Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

Revision

2

State

Released

Change Control Process

Purpose:

This Operating Procedure describes the Change Control process in ESS

This OP is applicable to:

This applies to all staff working within the ESS Programme and its underlying Projects.

Process owner:

Quality Function

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

TABLE OF CONTENTS 1.

General Prciples ............................................................................................... 3

2.

Classification.................................................................................................... 3

3.

Change Control Process ................................................................................... 4

3.1

Process Map ..........................................................................................................4

3.2

Process Details Change Request ..............................................................................4

3.2.1

Start – Assign Change Leader...............................................................................4

3.2.2

Create Change Request........................................................................................5

3.2.3

Assess CR ...........................................................................................................5

3.2.4

Review ...............................................................................................................5

3.2.5

Level 5 Decision ..................................................................................................6

3.2.6

Level 1-4 Decision ...............................................................................................6

3.3

Process Map Sub-process Implement Engineering Change .........................................6

3.3.1

Define Activities ..................................................................................................7

3.3.2

Execute ..............................................................................................................7

3.3.3

Review ...............................................................................................................7

3.3.4

Release ..............................................................................................................7

3.3.5

End of Process ....................................................................................................7

3.4

Process Map Sub-process Implement General Change ...............................................8

3.4.1

Carry out change activities ...................................................................................8

3.4.2

Verify intended outcome and impact .....................................................................8

3.4.3

Release change ...................................................................................................8

3.4.4

End - close CR.....................................................................................................9

4.

List of Abbreviations ........................................................................................ 9

5.

References ....................................................................................................... 9

Event symbols

Process map symbols

Input to the process

Start event/trigger

Output from the process

End of process/end event

Approval step

x.y

Related information in an OPI Template

Activity Gateway/Decision Point

x.y

2(9)

Process

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

1.

GENERAL PRCIPLES

The establishment of a Change Control process ensures traceability of all changes, identification of programme configuration and management decisions, ensures appropriate information is available throughout the life of the project and that changes are properly assessed and managed. The Configuration controller is responsible for administration and coordination of the overall baseline change control system. The Project Managers are responsible for implementing approved changes according to the set implementation schedule. 2.

CLASSIFICATION

Changes to released configuration items are accomplished through the change control process. Changes are managed in accordance with the approval process. Level of Change are classified according to the authority level required for approval and are defined for Level 1-5 in table 1. The ESS Delegation and Authorisation matrix governs the authority for decision making within ESS. In figure 1 the distribution of authority relating to changes in technical, cost and schedule baseline is elaborated. Table 1: Hierarchy of approvals in Change Control Level of change related to the Approving entity

Technical Baseline

Schedule Baseline

Cost Baseline

Level A

Changes that impact the technical requirements of the programme charter

Changes that impact the programme milestones

Changes that impact the costs related to the facility life cycle (construction, operation and decommissioning).

Changes that impact the facility requirements and interfaces.

Changes that impact the critical path of the programme (composition).

Changes that impact the contingencies the costs related to the facility life cycle.

Changes that impact the configuration items for several ESS systems.

Changes that impact the critical path of a project (composition and/or duration).

Balanced changes to cost with no impact on total cost.

ESS Board

Level B EPG Level C CCB Programme

Changes that may impact the general safety and environmental objectives.

3(9)

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

Level of change related to the Approving entity

Technical Baseline

Schedule Baseline

Cost Baseline

Level D

Changes that impact the configuration items for several work packages.

Changes to schedule with impact within the single project.

Balanced changes to Cost within the Project.

Changes that impact the design of a system but do not change the ability of that system to meet its functional and design requirements. Changes to correct clerical errors or to add clarification to documents are also classified as Level 5.

Changes to schedule with impact within the single work package.

Balanced changes to Cost within the Work Package.

CCB Project

Level E Chief Engineer of the system and/or WP Leader

Figure 1

Hierarchy of approvals in Change Control

3.

CHANGE CONTROL PROCESS

3.1

Process Map

CHANGE REQUEST

Rejection IMPLEMENT GENERAL CHANGE CREATE CR

ASSESS CR

Review

OK

CCB

Go ahead

Escalate to other CCB

IMPLEMENT ENGINEERING CHANGE

More information required

3.2

Process Details Change Request

3.2.1

Start – Assign Change Leader

Any person can detect a need for a change in the technical, cost or schedule baselines. This is communicated to the relevant WPL / PM as soon as possible. WPL / PM assigns a Change Leader. This person may vary depending on the nature of the change. The change can be reassigned to another change leader at any time if required.

4(9)

Responsible: WPL / PM

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

Assess if the change can be introduced and documented in a system supporting the change control process. 3.2.2

Create Change Request

Formally open the Change Request (CR) in CHESS and notify the Configuration Managers (Champions of CC).

Responsible: Change Leader

Fill in mandatory attributes in the form. Describe the proposed change in sufficient detail by using the Change request form presented in CHESS. When finalised the document is attached to the CR in CHESS 3.2.3

CREATE CR

Assess CR

Initial assessment

Responsible:

Make an initial impact analysis in terms of:

Change Leader

! ! ! ! ! ! !

Technical feasibility Performance Safety Interfaces Cost Schedule Risk

ASSESS CR

The impact analysis is documented in the CR form. In case additional documentation, reports, rationales etc is needed these are attached to the CR in CHESS along with the Change Request Form Depending on the result of the initial impact analysis establish a preliminary Change Level according to the criteria in table 1, and document it in the CR in CHESS. Promote the CR to the evaluator(s) Deeper assessment (performed if needed for Level 1-4 changes) Perform a more extensive analysis of the change. Summarise advantages and disadvantages and conclude on a recommendation to proceed. Document the findings in the Change Request or in a report associated to the Change Request in CHESS. 3.2.4

Review

Review the CR. Advise the change leader on any need of further elaboration. Confirm Change Level. When the CR is reviewed as complete accept or reject the CR in

5(9)

Responsible: Evaluator Review

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

CHESS. 3.2.5

Level 5 Decision

Level 5 Changes: Approve, reject or ask for more information. If approved, promote the change to the Change Leader for planning and implementation of the activities related to the change.

Responsible: Evaluator

Level 1-4 Changes: Promote the change to the chairman of the relevant change board or reject the change. If the change needs a deeper assessment before being promoted to the relevant change board promote the change to the Change Leader for additional assessment according to 3.2.3. 3.2.6

CCB

Level 1-4 Decision Responsible:

Make the decision: Yes, the change request is accepted to proceed to implementation. Document the decision in the CR in CHESS and promote the CR to the Change Leader for implementation.

Level 1: Board

!

No, the change request is rejected. Document the decision in the CR in CHESS.

Level 4: CCB Project

!

The analysis needs to be improved before a decision can be made. Promote the change to the Change Leader for additional information.

!

Level 2: EPG Level 3: CCB Progr.

or

Document the decision in the CR in CHESS.

3.3

Process Map Sub-process Implement Engineering Change

6(9)

CCB

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

3.3.1

Define Activities

Open Change Order(s) to manage change activities.

Responsible:

Go through the Change as described in the Change Request.

Change Leader/Senior Design Engineer/Lead Design Engineer

Ensure that the ECO contains the right Parts and Documentation. Describe the activities needed to achieve the change. Plan the activities. Promote the ECO to Lifecycle state Design Work.

3.3.2

DEFINE ACTIVITIES

Execute

Execute the Design Work according to the requested changes and requirements. Add additional Parts and Specifications if necessary. Ensure the Design Work is ready for the review.

Responsible: Change Leader/Senior Design Engineer/Lead Design Engineer EXECUTE

3.3.3

Review

Lead Design Engineer ensures that the work fulfils the requested change and the Requirements.

Responsible: Lead Design Engineer Review

3.3.4

Release Responsible:

Perform Design Review

Lead Design Engineer/Change Leader Rel.

3.3.5

End of Process

Close Change Order

Responsible:

Close related Change Request

Lead Design Engineer/Change Leader

7(9)

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

3.4

Process Map Sub-process Implement General Change

IMPLEMENT GENERAL CHANGE Cancellation

DEFINE ACTIVITIES

EXECUTE

Rev.

OK

Rel.

Approved

Continue Work

3.4.1

Carry out change activities

Open Change Order(s) to manage change activities.

Responsible:

If the change is introduced into a system supporting the change control process continue the process in the system.

Change Leader

When no relevant predefined process is available use the Change Order section of the template in appendix 1.

DEFINE ACTIVITIES

Describe the activities needed to achieve the change. Plan the activities.

EXECUTE

Assign the Change Order to persons responsible to perform the activities. Follow up on progress. Notify Configuration Controller when finalised. 3.4.2

Verify intended outcome and impact

Verify that the result of the change is in line with the original intentions. Verify that the impact analysis still is correct. The verification is documented in the Change Request form. 3.4.3

Responsible: Configuration Controller Review

Release change

Evaluate when the Change can be released.

Responsible:

Release the Change.

Configuration Manager

Notify concerned stakeholders

Rel.

8(9)

Operating Procedure Document Number

ESS-0001879

Date

Oct 8, 2013

3.4.4

End - close CR Responsible:

Close the Change Request.

Configuration Manager

4.

LIST OF ABBREVIATIONS

Abbreviation

Definition

CCB

Change Control Board

CO

Change Order

CR

Change Request

EPG

ESS Programme Group

PM

Project Manager

WP

Work Package

WPL

Work Package Leader

WU

Work Unit

WUL

Work Unit Leader

5.

REFERENCES

1.

Configuration Management Policy, Document Number

2.

ESS authorisation and delegation matrix, Document number

9(9)