Best Practices for Migrating to Office 365

Best Practices for Migrating Email to Office 365 Written by Chad Lindley, product manager, Dell Software, and Ron Robbins, product manager, Dell Softw...
Author: Lynne Fields
14 downloads 0 Views 1MB Size
Best Practices for Migrating Email to Office 365 Written by Chad Lindley, product manager, Dell Software, and Ron Robbins, product manager, Dell Software

Abstract

Introduction

Many organizations today are considering moving from a legacy email system — Exchange, Notes, GroupWise, Gmail or another platform — to Exchange 2013 and Office 365. After all, Office 365 offers a lower cost of ownership, reduces the burden on IT, ensures you have the latest fixes and enhancements, and guarantees enterprise-level reliability.

Why migrate to Exchange 2013 and Office 365? Before we get into best practices for migrating to Office 365, let’s first explore the business benefits of moving to this consolidated platform. As shown in Figure 1, they include:

This whitepaper explains key migration best practices to help ensure a complete, seamless transition. You’ll learn how to properly prepare for your migration — including not just planning the technical details but also considering how the migration will impact your business and operations. You’ll also see why it’s important to give special attention to large attachments, PSTs and other local email files, and why coexistence is critical to avoiding disruption and an impact to productivity. Finally, you’ll discover how to evaluate migration solutions, and why engaging a migration partner can be a smart investment.

• • • •

Lower cost of ownership Reduced burden on IT Regular updates High reliability

Lower cost of ownership Experts agree that Office 365 is usually more cost-effective than the on-premises alternative. For mid-sized to enterprise users, Office 365 rates range from US$8.20/month to US$23.20/month, or US$100–US$300 per user per year. Compare that to the total cost of ownership on an on-premises environment. First, there are the licensing costs for each Microsoft component you need: Exchange 2013,

Experts agree that Office 365 is usually more cost-effective than the on-premises alternative.

Office 2013, SharePoint 2013, Lync and so on. Then there are the costs associated with the hardware: you’ll need multiple servers, including web, application and database servers, which you will have to maintain and replace regularly, and the proper licensing for them as well. You’ll also need a secure location to house the servers, and you will bear the associated power and cooling costs. Last but by no means least, there are the staffing costs: you’ll need skilled resources to install, manage, maintain and troubleshoot the environment — resources that are in high demand and that are therefore expensive. Add up these costs, and the total likely dwarfs the annual cost of an Office 365 subscription. Reduced burden on IT Another big advantage of Office 365 is the reduced support burden — everything is managed as part of your subscription. While you won’t be able to completely eliminate IT staffing costs, you will need fewer people with the most in-demand (and therefore expensive) skills, such as SharePoint administrators and Exchange specialists. And the IT staff you do have will be able to focus on strategic projects that add value to your business, rather than on maintenance. Regular updates Regular software updates are critical to security, performance and efficiency,

and they often deliver valuable enhancements and new features. But installing service packs and upgrading to new versions while minimizing risk and disruption requires significant planning, skill and effort. With Office 365, Microsoft takes care of updates for you, eliminating both the effort and the risk. In fact, unless you check the web page that lists the updates, you may not even know that an update has been performed. Moreover, you’ll have the latest fixes and new features as soon as they are available, while on-premises deployments will have to wait for the next service pack or version. High reliability and security Finally, there’s reliability and security. You need your critical applications, especially email, available 24/7/365. Mid-sized and enterprise Office 365 plans come with a service level agreement (SLA), a financially-backed uptime guarantee, and a dedicated development and operations team to ensure those commitments are met. To ensure security, Office 365 stores your data in an environment completely separate from the service itself. Office 365 supports many security and compliance standards, including SAS 70/SSAE16 assessments, ISO 27001 certification, HIPPA and FISMA. And your information is not mined for any reason.

Reasons to consider Office 365

Lower cost of ownership

Reduced burden on IT

Regular updates

99.9% reliability

• CapEx vs. OpEx

• No need for dedicated admins or consultants

• Microsoft will release updates to Office 365 before on-prem

• Office 365 comes with a financiallybacked 99.9% up-time guarantee

• No servers • Fewer resources needed for support

• Frees your IT staff to focus on other tasks/projects

• Updates will be more frequent

Figure 1. There are many good reasons to consider Office 365.

Share: 2

Take a broad perspective in your pre-migration planning. How will the migration impact your business and operations? Once you’ve decided Office 365 is the right platform for your organization, how do you get there? Obviously, you need to gather information about the current environment, create an inventory of the data you’re going to migrate, determine what cleanup needs to take place, calculate the available bandwidth and so forth. However, there is more to pre-migration planning than just the technical details. It’s critical to consider how the migration will impact your business and operations. You must carefully plan the project in order to minimize disruption, loss of productivity and potential revenue impact. Focusing on the business will expand the types of information you collect and the analysis of that data. For example, you certainly want to gather information about the users and mailboxes, including where the data is located. And you’ll want to review the bandwidth and calculate how much data you can migrate in a given time period. However, you also need to take

a more holistic approach and analyze how these factors could potentially impact the business during the migration. For example, you need to consider delegation relationships between users — if a user is migrated but his or her delegate remains on the source platform, how will this impact their daily work? If these individuals are key resources in an acquisition attempt or ongoing litigation, how might this separation impact the organization as a whole? More broadly, you need to consider how the migration project could impact all important business and operational workflows. With that in mind, we recommend looking at pre-migration assessment within four areas, as shown in Figure 2, to ensure you cover each area with the appropriate depth for your organization. However, at the same time, you must also consider the relationships between areas. It is important to analyze multiple aspects simultaneously, because there are interaction points that can be problematic if overlooked as you start moving through the project. For example, as you work through your

Analysis

Messaging assessment

Application considerations

Contingency planning

Existing infrastructure

• Type, amount & location of data

• What functionality must be preserved?

• Maintenance schedules

• Locations / distribution

• Attachments

• Leverage native features if possible

• Backup and/or archive prior to migrating

• Bandwidth tests and considerations

• Back-out & recovery plan

• Plan to support mobile devices

• Compliance or security concerns

• Are you planning hardware changes or a server refresh?

• Local content • Usage and need • Email retention policies and quotas • Encrypted content • Delegation relationships and sharing

• What is required to support workflows? • Will process changes be implemented? • Archive content or rebuild app

• Prepare for the unknown

Figure 2. Pre-migration planning should cover not only technical details but business impact.

Share: 3

There is more to pre-migration planning than just the technical details. It’s critical to consider how the migration will impact your business and operations.

It is critical to plan your application migration in concert with your messaging migration.

messaging assessment, it is crucial to analyze applications simultaneously and consider the interactions between mail routing and application workflow. Depending on your mail platform, it may be more or less common for applications to leverage the email platform. However, with a system like Lotus Notes, there are typically key integration points that, if disrupted as the migration begins, will negatively impact the organization. As a result, it is critical to analyze these interactions in detail before initiating any aspect of the project. Messaging assessment During the messaging assessment, be sure to consider the following: • How many users and mailboxes will be involved in the migration? • What types of data are included? How much is there, and where is it located? Be sure to pay special attention to encrypted content, private folders and, in particular, large attachments. One of the common obstacles in migrations is large attachments that were acceptable in the source platform but that violate the policies and limits in Exchange Online. Some migration solutions log these exceptions and continue processing, but other solutions may fail and stop processing mailboxes altogether. In either case, the end result is lost data and additional complication. In addition, be sure to plan where large attachments will be migrated to on the target platform. Consider migrating them to OneDrive for Business, an unlimited storage location within Office 365. • What are the current and future retention policies and quotas? Which users have private or local storage files, such as PST files in Microsoft Outlook? In fact, this topic is so important that it merits a separate discussion; see the next section, “Give special attention to PSTs and other local email files.” • Which users have delegates, and how could disruption to those relationships affect business workflows? • What apps and business processes rely on the message environment? For example, any key integration points between the

Share: 4

applications and messaging, such as workflow approvals, will be critical to migration planning and scheduling.

Application considerations As we have just seen, it is critical to plan your application migration in concert with your messaging migration. In addition to exploring how applications and messaging interact in key business processes, be sure to ask questions such as: • What components and critical features of applications must be preserved? • How can you leverage the native features of the new platform to best achieve the functionality you need — and perhaps even get new functionality that you want? • Do you need to archive any inactive content for data retention purposes? • Will you need to rebuild any applications to run properly in the new environment?

Contingency planning Migrations involve many moving parts and interactions, so it is likely, despite your best planning efforts, that something will be missed. You may overlook a dependency, connectivity may be lost during a migration, or a scheduling miscommunication may result in a group of users being migrated before they are ready. Therefore, you need to be able to back users out of a migration event and recover to the state they were in before they were migrated. This needs to be planned and tested in advance so that it can be executed efficiently if required to ensure the business does not suffer. You also need a plan for addressing security and compliance requirements. Data needs to remain safe throughout the migration, with proper access controls in place. In addition, the migration needs to address any compliance policies your organization has in place. For example, if your retention policy requires that email be deleted after 90 days, the migration process should filter out all data older than 90 days when moving mailboxes and PST files.

Also plan for how you can optimize e-discovery by centralizing data on the target platform. Migrate archives, PST files and other data stores into one storage platform in Office 365 to facilitate searching and compliance. Analysis of existing infrastructure With the business concerns fleshed out, it’s time to return to the technical details, such as the specifics about data location and bandwidth. As you inventory your existing infrastructure, be sure to consider the following: • Will everyone move to Office 365, or just part of the organization? • Are there any critical timing considerations for the organization or particular departments? • How do you currently support mobile devices? How do you want to support them in the future? • Are you planning any hardware changes or server refreshes? Could those impact the migration, or be part of the migration plan?

Give special attention to PSTs and other local email files. Why users create local email files — and why they’re a problem Out of necessity, many organizations create storage quotas for users’ server mailboxes. Many also establish email retention policies to comply with internal or external regulations and support e-discovery for legal and other purposes. Users, however, often find their storage quotas too restrictive, and do not want to be negatively impacted by retention policies. Therefore, users often create local files to store some or even most of their email on their desktop. For Exchange users, these are PST files; for Notes and GroupWise users, they are archives or local mail files. This strategy reduces the annoying emails users get about exceeding their server mailbox quotas, but it also introduces new problems. With today’s compliance and e-discovery requirements, and the consequences for non-compliance, many messaging administrators have begun to worry

more and more about PST files. PST files become large quickly, which makes them prone to corruption and may lead to data loss. Administrators can’t easily back up the files because they can reside in any number of locations and the users typically have them open. They can’t make sure the files follow retention policies, or discover data in them. In fact, administrators have a hard time even determining which users are using PST files, making management all but impossible. Considerations for migration planning Discovering users’ PST files is, of course, essential for migration planning — PST files contain business-critical data that cannot be left behind. But discovery is only the first step. You need to analyze the data to determine what should be moved, what should be deleted, and what could be archived. You need to devise a strategy to re-integrate the valuable data back into the messaging environment either before, during or after the migration process. Moreover, you need to consider how to manage the messaging environment going forward and prevent users from circumventing policies that support business needs, including compliance and e-discovery — while also respecting users’ needs for easy access to historical email and a seamless user experience that facilitates productivity. For example, if you choose to archive PST file content, you need to ensure that users retain easy access to archived data they need while also automating timely deletion to comply with retention regulations.

Plan for coexistence. Why coexistence matters Most migrations do not happen overnight, or even over a weekend. In fact, many take weeks or months. During that time, it’s critical that users continue to communicate and collaborate effectively, no matter which users and resources have been migrated. Otherwise, your

Share: 5

Discovering users’ PST files is, of course, essential for migration planning — PST files contain business-critical data that cannot be left behind.

organization faces inefficiency and user disruption that impacts the bottom line (see Figure 4). Moreover, it can lead to a negative first impression of the new environment, which can lead to resistance and lack of adoption.

It’s critical that users continue to communicate and collaborate effectively, no matter which users and resources have been migrated.

Developing a coexistence strategy The definition of “coexistence” can be different for each organization. Some organizations make heavy use of free/ busy data; others barely use it. Some rely heavily on calendaring, while others are only concerned about a complete directory of users. As a result, it is critical to work with stakeholders to develop a coherent picture of what’s important within your organization and help everyone understand the importance of an effective coexistence strategy. Be sure to consider not only email but also calendars and shared resources such as conference rooms. Users must be able to email one another and, in most organizations, be able to access free/busy information and schedule meetings. This includes both single-instance and recurring meetings. Whether meetings were already scheduled or created during the migration, the accuracy of calendar data is essential throughout the project. You must ensure that users can, for instance, change a meeting room for a single instance of a recurring

meeting or cancel a single instance without causing resource conflicts and end-user confusion. Achieving full coexistence is particularly challenging if you are migrating from a non-Microsoft platform. Many of these systems treat and store calendars differently than Microsoft solutions. Therefore, proper planning and the right tools are particularly critical for those migrations.

Evaluate migration solutions carefully. Considerations to keep in mind Migration planning, of course, also includes choosing migration solutions. What should you consider as you evaluate your options? • Your source platform —You need a solution that can handle all the specific complexities of your source data, whether you’re on Exchange, GroupWise, Notes or another platform. Many of these platforms provide options for archiving and local content, include different calendaring features, and implement different sharing and delegation models. The solution you select must be capable of automatically translating these differences to match the format expected in the target platform. This is especially true for features heavily used within your organization and relied on by end users. • Migration scope and options — Consider whether the solution offers a fixed

Why does coexistence matter? 1 2 3

5 Improper processing of

Limited or inaccurate directory updates

Lack of free/busy information between systems

Inability to reschedule meetings

4 Improper handling of

meeting cancelations

custom recurring meetings

These pitfalls = inefficiency, user disruption and $$$

6 Incomplete processing of assigned tasks

7

Difficulty scheduling resources and conflicts between systems

8 Severed application workflow

Figure 4. Without full coexistence, employees can’t communicate and collaborate effectively, and the business suffers.

Share: 6









migration process or can be tailored to your organization’s specific needs. For example, a fixed migration process might not include migration of PST files or public folders or the consolidation of multiple Exchange forests as part of the migration to Office 365. Be sure to the solution you choose offers all the specific functionality and coverage required to meet the needs of your organization. Migration fidelity & throughput — Consider whether the migration solution provides a complete migration that preserves all of your email and calendar data, including local content, delegations and access control lists (ACLs). For migrations to systems with different message and attachment limitations (like Office 365), the solution must provide automated methods of preserving attachment data and migrating content to other storage mechanisms like personal archives and OneDrive for Business. In addition, the migration solution should be multithreaded and automatically handle any migration throttles of the source and target systems to ensure the most efficient migration possible. Encryption & data security — Verify that the solution ensures the security of your data, including private folders and encrypted items. If a vendor’s only option for migrating private and encrypted content is to expose it in the source prior to the migration, you may want to reconsider whether they have your best interests in mind. The solution should provide options for handling sensitive data throughout the migration to ensure the integrity of your data while preserving the content for future use. Business continuity & workflows — As discussed earlier, you need to think not only about the data that’s being migrated, but also about your business processes. As you evaluate migration solutions, consider whether they can ensure your business needs are met on the new platform, and whether they provide the coexistence required to keep systems and employees fully functional during and after the transition. Quality of support – In many cases, when you’re selecting a migration solution, the

strength of its technical support is as important as the quality of the migration solution itself. Ensure that you will be supported during the time that you plan to perform your migration and that you will be supported by a team who has experience guiding customers to successful migration projects.

Consider engaging a migration partner. Most organizations are not involved in migrations every day; in fact, your IT staff may never have been involved in planning and executing a migration of this magnitude. However, there are organizations specializing in migration that are staffed with IT professionals with years of experience completing migrations. This experience, when applied to your migration, can help avoid the pitfalls that might otherwise occur and thereby streamline the entire migration process. In addition, your resources can stay focused on the core business strategy rather than attempting to plan and execute an unfamiliar migration project. All of this can add up to a sound return on investment. Be sure to choose a migration partner that offers: • • • • •

Customized process and timing Full coexistence Multiple migration options and approaches High migration fidelity Security, including proper treatment of private and encrypted data

Ensure a successful transition with Dell. One of the best ways to ensure a successful migration is to use Dell as a trusted partner. Dell has migrated more than 75 million AD accounts, more than 50 million mailboxes to Exchange and hundreds of terabytes of data to SharePoint. In gaining this vast experience, Dell has developed a proven methodology (see figure 5) to ensure successful migrations that is built on four key pillars: • Prepare — Mitigate migration risks with detailed pre-migration assessments

Share: 7

Engaging an experienced migration partner can deliver a sound return on investment.

Prepare

Manage

Source platforms Lotus Notes

Pre-migration Assessment

Post-migration

Exchange Online

IT management

GroupWise

AD consolidation Archiving and clean-up

Google

Advanced reporting Security and access

Migrate

POP/IMAP Exchange

SharePoint Online

Coexist

SharePoint Exchange Public Folders Windows file shares

Schedule & automate tasks

Manage & report status

Provision users & sites

Figure 5. Dell Software offers a full suite of ZeroIMPACT migration solutions. that analyze the current state of your environment. You’ll have the details you need about what should be moved and what shouldn’t, ensuring a successful, worry-free migration with no surprises. You can also consolidate or restructure your Active Directory environment before the migration to properly prepare for Office 365. • Migrate — Mitigate the risk of data loss and minimize IT and end-user impact with a high-fidelity messaging migration. • Coexist — Ensure interoperability between users throughout the migration to minimize lost productivity. • Manage — Stay in control of your new messaging and collaboration environment with auditing, reporting, recovery and email discovery in Office 365 or your hybrid environment.

Conclusion Moving from a legacy email system — whether it is Exchange, Notes, GroupWise, Gmail or another

platform — to Exchange 2013 and Office 365 offers a wealth of benefits, including lower costs, reduced burden on IT, fast access to fixes and enhancements, and guaranteed enterprise-level reliability. The transition to Office 365 is one of the most important initiatives for any business because it has a direct impact on the business-critical email environment. Planning the migration with the business in mind, choosing the right tools, and engaging the right partner are essential parts of the process. To learn more about how Dell can help ensure your successful transition, visit www.DellSoftware.com/Office365.

About the authors Chad Lindley is a senior product manager with Dell Software for solutions including On Demand Migration for Email and the Notes

Share: 8

and GroupWise transition solutions. He has worked with Lotus, Novell, and Microsoft technologies since 1994 and has focused on migration since 1999. Chad joined Quest Software in 2005 and served in a variety of presales and systems consulting roles before assuming his current position as product manager. Ron Robbins is a senior product manager at Dell Software, where he is responsible for guiding the direction of Dell’s migration solutions for messaging and Active Directory and providing assistance to customers and strategic partners. Ron has over 15 years of experience in IT and has authored several white papers and articles covering the topics of Exchange migration and management. Prior to joining Dell, Ron provided IT support and consulting services to many different organizations, including Fortune 500 companies.

For More Information © 2015 Dell, Inc. ALL RIGHTS RESERVED. This document contains proprietary information protected by copyright. No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying and recording for any purpose without the written permission of Dell, Inc. (“Dell”). Dell, Dell Software, the Dell Software logo and products—as identified in this document—are registered trademarks of Dell, Inc. in the U.S.A. and/or other countries. All other trademarks and registered trademarks are property of their respective owners. The information in this document is provided in connection with Dell products. No license, express or implied, by estoppel or otherwise, to any intellectual property right is granted by this document or in connection with the sale of Dell products. EXCEPT AS SET FORTH IN DELL’S TERMS AND CONDITIONS AS SPECIFIED IN THE LICENSE AGREEMENT FOR THIS PRODUCT,

About Dell Software Dell Software helps customers unlock greater potential through the power of technology—delivering scalable, affordable and simple-to-use solutions that simplify IT and mitigate risk. The Dell Software portfolio addresses five key areas of customer needs: data center and cloud management, information management, mobile workforce management, security and data protection. This software, when combined with Dell hardware and services, drives unmatched efficiency and productivity to accelerate business results. www.dellsoftware.com.

If you have any questions regarding your potential use of this material, contact: Dell Software 5 Polaris Way Aliso Viejo, CA 92656 www.dellsoftware.com Refer to our Web site for regional and international office information.

Share: 9 Whitepaper-BestPractMigrateEmailOffice365-US-MJ-25680

DELL ASSUMES NO LIABILITY WHATSOEVER AND DISCLAIMS ANY EXPRESS, IMPLIED OR STATUTORY WARRANTY RELATING TO ITS PRODUCTS INCLUDING, BUT NOT LIMITED TO, THE IMPLIED WARRANTY OF MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE, OR NON-INFRINGEMENT. IN NO EVENT SHALL DELL BE LIABLE FOR ANY DIRECT, INDIRECT, CONSEQUENTIAL, PUNITIVE, SPECIAL OR INCIDENTAL DAMAGES (INCLUDING, WITHOUT LIMITATION, DAMAGES FOR LOSS OF PROFITS, BUSINESS INTERRUPTION OR LOSS OF INFORMATION) ARISING OUT OF THE USE OR INABILITY TO USE THIS DOCUMENT, EVEN IF DELL HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES. Dell makes no representations or warranties with respect to the accuracy or completeness of the contents of this document and reserves the right to make changes to specifications and product descriptions at any time without notice. Dell does not make any commitment to update the information contained in this document.