APPENDIX 3: PROJECT SCHEDULE

Environmental Assessment Application Proposed Knob Hill Wind Farm APPENDIX 3: PROJECT SCHEDULE January 26, 2004 Sea Breeze Energy Inc. Appendix 3...
Author: Victor Houston
9 downloads 0 Views 323KB Size
Environmental Assessment Application

Proposed Knob Hill Wind Farm

APPENDIX 3: PROJECT SCHEDULE

January 26, 2004

Sea Breeze Energy Inc.

Appendix 3

Project Schedule: ID

Task Name

1

Scouting Phase

4

Project Phases Start

Finish

1/1/02

3/21/04

Environmental Assessment Phase

6/11/02

7/17/04

114

Permitting Phase

8/12/02

7/17/04

118

Detailed Design Phase

3/22/04

8/16/04

121

Construction Phase (First 100MW)

7/18/04

3/25/05

129

Operation Phase

10/16/04

1/26/40

Project: Knob Hill Wind Farm

Tasks

2002 Qtr 1

Qtr 2

Qtr 3

Qtr 4

2003 Qtr 1

Qtr 2

Group of tasks

Page 1 Qtr 3

Qtr 4

2004 Qtr 1

Qtr 2

Qtr 3

Qtr 4

2005 Qtr 1

Qtr 2

Qtr 3

Qtr 4

Project Schedule:

Regulatory Process and Permitting

ID

Task Name

1

Scouting Phase

1/1/02

3/21/04

2

Prospecting

1/1/02

1/31/02

3

Speculative wind data collection

8/15/03

3/21/04

4

Environmental Assessment Phase

6/11/02

7/17/04

4/25/03

7/17/04

5

Regulatory Activities

Start

Finish

6

Section 10 Issued: EA Process Applies

6/11/03

6/11/03

7

Section 11 Issued: Procedural Order

7/31/03

7/31/03

8

Prepare Draft Terms of Reference

4/25/03

10/26/03

9

Public Review of Terms of Reference

10/27/03

11/26/03

10

Agency Review of Terms of Reference

11/27/03

12/3/03

11

Revision of Terms of Reference

12/4/03

1/13/04

12

Draft Terms of Reference Approved

1/14/04

1/14/04

13

Prepare EA Application

10/27/03

1/18/04

14

EAO Screens EA Application

1/19/04

2/17/04

15

Review EA Application

2/18/04

6/2/04

16

Referal to Ministers

6/3/04

7/17/04

17

Application Approved: EA Certificate

7/17/04

7/17/04

6/11/02

1/21/04

8/12/02

7/17/04

18

160

Environmental Research

Permitting Phase

161

LWBC: Investigatory Use Permit

8/12/02

8/12/02

162

LWBC: Wind Gauge license

3/27/03

3/27/03

163

Concurrent Permit Applications

1/19/04

7/17/04

164

Detailed Design Phase

3/22/04

8/16/04

165

Wind Modelling

3/22/04

4/10/04

166

Geotechnical Siting

7/18/04

8/16/04

7/18/04

3/25/05

10/16/04

1/26/40

167

Construction Phase (First 100MW)

175

Operation Phase

Project: Knob Hill Wind Farm

Task

2003

Qtr 1

Qtr 2

Milestone

Qtr 3

Page 2 Qtr 4

2004

Group of tasks

Qtr 1

Qtr 2

Qtr 3

Project Schedule:

Environmental Research

ID

Task Name

1

Scouting Phase

8/15/03

3/21/04

220 days

3

Environmental Assessment Phase

6/11/02

7/17/04

768 days

Start

Finish

Duration

4

Regulatory Activities

4/25/03

7/17/04

450 days

17

Environmental Research

6/11/02

1/21/04

590 days

18

Public Consultation

6/11/02

11/26/03

534 days

22

First Nations Consultation

9/12/02

9/26/03

380 days

26

Terrain Stability Impacts

3/17/03

1/21/04

311 days

6/7/03

6/9/03

3 days

27

Site Visit and Reconnaissance

28

Phase 1: Review of available information

3/17/03

5/23/03

68 days

29

Phase 2: Field Work

8/11/03

10/22/03

73 days

8/11/03

8/12/03

2 days

10/17/03

10/22/03

6 days

10/23/03

1/21/04

91 days

9/17/02

1/19/04

490 days

6/5/03

6/7/03

3 days

9/17/02

4/1/03

197 days

6/4/03

7/25/03

52 days

6/4/03

6/6/03

3 days

30

Wise and Hamilton inspect stream crossings

31

Field Work

32

33

Phase 3: Report Preparation

Geology Impacts

34

Site Visit and Reconnaissance

35

Phase 1: Mapping and Literature Review

36

Phase 2: Field Studies

37

Field Studies - Recconaissance Work

38

Field Studies

7/21/03

7/25/03

5 days

39

Phase 3: Final Report

7/26/03

1/19/04

178 days

2/1/03

1/21/04

355 days

2/1/03

3/12/03

40 days

8/11/03

10/28/03

79 days

8/11/03

8/12/03

2 days

10/27/03

10/28/03

2 days

10/29/03

1/21/04

85 days

3/22/03

1/17/04

302 days

6/5/03

6/7/03

3 days

3/22/03

6/6/03

77 days

40

Hydrology Impacts

41

Phase 1: Review of available information

42

Phase 2: Field Assessments

43

Wise and Hamilton inspect stream crossings

44

Assessment of crossings and trans. route

45

46

Phase 3: Report preparation

Vegetation and Soils Impacts

47

Site Visit and Reconnaissance

48

Phase 1: Review of available information

Project: Knob Hill Wind Farm

Task

Milestone

Page 3

2003 2004 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

Group of tasks

Project Schedule: ID

49

Page 4

Continued...

Task Name

Start

Phase 2: Field Assessments

Finish

Duration

6/7/03

7/26/03

50 days

50

Field Work

6/7/03

6/12/03

6 days

51

Field Work

7/22/03

7/26/03

5 days

8/13/03

1/21/04

162 days

12/12/02

1/21/04

406 days

6/5/03

6/7/03

3 days

12/12/02

2/10/03

61 days

52

53

Phase 3: Final Report for the EA

Wildlife Impacts

54

Site Visit and Reconnaissance

55

Phase 1 - Review of available information

56

Phase 2 - Field Assessments

6/5/03

7/23/03

49 days

57

Recconaissance work

6/5/03

6/6/03

2 days

58

Radar studies for Marbled Murrelets

6/12/03

6/17/03

6 days

59

Two researchers in the field

7/16/03

7/16/03

1 day

60

Two of John Cooper's assistants in the field

7/21/03

7/23/03

3 days

8/2/03

1/21/04

173 days

1/20/03

1/21/04

367 days

6/5/03

6/7/03

3 days

1/20/03

2/28/03

40 days

6/3/03

10/28/03

148 days

61

62

Phase 3 - Report Preparation

Fish and Fish Habitat Impacts

63

Site Visit and Reconnaissance

64

Phase 1: Literature Review

65

Phase 2: Field Studies

66

In the field

6/3/03

6/5/03

3 days

67

In the field

7/20/03

7/23/03

4 days

68

Wise and Hamilton look at Stream crossings

10/27/03

10/28/03

2 days

11/4/03

1/21/04

79 days

69

Phase 3: Report Preparation

70

Land Use and Other Resource Use Impacts

8/10/02

1/21/04

530 days

98

Archaeological, Cultural, and Heritage Impacts

12/9/02

1/21/04

409 days

112

Socio-Economic and Health Impact Assessment

12/13/03

1/21/04

40 days

115

Permitting Phase

3/27/03

7/17/04

478 days

119

Detailed Design Phase

3/22/04

7/30/04

131 days

122

Construction Phase (Frist 100MW)

7/18/04

3/25/05

251 days

130

Operation Phase

10/16/04

1/26/40

12886 days

Project: Knob Hill Wind Farm

Task

Milestone

2003 2004 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

Group of tasks

Project Schedule: ID

16

17

Detailed Design, Construction, and Operation Phases

Task Name

Start

Application Approved: EA Certificate

Environmental Research

Finish

7/17/04

7/17/04

6/11/02

1/21/04

158

Permitting Phase

3/27/03

7/17/04

162

Detailed Design Phase

3/22/04

8/16/04

163

Wind Modelling

3/22/04

4/10/04

164

Geotechnical Siting

7/18/04

8/16/04

7/18/04

3/25/05

165

Construction Phase (First 100MW)

166

Road Upgrades/Construction (First 100MW)

7/18/04

1/13/05

167

Foundation Laying (First 100MW)

8/27/04

3/4/05

168

Tower Erection (First 100MW)

9/26/04

3/25/05

169

Offsite Construction (First 100MW)

7/18/04

1/13/05

170

Utility Line Construction

7/18/04

2/18/05

171

Substation Construction

7/18/04

10/15/04

172

Switchyard Construction

7/18/04

10/15/04

173

Control Room Construction

7/18/04

8/16/04

10/16/04

1/26/40

174

Operation Phase

175

Power Production

10/16/04

1/26/40

176

Adaptive Monitoring

10/16/04

7/12/07

177

Ongoing wind data collection

10/16/04

7/28/10

178

WPPI

10/16/04

10/14/11

179

Rotor Maintenance (5 years)

4/28/09

8/25/09

180

Generator Overhaul (20 years)

4/29/24

4/28/25

Project: Knob Hill Wind Farm

Task

2004

Qtr 1

Milestone

Qtr 2

Qtr 3

Page 5 Qtr 4

Group of tasks

2005

Qtr 1

Qtr 2