Project Summary  

An Association’s Fence Solution It was a classic case, an existing residential development starting to feel or actually hear the problems of  a growing community.  The Evergreen Community Association (ECA) in Woodbury, MN, an eastern  suburb of Minneapolis and St. Paul, was sculpted on the site of a former Christmas tree farm back in  1980, and since that time, the population has quadrupled in the City of Woodbury.   In 1985 the ECA  constructed a 6‐ft (1.8 m) cedar fence on the eastern edge to add a little privacy to the homes as the  traffic increased along the bordering roadway.  Now, 23 years later, the ECA was facing two major  problems, deterioration of the existing fence and increase traffic noise.  After researching their options  the AB Fence System from Allan Block was the solution.    PROJECT LOCATION  Evergreen Community  Association,  Woodbury, MN    PRODUCT  AB Fence with Ashlar  Pattern    PROJECT SIZE  1400‐ft (427 m) long  8‐ft (2.4 m)tall    ALLAN BLOCK  MANUFACTURER  Amcon Block,        St. Cloud, MN 

PLAN  The existing cedar fence had deteriorated beyond repair and needed to be replaced.  It was becoming  an eyesore and the main entrance to the association was framed on either side by this fence.  Simply  replacing the fence with a second cedar fence was considered, but the future maintenance of a wood  fence was not heavily favored.  The association was looking for a fence option that was maintenance  free and enhanced the curb appeal of their main entrance.      Through their investigation, the AB Fence proved to be the best option.  The fact that the system was  built using mortarless, stackable concrete blocks meant the system would have not only the proven 

allanblock.com  1 

performance of reinforced concrete  and long term durability, but also a  reduction in total cost when  compared to other concrete fencing  options.    The first task was to create a cost  comparison between different 8‐ft     (2.4 m) fencing options.  By  comparing these alternatives and  considering both the average  installation costs, expected life cycle  of the product with any future  maintenance costs, the AB Fence  provided the best value.  To make the  choice even easier the association  found that by combining the four different AB Fence panel block shapes, an Ashlar Blend pattern was  created to best fit the look and feel of the surrounding area.    The second issue was the traffic noise coming from the  four lane road that ran along the eastern border of the  development.  By choosing a concrete product the  amount of sound that traveled through the barrier, sound  transmission, is greatly reduced.  The chart compares the  transmission loss in decibels (dB) of different fencing  materials.  By using the AB Fence the sound was reduced  by twice as much when compared to a wooden or vinyl  product.  The AB Fence system provided all the benefits of  a long‐term, cost efficient solution and sound abatement  they were looking for.     The ECA understood that all 408 homes within the association were not going to receive the same  benefits from the AB Fence.  The homes that bordered the eastern edge would receive the maximum  benefit from the sound reduction and the property enhancement by replacing the cedar fence with the  beautiful Ashlar Blend AB Fence.  Therefore, the ECA proposed that these homeowners pay 50% of the  cost while the ECA would pay for the remaining 50%.      In order for the ECA to finance their 50% portion of the  fence they worked with a local bank to obtain a loan that  would cover the initial fence costs.  To pay for the loan  each of the 408 homes would only need to pay $125.  The  ECA needed to propose a fence assessment to the  association, which outlined the following two payment  plans for the association’s residences, (1) a $30 per year  payment for the next five years or (2) an upfront payment  of $125.  According to the ECA’s bylaws, in order for this  assessment to pass it needed an approval vote from the  majority of the residences.  This was sent out to the  homeowners for a vote and passed easily.   

allanblock.com  2 

Design  The fence was to be located in the same place as the existing wooden fence; however, this required a  little creativity in design and layout.  The fence height was expanded to 8‐ft (2.4 m) to further reduce  noise transmission.  The fence needed to accommodate over a 40‐ft (12.2 m) grade change, which  meant the panels had to step down at both the post locations and, at times, within the panel itself.    

FENCE HEIGHT = 7.98 ft (2.4 m)

  Allan Block Corporation worked with the ECA to come up with the preliminary design for the Ashlar  Blend AB Fence.  The fence was designed with a wind loading of 80 mph (129 Km/hr) with moderate  exposure. This design allowed the 8‐foot (2.4 m) tall fence to have spacing between the posts of over    16 feet (4.9 m).  The designed pile footings for the fence were 2 ft (0.6 m) in diameter and 4.5 ft (1.4 m)  deep, however the City required a 5 ft (1.5 m) minimum depth.  The panels were designed with  reinforced bond beams located at the top and bottom of the  panel sections.  The bond beams were constructed by using  a #4 reinforcing steel between two courses of block that  were grouted together.  Since the panel sections were 12  courses tall, this meant that eight courses for a total height  of 5.3 ft (1.6 m) were dry stacked between the bond beams  making the AB Ashlar Pattern easier to install.  To carry the  AB Ashlar Pattern look throughout the full panel, a single  course pattern was used to build the bond beams.  The  design also called for flipping random blocks around to  change the appearance of the fence.  This ensured that both  sides of the fence had the aesthetics of a random AB Ashlar  Blend.    Additionally, water management was crucial.  There were  specific drainage points that the City of Woodbury required  to be maintained to ensure that backyards would not flood.   Working with the City to identify these areas, the contractor,  Sierra Exteriors, was able to construct the bottom bond  beam with openings to allow any water to flow through the  fence. 

allanblock.com  3 

 

Build  Construction began in November which allowed the contractor to keep his crews busy during the winter  months.  Like any successful fence project the contractor started with marking out the proper locations  for the pile footings.   Following the AB Fence Installation Guide and using the jigs made the job easier.   As the pile footings were being excavated, they encountered boulders and rocks below grade. Each rock  had to be removed to maintain the proper location of the post.  The pile footings were then filled with  concrete and the jigs were used to ensure that the vertical steel was properly positioned.     Once the footings were completed, the posts and panels of the AB Fence were started.  The fence  design used the full sized AB Fence Panel Block for the base.  This made it easier to install the panels  straight and level and simplified the installation of the reinforcing steel and 9 gauge wire stirrups  through the bond beam.  To finish the bond beam the cores of the panel blocks were filled with  concrete.  Because of the winter conditions, the contractor did have to protect the fresh concrete when  the temperature dropped below freezing during the evenings.  Temporary tents, heaters and insulated  blankets were used throughout the project.                    Before                           After     With the high visibility of the project, everybody was interested in the color of the block and the pattern  options for the fence.  The local Allan Block manufacturer, Amcon Block, provided a beautiful three  colored blend unit for the project.  To add to the random pattern look of the Ashlar Blend, random  blocks were flipped backwards to create a change in the face appearance.  This meant that both the City  of Woodbury and the homeowners enjoyed the beautiful aesthetic color and finish of the AB Fence  System.  A local building inspector from the City of Woodbury commented that, “This fence has just set  the standard for the fence projects in the City and it has exceeded our expectations”.  

allanblock.com  Allan Block Corporation  5300 Edina Industrial Blvd, Edina, MN 55439  952‐835‐5309 – Phone  952‐835‐0013 – Fax  US Pat. #5,623,797 Canadian Pat. #2,182,321 Int’l And Other Patents Pending  

Project Summary: 

US 17 Mount Pleasant, South Carolina        As with any community that once considered themselves small, the community of  Mount Pleasant, South Carolina has seen major population growth over the years.  With  this growth the traffic congestion and noise have continued to increase to a point that  DOT traffic studies gave the US 17 corridor a ‘D’ Grade.  This poor grade was only  projected to get worse, forcing the DOT and the city to develop a plan to expand and  upgrade the corridor.  This upgrade was not only to relieve traffic congestion but also to  reduce the increasing noise problems to the surrounding residential neighborhood.  The  city of Mount Pleasant, to date, had no sound walls and wanted to set a standard with  their first.  The City chose the AB Fence System with the Ashlar Blend Pattern for its  aesthetic quality, its performance in reducing noise and its competitive cost.   

  PROJECT LOCATION  Mount Pleasant, SC    PRODUCT  AB Fence with Ashlar Blend  Pattern    PROJECT SIZE  3000 ft (915 m) long  12 ft (3.7 m) tall    ALLAN BLOCK MANUFACTURER  Block USA, Atlanta, GA   

       

PLAN    The South Carolina Department of Transportation performed many noise studies in the  corridor to determine the optimum wall location and dimensions.  The city and state  engineers worked closely together during the planning process to develop a solid plan to  move forward with public hearings and product selections.   Sound walls were new to  the area and the plan initially met some resistance.  However, the hearings proved that  if the community was going to build their first sound walls, they wanted a quality wall  system that would look great long into the future.      

Design    The design of this project was dictated by the  South Carolina DOT, therefore it was required to  follow the AASHTO Guide Specifications for  Structural Design of Sound Barriers.  The Allan  Block engineering department assisted the  designing engineer, Steven Johnson of George A.  Z. Johnson, Jr., Inc., to work through the  preliminary and final designs.  The design  parameters set by AASHTO were 90 mph wind  loads multiplied by a customary 30 % increase for  wind gusts.  A reinforced drilled shaft footing  below each AB Fence post was designed by Johnson.  Additionally, the SC DOT required  a reinforced concrete leveling pad below each panel.  The design of the posts and panels  followed Allan Block’s Fence Engineering Manual, which calls for structurally reinforced  columns and dry‐stacked block panels with predetermined courses reinforced and cast  solid as bond beams.  The system works as a traditional post and panel system with the  panels transferring loads laterally to the posts and the posts transferring loads to the  footing.  Due to the larger coastal wind loads and AASHTO requirements, the project  utilized the Allan Block Large Post Block, which greatly increases the post capacity.   

Build    Because this was the first AB Fence project for  general contractors, Gulf Stream Construction,  they invited an Allan Block Project Specialist to  the site to train their installers.  The specialist  showed them how easy the AB Fence installs if  they start off correctly.  The installation crew  caught on quickly and were off to the races.   They followed the AB Fence Installation Guide  closely and brought in a few of their own tricks  along the way while maintaining the high 

quality of the system.  The most important  thing to know prior to construction is the  exact post spacing.  Allan Block recommends  that this dimension be determined by  measuring the actual product on site.   Because the AB Fence System is modular,  there can be slight variations in the delivered  product.  Gulf Stream brought in product and  set up mock posts and panels prior to digging  the drilled shafts to insure the correct post  spacing.       Due to the tight schedule, Gulf Stream  decided to mass‐produce the bond beams by  precasting them off‐site and trucking them to  the site.  The bond beams could then be  easily lifted off the trucks and lowered into  position within each panel.  They also worked  with a local ready mix company to develop a  fine mix for the bond beams that would meet  the strength requirements, be self‐ consolidating, and not require the extra  vibration step.   These steps proved to be real  time savers.      Because the project called for the Ashlar  Blend Pattern with random blocks flipped  back and forth for added facial texture, extra  time was required to achieve the high  aesthetic quality of each panel.  To reduce  installation time and maintain a consistent  pattern, Gulf Stream decided to have the  same crew that build all the precast bond  beams, also come to the site to place the dry‐ stacked pattern block that go between each bond beam.  Gulf Stream was also able to  hire additional workers as needed to aid in less technical projects around the site.   Another time saver was the prefabrication of all the column steel.  Instead of placing  and tying individual bars and stirrups together, they could lift in place the entire rebar  cage and start placing post block.     The speed at which the AB Fence System can be installed was one of the many factors  that made this project such a success.  The City of Mount Pleasant was so happy with  the overall project that the AB Fence System has been chosen for their 2011 US 17  expansion project which includes 4 separate walls totaling over 55,000 square feet.  US Pat. #5,623,797 Canadian Pat. #2,182,321 Int’l And Other Patents Pending DOC. #F0209‐0211 

Project Summary

Meadow Substation The citizens of Longmont, Colorado had serious issues with the way that local electrical Substations around town looked. They all contained large transformers and were surrounded by 6 to 8 foot tall chainlink fences that were re-enforced with barbed wire. Obviously, homeowners didn’t want these “eyesores” in their neighborhood, and they started to complain. The city of Longmont officials also had other issues regarding the chain-link fencing. For one, the transformers emitted a loud buzz, and the chain-link fences had absolutely no noise abatement. Secondly, there was a security issue. Chain-link fencing is easy to cut, and therefore, some of the Substations were being broken into. The Longmont officials needed a cost-effective solution that would satisfy both the needs of the citizens, as well as their own. PROJECT NAME & LOCATION Meadow Substation, Longmont, CO PRODUCT AB Fence PROJECT SIZE 10,440 square feet 870 ft (265 m) in length 12 ft (3.66 m) in height LOCAL ENGINEER Landmark Engineering GENERAL CONTRACTOR & WALL BUILDER Landmark Landscapes ALLAN BLOCK MANUFACTURER Basalite - Denver, CO

PLAN After much consideration, the city officials decided that a twelve foot tall concrete fence was going to look nicer, provide the necessary noise reduction, and enhance the security of their Substations. In a previous project, they had used a pre-cast concrete panel system that was only 2.5 inches thick, and so didn’t provide the desired noise abatement. Another disadvantage of the pre-cast system was its durability, or lack thereof. It simply did not provide the rigidity that Longmont considered necessary. Lastly, the pre-cast system was expensive. When the AB Fence was presented as a possible solution for the Meadows Substation, the city officials were enthusiastic about the benefits it offered. For one, the AB Fence was aesthetically pleasing. The various colors and design options meant that they could give the wall a unique appearance. Secondly, the thicker blocks and hollow cores allowed for higher noise reduction. Because the Meadow Substation was adjacent to two different neighborhoods, being able to suppress the buzzing noise from the transformers was extremely important. Thirdly, the AB Fence provided the desired security benefits. There are no foot holds for climbing and the rigidity of the system meant the only way in was by extreme force.

Once the city approved the system, Landmark Landscapes, a certified AB Fence installer, was contacted to submit a bid. They were ultimately able to beat out the competitors by a substantial sum. The city of Longmont was already reaping the cost savings that the AB Fence provides. With the bid awarded, work at the Meadow Substation was ready to begin.

DESIGN Landmark Engineering of Loveland, Colorado, with help from Allan Block and Basalite Concrete Products, designed the AB Fence for the Meadow Substation. The site location allowed the engineer to use exposure B with 90 mph wind loading. Due to site conditions and the height of the wall, four bond beams were required and post spacing was limited to 11.5 feet (3.5 m). Expansive soils led to pile depths of 8 ft (2.4 m).

BUILD In building the AB Fence at Meadow Substation, Landmark Landscapes did have one major obstacle to overcome, and that was working around all of the electrical equipment. Live wires were buried all over the site, so a lot caution had to be taken when digging the 8 ft (2.4 m) piers. One of those wires was eventually nicked by the auger, but damage was minimal and no one was hurt. Other than that, the site was relatively flat and there was plenty of room for product and raw materials making for a convenient installation process. In installing the fence, Landmark Landscapes precisely followed the steps laid out in the AB Fence Installation Guide. Spacing jigs were constructed for proper post spacing, base rock was compacted and leveled, and the

grout in the bond beams was vibrated for good consolidation. Knowing that this project could possibly lead to future projects with the city of Longmont, Landmark took no short cuts. All of the extra attention to detail made the project a complete success. Every entity associated with the Meadow Substation fence project came out on top. The neighborhood got a wall that both looks great and reduces noise. The city officials saved money by going with AB Fence and they made the citizens happy. Landmark Landscapes have since built another Substation perimeter wall for Longmont with the possibility of more in the future. The AB Fence proved to be the obvious solution and clearly satisfied everyone’s needs.

“The wall has received many complements from citizens who regularly walk on the path adjacent to the Substation. We are very pleased with the design you recommended and as an added bonus, the sound suppression of our noisiest transformer. This was a pleasant surprise and we realized that the hollow blocks contributed to the sound deadening. Unlike the solid panel wall at our Harvard Substation, this design does absorb a majority of the sound. We are also pleased with the progress of your contractor, Landmark Landscapes at the new County Line Substation”. - - Project Manager/Electrical Engineer, City of Longmont Power & Communications.

US Pat. #5,623,797 Canadian Pat. #2,182,321 Int’l And Other Patents Pending

Project Summary  

Garrison Woods      The City of Calgary's bylaws mandate noise attenuation as part of it's structured  planning process. Sound walls are the most common solution and were chosen for the  new residential housing development in S.W. Calgary called Garrison Woods. The  developer, Canada Lands Development Company, donated a portion of the  development to the City of Calgary to construct an affordable low‐income housing  project. Since this was now city property, the city was responsible for the noise wall  construction. While Canada Lands, through an RFP process ensured that the walls were  aesthetically pleasing and complementary to their project, the city had to ensure both  performance and budgets were met.   

 

PROJECT NAME & LOCATION  Garrison Woods  Calgary, Alberta, Canada    PRODUCT: AB Fence     PROJECT SIZE: 16,000 square feet    LOCAL ENGINEER: CWA Structural    GENERAL CONTRACTOR  & WALL  BUILDER  Year Round Landscaping    ALLAN BLOCK MANUFACTURER  CCI Industries, Alberta, Canada  

PLAN  CCI Industries proposed Allan Block Fence as an option  for the project.  This was the first time Allan Block Fence  had ever been presented for a city project and although  they liked the look of AB Fence, CCI Industries had to  prove that it could meet the City's technical  requirements. Not only did the Allan Block Fence  solution exceed performance requirements, it cost less  than the post & plank system and was preferred by the  developer for its attractiveness.  Phase One of the project called for a 1230‐foot (375 m)  long wall separating Crowchild Trail and the subdivision. The multi‐phase sub‐division, 

Garrison Woods, is adjacent to a six lane arterial roadway with a posted speed of 50  mph (80 kph). Patching and Associates Acoustical Engineers were retained to provide a  sound report. Out of this report it was determined that a noise barrier was required.  Wall heights were defined using bylaw design guidelines resulting in a 13‐foot (4m) high  wall to achieve the minimum five‐decibel noise reduction.  DESIGN   CWA Structural Engineering designed the Fence with assistance from Allan Block 's  Engineering department. The 13 foot (4m) high wall was designed for exposure B wind  loads of 80 mph and included even spacing of 4 bond beams. The 20‐foot (6m) piles  were deeper than normal due to 13 feet (4m) of poor fill soil on the site. Post spacing,  based on wind loads and wall heights, were determined to be 10 feet (3.3m).  BUILD  Year Round Landscaping had few construction  challenges on this flat and very accessible site. There  was lots of room for equipment movement and  material storage, making this a safe and high‐speed  production project. No interruptions to traffic or lane  closures were incurred, minimizing the construction  impact on commuters.      Joe Caputo of Year Round Landscaping commented on how critical the layout was. He  used the layout tips described in the AB Fence Installation Guide as well as a few trade  secrets of his own. Typical AB Fence construction practices were followed through the  pile hole drilling to post setting stages. The design specified the base course of panel  block on a void form, which was placed on compacted gravel base, rather than placing  pre‐fabricated bond beam sections. Overall, Year Round made money and are happy  with the way the project went and are looking forward to bidding their next AB Fence.     The Allan Block Fence system was a clear winner on this project, satisfying  performance, financial and aesthetic needs. The success of this project has lead to the  city of Calgary accepting Allan Block fence as a preferred noise wall solution for several  subsequent projects totaling over 500,000 square feet. Phase two of the AB Fence for  Garrison Woods has been completed and there are plans for the AB Fence to be  continued as the development continues its 5‐year build out.    After the project was completed, Allan Block Corporation hired Patching and Associates  Acoustical Engineers to determine what the actual noise reduction value was for the  Garrison Woods fence. The AB Fence achieved a 13‐dba‐noise reduction. Far exceeding  the required 5‐dba reduction.     US Pat. #5,623,797 Canadian Pat. #2,182,321 Int’l And Other Patents Pending 

Project Summary  

McDonald's Fence   

"It is very important to let your customers know all of the products you sell. They may  not need it today, but one never knows what will come in the future.", states the Allan  Block sales rep from Clayton Block. This was the case on a McDonald's Fence project  located in Union City, New Jersey. Towering as high as 22 ft, the AB Fence was built to  block out the loud traffic noise between a residential area and the McDonald's parking  lot. The McDonald's Fence in Union City is the tallest Allan Block Fence installed to date.

 

PROJECT NAME & LOCATION  McDonald's Fence,   Union City, NJ    PRODUCT  AB Fence with Large Post Block    PROJECT SIZE  200 feet long  22 ft maximum height    LOCAL ENGINEER   Allied Engineering    GENERAL CONTRACTOR  & WALL  BUILDER  Waiter Builder    ALLAN BLOCK MANUFACTURER  Clayton Block, Edison, NJ 

PLAN   While discussing a retaining wall project with Waiter Builders,  Clayton Block introduced the AB Fence system as another  option for site solutions. Waiter Builders specializes in  residential and commercial renovation as well as new  construction. As luck would have it, they just happened to  have another project in the works where an AB Fence  application could be the solution.     Waiter Builders was working on a home remodeling project for  the owner of several McDonald's Restaurants in area. The  homeowner had mentioned that the Union City officials were  requiring a fence to be put in to eliminate car headlights and  

 

 traffic noise from interfering with the residents adjacent to the McDonald's parking lot.  

The AB Fence system was perfect for this type of application. Not only could it provide  superior noise abatement, up to two times greater than the existing wood fence  system, it also has an incredible aesthetic style and is extremely durable. With all the  information on the AB Fence system, the builder was able to discuss this solution with  the owner of McDonald's. In no time, a design and estimates for the fence were under  way.  

DESIGN   Allan Block Corporation worked along with Allied Engineering Associates to come up  with a design for the fence. A preliminary design was completed, based on assumed soil  conditions that needed to be verified.     In the meantime, additional soil borings were conducted. It was discovered that there  was a layer of bedrock 3.5 to 7.5 ft from the grade. This meant that Allan Block and the  Allied Engineering team needed a revised design. The soil conditions were better for the  design, but made foundation construction a nightmare.     Drilling into the dense bedrock for post foundations was an expensive part of the  project but reduced the pile depths and the amount of bond beams needed. After the  final design, it was determined that the fence would utilize a post spacing of 6.5 blocks  (10.5 feet) at the maximum height, and the pile dimensions would need to be 8 ft deep  with a diameter of 2.5 ft.     The panel sections required five #5 bond beams, the post section required six #7 bond  beams and the pile required eight #7 bars for reinforcement. The final unit cost for the  system was $34.50 per square foot including labor, materials and profit. The majority of  the cost went to coring for the pile foundations. This alone cost over $35,000! This is  why it is so important to determine what type of soil exists beneath the surface before  determining labor costs on a project.    

 

 

BUILD   The new large post block was required to be run on a  Columbia Block Machine. Since Clayton Block does not have  this machine, the blocks had to be shipped in from another  Allan Block manufacturer to the project site. When it arrived,  an Allan Block Project Specialist was on site to help train the  installers. The key to the construction was to first build a jig  using the blocks that were delivered to the site. The diagram  below is a drawing of the spacing jig that was built for this  project. Once the jig was made, excavation began for the piles.   The vertical reinforcing bars were placed immediately into the  poured piles. Once the piles were constructed and the base  trench was excavated, they could now begin the post and  panel construction. 

 

  Jig Diagram  First, two post blocks were stacked, followed by the first row  of panel blocks. Then rebar was placed for the horizontal bond  beam directly on the first panel block course. After the bond  beam was laid, the second layer of panel blocks were placed  on top of the first layer and the first two courses of post and  panel block were filled with concrete grout.     Next the installers placed more vertical reinforcement into the  posts and continued this procedure until the top course was  complete and caps were glued in place.  

 

In just fourteen working days the project was complete. The 22 ft high project had a  final count of 3,146 panel blocks, 473 half‐panel blocks, 565 post blocks and 139 cap  blocks.     This remarkable fence now acts a beautiful sound barrier to both the patrons of  McDonald's and the residents of Union City New Jersey.    US Pat. #5,623,797 Canadian Pat. #2,182,321 Int’l And Other Patents Pending DOC. #F0209‐0211 

Advantage The

TM

Allan Block

December 1996

Specifying, Engineering, Designing & Installing AB Retaining Wall Systems

ALLAN BLOCK SURROUNDS THE AIR FORCE Wanting privacy and security, Fairchild Air Force Base in Spokane, WA was in search of a product to enclose key installations. AB Producer White Block and AB Sales Representative Ben Corrigliano provided the answer - AB FENCE. Offering a new look, customized color, fast and easy installation, all at a great price. White Block understood the long term potential of the AB Fence and set up a training seminar at their plant to walk potential contractors through the installation details. Jeff Gunderson, AB Technical Support Staff, presented the key ingredients of both design and construction during the “Learn As You Go” contractor seminar. From this rather simple beginning, enough experience and components were obtained to have two of the contractors that attended the seminar land jobs at Fairchild Air Force Base. Forrest H. Jackson, Inc. did the Museum Fence at 150’ long x 6’ high and the Berm & Irrigation Building Fence at 450’ long x 4’ to 7’ high. TKTM Corp. replaced a 3000’ long x 6’ high chain link fence with AB Fence. Both contractors initially stated there was an on-site learning curve but once their crews understood the process AB Fence went up fast. They also agreed that AB Fence was easier and cheaper than a CMU wall. On average, a 4 person crew could install between 60’-110’ per day depending on the layout of the fence. Fairchild Air Force Base is very pleased with the look of AB FENCE and are considering a second phase of approximately one mile long this spring. White Block and Allan Block teamed up to show that the AB Advantage carries through to AB Fence; easy to install, durable, cost effective, mortarless fencing. If you have a project where AB Fence would be a good alternative, call Allan Block for more information at 800-899-5309.

PROJECT: Fairchild Air Force Base Spokane, WA AB BLOCK PRODUCER: White Block CONTRACTORS: Forrest H Jackson Inc. TKTM (Tectum) Corp.

1