NOVEMBER/DECEMBER 2015

scaffold & access magazine

Solution to Access a National Treasure

ON THE COVER

SOLUTION TO ACCESS A NATIONAL TREASURE

By Joe Riccio

RARELY ARE WE PRESENTED WITH A PROJECT SO STEEPED IN HISTORY THAT WE NEED TO LOOK TO THE PAST TO PUT INTO PERSPECTIVE OUR CURRENT APPROACH TO A SOLUTION. THAT IS WHAT ZAMPELL DID TO PROVIDE SCAFFOLD ACCESS FOR A $12 MILLION TO $15 MILLION RESTORATION OF THE USS CONSTITUTION AT THE CHARLESTOWN NAVY YARD.

30

NOVEMBER/DECEMBER 2015

USS Constitution, “Old Ironsides,” was first launched on October 21, 1797. It was first restored at its current location in Charlestown Navy Yard 100 years later in 1897. In March of 2014, a team from Zampell met with the Naval History and Heritage Command Detachment Boston (NHHC), the caretakers of the iconic frigate. The discussion centered on the previous dry dock experience from 1992-1995. Construction practices, including engineered scaffold systems have become safer and more efficient over the past 20 years, and a solution to the difficult task developed. Working with engineers at Universal Manufacturing, a leading U.S. scaffold manufacturer based outside Pittsburg Pennsylvania, Zampell designed and proposed a complete scaffold system to ensure access to every inch of the aged warship’s hull.

SCAFFOLD & ACCESS MAGAZINE

31

Dry dock and ship challenges The challenge of designing a scaffold solution while Constitution was still afloat in Boston Harbor was overcome by utilizing ships drawings, dry dock sketches, and photographs past and present. Dry Dock 1, originally named Adams Dry Dock after President John Quincy Adams, opened in 1833 to host the Navy’s oldest warship for the first of several restorations throughout Constitution’s storied history. Without the ability to take hard measurements of the dry dock, hull and ship supports, the Zampell design team had to anticipate how the ship would be positioned once water was drained from the dry dock. The final positioning of strong backs and keel supports were critical to the scaffolds foundation design. Once the vessel was in position and water drained, our engineers and senior scaffold builders spent two days measuring the final positioning of the strong backs and keel supports. This enabled a final base layout to be designed. We used plumb bobs to determine locations of scaffold posts to

32

NOVEMBER/DECEMBER 2015

bow of the ship. We were able to give NHHC access to the bow within the first two weeks of the project. All remaining equipment was stored in the dry dock at the rear of the ship. This posed a serious concern as 75 percent of the ship still needing scaffold was stored over 150’ away from the work areas. Zampell utilized, a 150’ long adjustable conveyor from one of our other business units. The material handling unit was then able to transport 80 percent of the scaffold used for the ship to the areas needed.

ensure they missed critical parts of the ship. Spending a few days on site prior to the final design and bill of material being finalized proved critical to the success of the project. Logistics and material handling More than 250,000 lbs. of system scaffold components and several bundles of wood planking were used to complete the work platforms built to access the entire hull of Constitution. At 180’ L x 50’ W x 45’ H with work platforms every 6’6” in height we created a safe work environment for the Navy craftsmen to perform their work. Through partnering with the NHHC, scaffold materials were expedited to the work site. No tractor trailers were utilized for the delivery of scaffold, opting instead for carefully planned smaller loads. All deliveries happened by 6 a.m. as the area around the dry dock and the adjacent National Park were still open to the public. Two cranes and Navy riggers were utilized in moving scaffold materials into the more than 30’ deep dry dock.

Adding to the difficulty, was storing the large amount of scaffold equipment necessary to complete the work. Due to the limited space on site, the NHHC wanted all the scaffold in the dry dock. Additionally they requested access to the bow of the ship as soon as possible. Our engineers worked on final designs of the bow and bill of material that could be stored in the dry dock near the

Anticipating obstacles Attention to detail and a thorough understanding of the overall project was important in designing a scaffold system to be effective throughout the 30-month project. The difficult shape/contour of hull, existing rigging, positioning of strong backs and other obstacles protruding from the historic vessel created unique situations for the scaffold crew. The NHHC also did not allow any bracing of the scaffold off the ship and preferred to have any vertical posts two feet off the ship’s hull. Experienced

scaffold builders familiar with cone shaped vessels, large boilers, and submarine building proved to be crucial in developing a consistent approach to dealing with these challenges. Access? No problem. Stairways

designed into the system at four locations around the ship allowed workers access to the ship, dry dock, and ground level wood shop. The potential need to adjust the scaffold over time was not overlooked. The inherent nature of a long term project with varying scopes of work could present conditions impeding work to be performed. Throughout the scaffold installation, our design team was on hand to make adjustments in the design and to anticipate future changes. Constant communication with the NHHC staff made it possible to anticipate changes and make modifications to the design prior to final completion. The intent was to give the wood working crew easy access to the areas in need of repair and to minimize future modifications. The successful completion of scaffold installation took

approximately five weeks with work starting before the 2015 July 4th Holiday and completed at the beginning of August 2015. • About the Author Joe Riccio is the Senior Operations Manager at Zampell, a family owned business established in 1966. Zampell is an organization that is chiefly involved with the engineering and construction of refractories, insulation, and scaffolding within the industrial sector and facilities maintenance and management within the commercial sector. Zampell has branch offices in Massachusetts (headquarters), Maine, New Hampshire, Connecticut, Pennsylvania, Florida, Texas, and Oregon. Zampell also has a subsidiary, Zampell A/S, with locations in Jutland and Sjælland in Denmark.

IF THIS IS YOUR VIEW... Don’t take a risk, go for the best!

At great heights you only want to rely on the safest platform. Altrex has been guaranteeing safety, quality and innovation in access equipment for 65 years. From our head office and production facility based in the Netherlands. Using our own engineering department, state of the art welding robots and test lab. We only go for the best. Like our worldwide customers expect.

Choose wise and enjoy the view. Relax, it’s an Altrex!

www.altrex.com

www.beeaccess.com USA Distributor

SCAFFOLD & ACCESS MAGAZINE

33