Construction Proposal j. allen smith Design/ Build LLC. September 21, 2006 Moore Kitchen 6676 ABC Blvd. XYZ, Virginia 55555 j. allen smith Design/ B...
Author: Milo Sanders
74 downloads 0 Views 120KB Size
Construction Proposal j. allen smith Design/ Build LLC.

September 21, 2006 Moore Kitchen 6676 ABC Blvd. XYZ, Virginia 55555

j. allen smith Design/ Build LLC. 2510 Urbana Pike Suite 107 Ijamsville, Maryland 21754 301-810-5247– 301-874-2986

Proposal September 21, 2006 Between the Owner: Moore 6676 ABC Blvd. XYZ, Virginia 55555 555-555-555 And the Contractor: j. allen smith Design/ Build LLC. 2510 Urbana Pike Suite 107 Ijamsville, Maryland 21754 MHIC# 123776 V.A. # Class A- 132334A D.C.# Class C- 70101168 301-810-5247 For the Project: Moore Kitchen 6676 ABC Blvd. XYZ, Virginia 55555

Scope of Work: Provide labor ad materials to complete the kitchen renovation as shown on plan set from SDI dated 2/17/12. -DEMOLITION Remove all appliances and discard. (Save existing dishwasher, and garbage disposal and store safely for re-use. Remove all existing kitchen cabinetry and counter tops and discard. Remove existing knee wall and related parts. Remove existing railing on all stairs, foyer and balcony. Remove hardwood flooring throughout 1st floor. Remove existing sink and faucet and discard. Remove existing floor registers. -CONSTRUCTION CLEAN-UP JAS D/B will keep job site kept clean and safe throughout project duration. The home will be broom swept at the end of every day and vacuumed at the end of every work week prior to weekend or more often as needed. The site will be protected with zip walls at key points in the process to reduce dust migration to the rest of the home. Homeowner will need to provide space for a 30 yard construction waste container to be stored on site. All materials disposed of are recycled. :-) -HVAC Relocate (2) air supply vents into nearby cabinet bases.

-PLUMBING Disconnect and reconnect all kitchen plumbing fixtures and reinstall new in same locations. -ELECTRICAL Install plug mold at underside of wall cabinetry. Add switch to control under cabinet lighting. Reinstall disposal switch in new island. Reinstall outlet in new island. Add (1) new outlet in island. Relocate (1) recessed light to center of new island and tie into existing light circuit. Add (3) new recessed lights in the kitchen to the existing circuit. Add (4) new recessed lights in the family room. Move surface mounted light to be centered over table, Dim. TBD by SDI at time of rough-in. -INSULATION & DRYWALL Patch and point up all drywall with-in the kitchen and adjacent room to be painted. -INTERIOR TRIM & STAIRS Remove all existing hand rails to be replaced with new rails as speced. and drawn by SDI. Knoll posts and balusters to be paint grade, rails to be Brazilian cherry. Replace and install any base moulding needed up to new cabinetry to match existing. -TILE & CERAMICS Supply and set tile back splash as drawn by SDI. -FLOORCOVERING Remove all existing hardwood on 1st fl. Install new 5" Brazilian cherry, stain and finish w/ (3) top coats poly. Install new matching shoe moulding. -CABINETRY & COUNTER TOPS Install all cabinetry and cabinet accessories. Template, supply and install granite tops, slabs to be selected and approved by SDI. -INTERIOR FINISHES Spot prime all drywall repairs and point up areas. Apply (2) top coats of Benjamin Moore Latex paint in matte finish. Paint all new trim to match existing. -APPLIANCES Supply and Install SDI. speced appliances per. schedule. -ADMINISTRATION Provide project management resources to keep the project on schedule and on budget. Supervise all trades involved.

Special Conditions: JAS D/Bt to provide all cabinetry and cabinet accessories including cabinet pulls and trash pull-out. Client to provide kitchen faucet and sink. Client to provide all appliances. Project schedule to be built around hardwood install, sand and finish to be performed in the last (2) weeks of June dependent on contract being signed by May 1st to ensure timely cabinet delivery. Project duration to be no longer then (5) weeks.

Total Base Price:

$103,489.80

Standard Allowances (included in base price):

Project Totals: 02 Demolition 02L Demolition Labor 02O Demolition Removal Other Subtotal 02 Demolition

$3,001.09 $579.74 $3,580.83

03 Construction Clean Up 03L Construction Clean Up Labor 03M Construction Clean Up Materials Subtotal 03 Construction Clean Up

$1,295.87 $41.06 $1,336.93

08 HVAC System 08L HVAC System Labor 08M HVAC System Materials Subtotal 08 HVAC System

$341.02 $86.75 $427.77

09 Plumbing Systems 09L Plumbing Labor

$136.41

09L Plumbing Labor

$272.81

09M Plumbing Materials Subtotal 09 Plumbing Systems

$72.30 $481.52

10 Electrical Systems 10M Electrical Materials

$1,393.54

10S Electrical Subs

$2,087.03

10S Electrical Subs

$1,227.66

Subtotal 10 Electrical Systems

$4,708.23

13 Insulation & Drywall 13.2L Drywall Labor Subtotal 13 Insulation & Drywall

$272.81 $272.81

15 Interior Trim & Stairs 15L Int. Trim & Stairs Labor

$80.37

15M Int. Trim & Stairs Materials

$57.84

15S Int. Trim & Stairs Subs Subtotal 15 Interior Trim & Stairs

$8,457.24 $8,595.44

16 Tile & Ceramics 16L Tile & Ceramics Labor

$436.93

16M Tile & Ceramics Materials

$973.68

Subtotal 16 Tile & Ceramics

$1,410.61

17 Floorcovering 17S Floorcovering Subs

$27,390.53

Subtotal 17 Floorcovering

$27,390.53

18 Cabinetry & Countertops 18.1L Cabinetry Labor 18.1M Cabinetry Materials

$4,400.76 $40,927.05

18.2S Countertop Subs

$1,364.07

18.2S Countertop Subs

$5,393.53

Subtotal 18 Cabinetry & Countertops

$52,085.42

19 Interior Finishes 19L Interior Finishes Labor 19M Interior Finishes Materials Subtotal 19 Interior Finishes

$1,364.34 $795.25 $2,159.60

22 Appliances 22L Appliance Labor

$767.29

Subtotal 22 Appliances

$767.29

29 Administration 29.1L Administration Labor

$272.81

Subtotal 29 Administration

$272.81

GRAND TOTAL

$103,489.80