BILL OF QUANTITIES DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT - PHASE 3B

BILL OF QUANTITIES DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM 1.0 DESCRIPTION QTY UNIT 1 lot D...
Author: Dorothy Boyd
6 downloads 1 Views 303KB Size
BILL OF QUANTITIES DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM 1.0

DESCRIPTION

QTY

UNIT

1

lot

DETAILED ENGINEERING DESIGN Complete design of Clark - Mexico 230kV Double Circuit Transmission Line, Expansion of Clark and Mexico 230kV Substations, Expansion of Clark Substation Control House, and the Proposed Clark Substation Warehouse in accordance with PEC, IEC, ANSI, NESC, NBC, NSCP and DPWH Design Standards Compliance to NGCP requirements for the submission of factory tests, field tests, manuals, procedures and other documents for NGCP approval. Coordination and other requirements to energize the system. Permits, local and national and payments of fees and other documents as required to complete the project Compliance to the COA requirements for the submission of Detailed unit Cost Analysis of Items as listed in the Bill of Quantities Provide assistance in the R.O.W acquisition especially in the consultation/coordination with the Local Government Units and Barangay Officials having jurisdiction over the area that will be affected by the R.O.W. of the transmission line. Assists CDC on the procedure of payments and registration of property/ROW acquisition in accordance with R.A. 8974 and other applicable laws. Detailed Engineering Design Activities as per section 2 of scope of work a. Review of existing information b. Topographic and Parcellary survey c. Right of way acquisition d. Soil and material investigation e. Hydrological and hydraulic studies f. Environmental impact assessment (EIA) g. Detailed design plans and specifications h. Utility relocation plan i. Detailed estimate / unit price analysis j. Drawing submittals k. Reports Submit three (3) options of possible transmission line Alignments with cost benefit analysis, evaluation and recommendation (NLEX, existing 69 kv corridor, new route)

2.0

230 Kv TRANSMISSION LINE From Clark S/S to Mexico S/S Construction of Double Circuit (1 x 410 TSAR) on Steel poles or Steel towers, clearance over roadway as per PEC, IEC, ANSI, NESC, maximum span is 100 meters on 43 meter steel poles and 250 meters on 52 meters steel towers in accordance to the requirements of the Technical Data Sheet (TDS) and compliance to ATO requirements.

Page 1 of 15

35

KM

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM 3.0 A.

DESCRIPTION

QTY

UNIT

2

sets

4

sets

6

sets

10

sets

4

sets

14

sets

18

sets

30

sets

12

sets

CLARK SUBSTATION 230/69kV ELECTRICAL WORKS Supply, manufacture, factory testing, and furnishing of labor, equipment, tools and incidental materials for the delivery, assembly, erection, installation, field testing commissioning and ready for operation of the following substation equipment and its associated control and protection system and accessories

Bay 85 and Bay 86 At Clark 230 kV S/S A1.

A2.

A3.

A4.

A5.

A6

A7

A8

A9

Power Transformer 150 MVA Three winding autotransformer type 3-Phase 230/69kV wye-13.8 delta with neutral earthing resistor class ONAN/ONAF1/ONAF2 , complete with all appurtenances, accessories and onload tap changing mechanism with 16 taps of 0.625% above and 16 taps of 0.625% below 0 including paralleling device and control in accordance to the requirements of the Technical Data Sheet (TDS). Power Circuit Breaker Dead Tank 230kV, 3-phase, 2000A, 40, kA three pole operation, complete with the required accessories and support structure including bushing current transformers in accordance to the requirements of the Technical Data Sheet (TDS). Power Circuit Breaker Dead Tank 69kV, 3-phase, 2000A, 38 kA three pole operation, complete with the required accessories and bushing current transformer in accordance to the requirements of the Technical Data Sheet (TDS). Ganged Disconnect Switch 230kV, 3-phase, 2000A, 40KA equipped with 460 vac 3 phase motor and manually group operated, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 kA equipped with earthing blades, 230 vac motor and manually group operated, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 kA equipped with, 230 vac motor and manually group operated, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Voltage Transformer Capacitive type 230 kV, complete with the required accessories and support structure in accordance to the requirements of the Technical Data Sheet (TDS). Voltage Transformer 69 kV, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Surge Arresters 192 kV, station type, complete with support structure and the required accessories in accordance to the requirements of the Technical Data Sheet (TDS).

Page 2 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM A10.

A11.

A12.

A13

A14

A15.

A16.

A17.

A18.

A19

A20.

DESCRIPTION Surge Arresters 60 kV, station type, complete with support structure and the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Substation Gantry and Pedestal Steel Structures including bolts, washer, etc hot dipped galvanized complete with all the required accessories in accordance to the requirements of the Technical Data Sheet (TDS)

QTY 24

UNIT sets

1

lot

Metalclad Switchgear, 13.8 kv outdoor type outdoor type complete with arresters, VT, CT, breaker and 150 KVA 13.8/460 vac 3-phase transformer type ONAN Outdoor type in accordance to the requirements of the Technical Data Sheet (TDS) Installation Materials consisting of conductors, insulators, connectors, pole line hardwares, bus supports, and other accessories in accordance to the requirements of the Technical Data Sheet (TDS) Grounding Materials consisting of insulated and bare copper cables, lightning rod, copper rods, fittings. complete with the required materials for aerial and grounding mat and to substation equipment and structures in accordance to the requirements of the Technical Data Sheet (TDS). Distribution Board 125 VDC complete with enclosure, main breaker, Automatic transfer switch, tie breaker, branch breakers, and accessories for installation. Number of breakers to supply four (4) bays in accordance to the requirements of the Technical Data Sheet (TDS) Station Service Transformer 50 kva 480/230V, three phase, dry type and accessories in accordance to the requirements of the Technical Data Sheet (TDS). Distribution Board 3 Phase 460/230 VAC with enclosure, main breaker, tie breaker, automatic transfer switch, branch circuit and accessories Number of circuit breaker to include 4 additional bays, breaker to panel at bay 3 and 4, and spare breaker in accordance to the requirements of the Technical Data Sheet (TDS) Distribution Board 3 Phase 230 VAC with enclosure , main breaker, tie breaker, automatic transfer switch, branch circuit and accessories Number of circuit breaker for four (4) bays, breaker for panel at bays 3 and 4 and spare breaker in accordance to the requirements of the Technical Data Sheet (TDS) Power Control, Instrumentation and Protection Cables, 35kV, 15 kV and 600 volt insulation complete with insulated terminal lugs, glands, marking etc. in accordance to the requirements of the Technical Data Sheet (TDS) Cable Trays (various type) hot dipped galvanized, complete with supports, fittings, and other accessories in accordance to the requirements of the Technical Data Sheet (TDS). Cost of cable tray included at cable trenches

2

sets

1

lot

1

lot

2

sets

2

sets

2

sets

2

sets

1

lot

1

lot

Page 3 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM A21

A22

DESCRIPTION Switchyard Lighting System (Bay and Perimeter) complete with the required fixtures, posts, conduits, wires, magnetic contactor and photo cell, conduit fittings, conductors foundations, etc in accordance to the requirements of the Technical Data Sheet (TDS) Substation Control System a. Microprocessor Based Substation Control System (New back up set ) to include the integration of new and existing to accommodate all system (six bays). To include licensed copy of software (latest Version) and industrial type equipment for the Protection, control and monitoring of equipment for connection to SCADA, gateway, HMI and Work station. To include the integration, data base reconfiguration, parameterization of the existing and new MBSC system with BCU, and others to conform to the new set up of Clark S/S. To provide CDC with copy of license software in DVD or CD in accordance to the requirements of the Technical Data Sheet (TDS). b.

Closed Circuit Television System (New set of CCTV) new system for bays 3,4, 5, 6 and perimeter fence complete with all the required peripherals, industrial computer, accessories, wires and cable reconfiguration and integration with existing CCTV system. To include the supply and replacement of existing CCTV controller and reconfiguration. (No of PTZ dome camera arm mounted at gantry = six(6), Pole mounted Motorized pan tilt camera = two(2), CCtv player recorder controller = (2), Working station with 21 inch Monitor= two (2) and licensed software with CD or DVD in accordance to the requirements of the Technical Data Sheet (TDS).

c.

A23

Access Control and Alarm Monitoring System (ACAMS) revision / expansion/ integration of system to include new warehouse and relocation of existing affected by control building renovation d. Main Control Switchboard, with all instrument, meters, indicators, control switches, annunciators, push buttons, LED indicating lamps, terminal blocks, wiring and miscellaneous auxiliary and accessory devices Substation Protection System a. Transformer Protection ( Main 1) complete with the required protective relays and accessories in one (1) panel. Different manufacturer from Main 2 in accordance to the requirements of the Technical Data Sheet (TDS) b. Transformer Protection ( Main 2) complete with the required protective relays and accessories in one (1) panel, Different manufacturer from Main 1 in accordance to the requirements of the Technical Data Sheet (TDS) Page 4 of 15

QTY 1

UNIT lot

1

sets

1

sets

1

lot

1

lot

2

sets

2

sets

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM c.

d.

e.

d.

f.

g.

DESCRIPTION Breaker Failure Protection System Complete with the required protective relays and accessories for four (4) 230 kV Power Circuit Breakers in one panel in accordance to the requirements of the Technical Data Sheet (TDS). 230 kV Bus Protection System, Main 1 - complete with accessories for connection of new breaker 803CB24CLA and 8-04CB24CLA at Bus 8BS03CLA to existing GE B30-8BS03CLA in accordance to the requirements of the Technical Data Sheet (TDS) 230 kV Bus Protection System, Main 1 - complete with accessories for connection of new breaker 803CB08CLA and 8-04CB08CLA at Bus 8 BS04CLA to existing GE B30-8BS04CLA in accordance to the requirements of the Technical Data Sheet (TDS) 230 kV Bus Protection System, (Main 2) complete with the required protective relays and accessories for the integration of five (5) 230 kV Power Circuit Breakers (Bus Tie, Bay 3,4,5 and 6 Breakers) in accordance to the requirements of the Technical Data Sheet (TDS) 69 kV Feeder Protection System, complete with the required protective relays and accessories for the following outgoing 69 kV feeders in accordance to the requirements of the Technical Data Sheet (TDS) f.1 Three (3) 69 kV breakers with two (2) 69 kV outgoing feeders in one (1) panel f.2 Three (3) 69 kV breakers with two (2) 69 kV outgoing feeders in one (1) panel Bay Control Unit with provision for integration to existing and new Microprocessor Based Substation Control system complete with necessary accessories in accordance to the requirements of the Technical Data Sheet (TDS)

QTY 1

UNIT sets

1

sets

1

sets

2

sets

1

sets

1

sets

2

sets

2

sets

2

sets

6

units

Bay 83 and Bay 84 at Clark 230 kV S/S A24

A25

Line Protection System a. Line Protection for 230 kV system (Main 1 Distance Relay) complete with the required protective relays and accessories in accordance to the requirements of the Technical Data Sheet (TDS). b. Line Protection for 230 kV system (Main 2 - Line Differential Relay) complete with the required protective relays and accessories in accordance to the requirements of the Technical Data Sheet (TDS). Capacitive Voltage Transformer 230 kV, complete with the required accessories and support structure in accordance to the requirements of the Technical Data Sheet (TDS).

Page 5 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM A26

A27

A28

A29

A30

A31

A32 A33

A32

A33

DESCRIPTION Surge Arresters 192 kV, station type, complete with support structure and the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Ganged Disconnect Switch 230kV, 3-phase, 2000A, 40KA equipped with 460 vac 3 phase motor and manually group operated, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS). Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 kA equipped with 230 vac motor and manually group operated, complete with the required accessories in accordance to the requirements of the Technical Data Ganged Disconnect Switch 69kV, 3-phase, 2000A, 38 kA equipped with earthing blades, motor and manually group operated, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS) Voltage Transformer 69 kV, complete with the required accessories in accordance to the requirements of the Technical Data Sheet (TDS) BATTERY 125 VDC POWER SUPPLY SYSTEM 800 amp-hour capacity indoor type complete with the required rack and accessories in accordance with the requirements of Technical Data Sheet (TDS) Battery Charger 460 vac 3 phase in accordance with the requirements of the Technical Data Sheet (TDS). Supply and Installation of Emergency Generators with a capacity of 225 KVA, 460/230 vac, 60 HZ with diesel engine, Day Tank and four (4) 400 amps 480 vac 3phase 4 poles ATS NETWORK DISTURBANCE MONITORING EQUIPMENT (NDME) Supply of Data acquisition units complete with required peripherals and accessories. Reconfiguration of existing NDME to conform with the new set-up/configuration under this project to include Bay 81, 82, 83, 84, 85 & 86. The units should be the same brand or latest model and compatible with the existing unit at the control room. FIBER OPTIC COMMUNICATION SYSTEM a. Fiber Optic Terminal Equipment complete with Optical Distribution Frame (ODF), access multiplexers, circuit protections, indicators, annunciators, appurtenances, pigtails, patch cords, complete with the required accessories. b.

Fiber Optic Approach Cable, 36 fibers, 1550 nm, Signal Mode (from station gantry to the Optical Distribution Frame at the FOT Equipment Room).

Page 6 of 15

QTY 6

UNIT units

2

units

2

units

2

units

12

units

2

units

2

units

1

unit

1

lot

1

lot

1

lot

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM

QTY 2

UNIT lot

a.1 Clark S/S a.2 Mexico S/S b. Multiplex Equipment / Channel Bank and associated cards including all necessary peripheral equipment and installation accessories i.e. rack/shelf assembly, VF jack field, MDF, interface and data cable b.1 Clark S/S b.2 Mexico S/S c. Antenna System and Waveguides including all installation accessories and peripheral equipment i.e. antenna mount and support pipe, strut hardware kit, waveguide support hardware, flanging tools, waveguide connector etc. c.1 Clark S/S c.2 Mexico S/S d. Network Management System including all the necessary hardware and software modules for management of node element / sub network, i.e. industrial portable PC with licensed Windows Operating System and pre installed Network Management software.

1 1

lot lot

1 1

lot lot

1 1

lot lot

d.1 Clark - Mexico MW Radio link e. Protection Signaling Equipment complete with all the necessary interface cables, software and manuals. Programmable teleprotection unit for transmitting / receiving minimum of four (4) independent command signals capable of communicating over analog and digital communication channel i.e., MUX (4WE&M, RS232, V.32, X.21, etc), PLC, copper wire and fiber optic.

1 2

lot lot

1 1 1 1 1 1 1 1

lot lot lot lot lot lot lot lot

c.

A34

A35

DESCRIPTION Protection Signaling Equipment complete with all the necessary interface cables, software and manuals. Programmable teleprotection unit for transmitting / receiving minimum of four (4) independent command signals capable of communicating over analog and digital communication channel i.e., MUX (4WE&M, RS232, V.32, X.21, etc), PLC, copper wire and fiber optic.

MICROWAVE RADIO COMMUNICATION SYSTEM a. Digital Microwave Radio Terminal, 16E1, 7GHz, 1+1 MHSB including all necessary accessories i.e. mounting cabinet, rack/shelf assembly, order wire, fuse and alarm panel, power supply and jack field (for 16 tributaries)

Spares, Spare parts and tools( see list as per TDS) a. Power Transformer b. Power Circuit Breaker 230 kV and 69 kV c. 230 kV and 69kV Ganged Disconnect Switches d. 230 Kava and 69 kV Voltage Transformers e. 230 kV and 69 kV Surge Arresters f. Metal clad Switchgear 13.8 kV g. Station Service Transformer h. AC DC aux switchboard Page 7 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM

A36

A37

DESCRIPTION i. Storage Batteries j. Battery Charger k. MBSC l. CCTV m. Substation Protection System n. Line Protection System o. Network Disturbance Monitoring p. Fibre Optical Terminal Equipment q. Protection Signaling Equipment r Microwave Radio Telephone equipment Clark Load End Substation at PSPC Station Service Transformer 75 kva 22.9/0.23kV, three phase, Outdoor ONAN type, 35 kV xlpe cable, 300:5 amp 22.9 kV CT, and accessories in accordance to the requirements of the Technical Data Sheet (TDS). To includes bus bar modification, current transformer, cover, support and wiring/termination to substation protection system. The scope covers the construction of foundation, HV and LV wiring and installation of new transformer. Distribution Board 3 Phase 230 VAC with enclosure , main breaker, tie breaker, automatic transfer switch, four (4) 3 poles branch circuit breakers, assorted copper wires, conduits and accessories in accordance to the requirements of the Technical Data Sheet (TDS). The scope includes the wiring and termination to existing MTS/AC panel and fire suppression panel.

QTY 1 1 1 1 1 1 1 1 1 1

UNIT lot lot lot lot lot lot lot lot lot lot

2

lot

2

sets

2 12 72 12 24 24 48 1 1

lot lot lot lot lot lot lot lot lot

SUB-TOTAL FOR ITEM 3A ELECTRICAL WORKS B

B1

B2

CIVIL WORKS FURNISH, INSTALL, CONSTRUCT, PLACE, APPLY AND / OR LAY, INCLUDING FURNISHING OF PLANT, LABOR, EQUIPMENT AND MATERIALS EQUIPMENT FOUNDATION Consisting of concrete (211kg/cm²), Non-shirk Grout, Reinforcing Steel Bars (Grade 275), Excavation and backfill, Leveling Concrete (141 kg/cm²) and other incidentals required to complete the works. a. Power Transformer b. Power Circuit Breaker c. Current Transformer d. Voltage Transformer e. Surge Arresters f. Ganged Disconnect Switch G. Bus Supports f. Emergency Generator set 230 kV Gantry Structure Foundation Consisting of concrete (211kg/cm²), Non-shirk Grout, Reinforcing Steel Bars (Grade 275), Excavation and backfill, Leveling Concrete (141 kg/cm²) and other incidentals required to complete the works.

Page 8 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM B3

B4

B5

B6

B7

B8

B9

B10

B11

DESCRIPTION QTY UNIT 2227 sq.m Roadways, Parking Area, Concrete Curve & Gutter, Open stock yard Construction of access road from the existing roadway to the transformer area and parking area at warehouse, consisting of Concrete Pavement (246kg/cm²), Curb and Gutter (211kg/cm²) including dowels, Reinforcing steel bars (Grade 275), Aggregate Sub-Base and other incidentals to complete the work. 435 lm Drainage System - Consisting of different sizes of (Main) RCDP, Drainage Appurtenances consisting of Concrete (211kg/cm²), Reinforcing steel bars Grade 275, 300 lm Excavation and backfill, Miscellaneous Steel (ASTM (Sec.) A36), CHB including demolition/restoration works for the affected portion of the existing drainage appurtenances and other incidentals to complete the work. 1 lot Oil/Water Separator - Consisting of concrete (211kg/cm²), Reinforcing Steel Bars (Grade 275), Excavation and backfill, Miscellaneous Steel, Galvanized Steel pipe, B.I. Pipe, including its tapping to the nearest drainage system and other incidentals required to complete the work. 1 lot Concrete Firewall - Between transformers consisting of Concrete (211kg/cm²), Reinforcing Steel Bars (Grade 275), Excavation and Backfill, Leveling Concrete (141kg/cm²) and other incidentals required to complete the work. 400 l.m. Cable Trenches - Consisting of Concrete (211kg/cm²) (Main) Reinforcing Steel Bars (Grade 275), Excavation, leveling Concrete (141kg/cm²), Checkered Steel Plate Cover, Stiffener, Embedded Metals, Steel angle, galvanized 200 l.m. cable tray, pits, Discharge Pipes including demolition/restoration works for the affected portion of (Branches) the existing cable trench to connect the new cable trench and other incidentals to complete the work. 12 l.m. Cable Pipe Crossing Roadways - Consisting of concrete (211kg/cm²), Reinforcing Steel Bars (Grade 275) Excavation, Sand and Gravel bedding, uPCV Pipes, Discharge Pipes and other incidentals required to complete the works. 1200 cu.m Switchyard Gravel Surfacing - Gravel surfacing on the bays where the equipment will be installed with the lines and extent as directed by the owner. 235 l.m. Seclusion Fence and Gate - Enclosing the 230kV and 69kV switchyard consisting of Hot Dipped Galvanized Wire Mesh Gauge #10, G.I. Pipes Schedule 40, Miscellaneous Steel (ASTM A36), Concrete (211 kg/cm²) Reinforcing Steel Bars (Grade 275), Excavation and Backfill, and other incidentals to complete the work. 7040 sq.m. Embankment of Substation Expansion Area Consisting of clearing, grading, and embankment with compaction in layers to match the existing finish grade in accordance with DPWH Standard Specifications.

Page 9 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM B12

B13

B14

B15

B16

B17

B18

DESCRIPTION Retaining Wall and Perimeter Fence of Substation Expansion Area - Consisting of Concrete (211kg/cm²), Reinforcing steel bars Grade 275, Excavation and backfill, CHB including demolition/restoration works for the affected portion of the existing retaining wall/perimeter fence and other incidentals to complete the work. To include painting of walls and perimeter fence and affected areas. 69kV Gantry Structure Foundation Consisting of concrete (211kg/cm²), Non-shirk Grout, Reinforcing Steel Bars (Grade 275), Excavation and backfill, Leveling Concrete (141 kg/cm²) and other incidentals required to complete the works. Expansion of Existing Clark 230KV S/S Control House Consisting of architectural, civil, electrical, mechanical, and finishing works to match the existing. To include supply of 3-3 tons split air conditioning units, industrial type exhaust fan, fire detection units to connect to existing Fire Alarm panel, lights and outlets, wiring and other accessories and incidentals to complete the work. To include repainting of Bldg external and affected areas. Proposed Clark 230KV S/S Warehouse Consisting of architectural, civil/structural, electrical, and mechanical works for the construction of steel frame warehouse with minimum beam height of 6.00 meters. To include supply and installation of industrial exhaust fans, lighting fixtures and outlets. Painting of building internal and external.

QTY 295

UNIT l.m.

1

set

115

sq.m.

288

sq.m.

440 110 200 100

mtrs mtrs mtrs mtrs

1

set

420

mtrs

12

sets

9

mtrs

100

mtrs

1

unit

Fire Water System, a. Cleaning & Flushing of following existing facilities 1. 100 mm 2. 50 mm 3. 40 mm 4. Assorted sizes to control room, guard house and green area 5. Elevated Water Tank 10,000 gal b. New Installation of the following 1. 100 mm GI super sched 40 underground line with fittings, valves sand beddings and with protection membrane 2. Fire hose reel cabinet with 40 mm brass nozzle, 40 mm x 30 mtrs hose, 40 mm brass valve, fittings, glass, painted gauge #10 metal sheet and concrete foundation. 3. Road Crossing of Fire water line, include cutting, excavation, backfilling, sand bedding and road concreting Rehabilitation of Existing Water Well, includes suctioning/cleaning of existing water well including use of equipment (air compressor and other cleaning equipment) Replacement of Existing Submersible Pump multistage type, 100 GPM, 95 meters TDH complete with control and including Pull out of existing and installation of new submersible pump. Page 10 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM B19

B20

B21

DESCRIPTION Rehabilitation of Existing Fire Pump, includes cleaning of pumps, testing, electrical system and ready for operation. Rehabilitation of Existing Jockey Pump, includes cleaning of pumps, testing, electrical system and ready for operation. Brand New Truck Loader Cargo Crane Gross vehicle mass including crane 8,000, Crane capacity 5,000 kg at 2.4 meters, Maximum lift above ground 10 Meters, With Hydraulic motors for winch, and swing, Hydraulic extended Outriggers, Hydraulic pump, and powered thru PTO. For turn over to CDC-ECMD

QTY 1

UNIT unit

1

unit

1

unit

6

sets

SUB-TOTAL FOR ITEM 3B CIVIL WORKS

TOTAL CLARK SUBSTATION 230/69KV

4.0

Metering System (230kV System) Current transformer Multi ratio 2000:5A 0.3 accuracy class, Burden B-0.1 to 0.9, Voltage transformer 0.3 accuracy, weather proof enclosure for Billing meter for the electronic billing system in accordance to the requirements and specification of the power provider (NGCP/TRANSCO) for T1, T2, T3, T4, T5 and T6.

5.0

GRID IMPACT STUDY, including request and payment for the data, review and approval of NGCP

1

lot

6.0

OCCUPATIONAL HEALTH AND SAFETY includes personal protective equipment, clinical materials, signage's and barricades, and the salary and wages of health and safety personnel.

1

lot

7.0

Facilities For The Engineer such as temporary field office, including all necessary electricity, water, telephone services, office equipment, furniture and the following for the use of CDC/ECMD Engineers. For turn over to CDC-ECMD after the completion of the project 2 4

units units

2

units

2 2 2

units units units

1

unit

a b c d e f

g

Field Office (20 ft Container with AC unit) Laptops Intel Core i7-2410 processor, Window 7 pro, MS Office 2007 with external 1TB hard Drive Desktop Intel i7-550 Processor, Window 7 pro, MS office 2007 with external 1TB hard drive Licensed AUTOCAD (2010 or latest) softwares Licensed Ms Project (2010 or latest) softwares Service Vehicle Twin Cab Pick up 4 x 4 (3.0 diesel engine, common rail direct injection) with fuel, driver, maintenance, other costs (Toll fee, parking) for 14 months (lease to own) Service Vehicle AUV 4 x 2 (2.5 Diesel engine) with fuel, driver and maintenance, others (Toll, parking fee) costs for 14 months (lease to own) Page 11 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM h i j k l

DESCRIPTION Digital SLR Camera 15 megapixel with zoom 105, extra 8GB memory card and bag. Flat bed scanner A4 Color Printer A3 paper size complete with supply of paper and ink for the duration of the project Professional Infrared Thermal Imagers Voice recorder 8GB, Built-in Li-Ion Battery

QTY 2

UNIT units

1 1

unit unit

1 1

unit unit

2

sets

MEXICO 230 KV SUBSTATION Bay 87 and 88 8.0 A

A1

(All in accordance with NGCP specifications) ELECTRICAL WORKS Supply, manufacture, factory testing, and furnishing of labor, equipment, tools and incidental materials for the delivery, assembly, erection, installation, field testing commissioning and ready for operation of the following substation equipment and its associated control and protection system and accessories Power Circuit Breaker Live Tank 230kV, 3-phase, 3000A, 40, kA single and three pole operation (3+1), complete with the required accessories and support structure

A2

Ganged Disconnect Switch 230kV, 3-phase, 3000A, 44KA equipped with 460 vac 3 phase motor and manually group operated, complete with the required accessories

2

sets

A3

Ganged Disconnect Switch 230kV, 3-phase, 3000A, 44KA equipped with earthing, 460 vac 3 phase motor and manually group operated, complete with the required accessories

2

sets

A4

Capacitor Voltage Transformer (CVT) 230 kV, complete with the required accessories and support structure.

3

sets

A5

Surge Arresters 192 kV, station type, complete with support structure and the required accessories Substation Gantry and Pedestal Steel Structures including bolts, washer, etc hot dipped galvanized complete with all the required accessories

3

sets

1

lot

A7

Installation Materials consisting of conductors, insulators, connectors, pole line hardwares and other accessories

1

lot

A8

Grounding Materials consisting of insulated and bare copper cables, lightning rod, copper rods, fittings. complete with the required materials for aerial and grounding mat and to substation equipment and structures.

1

lot

A9

AC and DC Auxiliary Panels Indoor type, complete with the required equipment, devices and required accessories

1

lot

A6

Page 12 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM A10

DESCRIPTION Distribution Board 125 VDC complete with enclosure, main, Automatic transfer switch, tie breaker, branch breakers, and accessories for installation.

QTY

1

UNIT lot

A11

Distribution Board 3 Phase 230 VAC with enclosure , main breaker, tie breaker, automatic transfer switch, branch circuit and accessories

1

lot

A12

Cable Trays (various type) hot dipped galvanized, complete with supports, fittings, and other accessories. Cost of cable tray to be included at cable trenches

1

lot

A13

Substation Control System Main Control Switchboard, with all instrument, meters, indicators, control switches, annunciators, push buttons, LED indicating lamps, terminal blocks, wiring and miscellaneous auxiliary and accessory devices

1

lot

1

lot

1

set

1

lot

2

sets

2

sets

Bay Control Unit with provision for integration to existing Micro Processor Base Control System complete with necessary accessories A14

Substation Protection System a. Breaker Failure Protection System Complete with the required protective relays and accessories for four (4) 230 kV Power Circuit Breakers in one panel. b.

A15

230 kV Bus Protection System, - complete with the required Peripheral Unit protective relays and accessories for the integration of two (2) 230 kV Power Circuit Breakers

Line Protection System a. Distance Protection System (Main 1 and Main 2) Main 1 complete with the required protective relays and accessories in one panel and Main 2 complete with the required protective relays and accessories in one panel. b.

Differential Protection System (Main 1 and Main 2) Main 1 complete with the required protective relays and accessories in one panel and Main 2 complete with the required protective relays and accessories in one panel.

A16

Current Transformers 230 kV, Multi-ratio, three core, outdoor type oil filled, free standing complete with support structure and required accessories in accordance with NGCP specs.

12

sets

A17

Power Control , Instrumentation and Protection Cables, complete with insulated terminal lugs, glands, etc.

1

lot

Page 13 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM DESCRIPTION A18 Fiber Optic Communication System a. Fiber Optic Terminal Equipment complete with Optical Distribution Frame (ODF), access multiplexers, circuit protections, indicators, annunciators, appurtenances, pigtails, patch cords, complete with the required accessories.

A19

QTY

UNIT

1

lot

b.

Fiber Optic Approach Cable, 36 fibers, 1550nm, signal mode (from station gantry to the Optical Distribution Frame at the FOT Equipment Room.

1

lot

c.

Protection Signaling Equipment complete with all the necessary interface cables, software and manuals. Programmable teleprotection unit for transmitting / receiving minimum of four (4) independent command signals capable of communicating over analog and digital communication channel i.e., MUX (4WE&M, RS232, V.32, X.21, etc), PLC, copper wire and fiber optic.

1

lot

1

lot

1

lot

1

Lot

1 1 1 1 1 1 1

lot lot lot lot lot lot lot

Microwave Radio Communication System a. Complete integration and interconnection of existing FOT and MW telecommunication system with associated equipment including interface cables, MUX equipment / channel cards, etc. b.

A20

A21

B

Protection Signaling Equipment complete with all the necessary interface cables, software and manuals. Programmable teleprotection unit for transmitting / receiving minimum of four (4) independent command signals capable of communicating over analog and digital communication channel i.e., MUX (4WE&M, RS232, V.32, X.21, etc), PLC, copper wire and fiber optic. NETWORK DISTURBANCE MONITORING EQUIPMENT Supply of DAU complete with cables and accessories, Reconfiguration of the existing NDME to conform with the new setup/configuration of the substation under this project Spares, Spare parts and tools: a. 230 kV Power Circuit Breakers b. 230 kV Ganged Disconnect Switches c. 230 kV Coupling Capacitor Voltage Transformers d. 230 kV Surge Arresters e. 230 kV Current Transformers f. Substation and Line Protection System (incl at Clark SS) g. 460,230 VAC & 125 VDC Auxiliary Switchboard SUB-TOTAL FOR ITEMS 8A ELECTRICAL WORKS CIVIL and ARCHITECTURAL WORKS Complete Design, Furnish, install, construct, place, apply and/or lay, including furnishing of plant, labor, equipment and materials

Page 14 of 15

UNIT COST

AMOUNT

DESIGN AND BUILD SERVICES FOR THE CLARK 230 KV POWER TRANSMISSION LINE PROJECT PHASE 3B ITEM B1

QTY

UNIT

a. Power Circuit Breakers b. Ganged Disconnect Switches c. Capacitor Voltage Transformers d. Surge Arresters e. Current Transformers 230 kV Gantry Structure Foundation Consisting of concrete (211kg/sq cm), Non-shrink Grout, Reinforcing Steel Bars (Grade 275), Excavation and backfill, Leveling Concrete (141) kg/sq cm) and other incidentals required to complete the works. Roadways, Concrete Curve & Gutter Construction of access road from the existing roadway to the switchyard area, consisting of concrete pavement (246 kg/ sq cm), curb and gutter (211 kg/ sq cm) including dowels, Reinforcing Steel bars (Grade 275, Aggregate sub-base and other incidentals required to complete the work.

6 12 3 3 12 1

lot lot lot lot lot lot

1

lot

Drainage System, Consisting of different sizes of RCDP, drainage appurtenances consisting of concrete (211kg/ sq cm), Reinforcing steel bars Grade 275, Excavation and backfill, miscellaneous Steel (ASTM A36), CHB including demolition/restoration works for the affected portion of the existing drainage appurtenances and other incidentals required to complete the works. B5 Cable Trenches Consisting of concrete (211 kg/sq cm) Reinforcing Steel Bars Grade 275, Excavation, leveling concrete (141 kg/sq cm), checkered steel plate cover, stiffener, embedded metals, steel angle, pits, discharge pipes including demolition/restoration and works for the affected portion of the existing cable trench to connect the new trench and other incidentals required to complete the works. B7 Switchyard Gravel Surfacing, Gravel surfacing on the bays where the equipment will be installed with lines and extent as directed by the owner. SUB-TOTAL FOR ITEM 8B CIVIL WORKS 9.0 Reconfiguration/ Parameterization/ Data Base Configuration of existing MBSC System complete with Bay Control units, Cables, accessories, peripheral, etc. to conform with the new set-up of NGCP Mexico Substation

1

lot

50

l.m.

1

lot

1

lot

B2

B3

DESCRIPTION Equipment Foundation consisting of concrete (211 kg/sq. cm, NGCP specs), Non-shirk Grout, Reinforcing steel Bars (Grade 275, NGCP specs), Excavation and backfill, Leveling Concrete (141 kg/sq. cm) and other incidentals required to complete the works.

B4

TOTAL MEXICO SUBSTATION 230KV

TOTAL PROJECT DIRECT COST

Page 15 of 15

UNIT COST

AMOUNT

Suggest Documents