Chilled Water Plant Design and Control 65 ECWT
0.555 KW/ton
56°F
0.59 KW/ton 48°F
CH-1
95°F
40°F
KW/ton
0.52 KW/ton
CH-2
90°F
75 ECWT
85 ECWT
1.0
0.8
0.6
0.4
85°F
0.2
25
50
75
Percent Loaded
Kent W. Peterson, PE, FASHRAE P2S Engineering, Inc. Long Beach, CA
[email protected]
March 2, 2012
100
Handouts
A copy of the today’s slides in PDF format will be available from Trent Hunt
2
Agenda
CHW Distribution Systems CHW Distribution System Balancing CW Distribution Systems Break Selecting CHW Distribution Systems Selecting CHW ΔT Selecting CW ΔT Selecting Chillers Optimizing Control Sequences Questions 3
Optimizing Energy Usage
Chillers
•
Type, efficiency, size, VFD
Cooling Towers
•
Fan type, efficiency, approach, range, speed control, flow turndown
Chilled Water Pumps
•
Arrangement, flow rate (delta-T), pressure drop, VFD
Condenser Water Pumps
•
Flow rate (delta-T), pressure drop, VFD
Air Handling Units
•
Coil sizing, air-side pressure drop, water-side pressure drop 4
Pop Quiz 1 What
happens to component energy usage if we lower CWS setpoint?
• Chiller • Towers • Pumps
Pop Quiz 2 What
happens to component energy usage if we lower CW flow?
• Chiller • Towers • Pumps
Pop Quiz 3 What
happens to component energy usage if we lower CW flow AND the CWS setpoint?
• Chiller • Towers • Pumps
Optimizing CHW Plant Design Ideal:
Design a plant with lowest life cycle costs (first cost plus lifelong operating costs) accounting for all the complexities and interaction among plant components
Practical:
Design plant subsystems to be near-life cycle cost optimum using techniques that are simple and practical enough to be used without a significant increase in design time 8
Chilled Water Distribution Systems
9
Chilled Water System Classes Constant
Flow
• No control valves • 3-way control valves
Variable
Flow
• Primary-Only • Primary/Secondary (/ Tertiary) • Primary/Distributed Secondary • Primary/Variable Speed Coil Secondary
These are the major categories of distribution systems. The list is by no means complete. There are many permutations and combinations. 10
Constant Flow Single Chiller, Single Coil, No Control Valve
11
“Constant” Flow 3-Way Valves 3-Way Mixing Valve
DPft 20
Bypass Balance Valve
Item
Pressure Drop @ 100 GPM 100% to Coil 50% to Coil 0% to Coil
Pipe/Valves Coil and/or Bypass Globe Control Valve Total GPM @ 20’ ΔP*
2 8 10 20
2 2 7.5 11.5
2 6 12 20
100
132
100
*actual ΔP available may change 12
Constant Flow Single Chiller, Multiple Coils
13
Constant Flow Multiple Parallel Chillers, Multiple Coils
CH1 240 gpm
How many chillers do we need to run?
CH2 240 gpm
Ballroom A 240 gpm 100% Loaded
Ballroom B 240 gpm Unoccupied
14
Variable Flow Vary
Flow Through Coil Circuit
• Two-way valves • Variable speed coil pump
Configurations
• Primary-secondary • Primary-secondary variations • Primary-secondary-tertiary • Primary-only 15
Variable Flow Chilled Water Systems Old
Paradigm
• Controls respond to changes in CHW temperature • Variable flow causes low temperature trips, locks out chiller, requires manual reset (may even freeze) • Hence: Maintain constant flow through chillers 16
Variable Flow Primary/Secondary, Multiple Chillers and Coils
Hydraulic Independence
If there is no resistance in the common leg, then no flow is induced in the other circuit. 17
Variable Flow Series Flow, Multiple Chillers
18
Variable Flow Primary/Distributed Secondary
19
Variable Flow Primary/Secondary/Tertiary
20
Variable Flow Chilled Water Systems New
Paradigm
• Modern controls are robust and very responsive to both flow and temperature variations • Variable flow OK within range and rateof-change spec’d by chiller manufacturer
21
Variable Flow Primary-only, Multiple Chillers
22
Variable Flow Primary, Bypass Valve
Location
•
•
Near chillers Best for energy Controls less expensive Control more difficult to tune – fast response
Remote Smaller pressure fluctuations (easier to control) Keeps loop cold for fast response
Sizing
• •
Sizing critical when at chillers/pumps Different size if pump has VFD or not
Flow measurement
• •
Flow meter Most accurate Needed for Btu calc for staging
DP across chiller Less expensive Accuracy reduced as tubes foul One required for each chiller 23
Primary CHW Pump Options
Headered Pumping Advantages: Dedicated Pumping Advantages: • Better redundancy • Less control complexity • Custom pump heads w/ unmatched chillers • Valves can “soft load” chillers with primary-only systems • Usually less expensive if each pump is • Easier to incorporate stand-by pump adjacent to chiller served • Pump failure during operation does not cause multiple chiller trips 24
Balancing Variable Flow Systems
25
Balancing Issues
Ensure “adequate” flow available at all coils to meet loads
•
Ensure differential pressure across control valves is not so high as to cause erratic control
• •
Less than design flow may be “adequate” most of the time
“Two-positioning” Unstable control at low loads
Cost considerations
• • •
First costs (installed costs and start-up costs) Pump energy costs (peak demand and annual) Rebalancing costs (if any) as coils are added to system 26
Balancing Options 1.
2.
3. 4. 5. 6. 7. 8.
No balancing
•
Relying on 2-way control valves to automatically provide balancing
Manual balance
• •
Using ball or butterfly valves and coil pressure drop Using calibrated balancing valves (CBVs)
Automatic flow limiting valves (AFLVs) Reverse-return Oversized main piping Undersized branch piping Undersized control valves Pressure independent control valves 27
Option 5: Oversized Main Piping Advantages • No balancing labor • Coils may be added/ subtracted without rebalance • Reduced overpressurization of control valves close to pumps • Lowest pump head/ energy due to oversized piping, no balance valves • Increased flexibility to add loads due to oversized piping
Disadvantages • Added cost of larger piping
28
Option 6: Undersized Branch Piping
Advantages • No balancing labor • Reduced cost of smaller • •
piping Coils may be added/ subtracted without rebalance Reduced overpressurization of control valves close to pumps where piping has been undersized
Disadvantages • Limited effectiveness and
• • • •
applicability due to limited available pipe sizes High design and analysis cost to determine correct pipe sizing Reduced flexibility to add coils where piping has been undersized Coils may be starved if variable speed drives are used without DP reset Slightly higher pump energy depending on flow variations and pump controls 29
Option 7: Undersized Control Valves
Advantages • No balancing labor • Reduced cost of smaller
• •
•
control valves Coils may be added/ subtracted without rebalance Reduced overpressurization of control valves close to pumps where control valves have been undersized Improved valve authority which could improve controllability where control valves have been undersized
Disadvantages • Limited effectiveness and
• • •
applicability due to limited available control valve sizes (Cv) High design and analysis cost to determine correct control valve sizing Coils may be starved if variable speed drives are without DP reset Slightly higher pump energy depending on flow variations and pump controls
30
Option 8: Pressure Independent Control Valves
Advantages • No balancing labor • Coils may be added/
• • • •
subtracted without rebalance No over-pressurization of control valves close to pumps Easy valve selection – flow only not Cv Perfect valve authority will improve controllability Less actuator travel and start/stop may improve actuator longevity
Disadvantages • Added cost of strainer • • • •
and pressure independent control valve Cost of labor to clean strainer at start-up Higher pump head and energy due to strainer and pressure independent control valve Valves have custom flow rates and must be installed in correct location Valves can clog or springs can fail over time 31
PICVs May Improve ΔT?
NBCIP Test Lab (as reported by manufacturer)
32
Ranks Balancing Method
Controllability (all conditions)
Pump Energy Costs
First Costs
1
No balancing
7
3
3
2
Manual balance using calibrated balancing valves
4
6
6
3
Automatic flow limiting valves
4
Reverse-return
5
Oversized main piping
6
Undersized branch piping
7
Undersized control valves
7 2 3 6 5
7 2 1 4 4
7 5 4 2 1
8
Pressure independent control valve
1
78
8
33
Conclusions & Recommendations for Variable Flow Hydronic Systems
Automatic flow-limiting valves and calibrated balancing valves are not recommended on any variable flow system
•
Reverse-return and oversized mains may have reasonable pump energy savings payback on 24/7 chilled water systems Undersizing piping and valves near pumps improves balance and costs are reduced, but significant added engineering time required Pressure independent valves should be considered on very large systems for coils near pumps
• •
Few advantages and high first costs and energy costs
Cost is high but going down now with competition When costs are competitive, this may be best choice for all jobs
For other than very large distribution systems, option 1 (no balancing) appears to be a reasonable option to consider
•
Low first costs with minimal or insignificant operational problems
34
Problems Caused by Degrading ∆T
Q= 500 X GPM X ΔT
For a given load Q, when ΔT goes down, GPM goes up
Result:
• • •
Increases pump energy Can require more chillers to run at low load, or coils will be starved of flow Can result in reduced plant effective capacity: chiller capacity without the capability of delivering it
35
ΔT Degradation in Large Chiller Plant (January through March)
Design ΔΤ=10oF
9.5°F-10.0°F
Evaporator Delta T (°F)
Coincident Wet Bulb Ranges 7.0°F-7.5°F
35°F-40°F 40°F-45°F 45°F-50°F 50°F-55°F 55°F-60°F
4.5°F-5.0°F
2.0°F-2.5°F
0
100
200
300
400 Approximate hrs/yr
500
600
700
800
∆T Conclusions Design,
construction, and operation errors that cause low ΔT can and should be avoided But other causes for low ΔT can never be eliminated Conclusion: At least some ΔT degradation is inevitable Therefore: Design the CHW Plant to allow for efficient chiller staging despite degrading ΔT 37
Some Solutions
Design CHW distribution system so chillers can have increased flow so they can be more fully loaded at low ΔT
• Primary-only pumping • Unequal chiller and primary pump sizes, headered • •
pumps so large pump can serve small chiller Low design delta-T in primary loop Insures low ΔT in secondary Higher primary loop first costs & energy costs
Primary/secondary pumping with check valve in common leg
38
Check Valve in the Common Leg
CHECK VALVE IN COMMON LEG
39
Supposed Disadvantages Check Valve in Common Leg
Circuits are not hydraulically independent
•
So what?
•
Seldom a real problem - pump capabilities usually fall off fast enough due to high chiller ΔP Maximum flow rates are usually arbitrary – occasional excursions should not be a problem Resolved by using high design ΔTs (or adding auto-flow limiting valves at chillers as last resort)
Flow rate may exceed maximum allowed by chiller manufacturer
• •
Pumps in series may force control valves open
•
Not true with variable speed driven secondary pumps.
Primary pumps may ride out their curves and overload
•
Seldom a real problem - pump capabilities usually fall off fast enough due to high chiller ΔP, and motor may be selected to avoid this problem. 40
Real Disadvantages Check Valve in Common Leg
Possible
dead-heading secondary pumps if primary pumps are off and chillers isolation valves are closed
• Logically interlock secondary pumps to primary pumps
flow through inactive chillers with dedicated pumps
“Ghost”
• Use isolation valves rather than dedicated pumps 41
Check Valve in the Common Leg
Recommendation
• For fixed speed chillers with ∆T problems, a check
•
valve in the common leg can help. Make sure pump design/controls address secondary pump deadheading and ghost-flow issues. Select a check valve with low pressure drop (i.e. swing check, not spring) For variable speed chillers, do not put check valve in common leg. It has little value (unless ΔT degradation is severe) since chiller plant will not be inefficient by staging chillers on before they are fully loaded 42
Condenser Water Distribution Systems
43
Condenser Water Systems Old
paradigm: constant flow & speed New paradigm: variable flow & speed
• Control logic to maximize efficiency?
44
Variable Speed CW Pumps
VSCW
CSCW 45
Condenser Water Pump Options
Dedicated Pumping Advantages: • Less control complexity • Custom pump heads w/ unmatched chillers • Usually less expensive if each pump is adjacent to chiller served and head pressure control not required
Headered Pumping Advantages: • Better redundancy • Valves can double as head pressure control • Easier to incorporate stand-by pump • Can operate fewer CW pumps than chillers for fixed speed pumps 46
Tower Isolation Options
1.
Select tower weir dams & nozzles to allow one pump to serve all towers
• • • 2. 3.
Always most efficient Almost always least expensive Usually possible with 2 or 3 cells
Install isolation valves on supply lines only
•
Need to oversize equalizers
Install isolation valves on both supply & return
•
Usually most expensive but fail safe 47
Non-integrated water-side economizer (WSE) Try to avoid this!
Twb 36F Twb 41F
44F
You have to shut off the economizer to satisfy the load!
44F
44F 49F
44F >46F
60F
41F 46F
Heat Exchanger in parallel with chillers
Integrated water-side economizer Twb 41F
You can use either a control valve or pump
44F
44F
46F
100 gpm)
Any
None
Variable
Small (< 100 gpm)
Low (< 40 feet)
3-way
Constant or Staged
Primary-only
Small (< 100 gpm)
High(> 40 feet) Variable
Primary-only Or Primary-Secondary
Few (2 to 5) serving similar loads or system has only one chiller Few (2 to 5) serving similar loads Many (more than 5) or few serving dissimilar loads
Small (< 100 gpm)
2-way Any
Primary/ distributed secondary Primary/coil secondary
55
Primary/Secondary Secondary Pump w/ VFD at Chiller Plant
2-Way Control Valves at AHUs
56
Primary/Distributed Secondary Distributed Secondary Pump w/ VFD Typical at each Building No Secondary Pumps at Plant
Central Plant 57
Advantages of Distributed P/S versus Conventional P/S or P/S/T Reduced
pump HP - each pump sized for head from building to plant Self-balancing No over-pressurized valves at buildings near plant Reduced pump energy, particularly when one or more buildings are off line No expensive, complex bridge connections used in P/S/T systems Similar or lower first costs 58
Primary/Coil Secondary Distributed Secondary Pump w/ VFD Typical at each AHU No Secondary Pumps at Plant
No Control Valves at AHUs Large AHU-1
Large AHU-2
59
Hybrid Systems
Advantages of VFD Coil Pumps versus Conventional P/S system
Reduced pump HP
• •
Each pump sized for head from coil to plant Eliminated 10 feet or so for control valves
Self-balancing
•
No need for or advantages to balancing valves, reverse return
Lower pump energy
• •
No minimum DP setpoint Pump efficiency constant
Better control
• •
Smoother flow control - no valve hysteresis No valve over-pressurization problems
Usually lower first costs due to eliminated control valves, reduced pump and VFD HP 61
Disadvantages of VFD Coil Pumps Versus Conventional P/S system Cannot
tap into distribution system without pump
• May be problem with small coils (low flow, high head pump)
Possible
reduced redundancy/reliability unless duplex coil pumps are added Possible low load temperature fluctuations
• Minimum speed on pump motor • May need to cycle pump at very low loads
62
Primary-only System Headered Pumps & Auto Isolation Valves Preferred to Dedicated Pumps: • Allows slow staging • Allows 1 pump/2 chiller operation • Allows 2 pump/1 chiller operation if there is low ΔT
BYPASS VALVE
Flow Meter or DP Sensor Across Chiller
63
Advantages of Primary-only Versus Primary/Secondary System Lower
first costs Less plant space required Reduced pump HP
Reduced pressure drop due to fewer pump connections, less piping Higher efficiency pumps (unless more expensive reduced speed pumps used on primary side)
Lower pump energy Reduced connected HP “Cube Law” savings due to VFD and variable flow through both primary and secondary circuit 64
Pump Energy Primary vs. Primary/Secondary (3-chiller plant) 40.00 35.00 30.00
Pump kW
25.00
Primarysecondary
20.00 15.00 Primary-only 10.00 5.00
%
0.00 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % GPM
65
Disadvantages of Primary-only Versus Primary/Secondary System
Failure of bypass control
• Not as fail-safe - what if valve or controls fail? • Must avoid abrupt flow shut-off (e.g. valves interlocked •
with AHUs all timed to stop at same time) Must be well tuned to avoid chiller short-cycling
Flow fluctuation when staging chillers on
• Flow drops through operating chillers • Possible chiller trips, even evaporator freeze-up • Must first reduce demand on operating chillers and/or slowly increase flow through starting chiller; causes temporary high CHWS temperatures
(Problems above are seldom an issue with very large plants, e.g. more than 3 chillers)
66
Primary-only System Staging 0 GPM
0 GPM
1000 GPM
67
Primary-only System Staging 0 GPM
500 GPM
500 GPM
68
Variable Flow Primary/Secondary with CHW Storage
Advantages
• • • • •
Peak shaving Simplifies chiller staging Provides back-up for chiller failure Secondary water source for fire department Secondary water source for cooling towers
Disadvantages
• •
Installed cost Space
69
Primary-only vs. Primary/Secondary
Use primary-only systems for:
• Plants with many chillers (more than three) and with
•
fairly high base loads where the need for bypass is minimal or nil and flow fluctuations during staging are small due to the large number of chillers; and Plants where design engineers and future on-site operators understand the complexity of the controls and the need to maintain them.
Otherwise use primary-secondary
• Also for plants with CHW storage
70
Pipe Sizing
Pipe Sizing Need
to balance
• Cost of pipe and its installation • Cost of pump energy • Longevity of piping (erosion) • Noise • Sometimes space limitations
72
Accurately sizing pump head
Guessing at pump heads
• •
Wastes money in oversized pumps, motors and (sometimes) VFDs and (sometimes) need for impeller trimming Wastes energy (minor impact w/VFD or if impeller is trimmed)
Calculating pump heads
•
Takes about 20 minutes of engineering time
Guessing cannot possibly be cost effective!
73
Optimum ΔT
Flow Rate and ΔT
Q = 500 GPM ΔT Load from Load Calc’s (Btu/hr)
Flow rate (GPM)
Conversion “constant” =8.33 lb/gal * 60 minutes/hr
Temperature Rise or Fall (ºF)
75
CHW ΔT Tradeoffs ΔT Low
High
Typical Range
8°F
25°F
First Cost Impact
smaller condenser
smaller pipe smaller pump smaller pump motor
Energy Cost Impact
lower fan energy
lower pump energy
76
Coil Performance with ΔT Chilled Water ΔT Coil water pressure drop, feet H2 O Coil airside pressure drop, inches H 2 O
11 28
13 20
15 15
18 10
20 8.1
0.46 0.48 0.49 0.52 0.54
43°F chilled water supply temperature, 78°F/62°F entering air and 53°F leaving air temperature.
77
System Performance With ΔT Varying Airside Pressure
1200 CHP Energy kWh/year Chiller Energy kWh/year
1000
Fan Energy kWh/year
kWh/ton/year
800
600
400
200
0 11
13
15
18
20 CHW Delta-T
CHWST = 44F 78
System Performance and ΔT Constant Airside Pressure
1400
CHP Energy kWh/year Chiller Energy kWh/year
1200
Fan Energy kWh/year
kWh/ton/year
1000 800 600 400 200 0 41/16
42/14
43/12
44/10 CHWST/Delta-T 79
Choosing the “Right” CHW ΔT
Both energy and first costs are almost always minimized by picking a very high ΔT (>18°F to 25°F) Savings even greater with systems that have
• Large distribution piping network • Water-side economizers • CHW thermal energy storage
80
Condenser Water (Tower) Range at Constant CWST ΔT Low
High
Typical Range
8°F
18°F
First Cost Impact
smaller condenser
Energy Cost impact
lower chiller energy
smaller pipe smaller pump smaller pump motor smaller cooling tower smaller cooling tower motor lower pump energy lower cooling tower energy
81
Condenser Water Range at Constant Tower Fan Energy
600 Tower Fan CW pump
kWh/ton/year
500
Chiller
400 300 200 100 0 73/16
73.5/14
74.5/12
75.5/10 CWST/Delta-T 82
COOLING TOWER SELECTION DOE 2 Curve: Percent rated capacity at 70.0°F wet bulb
2 X design capacity Design capacity 210%
% Design Capacity
200%capacity 1/2 of design 190% 180% 170% 160% 150% 140% 130% 120% 110% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
19 17 15 1
13 2
3
4
11 5 Range (°F)
6
9 7
8
Approach (°F)
200%-210% 190%-200% 180%-190% 170%-180% 160%-170% 150%-160% 140%-150% 130%-140% 120%-130% 110%-120% 100%-110% 90%-100% 80%-90% 70%-80% 60%-70% 50%-60% 40%-50% 30%-40% 20%-30% 10%-20% 0%-10%
7 9
10
5 11
83
Cooling Tower Selection Fan
Control Efficiency Approach
84
Tower Fan Control One Cell Tower
Single Speed Fan
% Power
Free Cooling ~ 15% of Capacity
Two-Speed or Variable-Speed Fan
% Capacity
85
Tower Fan Control Two Ce ll Towe r 100%
Two Cell Tower 90%
Two 1-Speed Fans
80%
70%
One 1-Speed Fan and One 2-Speed Fan
% Power
60%
50%
40% Two 2-Speed Fans 30% Two Variable Speed
Free Cooling Below 15% Capacity
20%
10%
0% 0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
% Capacity
60%
65%
70%
75%
80%
85%
90%
95%
100 %
86
Tower Fan Control
One-speed control is almost never the optimum strategy regardless of size, weather, or application VFD fan speed control is best choice now
• • • • •
Costs now comparable to two speed motors & starters Soft start reduces belt wear Lower noise Control savings for DDC systems (network card options) More precise control
Multiple cell towers should have speed modulation on at least 2/3 of cells (required by ASHRAE 90.1). For redundancy, use VFDs on all cells
87
Tower Efficiency LCC
1000 ton Oakland Office
90 GPM/HP
70 GPM/HP
50 GPM/HP 88
Tower Efficiency Guidelines
Use Propeller Fans
• Avoid centrifugal except where high static needed or •
where low-profile is needed and no prop-fan options available Consider low-noise propeller blade option and high efficiency tower where low sound power is required
Efficiency
Approach
• Minimum 80 gpm/hp for commercial occupancies • Minimum 100 gpm/hp for 24/7 plants (data centers) • Maximum 10°F for large central plants • 3°F for 24/7 plants (data centers) 89
Break
CHILLER SELECTION
Part-Load Ratio
91
Chiller Procurement Approaches Most
Common Approach
• Pick number of chillers, usually arbitrarily or as limited by program or space constraints • Take plant load and divide by number of chillers to get chiller size (all equal) • Pick favorite vendor • Have vendor suggest one or two chiller options • Pick option based on minimal or no analysis • Bid the chillers along with the rest of the job and let market forces determine which chillers you actually end up installing
92
Chiller Procurement Approaches Better
Approach
• Estimate plant annual load profile • Understand chiller efficiency curves • Request chiller options from multiple
manufacturers based on a performance desired. Multiple options encouraged. • Estimate energy usage of options with a detailed computer model of the building/plant
93
Sample Load Profile 800
700
Hours per year
600
500
Percent Load
400
300
200
100
0
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
94
Chiller Procurement Approaches Another
Option
• Pick a short list of vendors based on past
experience, local representation, etc. • Request chiller bids based on a performance specification. Multiple options encouraged. • Adjust bids for other first cost impacts • Estimate energy usage of options with a detailed computer model of the building/plant • Select chillers based on lowest life cycle cost • Bid the chillers at end of design development phase 95
Chiller Bid Specification
Don’t Specify:
• • • • •
Number of chillers Chiller size Chiller efficiency Chiller unloading mechanism As much as possible – keep the spec flexible!
Do Specify:
• Total design load • Anticipated load profile • Minimum number of • • • • •
chillers and redundancy requirements Design CHW/CW entering and leaving temperatures and/or flows (or tables of conditions) Available energy sources Physical, electrical or other limitations Acoustical constraints Acceptable refrigerants 96
Zero Tolerance Data Do
NOT allow tolerance to be taken in accordance with ARI 550/590 Why insist on zero tolerance?
• Levels playing field – tolerances applied
inconsistently among manufacturers • Modeled energy costs will be more accurate • High tolerance at low loads makes chillers appear to be more efficient than they will be, affecting comparison with unequally sized, VFDdriven, or multiple chiller options 97
Zero Tolerance Data ARI 550/590 Tolerance Curve
45% 40% 35%
% Tolerance
30%
10F Delta-T 15F Delta-T
25%
20F Delta-T
20% 15% 10% 5% 0% 0%
20%
40%
60%
80%
100%
120%
% of Full Load
98
Factory Tests Certified
Factory Tests
• Need to verify performance to ensure accurate claims by chiller vendors in performance bids • Field tests are difficult or impossible and less accurate • Last chance to reject equipment
99
Chiller Bid Evaluation Adjust
for First Cost Impacts Estimate Maintenance Costs Calculate Energy Costs
• Energy model of building(s) and plant
Calculate
Life Cycle Costs Temper Analysis with Consideration for “Soft” Factors Final Selection
100
Advantages & Disadvantages OF RECOMMENDED CHILLER SELECTION APPROACH
Disadvantages
• Extra work for both engineer and vendor • Difficult to include maintenance impact • Assumes energy rate schedules will remain as they are now with simplistic adjustments for escalation
Advantages
• Allows manufacturers to each find their own
“sweet” spots, both for cost and efficiency • Usually higher energy efficiency • More rational than typical selection approaches 101
OPTIMIZING CONTROLS
102
Optimizing Control Sequences Cookbook
Solution
Relational
Control Approach
• Staging Chillers • Controlling Pumps • Chilled Water Reset • Condenser Water Reset
103
Staging Chillers
Fixed Speed Chillers
• Operate no more chillers than required to meet the • • •
load Stage on when operating chillers maxed out as indicated by measured load (GPM, ΔT), CHWST, flow, or other load indicator For primary-secondary systems w/o check valve in the decoupler, start chiller to ensure primary-flow > secondary-flow Stage off when measured load/flow indicates load is less than operating capacity less one chiller – be conservative to prevent short cycling 104
Staging Chillers, continued Variable
Speed Chillers
• Operate as many chillers as possible provided load on each exceeds 30% to 40% load • Energy impact small regardless of staging logic • You MUST use condenser water reset to get the savings
105
Part Load Chiller Performance w/ Zero ARI Tolerance
100% 90% Fixed Speed
80%
Variable Speed 70%
%kW
60% 50% 40% 30% 20% 10% 0% 0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
% Load (with Condenser Relief) 106
Controlling CHW Pumps Primary-only
Pumps
and Secondary CHW
• Control speed by differential pressure measured as far out in system as possible and/or reset setpoint by valve demand • Stage pumps by differential pressure PID loop speed signal:
Start lag pump at 90% speed Stop lag pump at 40% speed For large HP pumps, determine flow and speed setpoints with detailed energy analysis
107
VFD Pump Power vs. Setpoint 100% 90%
DP setpoint = Design Head DP setpoint = Head*.75
80%
DP setpoint =Head/2 DP setpoint =Head/3
Percent Pump kW
70%
DP setpoint = 0 (reset) 60% 50% 40% 30% 20% 10% 0% 0
10%
20%
30%
40%
50%
60%
Percent GPM
70%
80%
90%
100%
108
Chilled Water Setpoint Reset
Reset Impacts
• •
Resetting CHWST upwards reduces chiller energy but will increase pump energy in VFD variable flow systems Dehumidification Reset with “open” or indirect control loops (e.g. OAT) can starve coils and reduce dehumidification Reset by control valve position will never hurt dehumidification − humidity of supply determined almost entirely by supply air temperature setpoint, not CHWST
Recommendations
• •
Reset from control valve position using Trim & Respond logic For variable flow systems with VFDs Reset of CHWST and VFD differential pressure setpoint should be sequenced − not independent like VAV systems since control valves are pressure-dependent Sequence reset of CHWST and DP − next slide…
109
CHWST/DP Setpoint Reset for VSD CHW System DPmax
Tmin+ 15ºF
DP setpoint
CHW setpoint DP setpoint
CHW setpoint
Tmin
5 psi 0
50% CHW Plant Reset
100%
Back off on CHWST first Then back off on DP setpoint 110
CHW vs. DP Setpoint Reset
Plant with 150 ft CHW pump head 111
Condenser Water Setpoint Reset
Optimum Strategy Cannot Easily Be Generalized
• •
Depends on efficiency/sizing of tower and type of chiller Relational control by monitoring plant efficiency
Recommendations
• •
CWS reset by plant load from [as low as manufacturer recommends] at 30% plant load up to [design CWST] at 80% load Reset based on wetbulb temperature not effective given inaccuracy of sensors
112
Optimum Sequences All
plants are different
• Tower efficiency, approach • Chiller efficiency, unloading control • Pump efficiency, head, unloading control • Number of chillers, pumps, towers
A
generalized sequence can be developed but it will not be optimum Solution? 113
Summary
In this course, you have learned techniques to design and control chiller plants for nearminimum life cycle costs, including:
• • • • •
Selecting optimum chilled water distribution system Selecting optimum CHW supply & return temperatures Selecting optimum CW and tower range and approach temperatures, tower efficiency, and fan speed controls Selecting optimum chillers using a performance bid and LCC analysis Optimizing control sequences and setpoints
114
Questions
115