or early 2014

Pipeline Intelligence Report, November 1, 2012 – 8

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Empire Pipeline (A National Fuel Gas Co.) Williamsville, NY

25 mi.

24” or 30”

“The Tioga County Expansion Phase II”. Project will be located in Bradford, Lycoming & Tioga counties PA.

Out for bids Summer 2013 Construction Fall 2013

Enbridge Energy Houston, TX

75 mi.

36”

“The Eastern Access Projects” take up and relay old 30”. Line located in Indiana & Michigan.

Construction 2014

Enbridge Energy Houston, TX

35 mi.

36”

Will run adjacent to the Toledo Pipeline in Michigan.

Construction 2014

Enbridge Energy Houston, TX

36 mi.

12”

The Sanish Pipeline will run from Johnson’s corner to Beaver Lodge and Berthold Stations and into Cromer, ND.

Construction late 2012 or early 2013

Enbridge Energy Houston, TX

600 mi.

36”

“The Flanagan South Pipeline Project” will start near Flanagan, IL and end near Cushing, OK.

Construction to begin Spring/ Summer 2013

Enbridge Energy - Houston, TX Enterprise - Houston, TX Anadarko - Woodlands, TX

580 mi.

20”

“Texas Express Pipeline will begin near Skellytown, TX and end near Mont Belvieu, TX..

Construction could be early 2013

Pipeline Intelligence Report, November 1, 2012 – 9

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

EnCana Oil & Gas Denver, CO

11.2 mi.

24”

Project located near Rifle, CO. Also includes steel pipe water line. 6.7 mi. of 16”

In planning stages

Energy Transfer Dallas, TX

37 mi.

30”

Rich Eagle Ford Mainline located in South Texas.

Construction Summer 2013

Energy Transfer Dallas, TX Regency Energy Dallas, TX

472 mi.

16”

“Lone Star NGL” Project begins in Winkler county, TX & runs to Jackson county, near Victoria, TX.

Troy Construction Houston, TX Precision Pipeline, LLC Eau Claire, WI Pumpco Giddings, TX

Enterprise Mid-America Pipeline Houston, TX

246 mi.

16” & 20”

“Western Expansion Pipeline III” will consist of 7 loops starting near Farmington, NM & end near Hobbs, MN.

BLM approved Construction to begin April 2013

Enterprise Products Houston, TX Anadarko Petroleum The Woodlands, TX DCP Midstream Denver, CO

420 mi.

12” & 16”

“Front Range Pipeline” will run from near Denver, CO to near Skellytown, TX.

Construction 1st Quarter 2013

Pipeline Intelligence Report, November 1, 2012 – 10

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Enterprise Products Houston, TX

80 mi.

20”

Eagle Ford Shale pipeline Phase II Extension begins in Wilson County, TX and ends in LaSalle county, TX.

Construction early 2013

Enterprise Products Houston, TX

369 mi. 55 mi.

20” 20”

“ATEX Express” to run from Washington county, PA to Seymour, IN. It will tie into an existing line that will be reversed. 55 mi. of new lay will take place near Mont Belvieu, TX.

Construction 2013

Enterprise Products Houston, TX

173 mi.

16”

Commonwealth project will run from Yoakum, TX to LaSalle, TX.

Out for bids 4th quarter 2012

Explorer Pipeline Tulsa, OK

18 mi.

24”

The Diluent Pipeline Extension Project. Located near Wood River, IL.

Construction 2014

Genesis Energy Houston, TX

17.5 mi.

18”

Project will run from Webster, TX to near Texas City, TX.

Fall 2012 Construction

Inergy Midstream, LP Kansas City, MO

230 mi.

30”, 36”

Project will run from Centra, PA to Charles county, MD.

Construction could be 2015 or 2016

SPECIALTY POLYMER COATINGS, INC. INNOVATION IS OUR SPECIALTY On site and mill applied epoxy and urethane coatings for: Girthwelds Horizontal Directional Drills Rehabilitation of existing pipelines High Temperature Pipelines Specialty Coatings Available For: High Temperature Applications For Inservice Applications up to 150°C (302°F) Damp Substrate Applications Cold Weather Cure Applications General Purpose Epoxies (No Abrasive Blast Requirement)

CHECK OUT OUR WEB PAGE AT: WWW.SPC-NET.COM CANADA: (604) 514-9711 USA: (281) 332-6948 UK: (44) 208-337-4953 Pipeline Intelligence Report, November 1, 2012 – 11

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Iriquois Gas Transmission Shelton, CT

66 mi.

36”

NYMARC Pipeline to be located in the New York and New England areas.

Construction could be 2014

Iroquois Gas Transmission Shelton, CT

135 mi.

36”

“NYMarc Penn Option” to be located in PA and NY. Includes one compressor station east of the Millennium Pipeline.

Construction could be 2014

Kennesaw Pipeline (A Nisource Company) Houston, TX

269 mi.

36” & 42”

Project will run from Banner, MS to Rome, GA.

In planning stages Construction could be late 2013 or early 2014

Kinder Morgan Houston, TX

210 mi.

Undet.

“Pony Express Crude Oil Pipeline Project”. The new lay will run from central Kansas to near Cushing, OK. Also included is 500 mi. of existing pipeline to be converted from natural gas to oil. Existing line runs from near Guernsey, WY to Central KS.

Construction 2013 or 2014

Kinder Morgan Houston, TX

233 mi.

16”

Project would start at the terminal in Colton, NV and run parallel to two existing lines and end at a facility in Las Vegas, NV.

In planning stages

Pipeline Intelligence Report, November 1, 2012 – 12

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Kinder Morgan Houston, TX

240 mi.

16”

Project to begin near Moundsville, WV and end near Wauseon, OH.

Still in planning stages

Kinder Morgan Houston, TX

27 mi.

12”

Lateral pipeline extension to be built and will connect at Phillips 66 Texas refinery. Project located in the Eagle Ford region.

Awaiting environmental approval

Kinder Morgan Houston, TX

60 mi.

36”

“Sasabe Lateral” will run from Tucson, AZ to Sasabe, AZ.

Construction late 2014 or early 2015

Magellan Midstream & Occidental Petroleum Corp. Houston, TX

400 mi.

20”

“BridgeTex Pipeline” would run from near Colorado City, TX to Texas City, TX.

Construction could be mid to late 2013

Magellan Midstream Houston, TX

480 mi.

18”

Longhorn Pipeline line reversal to crude oil service. Located between Crane, TX and Houston, TX.

Awaiting Approval Construction could be 2013

Marathon Pipe Line Co., LLC Findlay, OH

29 mi.

24”

"The Detroit Heavy Oil Upgrade Project" will be located in Monroe and Wayne counties, MI.

Delayed - could be 2013

Pipeline Intelligence Report, November 1, 2012 – 13

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

MDU Resource Group Bismark, ND

24 mi.

10”

Project to be located near Mandan, ND.

Construction early to mid 2013

National Fuel Gas Supply Williamsville, NY

32 mi.

30”

Phase I. Project to run through Elk, Cameron, & Clinton counties, PA.

Filed w/FERC August 2011 Construction 2013

National Fuel Gas Company Williamsville, NY

50 mi

30”

Phase II. Project will run through Clearfield, Jefferson, & Elk counties PA.

Filed w/FERC August 2011 Construction 2013

Northwest Natural Portland, OR

16 mi.

4”

Project would run from Roseburg, OR to Coos county, OR.

Construction 2014

Oneok Partners, L.P. Tulsa, OK

1,300 mi.

Undet.

“Bakken Crude Express Pipeline” would run from ND to Cushing, OK.

Open season to close Nov. 2012 Construction 2014 or 2015

Oneok Partners Tulsa, OK

230 mi.

12” or 16”

NGL Pipeline to be built in CanaWoodward and Granite Wash areas. It will connect to three new third party natural gas gathering processing facilities being constructed and three existing third party natural gas processing facilities that are being expanded.

Construction late 2012 or early 2013

Pipeline Intelligence Report, November 1, 2012 – 14

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Oneok Rockies Midstream Tulsa, OK

37 mi. 27 mi.

16” 12”

Project would start at a gas processing plant in Williams county, ND.

Planning stages

Oneok Partners Tulsa, OK

570 mi.

Undet.

“Sterling III” pipeline will run from Medford, OK to Mont Belvieu, TX.

Construction 2013

Oregon Pipeline, LLC Warrenton, OR

85 mi.

36”

Would begin near Warrenton, OR and end near Woodland, WA and tie into an existing Williams line.

Awaiting FERC approval Construction could be 2014

Pacific Gas & Electric Portland, OR Northwest Pipeline Salt Lake City, UT

231 mi.

36”

“The Pacific Connector” project starts near Jordan Cove, OR and runs to Malin, OR, southeast of Klamath Falls, OR.

Delayed Construction early 2015

Palomar Gas Transmission, LLC Portland, OR

110 mi.

36”

Phase I will start at the existing GTN line in north-central OR near Molallu, OR. Phase II was cancelled.

Delayed - Could be 2013

Pennant Midstream LLC Houston, TX Canisource & Hillcorp (Joint Venture)

50 mi.

20”

Wet Gas Gathering pipeline to be located in Northeast OH and Western PA.

Construction Summer 2013

Pipeline Intelligence Report, November 1, 2012 – 15

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Penn Virginia Resources Partners Radnor, PA

10 mi.

16”

Project located in Tioga, county, PA..

Construction Summer or Fall 2013

Piedmont Natural Gas Charlotte, NC

12 mi. 1.5 mi.

20” 12”

South Nashville Pipeline Project. Project located in Davidson county, TN.

Construction early 2013

Piedmont Natural Gas Charlotte NC

120 mi. 8 mi.

20” 30”

Project located in Iredell, Mecklenburg, Cabarros, Anson, Richmond, Scotland and Bladen counties, NC.

Construction late Fall 2012

Plains All American Pipeline L.P. Houston, TX

220 mi.

Undet.

Project begins at Plains Baker Montana Station and ends near Billings, MT.

Open Season ran thru May 2012

Plains All American Pipeline, LP Houston, TX

170 mi.

Undet.

“Mississipian Line” pipeline project would run from Alva, OK to Cushing, OK.

Construction late 2012 or early 2013

Prospector Pipeline Company Carson City, NV

24 mi.

8” & 12”

Project to start at the Ruby Valley pipeline near Willow Creek Reservoir to the mill at Barrick Goldstrike, NV.

Awaiting BLM approval in September 2012. Construction could be late 2012

Pipeline Intelligence Report, November 1, 2012 – 16

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Rose Rock Midstream Tulsa, OK

210 mi.

Undet.

“Glass Mountain Pipeline” includes two laterals. One will begin near Alva, OK, the other near Arnett, OK. They will connect near Cleo Springs and then finish up at Cushing, OK.

Construction Summer 2013

Saddle Butte Pipeline, LLC Durango, CO

450 mi. 17 mi. 8 mi.

16” 16” 16”

“High Prairie Pipeline” project will begin in the Williston Basin of ND and end near Clearbrook, MN. It also includes two laterals. The 17 mi. lateral will be in McKenzie cnty, ND and the 8 mi. lateral in Montrail county, ND.

Construction Summer 2013

Shell Pipeline Houston, TX

220 mi.

Undet.

“Westward HO” project would run from St. James, LA to near Port Arthur, TX.

Construction could be early 2015

Spectra Energy Houston, TX

230 mi.

24”, 30”, 36”

“Renaissance Gas Transmission” project would begin in Tennessee and would end near Atlanta, GA.

Construction 2015

Spectra Energy Houston, TX Chesapeake Energy Oklahoma City, OK

70 mi.

Undet.

“The Ohio Pipeline Energy Network” project will connect Ohio’s Utica & Marcellus Shale gas supplies.

Construction 2014

Pipeline Intelligence Report, November 1, 2012 – 17

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Spectra Energy Houston, TX

15.5 mi. 5 mi.

36”, 42”

“New Jersey-New York Expansion” Project will begin near Linden, NJ and will run into Manhattan, NY.

FERC Approved Construction late 2013

St. Lawrence Gas Massena, NY

35 mi.

8”

Project will be located near North Lawrence, NY.

Over & Under Piping Contractors Auburn, NY

Summit Natural Gas of Maine, Inc. Littleton, CO

56 mi.

8”

Pipeline will run from Richmond to near Madison, ME. This line will tie into an existing Maritimes line.

Construction Spring 2013

Sunoco Logistics Philadelphia, PA

45 mi.

12”

“Mariner East” will begin in Washington Co., PA and end near Marcus Hook, PA. Propane & Ethane line.

Construction could be late 2013

Sunoco Logistics Philadelphia, PA

300 mi.

12”

“Permian Express Phase II” would run parallel to the existing West Texas Gulf pipeline, from Colorado City, TX to Wortham.

Construction could be Summer or Fall 2013

Sunoco Logistics Philadelphia, PA

159 mi.

12”

The Allagheny Access” pipeline will run from near Pittsburg, PA to eastern Ohio. It will tie into other existing lines.

Construction will be late 2013 or early 2014

Pipeline Intelligence Report, November 1, 2012 – 18

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Tennessee Gas Pipeline Company Houston, TX

5.41 mi. 1.99 mi. 8.14 mi. 16.34 mi. 7.6 mi.

30” 30” 30” 30” 30”

“Northeast Upgrade Project” located in PA and NJ. 5 loops to start near TGP Station 319 and ends at the Mawah Station.

FERC approved Construction could be Fall 2012

Tennessee Gas Pipeline Company Houston, TX

7.9 mi.

30”

The MPP Project will be located in Potter county, PA. Looping project will run near their existing 300 line project.

Filed w/FERC Fall 2011 Construction Summer 2013

TexStar Midstream Services LP San Antonio, TX

70 mi.

12”

Project will run from Gardendale, TX to near Cotulla, TX.

Construction 2012

UGI Energy Services Wyomissing, PA Inergy Midstream Kansas City, MO

200 mi.

Undet.

The “Commonwealth Pipeline” would begin in Lycomming county, PA and end near Baltimore, MD.

Construction late 2014

UGI Energy Services Wyomissing, PA

30 mi.

Undet.

“Auborn Gathering Expansion” project will run from Wyomissing county, PA to a Transco line in the Marcellus Shale Area.

Could be 2013

Pipeline Intelligence Report, November 1, 2012 – 19

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Velocity Midstream Tulsa, OK

100 mi.

8” & 10”

“Phase II Eagle Eye” project located near Gardendale, TX.

Construction 2012

Vermont Gas Systems Middlebury, UT

50 mi. 10.5 mi.

10” 10”

“Addison Natural Gas Project”. Project would run from Colchester to New Haven, VT and then branch off to Middlebury and Vergennes, VT. Will also include 10.5 mi. lateral to Papermill.

Clough, Harbour & Assoc. (Engr) Albany, NY Will file permits late 2012

Williams-Northwest Pipeline Salt Lake City, UT

35 mi.

36”

“The Cowlitz County Expansion” would run from near Sumas, WA to near Woodland, WA”.

Will file w/FERC 1st Quarter 2013 Construction 2016

Williams-Northwest Pipeline Salt Lake City, UT Puget Sound Bellevue, WA

4 mi.

16”

“The South Seattle Delivery Lateral Expansion” Take up and relay located near Seattle, WA.

Filed w/FERC Spring 2012 Construction Summer 2013

Williams-Northwest Pipeline Salt Lake City, UT

2.4 mi.

16”

“Kalama Lateral Pipeline Project” project located at Port of Kalama in WA.

Filed w/FERC Spring 2012 Construction Summer 2014

Pipeline Intelligence Report, November 1, 2012 – 20

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Williams Northwest Pipeline Salt Lake City, UT

136 mi.

36”

“The Washington Expansion Project” will begin at he Sumas Comp Station in Whatcom county, WA and end at the Oregon LNG Interconnect near Woodland, WA. Includes 10 loops and compressor station upgrades.

Will file w/FERC in 2013 Construction could be 2015 or 2016

Williams-Transco Houston, TX

100 mi.

24”

“Virginia Southside Expansion” would run from Pittsylvania county, VA to Brunswich county, VA.

Construction could be Summer 2014

Williams-Transco Houston, TX

2.6 mi.

42”

“Northeast Supply Link Expansion.” Muncy Loop located in Lycoming county, PA.

Filed w/FERC December 2011 Construction Spring 2013

Williams-Transco Houston, TX

258 mi.

36”

“The Atlantic Access Project” will run from West Virginia across much of Southern Pennsylvania.

Construction 2015

Williams-Transco Houston, TX

3.23 mi.

26”

“The Rockaway Delivery Lateral Project will be .35 mi. onshore with 2.88 being offshore. Located near New York City, NY.

Construction could be mid to late 2013

Pipeline Intelligence Report, November 1, 2012 – 21

Approx. Bid Date/ Awarded Contractor

Company

Length

Diameter

Location/Description

Williams-Transco Houston, TX

3.7 mi.

42”

“Northeast Supply Link Expansion.” Palmerton Loop located in Monroe county, PA.

Filed w/FERC December 2011 Construction Spring 2013

Williams-Transco Houston, TX

6.8 mi.

42”

“Northeast Supply Link Expansion.” Stanton Loop located in Hunterdon county, NJ.

Filed w/FERC December 2011 Construction Spring 2013

Williams-Transco Houston, TX

1.4 mi.

42”

“Northeast Supply Link Expansion.” Take up & relay located in Richmond/ Kings, NY.

Filed w/FERC December 2011 Construction Spring 2013

Williston Basin Interstate P/L Co. Bismark, ND

100 mi.

16”

“The Bakken Pipeline Project starts at existing system near Tioga, ND & ends near Antler, ND.

Delayed Could be Spring 2013

X-Cel Energy Denver, CO

34 mi.

24”

Project located near Denver, CO.

Filed permits in early 2012 Construction 2013

Pipeline Intelligence Report, November 1, 2012 – 22

FIRST CLASS

First Class Mail U.S. Postage PAID Sugarland, TX Permit No. 345

Order Form

Pipeline Intelligence Report – Master subscription $300 per year for 24 issues. Additional subscriptions for same Company available to any address $150 per year for 24 issues. 2011 Pipeline Intelligence Directory $75 plus S & H $60 for each additional copy. 2011 Pipeline Intelligence Directory CD in Excel format: Pipeline Company, Contractor or Supplier Section – $150 per section or $400 for all three. ** Tax: All orders in Texas are subject to 8.25 % state sales tax. Method of payment:  A check for the total amount is enclosed. Charge to my:  MasterCard  Visa Exp. Date: Mo.

Card Number

Yr.

Signature Bill me. Purchase Order No:

(if required) Title

Name Company Address City

State

Zip

Phone number (

)

----------------------------------------------------------------------------------------------------------------------------------------------------------------Pipeline Intelligence Report (PIR) is published 24 times per year by Pipeline Intelligence Company, PO Box 1099, Missouri City, TX 77459-1099, phone (281) 499-3131. Copyright 1990 by Pipeline Intelligence Co. All rights reserved. Subscription rate is $300 per year; mailed in U.S. Texas residents please add 8.25% sales tax. PIR reports on construction projects contemplated by hydrocarbon transporters. Since this information is received from others, PIR cannot guarantee the accuracy of any information. Postmaster: Please send address changes to Pipeline Intelligence Report, PO Box 1099, Missouri City, TX 77459-1099.

Pipeline Intelligence Report, November 1, 2012 – 24