CTRT Business Case. PURPOSE: Full Business Case for approval for chemotherapy clinical Trials Unit at Mount Vernon Hospital

Agenda Item No: 9  CTRT Business Case  PURPOSE:  Full Business Case for approval for chemotherapy clinical Trials Unit at Mount Vernon  Hospital  IM...
Author: Guest
0 downloads 0 Views 414KB Size
Agenda Item No: 9 

CTRT Business Case  PURPOSE:  Full Business Case for approval for chemotherapy clinical Trials Unit at Mount Vernon  Hospital 

IMPLICATIONS:  Risks 

Financial 

Human resources 

National Policy  Links to Corporate  objectives 

Legal issues 

A full risk management register has been compiled and forms part  of the FBC  Capital funding comes entirely from charitable funding and legacy  funding. No funding from the Trust. Capital costs includes rental to  Hillingdon for temporary accommodation.  The facility will provide a better working environment and support  the development and implementation of new models of care and  treatment techniques  To achieve recruitment targets of patients entering clinical trials as  set out by National Cancer Research Network  Compliance with requirement for quality and safe patient care:­  Ø  Maintain and improve access to experimental and standard  chemotherapy  Ø  Improve quality of care for patients involved in research  Agreement between CTRT and the Trust is drafted and attached to  FBC 

RECOMMENDATION:  Full Business Case to be approved subject to capital costs being confirmed at £1.4m and  continuing assurances to the Project Board that no funding is to be provided by the Trust. 

DIRECTOR: 

Director of Strategic Development 

PRESENTED BY: 

Director of Strategic Development 

AUTHOR: 

Mike Cullum (Project Manager) 

DATE: 

March 2009

EAST AND NORTH HERTFORDSHIRE NHS TRUST

FULL BUSINESS CASE FOR REDEVELOPMENT OF THE CANCER CENTRE CHEMOTHERAPY SUITE TO INCORPORATE A CLINICAL TRIALS UNIT

Version: Final February 2009

Page 2 of 32 

CONTENTS

Executive summary Section 1

National priorities and local objectives

p.8

Section 2

Guidance documents

p.8

Section 3

Strategic context

p.9

Section 4

Activity analysis

p.11

Section 5

Option appraisal

p.13

Section 6

Risk Management

p.17

Section 7

Costs

p.17

Section 8

Consultation

p.19

Section 9

Key Stakeholders and Project Management Team

p.19

Appendices Appendix I

Financial summary

Appendix II

Agreement between the CTRT appeal committee and East and North Herts Trust

Appendix III

Risk Management Plan

Appendix IV

FBC Report C&B (to follow)

Page 3 of 32 

EXECUTIVE SUMMARY Introduction This Full Business Case (FBC) outlines the requirements to extend, and refurbish the Chemotherapy Suite at the Mount Vernon Cancer Centre, incorporating within the new design facilities for the treatment of patients involved in clinical trials of chemotherapy. A dedicated clinical trials facility is required to meet the needs of increasing patient numbers and respond to regulatory requirements for conducting research. The existing facilities for delivering chemotherapy are substandard and in need of investment. The planned construction of an extension to the building for clinical trials has provided an opportunity to review the function of the entire unit. Fundraisers, stakeholders, patients and carers have been involved in the review, and fully support the proposal to construct an integrated unit, which will benefit patients receiving standard and experimental chemotherapy. This case has been developed in response to a partnership developed between the Cancer Treatment and Research Trust and the East and North Hertfordshire NHS Trust, through its registered charity, to jointly fundraise with an appeal for

£1.5 million to

develop a clinical trials unit capable of delivering chemotherapy treatment to patients enrolled in clinical trials. Approval of the Full Business Case by the East and North Hertfordshire NHS Trust will trigger the appointment of a contractor subject to fundraised income targets being met. This document will identify the options that have been considered and identify the chosen option. Primary Care Trust (PCT) Support PCTs will be kept informed of the proposals set out in this document via the quadrant meeting system. Consumer involvement A survey to obtain the views of patients using the existing facilities has been conducted and has informed the design of the new development.

Page 4 of 32 

Proposed Clinical Trials Facility Within the proposed unit there will be discrete areas for the treatment of patients involved in clinical trials and for those receiving standard chemotherapy treatment. However, the proposed design allows for shared resources such as consultation rooms and utility rooms, and for cross­cover between the non­research and research clinical cases. Primary Objectives The purposes of this Full Business Case (FBC) are to: ·

describe the present position

·

justify the project proposals for the redevelopment of the Chemotherapy Suite

·

structure the proposals to meet the primary objectives for a business case as set out by the East and North Hertfordshire Trust.

The main objectives of this case are to: 1.

Maintain and improve capacity and access to cancer clinical trials involving chemotherapy.

2.

Provide a centralized treatment centre thereby enhancing efficiency of treatment delivery, increasing patients’ well being and staff productivity.

3.

Enhance the surroundings for patients receiving chemotherapy treatment in accordance with NHS standards (control of infection, privacy and dignity, etc).

4.

Deliver a service appropriate for a 21st century cancer centre thus sustaining the centre’s world­renowned reputation.

5.

Achieve recruitment targets of patients entering clinical trials as set out by The National Cancer Research Network

6.

Ensure data confidentiality. At present lack of appropriate space means that case report forms containing research data by necessity must be left in non­secure locations during treatment.

7.

Provide staff access to electronic research data at the point of treatment delivery

Page 5 of 32 

Trust Estate The Mount Vernon Cancer Centre is situated on a site that is owned and managed by Hillingdon Hospitals NHS Trust. A lease is paid to that organisation based upon area of occupied space. The Trust provides estates management to the cancer centre. The areas currently used for research purposes are inadequate. Limited research space and lack of data confidentiality are just two examples. Many on­study research patients are presently treated in non­designated areas when non­research cases require the use of the facility. The proposed accommodation will partly utilise existing shared facilities, meaning that only a relatively small additional revenue charge associated with lease and maintenance service charges will be incurred. It is the intention that fundraised income will cover these revenue costs. The proposed development has the full support of the Hillingdon Hospitals Trust. The Head of Estates and Facilities has provided written confirmation that the Trust Board has agreed that the development may proceed. Strategic context Under the Investing in Your Health strategy for Bedfordshire and Hertfordshire, a proposal was developed in 2003 to build a new hospital in Hatfield that would host the Cancer Centre. However, a review of the revenue costs associated with the new hospital revealed that the proposal was not affordable. In September 2006, the new Hertfordshire PCTs were asked by the East of England Strategic Health Authority to review the original assumptions underpinning Investing in Your Health as part of a wider review of acute hospital services within the East of England.

Currently the findings of the review are subject to a wide consultation with a view to developing proposals. The time frame for this re­provision of services is likely to be 2013 at the earliest so services on the present site must develop to maintain the quality of service presently delivered to our patient population. To this end a developmental review of the Cancer Centre is being undertaken.

Page 6 of 32 

Since the Mount Vernon Cancer Network joined the National Cancer Research Network in April 2002, 36 research staff (26.5 whole time equivalent) have been appointed within the Cancer Centre. Recruitment of patients to national studies has risen from a baseline of 85 patients in 2001/02 to 591 patients in 2007/08 (204 patients to treatment trials, 387 patients to genetic studies). In addition, there is a large portfolio of commercial and early phase trials operational within the Cancer Centre. 113 patients were recruited to these studies during 2007/08.

Option Appraisal Five main options have been considered. Option I

Do Nothing.

Option II

Redesign and refurbish the existing chemotherapy suite at the

Mount Vernon Cancer Centre, incorporating within the new design facilities for the treatment of patients involved in clinical trials of chemotherapy. This option will involve adjustment to the existing building and arrangements have been made to relocate the chemotherapy service during the construction phase. The first floor of the building will be redeveloped within the project to improve office accommodation for research staff. Option III Relocation of the existing chemotherapy suite to the Upper West Wing at Mount Vernon Hospital and development of the clinical trials unit within the same area. This option would permit the use of existing facilities and may involve less structural work than option II. Option IV Relocation of the existing chemotherapy suite to the Ged Adams building within the Gray Cancer Institute Mount Vernon Hospital and development of the clinical trials unit within the same area. This option would permit the use of existing facilities and may involve less structural work than option II.

Costs and Affordability It is critical that all options are cost neutral both in capital and revenue terms for the Trust in order to secure the support of the Trust Board and PCTs.

Page 7 of 32

Procurement Procurement of this facility will follow standard NHS policies and procedures to ensure value for money. It should be noted that some of the required equipment is already in place and in use within the centre. Timetable This scheme has several timetabling requirements. A practical and realistic timetable has been defined and will be adhered to. A proposed timetable for approval of the project is as follows: Feb 2009

Submit full business case with pre­tender estimate to E&N Herts Treasury and Investment Committee

Feb – March 09

Tendering process and appointment of contractor

Feb 09

Relocation of chemotherapy unit to outpatient department

April 09

Construction commences

November 09

Return of chemotherapy service to new unit

Conclusion This Full Business Case (FBC) describes the need for a dedicated clinical trials area within the chemotherapy suite at the Cancer Centre at Mount Vernon Hospital. The proposal has the support of the Sponsors and the Mount Vernon Cancer Board. The local PCTs will be consulted at every stage of development. A full options appraisal has been conducted and justification for the preferred option is provided. It is envisaged that once the refurbishment is complete the Cancer Centre will be able to attract additional funds to support research and development in chemotherapy. Approval of this FBC is sought in order to confirm the following: ·

Approval that the scheme meets Trust priorities

·

Approval to commence the building phase, on the basis that sufficient funding has been raised or underwritten to cover the cost

Page 8 of 32 

Section 1

NATIONAL PRIORITIES AND LOCAL OBJECTIVES

The key objectives of the Mount Vernon Cancer Centre Cancer Board are: ·

Maintain and improve access to standard and experimental chemotherapy within the Mount Vernon Cancer Centre

·

Improve the quality of care provided for patients involved in research.

·

Enhance the surroundings for patients receiving chemotherapy

·

Deliver a service appropriate for a 21st century cancer centre thus sustaining the centre’s world­renowned reputation in research.

·

Achieve and maintain clinical trials recruitment targets set out in the National Cancer Plan

At present, the national priorities for research and local objectives described above cannot be achieved due to the lack of dedicated facilities for clinical research on the Mount Vernon Site. This Full Business Case describes the disadvantages and risks associated with the existing facilities. These are set out in the Options Appraisal and the chosen option is indicated.

The FBC is intended to be a planning document that

contains relevant information about the project. The document re­enforces the importance of a clear and transparent framework for making capital investment decisions via local strategic planning, asset management strategies, business case and option appraisal.

Section 2

ALIGNMENT WITH THE UK’s STRATEGIC GOALS FOR CANCER SERVICES AND RESEARCH, THE NHS PLAN (2000)

The NHS Plan sets out a strategic and operational framework for the modernisation of the facilities and services within the NHS, in line with the needs of the 21st century. The aim of the NHS plan is to deliver a more patient focussed service with greater integration both within the NHS and other agencies, thus promoting a seamless service. The plan places significant emphasis on the delivery of care within local high quality facilities.

Page 9 of 32 

The NHS Plan describes a new NHS National Cancer Research Network (NCRN). The initial aim of NCRN is to double the total proportion of adult cancer patients entering clinical trials. Report of the Science and Technology Committee on Cancer Research (2000) The National Cancer Research Network (NCRN) was created in response to the need to improve the infrastructure within the NHS for clinical research in cancer and to ensure that research is better integrated with cancer care. Section 3 3.1

STRATEGIC CONTEXT

Overview of the Trust and Cancer Centre

Mount Vernon Cancer Centre was, until March 31st 2005, under the management of West Hertfordshire Hospitals NHS Trust. On 1st April 2005 the management was transferred to East and North Hertfordshire Hospitals NHS Trust.

This transfer was a

strategic decision relating to the delivery of the “Investing in Your Health” programme. The design of this new facility falls under the remit of East and North Hertfordshire Hospitals NHS Trust and the cancer centre team can now assist in the development process from within that organisation. The present population served by the cancer centre is over 1.9 million. This is due to rise to 2.2 million by 2013. The centre has to provide services to meet the needs of this increased population. The Clinical Trials Unit will be an essential facility to meet this increased demand effectively. Mount Vernon Cancer Centre is within the Mount Vernon Cancer Network but also provides radiotherapy and complex chemotherapy services to parts of North and West London as well as the Thames Valley cancer network. The population areas currently served by the cancer centre include Hillingdon, Harrow, East Berkshire, South Buckinghamshire, Barnet, Luton, Watford, Hemel Hempstead, St Albans, Hatfield, Hitchin, Baldock and Stevenage. The East and North Hertfordshire Hospitals NHS Trust comprises three hospital sites including the Mount Vernon Cancer Centre. The Trust offices are on the Lister Hospital site in Stevenage. All administrative work associated with cancer clinical research is carried out on the Mount Vernon site.

Page 10 of 32

The Mount Vernon Cancer Centre is situated on a site that is owned and managed by Hillingdon Hospital NHS Trust, which provides estate management services. A lease is paid to that organisation based on the area of the occupied space. There are 64 cancer beds within the centre over three wards, of which one covers five­day stay patients only.

Services within the cancer centre include a large radiotherapy

department delivering over 4000 new courses of external beam radiotherapy per year, and chemotherapy suite delivering approximately 2000 courses per year. 3.2

The ‘Vision’

The Centre’s vision is to continue to deliver the best cancer treatment service possible and to develop new and updated techniques and systems of work that are patient focussed underpinned by evidence­based medicine. The Trust’s vision is to provide safe and effective services to our catchments population whilst supporting clinical research and development. The proposed development of the will facilitate the achievement of that vision. 3.3

The NHS Plan

The NHS Plan sets out a strategic and operational framework for the modernisation of the facilities and services, in order to provide a service in line with the needs of the 21st century. The aim of the NHS plan is to deliver a more patient focussed service with greater integration both within the NHS and other agencies, thus promoting a seamless service. The plan places significant emphasis on the delivery of care within local high quality facilities. 3.4

Strategic Fit

The development of the clinical trials unit and upgrading of existing facilities is totally aligned to the strategic aspirations of both the National Priorities for Cancer Research and the Mount Vernon Cancer Centre Board. For example: New Ways of Working – Revised and updated patient pathways and models of care will be developed to fully utilise the upgraded facilities. Higher Quality of Care – Whilst retaining its own identity, the trials unit will be fully integrated with the existing Chemotherapy Suite to enable a supportive and dynamic environment. The unit will provide a dedicated area for the administration of innovative treatments and techniques associated with on­going clinical research.

Page 11 of 32

Better Conditions for NHS Staff – The new facility will be a purpose­designed area providing a better working environment and will support the development and implementation of new models of care and treatment techniques. Maintain Reduced Waiting Times – The re­provision of the service will allow a more efficient use of existing equipment and administrative processes, keeping waiting times to a minimum. Patient Centred Care – The design of the unit incorporates enhanced patient and carer waiting facilities and improved privacy during both treatment and consultations. Better Facilities – This unit will be a 21st century facility, fit for purpose and ready for future developments in this form of treatment delivery.

Section 4

ACTIVITY ANALYSIS

The proposed facility will have no effect on the level of treatment activity for patients receiving standard chemotherapy within the chemotherapy suite.

It will however

accommodate the projected increase in research activity shown in table 1.

The

financial benefits for the Trust are twofold. Firstly, a significant number (see table 2) of research patients that are currently treated on the cancer wards will to be treated in the new unit as outpatients.

This will increase capacity on the wards, providing

opportunities for generating income.

Capacity in outpatient clinics will also be

increased as the proposed unit will provide facilities for other research­related activity currently performed in the clinics such as obtaining consent and data collection. The second financial benefit is that the new unit will enable more patients to be treated within clinical trials. The new funding arrangements for R&D are firmly linked to research activity and it is therefore essential to increase accrual to trials in order to sustain the level of funding allocated to the Trust in previous years. The new unit will also facilitate growth in the portfolio of commercial trials within the Cancer Centre, giving patients access to new agents and providing industry funding.

Page 12 of 32

Table 1 Projected increase in research activity assuming proposed unit goes ahead. Pts recruited to non ­ commercial treatment trials

Pts recruited to commercial treatment trials

Total patients recruited to treatment trials

2005/06

131

41

172

2006/07

152

111

263 (up 52% on previous year)

2007/08

204

113

317 (up 20%)

2008/09 (projected)

228

120

348 (up 10%)

2009/10 (projected)

252

130

382 (up 10%)

2010/11 (projected)

280

140

420 (up 10%)

2011/12 (projected)

312

150

462 (up 10%)

2012/13 (projected)

348

160

508 (up 10%)

NB Rate of increase in research activity 05/06 to 06/07 reflects rapid expansion in workforce. The expansion in staff numbers was less marked between 06/07 and 07/08 and is likely to be slow but sustained in future years.

Table 2 Projected increase in availability of inpatient beds Number of research patients relocated from inpatient to outpatient facilities based on 20% of patients relocated

Number of ‘bed days’ released (assuming 6 treatments per patient)

2008/09 (projected)

70

420

2009/10 (projected)

76

456

2010/11 (projected)

84

504

Page 13 of 32 

2011/12 (projected)

92

552

2012/13 (projected)

101

606

Section 5

OPTION APPRAISAL

Five options have been considered for the improvement of the accommodation to a modern standard at the hospital, the benefits and drawbacks associated with each option have been outlined.

5.1

The Options The four options are as follows:

Option I

Do Nothing

This has been considered to assess whether there is any merit in maintaining the status quo. This business case has assumed activity growth in research of at least 10% per annum. The existing facilities for treating patients receiving standard chemotherapy are inadequate and not fit for purpose. ·

The reception area is dark, drafty and unwelcoming.

·

The consultation rooms are gloomy and oppressive mainly because they do not receive any natural light.

·

The treatment area is badly designed resulting in very poor use of space and restriction to the number of patients that can be treated.

·

The views from the windows are bleak and patients do not have access to outside areas.

·

There is no sluice for disposal of patients’ body fluids.

·

Security is poor.

·

There is no nurse call system within the unit (apart from the toilet areas)

Page 14 of 32

The space for research within the current chemotherapy unit is barely adequate for meeting the needs of patients in clinical trials. At present only 4 research patients can be treated per day. The research team has limited access to a bed in the chemo suite. Overflow research patients at present are treated in the cancer ward. This procedure is clearly inadequate because: a.

It blocks in­take of new patients into the cancer centre

b.

It scatters resources and personnel

c.

It increases level of anxiety of patients because of unfamiliar surroundings

d.

Lack of privacy for holding private consultation between staff and patients compromises confidentiality

Furthermore, there is no additional space, either as an internal or external sitting area, for patients requiring rest and respite during treatment. The waiting area in the current chemotherapy unit is not big enough to accommodate both research and non­research patients and their relatives or carers. There is no space for storing expensive monitoring equipment, which at present must be left in wards or corridors. The current chemotherapy suite does not have Dirty Utility area where one can process and store blood products and dispose of patients’ body fluids.

Option II Development of an integrated area for the treatment of patients receiving standard and experimental chemotherapy. This option takes into account the generous offer of volunteers who aim to fundraise for the sum of £1,500,000 towards this project. This option also involves some redevelopment of the first floor of the existing building. This option has the major advantage of sharing facilities with an existing service, namely the Chemotherapy Suite. This new structure would contain:

Page 15 of 32

1.1.1

An area for treating a maximum of 15 patients receiving standard chemotherapy and 6 patients receiving experimental chemotherapy at any one time. The area will contain 19 treatment chairs and 2 beds.

1.1.2

3 consulting rooms: for examination of patients, clinical procedures, follow­up appointments and private discussions with patients or relatives.

1.1.3

1 counselling room for consultations that may involve breaking distressing news.

1.1.4

Dedicated area for safe storage of clinical data

1.1.5

2 storage areas for monitoring equipment, chemotherapy administration equipment and disposables

1.1.6

Dirty Utility Room: this will be a shared facility with the Chemotherapy Suite and would allow the safe disposal of body fluids. A sluice would be essential for disposing of waste in purpose built containers. The area will also contain a dedicated area for sample preparation (for example separating blood products by spinning in centrifuge) and storage of samples in specialised freezers at required temperature.

1.1.7

2 prep areas for laying up trolleys for phlebotomy and chemotherapy administration, and for checking drugs.

1.1.8

Enlargement of waiting room area: to accommodate increase numbers of research and non­research patients together with their relatives and or carers.

1.1.9

2 landscaped gardens viewed from the clinical areas: for those patients requiring access to fresh air and respite during treatment.

1.1.10 Refurbishment of staff room. Work will also be undertaken in the first floor. The two main aims are to improve access to the lecture room and to improve the fire escape as the building does not comply with fire regulations. Finally 2 opened planned offices, used by research staff, need to be refurbished, their privacy improved to improve data protection and staff well­being.

Page 16 of 32

Option III Relocation of the existing chemotherapy suite to the Upper West Wing at Mount Vernon Hospital and development of the clinical trials unit within the same area.

This option utilises existing facilities and would involve less structural work than the development of a new unit, however adjustments would be required to the fire escape and lift. The main drawback to this option is that the area is situated on the first floor and access would need to be considered.

Option IV Relocation of the existing chemotherapy suite to the Ged Adams Building within the Gray Institute and development of the clinical trials unit within the same area.

This option utilises existing facilities and would involve less structural work than the development of a new unit, however significant internal adjustments would be required. The main drawback to this option is that the area is situated at some distance from the facilities used by patients within the Cancer Centre such as the Lynda Jackson support centre.

5.2

Rejected options

Option 1 should be discounted for the following reasons: 1. The existing arrangement means that clinical research is not conducted in one place, leading to an inefficient use of resources and personnel. 2. At present the space allocated to research patients in the Chemotherapy Suite is inadequate. 3. Inpatient facilities are used for research patients that could be treated as outpatients leading to unnecessary expenditure. 4. There are no facilities in the current unit for the disposal of body fluids. 5. The waiting area is too small resulting in overcrowding at busy times. 6.

The rooms designated for private discussions are unwelcoming and in need of refurbishment.

Option III should be discounted because the space required for the existing chemotherapy services and the proposed clinical trials unit is estimated at 340m2. The space in the Upper West wing is 210m2 .

Page 17 of 32 

Option IV should be discounted because the space required for the existing chemotherapy services and the proposed clinical trials unit is estimated at 340m2. The space in the Ged Adams Building is 162m2.

5.3

Preferred Option

Option II is the preferred option because it would provide a centralized treatment area, with good and more cost­effective use of resources and personnel. It also minimizes risks to patients and provides comfortable, familiar surroundings to them, personnel and ancillary staff. Planning permission for this option has been granted and is effective for 5 years from September 2005. 5.4

Staffing

Existing staff will provide manpower for the proposed development. As an additional member of staff, a Clinical Trials Assistant with administrative responsibilities of stocktaking and maintenance, supervisor and receptionist is being considered, providing sufficient funding becomes available from non­NHS Trust sources. The unit could be developed and satisfactorily run without this change to staffing.

Section 6

RISK MANAGEMENT PLAN

The risks associated with this project have been identified and risk management plans identified (see appendix III – p24).

Section 7

COSTS

The income and costs associated with this project are summarised in appendix I (p20). 7.1

Capital Costs

The cost estimate for Option II is £1.47 million. This estimate is fully inclusive of all costs associated with the project apart from revenue costs, which will be covered by the

Page 18 of 32

anticipated increase in research income as a result of the improved facilities for research. 7.2

Equipment costs

The cost of additional medical equipment is £41,732 including VAT 7.4

Revenue costs

There are no additional staff costs associated with this project as the proposed unit will be covered by existing staff. As research activity increases, additional staff will be funded from existing funding streams. 7.5

Cost of relocating chemotherapy service for the duration of building works

The costs associated with decanting services to the Hillingdon outpatients department building during the building works of the project are included within the attached financial summary. 7.6

Funding

The entire cost of the project will be funded by voluntary donations. The Cancer Treatment and Research Trust will make a significant contribution including £150,000 raised via previous fundraising activities. It will also provide a volunteer fundraising committee. A Memorandum of Understanding has been agreed between the CTRT and the East and North Hertfordshire NHS Trust in order to clarify the funding relationship between the parties (Appendix II)

Section 8 CONSULTATION A consultation plan and communication protocol will be implemented with appropriate consultation mechanisms which will facilitate and ensure transparent decision making at all levels where all the key stakeholders will be encouraged to give their views and provide feedback on the project proposals and the service provision.

Page 19 of 32

Section 9

8.1

KEY STAKEHOLDERS AND PROJECT MANAGEMENT TEAMS

Key Stakeholders Louise Hobday

Manager Chemotherapy Suite

Heather Phillips

Research Network Manager

Kay Bell

Head of Nursing Cancer and Palliative Care

Jane Boxall

Research Nurse

Michael Powell

Network Lead Pharmacist

Teresa Young

Research Data Manager

Professor Gordon Rustin

Consultant Oncologist

Project Management Team Cathy Williams

Cancer Centre General Manager

Heather Phillips

Research Network Manager

Kay Bell

Head of Nursing for Cancer and Palliative Care

Professor Gordon Rustin

Consultant Oncologist

Dean Goodrum

Senior Capital Projects Manager

Malcolm Lynch

Capital Projects Manager

Michael Powell

Network Lead Pharmacist

Louise Hobday

Senior Sister Chemotherapy Day Unit

Mark Wheeler

Deputy Financial Controller

Project Board Stephen Posey

Director of Strategic Development

Heather Phillips

Research Network Manager

Professor Gordon Rustin

Consultant Oncologist

Daniel Fletcher

Head of Fundraising Development

Brian Abbott

Head of Fundraising

Malcolm Lynch

Capital Projects Manager

Page 20 of 32 

Appendix 1 Financial summary

CTRT Project  Cost Summary 

£000 

Capital  Build including refurbishment and professional fees  Decanting Costs  Rent of Gray Labs  Porter  IT Infrastructure  Removal Costs 

£000 

1,203 

140  11  4  11  166 

Equipment  Additional Chairs  Other 

4  38  42 

Project Management Cost 

60 

Total Project Cost 

1,471 

Charitable Funding Summary  Charitable Fund (V8515) (This amount includes £300k transferred from V2265) as at 31/1/09  R&D funding  Legacy funding 

963  50  100 

Wolfson Pledge 

405 

Total ­ Charitable Funds 

1,518

Page 21 of 32 

Appendix II– Agreement between CTRT and the Trust This Agreement is made the

day of

2006 between:­

1. East and North Hertfordshire NHS Trust, of Lister Hospital, Coreys Mill Lane, Stevenage, SG1 4AB (‘the Trust’) and 2. East and North Hertfordshire NHS Trust Charitable Fund, registered charity 1053338, trading as ‘enhance herts’ of Lister Hospital, Coreys Mill Lane, Stevenage, SG1 4AB (‘enhance herts’) 3. Professor Gordon Rustin and Dr Paul Nathan being two of the trustees of the Cancer Treatment and Research Trust, registered charity 292909, of Clocktower, Mount Vernon Cancer Centre, Rickmansworth Road, Northwood, HA6 2RN (‘CTRT’) Background:­ The parties are working together to raise funds for a clinical trials unit and ongoing cancer research as described in the attached document which sets out the project goals, responsibilities, governance and financial controls (‘the Project’). The parties recognise that the Trust needs a clinical trials unit to be built at Mount Vernon Cancer Centre to support clinical trials and ongoing research into cancer and its treatments. The cost of the Project is expected to be no less than £1,000,000 including approximately £750,000 towards the capital project to construct a clinical trials unit, and £250,000 to cover revenue requirements to run the unit and for ongoing research activity. The Trust and enhance herts recognise that CTRT has experience in fundraising towards cancer treatment and research at Mount Vernon Cancer Centre. Heads of Agreement:­ 1.

The parties agree that CTRT will work with the Trust through its registered charity, East and North Hertfordshire NHS Trust Charitable Fund, known as enhance herts, in order to raise at least £1,000,000 (net of certain expenses) for the Project.

2.

The parties agree that all funds raised towards the Project shall be paid into the enhance herts bank account. CTRT shall forthwith transfer all monies held by CTRT designated for the Project net of ongoing expenses and commitments to the enhance herts bank account.

3.

The CTRT designated representatives will only undertake such fundraising activities for the Project as have previously been agreed in writing in advance with the enhance herts Head of Fundraising Development.

4.

The Trust and enhance herts undertake to spend the money raised only in connection with the Project or any part or parts of the Project (or if that is not possible, as otherwise agreed in writing with CTRT). The manner of the expenditure of the monies raised shall be in the discretion of the Trust in the context of the Project.

5.1

In respect of the building construction element of the Project, the parties agree that construction of the clinical trials unit will not commence until a Full Business Case has been completed and approved by the Trust, and the Trust is satisfied that all necessary money has been raised to meet all financial commitments described within the Full Business Case. CTRT’s consent to the Full Business Case is not required.

5.2

In respect of the research element of the Project, expenditure on the research activities envisaged by the Project will occur in the Trust’s discretion in accordance with the Trust’s policy for research initiatives (involving consultation with relevant specialist consultant practitioners employed by the Trust) and the Trust may use the monies raised in connection with the Project for those research activities as and when it sees fit.

Page 22 of 32 

6.

The parties may at any time end their fund raising relationship envisaged by this agreement on giving written notice to the other parties. Notwithstanding termination of the relationship between the parties, clauses 4 and 5 shall continue to have effect and monies donated or raised by CTRT shall not become repayable to CTRT provided they are used within a period of [5] years from the date hereof as envisaged by this agreement or as otherwise specifically agreed in writing between the parties.

7.

This agreement shall be governed by English Law

The parties confirm their agreement by signing on the day before written.

………………………………………………………………………………………… Dr Paul Nathan Dr David Miles Professor Jane Maher Trustees of the Cancer Treatment and Research Trust

Robin Ellison

………………………………………………………………………………………… Chief Executive Director of Finance Treasury Investment Committee Chairman on behalf of The East and North Hertfordshire NHS Trust

………………………………………………………………………………………… Chief Executive Director of Finance Treasury Investment Committee Chairman on behalf of The East and North Hertfordshire NHS Trust acting as Trustee of enhance herts ‘the Project’ Project goals The object of the relationship is to fund the development of a new clinical trials unit for cancer research alongside funding of ongoing and new non­commercial research activity in the unit. Construction is aimed to commence January 2007. Approximately £215,000 has been committed so far from CTRT, with a potential additional £200,000 also available from funds earmarked for cancer research within enhance herts. A SOC for constructing the clinical trials unit with an estimated cost of £750,000 is nearing completion. The aim is to raise a further £250,000 to fund the ongoing research activity for 2006­7. The project has the potential to form an ongoing fundraising campaign to fund an increasing proportion of cancer research for the Trust, and current fundraising frameworks are being considered in light of this. Project responsibilities The Project involves close liaison between East and North Hertfordshire NHS Trust, enhance herts and the Cancer Treatment and Research Trust (CTRT). Enhance herts was established in 1996 and is known formally as East and North Hertfordshire NHS Trust Charitable Fund. It has stated objects of any charitable purpose or purposes relating to the National Health Service wholly or mainly for the service provided by East and North Hertfordshire NHS Trust. Its income has varied from £400,000 to more than £3m over the past five years. The CTRT was established in 1985 with the stated objects of the promotion of medical and scientific research into the causes and treatment of cancer and related diseases and the dissemination of the useful results of such research and for the treatment and care of people suffering from cancer and related diseases. Its annual income has varied from £250,000 to £860,000 over the last five years. CTRT includes four (Rustin, Maher, Nathan, Miles) Mount Vernon clinicians on its eight­strong trustee board, led by Professor Gordon Rustin. The CTRT has recruited a volunteer fundraising committee chaired by Ray Payne. Committee members will be approaching companies, including pharmaceuticals, schools, community organizations and individuals who are interested in fundraising events and sponsored activities. Other fundraising activity will be undertaken either directly by or under the supervision of enhance herts, including contacting current and former patients of initially Prof Rustin, to ask them if they are prepared to get involved in the appeal, and if so, to ask them for ongoing support and applying to grant­making trusts. All the other oncologists have agreed to their patients also being approached. Enhance herts will also provide training and oversight of approaches made to high net worth individuals known to committee members.

Page 23 of 32

Governance and financial controls Money raised to date comes from CTRT reserves, and specific donations of around £15,000 made to the Appeal. An additional £200,000 has been earmarked from enhance herts, from the Cancer Research fund, based at Mt Vernon. This essentially is being used to under­write part of the project, in order to enable pre­construction surveys and work to commence before all the funds have actually been received. All new donations resulting from the CTRT appeal will be deposited into an enhance herts fund designated for the CTRT Appeal. Gordon Rustin will be the fund manager. As such, the standard accountability between enhance herts trustees and fund managers will be applicable, and fund transactions will be under the Trust’s Standing Financial Instructions and Standing Orders. All fundraising activity, including that undertaken by volunteers, comes under the auspices of enhance herts and will be managed by the Head of Fundraising Development. Day­to­day oversight of the committee will be undertaken by the paid­CTRT administrator Brian Abbott, who will work closely with the Head of Fundraising Development. The appeal will be called the CTRT Appeal, recognising the support of the CTRT and also because the majority of potential donors do not have a geographic affiliation to East and North Hertfordshire and would be happier with the concept of giving to a ’Cancer’ charity linked to Mount Vernon Cancer Centre. It will however be made clear to donors that enhance herts will hold funds raised for this project.

Page 24 of 32 

Page 25 of 32

Appendix III Risk Management Plan  MOUNT VERNON HOSPITAL  CLINICAL TRIALS & CHEMOTHERAPY SUITE  CONSTRUCTION RISK REGISTER 20/11/08  1 TO 8 LOW, 9 TO 16 MED, 17 TO 25 HIGH  No.  Risk 

Consequence 

Control 

Manager  Owner 

1. 

Design changes 

Clear brief at outset 

2. 

Potential delay and  disruption  Project delay 

Refusal of planning  variation  Building Regulation  Project delay  refusal  Fire Authority  Project delay  refusal 

Client  PM  Architect 

3.  4. 

5. 

Insufficient  electrical capacity 

Project delay/large  additional cost 

6. 

Design difficult to  construct 

7. 

Unsafe design 

Inefficient  construction & poor  value for money  Dangerous to all 

Impact  Rating  Rating 

M Lynch 

Proba  bility  2 



16 

Med 

J Haigh 





16 

Med 

Architect 

J Haigh 







Low 

Architect  Fire  Safety  Manager  H of CP  Client  PM and  M&E  Designer  Architect 

J Haigh/  B Rennie 



10 

20 

High 



20 

160 

High  Very  High 

J Haigh 







Low 

Architect  M&E  Designer  P C 

J Haigh  &  J Sims  A Carey 







Low 

Design programme  Information required schedule  Project Execution Plan to  detail approvals process map 

Architect  Architect  Client  PM 

J Haigh  J Haigh  M Lynch 







Low 







Low

Milestones to be on design  programme 

Architect 

J Haigh 

Early informal meeting with  the Planners  Early informal meeting with  BCO  Negotiation on scope 

Decision to proceed at risk  Early site survey and  monitoring with “hawks” 

Construction input to design  meetings  Design risk assessments 

Planning Co­ordinator to  review  8. 

Design Process  Late information 

Delay & cost 

9. 

Late approvals 

Delay & cost 

D Goodrum  M Lynch  &  J Sims 

Page 27 of 32 

Low 

10. 

Insufficient  resources 

Programme loss 

11. 

Unrealistic  programmes  Operational Issues  Unsafe  environment 

We all fail 

12. 

13  14. 

15. 

16. 

17.  18. 

19. 

Nuisance/  Noise/Dust  Interruption of  services to Chart  Lodge 

Unplanned project  overrun 

Existing Data  Inadequate /  unreliable record  information  Damage to buried  services  Asbestos 

Client Routines  Fire Alarm Tests 

All partners to ensure  adequate resources are  made available  All team members to  challenge if concerned 

All 

All 







Low 

Architect 

J Haigh 







Low 

Adherence to Trust  procedures 

Site  Manager 

TBA 







Low 

Adherence to H&S Plan 

TBA 

Detailed planning  Liaison meetings to discuss  Detailed survey to establish  locations of services 

Site  Manager  Site  Manager  Client  PM 

TBA 





10 

Med 

M Lynch 





10 

Med 

Marking and protection of the  service routes  Regular programme review. 

Site  Manager  Architect 

TBA  1 





Low 

Honest, realistic reporting. 

Site  Manager 

TBA 

All records to be collated and  handed to the site team 

Planning  Co­  ordinator  Site  Manager  Client  PM 

A Carey 







Low 

TBA 





10 

Med 

M Lynch 



10

10

Med 

Partial Hospital  Consult Hillingdon Trust’s  closure if asbestos is  asbestos survey  found in the  electrical ducts 

Planning  Co­  ordinator 

A Carey 

10 

25 

250 

Very  high 

None 

Site  Manager 

TBA 







Low

Potential injury.  Client and/or  construction  operations halted 

Production stopped  Residential  accommodation  unavailable 

Missed targets.  Threat to Trust  Foundation status.  Reduced future  funding.  Injury / lost  production /  disruption / cost  Disruption to  Hospital operations  Disruption & delay to  site operations. 

As Item 14  Conduct Type 2 Asbestos  survey of Chemo’ Suite 

Site induction training 

J Haigh 

Page 28 of 32 

20. 

Site Safety Issues  Restricted access 

21. 

Restricted Site 

22. 

Confined working  spaces 

28. 

Falls from heights 

Congestion /  increased risk of  injury / lost  production  Congestion /  increased risk of  injury / lost  production  Congestion /  increased risk of  injury / lost  production  Disruption / partial  hospital closure  /missed targets /  future funding threat  / lost production  Unnecessary loss of  life and property /  prosecution  Disruption to both  Client & Contractor  Infection risk.  Safety hazard.  Personal injury.  Dismissal.  Prosecution.  Personal injury 

29. 

Theft 

Criminal prosecution 

30. 

Vandalism 

Criminal prosecution 

31. 

Terrorism 

Criminal prosecution  Hospital closure /  missed targets / lost  production 

23. 

Site fire 

24. 

Obstructed Fire  Brigade access 

25. 

Obstruction due to  delivery vehicles  Poor waste  management  Drugs & alcohol  abuse 

26.  27. 

Detailed planning.  Good site control 

Site  Manager 

TBA 







Low 

Detailed planning.  Good site control. 

Site  Manager 

TBA 







Low 

Health & Safety Plan 

Site  Manager 

TBA 







Low 

Site fire plan.  Site induction training.  Hot works permits. 

Site  Manager 

TBA 







Low 

Traffic management plan.  Site induction training 

Site  Manager 

TBA 







Low 

Add instructions to all  material and plant orders  Environmental plan 

Site  Manager  Site  Manager  Site  Manager 

TBA 







Low 

TBA 







Low 

TBA 







Low 

Site  Manager  Site  Manager 

TBA 





10 

Med 

TBA 







Low 

Site  Manager 

TBA 







Low 

Site  Manager 

TBA 







Low

CTA Training 

Site policy.  Health & Safety Induction  Training  Health & Safety Plan  H&S procedure  Increased awareness of  suspicious incidents.  Report to Site Manager.  Increased awareness of  suspicious incidents.  Report to Site Manager  Increased awareness of  suspicious incidents.  Report to Site Manager.  Follow Trust’s Major Incident  Procedures. 

Page 29 of 32 

32 

Lack of protection 

Damage to property  Injury to personnel 

33. 

Construction  accidents 

Personal injury 

34. 

Unplanned  restricted working  hours  Disruption caused  by smoking, radios,  mobile phones  Inadequate car  parking 

37. 

Prohibition by HSE 

Project delay 

38. 

Insufficient funds  available 

Project curtailed 

35. 

36. 

39. 

Decant Operation  OPD not available 

40. 

OPD only available  for 6 months 

41. 

Insufficient data  outlets in OPD  Partnership Issues  Poor  communications  Personality clashes 

42.  43.  44. 

Loss of key  personnel 

Detailed method statements  Detailed Planning  Liaison meets to discuss  Health & Safety Plan  procedure 

Site  Manager 

TBA 







Low 

Site  Manager 

TBA 







Low 

Increased cost 

Detailed planning  Liaison meetings to discuss 

Site  Manager 

TBA 







Low 

Production stopped 

Detailed planning  Liaison meetings to discuss  Induction training  Site parking plan.  Incorporate plan into  subcontract orders.  Robust Safety Plan and site  control  Accurate accounting of the  Charitable Funding.  Accurate cost reporting.  Value engineering. 

Site  Manager 

TBA 







Low 

Site  Manager 

TBA 







Low 

Site  Manager  Finance 

TBA 







Low 

M Wheeler 







Low 

Client  PM 

M Lynch 

Don’t even  contemplate.  Huge delay.  Would create an  impossibly short  construction period.  Huge delay.  Additional cost 

Plan B – Negotiate rental of  Gray Lab Building 

General  Manager 

C Williams 



15 

75 

High 

Plan B – Negotiate rental of  Gray Lab Building 

General  Manager 

C Williams 

10 

15 

150 

Very  high 

Survey of existing 

IT Project  J Roberts  Manager 





10 

Low 

Dysfunctional team 

Project Execution Plan 

M Lynch 







Low 

Dysfunctional team 

Project Execution Plan 

M Lynch 







Low 

Loss of information  continuity 

Keep consistent staff as far  as possible.  No staff changes without prior  discussion with Client PM. 

Client  PM  Client  PM  All 

All 







Low

Disruption &  inconvenience 

Page 30 of 32 

REGISTER OF RISKS NOT RELATED TO CONSTRUCTION  20/11/08 

1 TO 8 LOW, 9 TO 16 MED, 17 TO 25 HIGH 

No.  Risk 

Consequence 

Control 

Manager 

Owner 

Proba  bility  2 

Impact  Rating  Rating 



Reluctance of staff  to relocate  temporarily to  Outpatients Dept  during construction  phase 

Discord within the  staffing team 

Robust communications with  staff and involvement in  planning service relocations. 

Research  Network  Manager/  Head of  Nursing 

Kay Bell 





Low 



Temporary  Disruption to service  accommodation not  fit for purpose 

Full assessment of area prior  to relocation and remedial  works (eg improvements to IT  infrastructure) completed. 

Research  Network  Manager/  Capital  Planning  Manager 

Malcolm  Lynch 



10 

10 

Med 



Different patterns of  Discord within the  working due to  staffing team  integration of  research and  service provision 

Robust communications with  staff and involvement in  planning integrated service. 

Research  Heather  Network  Phillips  Manager/Che  mo manager  Louise  Hobday 





21 

High 



Loss of pneumatic  chute during  relocation period 

Drugs and blood  specimens will need  to be transported  manually 

Employ porter dedicated to  working in unit during  construction phase 

Head of  Nursing 

Kay Bell 





16 

Med 



Temporary  accommodation is  distant from Cancer  Centre 

May cause  difficulties for  patients with low  mobility 

Employ porter dedicated to  working in unit during  construction phase 

Head of  Nursing 

Kay Bell 





20 

High 



Temporary  accommodation is 

Patients may have  difficulty finding the 

Ensure good signage 

Research  Network 

Estates  Department 







Low

Page 31 of 32 

distant from Cancer  chemotherapy unit  Centre 







10 

Manager 

Damage to  equipment during  move to and from  temporary location  Disruption to  chemotherapy  service during  move to  Outpatients Dept  Costs of capital  project are higher  than income from  CTRT charity 

Cost implications  and disruption to  service 

Employ removal company  known to Cancer Centre 

Service  Manager 

Jillian David 



10 

10 

Med 

Delay in treatment 

Relocate over weekend 

Service  Manager 

Jillian David 





12 

Med 

Insufficient funding  to complete project 

Deputy  Financial  Controller 

Mark  Wheeler 





16 

Med 

Costs of services  once unit is open  are higher than  FBC costings. 

Unforeseen costs to  Trust 

Realistic costings at FBC  stage. Robust financial  management of project.  Notification to Trust at early  stage of shortfall in income.  Realistic costings at FBC  stage. 

Deputy  Financial  Controller 

Mark  Wheeler 







Low

Page 32 of 32