ALTERNATIVE ENERGY STATUS IN PAKISTAN PROF DR NASIM A. KHAN SENIOR EXECUTIVE DIRECTOR OSMANI & COMPANY (PVT) LTD 14 MARCH 2013 DR.
[email protected],
[email protected]
EARLY GOVERNMENT EFFORT • Originally the Pakistan Atomic Energy Commission initiated projects in solar energy but this effort was soon transferred to other Ministries. 1960’S [PEC] • They include Solar Energy Research Centre [SERC] under Pakistan Council for Scientific and Industrial Research [PCSIR] in the Ministry of Science and Technology; • Appropriate Technology Development Organization (ATDO) in the Ministry of Science and Technology; • a Directorate General of Renewable Energy Resources (DGER) in the Ministry of Petroleum and Natural Resources; and • a Directorate of Renewable Energy [DAE] under the Water and Power Development Authority (WAPDA) in the Ministry of Water and Power.
Several solar-lit villages in different parts of the country and a small wind turbine established by the Directorate of New and Renewable Energy Resources during the 80’s
SERC RESEARCH RESULTS
EARLY GOVERNMENT EFFORT • ATDO was later upgraded and renamed as the Pakistan Council for Appropriate Technology (PCAT) [1980’S]. • A new organization the National Institute of Silicon Technology [NIST], was also created in the Ministry of Science and Technology to develop solar cell manufacturing. [1980’S] • All organizations under the Ministry of Science and Technology were later merged into the Pakistan Council for Renewable Energy Technology (PCRET) [1990’S], while DGER and the Renewable Energy Directorate under WAPDA were either closed or were not utilized.
NATIONAL INSTITUTE OF SILICON TECHNOLOGY NOW PCRET BUILDING
PRIVATE SECTOR • ALMOST NON EXISTENT
FINANCING/ LEGAL INSTITUTES • ALMOST NON EXISTENT
EXISTING ALTERNATIVE ENERGY DEVELOPMENT ORGANIZATIONS IN PAKISTAN – AEDB [ALTERNATIVE ENERGY DEVELOPMENT BOARD] [2003/4] – PCRET [ PAKISTAN COUNCIL FOR RENEWABLE TECHNOLOGIES] – AED SINDH [ ALTERNATIVE ENERGY DEPARTMENT, GOVERNMENT OF SINDH] [2005/6] – PUNJAB POWER DEVELOPMENT COMPANY [2007/8] – SINDH ELECTRICTY COMPANY [2009/10]
CURRENT PRIVATE SECTOR • RENEWABLE ENERGY ASSOCIATION OF PAKISTAN • PAKISTAN WIND ENERGY ASSOCIATION • SOLAR ENERGY SOCIETY • CONSULTANTS • INSURANCE COMPANIES • STUDENTS • ENERGY ENGINEERING DEPARTMENTS IN UNIVERSITIES • SEVERAL BUSINESSES OPERATING • SEVERAL NGO’S PRESENT
ENERGY SECURITY DILEMMA • POPULATION PATTERN • ENERGY GENERATION PATTERN • SOLAR AND WIND ENERGY SCENARIO
POPULATION PATTERN
• ENERGY GENERATION PATTERN
HYDROPOWER JAMMU& KASHMIR
EXISTING AND POTENTIAL HYDROPOWER PROJECTS IN PAKISTAN
• ENERGY GENERATION PATTERN
HYDROPOWER JAMMU& KASHMIR
OIL KHOST SHARIG SOR-RANGE
THERMAL SUI
LAKHRA
THERMAL
THAR COAL
EXISTING AND POTENTIAL OIL, GAS AND COAL RESERVES IN PAKISTAN
JAMMU& KASHMIR
AVAILABILTY OF SOLAR ENERGY IN POPULATION CENTERS IN PAKISTAN
APRIL
SOURCE: SOLAR ENERGY GUIDE AND DATABOOK FOR PAKISTAN N.A.KHAN
GUPIS GILGIT CHITRAL 1.5 3.3
MONTHLY WIND MAPPING OF PAKISTAN MONTH:
MAY
ANEMOMETER HEIGHT 30METERS
0.9
DATA SOURCE: METEOROLOGICAL DEPARTMENT OF PAKISTAN
1 M/S
6 M/S
2 M/S
7 M/S
3 M/S
8 M/S
4 M/S
9 M/S
2.5 BUNJI 3.0 2.3 CHILAS ASTOR 2.6 SKARDU
3.8 DROSH 3.0 DIR
PESHAWAR
1.7
1.9 PARACHINAR 3.0
1.3
MUZAFFARABAD BALAKOT
0.9 KAKUL 1.9 ISLAMABAD 1.2 JHELUM 0.9
5 M/S
D. I. KHAN 2.4
10 M/S
WIND SPEED COLOUR CODE
KOTLI 3.9
1.8 ZHOB
3.3
3.4 3.5
KALAT
JACOBABAD 3.0
MAY
KHUZDAR
PANJGUR 3.3
STUDY REPORT BY PAKISTAN COUNCIL FOR APPROPRIATE TECHNOLOGY
NAWABSHAH 4.2 PADIDAN
JIWANI
1.9 KHANPUR
SUKKUR 2.1
3.5
5.0
3.2 BAHAWALNAGAR
2.1 BAHAWALPUR
2.0
DALBANDIN NOKUNDI
2.7 MULTAN
BARKHAN
SIBI
2.1
5.1
2.5
LAHORE
1.6 FAISALABAD
LORALAI
QUETTA
SIALKOT
2.3 HYDERABAD
10.8 ORMARA
KARACHI 5.9
4.5 8.3 BADIN
COMPILED BY BRIG DR NASIM A. KHAN 9.1 CHOR
GUPIS GILGIT 2 .5 CHITRAL 1.5 BUNJI 4.6 3.1 DROSH 3 .3 2 .5 CHILAS ASTOR DIR 2 .9 SKARDU 1.0 3.6
MONTHLY WIND MAPPING OF PAKISTAN MONTH:
JUNE
ANEMOMETER HEIGHT 30 METERS DATA SOURCE: METEOROLOGICAL DEPARTMENT OF PAKISTAN
1 M/S
6 M/S
2 M/S
7 M/S
3 M/S
8 M/S
4 M/S
9 M/S
PESHAWAR 1.9 PARACHINAR 3 .4 1.9
1.3
MUZAFFARABAD BALAKOT 1.1 KAKUL 1.7
ISLAMABAD 1.4 JHELUM 0.9
5 M/S
D. I. KHAN 2 .5
10 M/S
WIND SPEED COLOUR CODE
KOTLI 3.3
2 .2 ZHOB
4.3
FAISALABAD
4.1
MULTAN 2 .5
2 .2
DALBANDIN
KALAT
JIWANI
2.5
JACOBABAD 3.4
KHANPUR
JUNE
SUKKUR 2.9
KHUZDAR
STUDY REPORT BY PAKISTAN COUNCIL FOR APPROPRIATE TECHNOLOGY
NAWABSHAH 6.1
9.7 ORMARA
3.8 BAHAWALNAGAR
2.5 BAHAWALPUR
PADIDAN 5.1
BARKHAN
SIBI
2 .2
3.1
PANJGUR 3.6
4.0
3 .3
QUETTA
NOKUNDI
LAHORE
2 .3
LORALAI
7.8
SIALKOT
KARACHI 5.9
3.0
5.2 HYDERABAD 8.1 BADIN
9.0 CHOR
COMPILED BY BRIG DR NASIM A. KHAN
WIND MAPPING SURVEY FOR POWER POTENTIAL
PAKISTAN METEOROLOGICAL DEPARTMENT – WIND MEASURING SITES IN BALUCHISTAN
Pakistan Meteorological Department
WIND MAPPING SURVEY FOR POWER POTENTIAL
PAKISTAN METEOROLOGICAL DEPARTMENT–WIND MEASURING SITES IN SIND
WIND TURBINES ON COASTLINE OF KARACHI
DEVELOPED BY
DIRECTOR PROJECT 10 CORPS, ADVANCED ENGINEERING RESEARCH ORGANIZATION (AERO), SOLAR TEAM EME, NATIONAL COMMISSION FOR ALTERNATIVE ENERGY (NCAE) IN COLLABORATION WITH
DHA KARACHI, VOLTA BATTERIES,
OCEAN SERVICES, NICE LINK TRUST, SOLAR PRODUCTS INCORPORATED PAKISTAN, WIND
BARON
WIND LIT COAST OF DHA KARACHI
Street lights of Beach Avenue, DHA Karachi
Micro wind turbines installed at Village Dandari, Ghora Bari, Thatta Sindh
TWO WIND PUMPS BY MERIN PVT OPERATIONAL IN BALOCHISTAN
Project experience Technical Advisor Hybrid Power System Community Managed
Client •
New Zealand Ministry of Foreign Affairs & Trade (MFAT)
Location •
Coastal Balochistan, Pakistan
Date •
2002 – ongoing, (Co-partnered with Empower Consultants Ltd) Facilities; Solar-diesel hybrid system Services; Resource assessment, System design, Site installation
Project experience Technical Advisor Client •
New Zealand Ministry of Foreign Affairs & Trade (MFAT) (Co-partnered with Empower Consultants Ltd)
Location •
Durgai, Baluchestan, Pakistan
Date •
2003
Facilities • 7.5 kW wind turbine, 0.5 kW solar panels, a 10 kW diesel generator, and 60 x 2v long-life acid batteries. Services Hybrid System Installation Resource assessment Wind, •Solar and Diesel • System design
•
Site installation
GHARO-KATIBANDAR-HYDERABAD WIND CORRIDOR AT 50 METERS
14
METERS/SECOND
12
10 8
HYDERABAD GHARO
6
KATIBANDAR
4
2 0 JAN
FEB
MAR
APR
MAY
JUN
JUL
MONTH
AUG
SEP
OCT
NOV
DEC
.
MONTH:
GUPIS GILGIT
3.6
MONTHLY WIND MAPPING OF PAKISTAN
CHITRAL 4.6 DROSH 3 .3
JUNE
1.5
BUNJI 3.1 2 .5 CHILAS ASTOR 2 .9 SKARDU
DIR
ANEMOMETER HEIGHT 30 METERS
2 .5
1.0
DATA SOURCE: METEOROLOGICAL DEPARTMENT OF PAKISTAN
1.3
PESHAWAR 1.7
1.9 PARACHINAR
MUZAFFARABAD BALAKOT
1.1 KAKUL
1 M/S
6 M/S
2 M/S
7 M/S
3 M/S
8 M/S
1.4 JHELUM
4 M/S
9 M/S
KOTLI
3 .4
1.9
ISLAMABAD
0.9
5 M/S
D. I. KHAN
10 M/S
WIND SPEED COLOUR CODE
3.3
2 .5
2 .2
4.3 2 .3
LORALAI
FAISALABAD 4.0 3 .3
QUETTA
MULTAN 2 .5
BARKHAN
SIBI
2 .2
KALAT
2.5
JACOBABAD
KHANPUR
3.4 3.1
3.8 BAHAWALNAGAR
2.5 BAHAWALPUR
2 .2
DALBANDIN NOKUNDI
LAHORE
ZHOB
4.1
7.8
SIALKOT
JUNE
SUKKUR 2.9
Average summer wind direction from Gharo to Hyderabad
PANJGUR
KHUZDAR
3.6
STUDY REPORT BY PAKISTAN COUNCIL FOR APPROPRIATE TECHNOLOGY
NAWABSHAH 6.1 PADIDAN 3.0
5.1 JIWANI
9.7 ORMARA
KARACHI 5.9
5.2 HYDERABAD 8.1 BADIN
9.0 CHOR
COMPILED BY BRIG DR NASIM A. KHAN
WIND PROJECTS IN PAKISTAN
MICRO SITING OF WIND FARMS BY AEDB EXPERTS
GHARO AREA
AEDB DATA
50m Wind Mast –Zephyr Power
WIND PROJECTS IN PAKISTAN
60m Wind Measuring Mast- NPE
First 60m Wind Measuring mast in Pakistan (www.KonDen.com)
WIND PROJECTS IN PAKISTAN
JHIMPIR
AEDB DATA LAND IN JHIMPIR, THATTA DISTRICT, SINDH
JHIMPIR AREA WIND FARMS
AEDB DATA
85m Wind Measuring Mast- Masterwind
85m Wind Measuring Mast- Masterwind
85m Wind Measuring Mast- Zorlu
85m Wind Measuring Mast- Zorlu
WIND FARM AT JHIMPIR
NUMBER OF WIND SPEED DATA COLLECTION MASTS INSTALLED IN PAKISTAN 80
70
60
50
40
30
20
10
0 2001
2002
2003
2004
2005
2006
INSTALLED/YR
2007
2008
CUMULATIVE MASTS
2009
2010
2011
2012
WIND ENERGY POWER PROJECTS TARIFF AEDB DATA S.No Name of IPP 1 Dawood Power Ltd 2 Zorlu Enerji 3 FFC Energy Ltd Three Gorges First WInd Farm 4 Pakistan 5 Yunus Energy Ltd 6 Foundation Wind Energy - I Ltd 7 Foundation Wind Energy - II Ltd 8 Tenaga Generasi Ltd 9 Gul Ahmed Wind Power Ltd 10 Sapphire Wind Power Company Ltd 11 Metro Power Company Ltd 12 Master Wind Energy Ltd 13 Zephr Power Ltd 14 Sachal Energy Development Pvt Ltd
Tariff (US$ Cents per kWh) 11.87 13.3456 16.109 13.9399
13.9399 17.3672 14.1359 14.1164 13.6202 14.6098 13.2483 14.5236 14.532 15.9135 14.8618
Date Announced 6 Dec, 2008 13 Dec, 2011 10 Aug, 2010 15 Dec, 2011
15 Dec, 2011 15 Feb, 2012 16 Mar, 2012 16 Mar, 2012 26 April, 2012 8 May, 2012 8 May, 2012 15 May, 2012 29 June, 2012 24 May, 2012 3 Jan, 2012
STAKEHOLDER ORGANIZATIONS INVOLVED IN WIND POWER PROJECTS
• • • • • • •
AEDB GOVT OF SINDH NEPRA NTDC HESCO KESC INVETSTORS
INVESTORS • • • • • • •
STATE BANK OF PAKISTAN NATIONAL BANK OF PAKISTAN HABIB BANK OF PAKISTAN MUSLIM COMMECIAL BANK ALLIED BANK FAYSAL BANK ASKARI BANK
LEGAL AND FINANCING INSTITUTES DEVELOPED • LEGAL COUNCILS; – KABRAJI & TALIBUDDIN – HAIDERMOTA & CO
• FINANCIAL CONSULTANTS; – BRIDGE FACTOR
• WIND ENERGY CONSULTANTS – – – – –
ME CONSULT RER OSMANI WIND ROSE IPEC
EXISTING SOLAR ENERGY SCENARIO IN PAKISTAN
SOLAR POTENTIAL OF PAKISTAN TOTAL ANNUAL SOLAR ENERGY OVER PAKISTAN= 2,324,320,000,000
MWH
SOLAR POTENTIAL IS
30,000 TIMES ANNUAL ENERGY GENERATED IN PAKISTAN
GOMA
NARAM ADM GYONG
OLDING
ADIL
PAIJU IHEC
GHAYARI DUMBA BAO
SKARDU
HAMZI GHUND
GILGIT BURZIL
LEH NULLAH
GULTARI
SHAKMA
NEKRUN
BUNYAL
KEL
QUETTA
SHARDA
SERVING THE NATION WITH A DIFFERENCE VINJORE
AWARAN
RANAK DHAR GHARO KARACHI
MARA POST
URAN KEL
TARIQ CAMP
SOLAR SYSTEMS LAB COLLEGE OF EME
MINI SOLAR THERMAL POWER PLANT SPONSORED BY MINISTRY OF S&T AND UNESCO
MINI SOLAR THERMAL POWER PLANT SPONSORED BY MINISTRY OF S&T AND UNESCO
SOLAR CELL FABRICATION MACHINE AT SOLAR SYSTEMS LAB
CADMIUM TELLURIDE SOLAR CELLS FABRICATED AT SOLAR SYSTEMS LAB
SOLAR WATER DISINFECTOR FOR 100 LITERS/DAY
INSTL OF SOLAR PANEL AT IHEC 18,500 FEET ELEVATION
SOLAR LIGHTS AT GOMA HOSPITAL
SOLAR LIGHTS AT GOMA WORKSHOP
DEMONSTRATION OF SOLAR PV SYSTEMS TO MASSES IN NA
Solar lighting System on top of Mosque in Awaran, Balochistan
SOLAR LIT ROOMI PARK RAWALPINDI
SOLAR LIT PRESIDENCY PARK
SOLAR LIT PARK AT GILGIT
SOLAR LIT CAA PARK GILGIT
FCNA GATE LIT BY NIGHT WITH SOLAR ENERGY
SOLAR CAR DESIGNED BY STUDENTS AT SOLAR SYSTEMS LAB CAN BE IMPROVED FOR AUTO RICKSHAWS
FRONT WALL AFTER GLASS FITMENT
FINAL FRONT VIEW OF THE HOSPITAL IN WINTERS
Hospital at Jambar Kashmir being heated by solar heated water
• STIRLING ENGINE DEVELOPED IN PAKISTAN
• STIRLING ENGINE DEVELOPED IN PAKISTAN
Remote Village Electrification •
Demonstration project of 100 solar homes at Narian Khorian completed, and inaugurated by the Prime Minister in June 2005.
•
Pilot project of 100 solar homes in each province completed.
•
A total of 1,762 homes electrified in 30 villages so far in all four provinces
•
7,874 off-grid villages to be electrified by AEDB in Balochistan (6,968) and Sindh (906)
•
400 (300 in Balochistan and 100 in Sindh) to be electrified in the Ist phase of the program
•
3000 homes in Sindh electrified
SINDH 3000 HOMES
Overview of village Bharomal (Sindh)
ALLAH BAKHSH DANDAR, BALOCHISTAN
SOLAR WATER PUMPING FROM COAL MINE
NE recently completed a successful installation of Pakistan's largest solar water pumping system. The system employs a solar array size of 7 kW and is capable of delivering a daily water output of more than 600,000 litres.
DHA CITY KARACHI
PAKISTAN ENGINEERING COUNCIL ISLAMABAD
SOLAR PV CELL MANUFACTURERS • AKHTER SOLAR • SARA SOLAR • AROUND 9 MW OF SOLAR PV CELLS HAVE BEEN MANUFACTURED AND INSTALLED IN PAKISTAN • Around $ 100 MILLIONS MARKET
BIO-ENERGY • BIO-DIESEL POLICY APPROVED AND AVAILABLE • THOUSANDS OF ACRES OF JATROPHA, PONGAMIA PLANTED • BIO GAS PLANTS [5000 INSTALLED, 1000 BEING INSTALLED IN PUNJAB]
GERMAN AGENCY FOR TECHNICAL COOPERATION (GTZ)
•
“Renewable Energy & Energy Efficiency
Programme” of six years duration • Initiated in October 2003 • Euro 3,500,000 committed by Germany for the first two years of the Programme • Aims to improve capacity / capability of the Public & Private Sectors for RE, including i) Rural Electrification ii) Energy Efficiency activities in selected
UNDP-GEF • Two-year project for “Sustainable Development of Utility Scale Wind Power Production” approved by GoP • Project funding amounts to US $ 3.1 Million • Aims to elaborate on the existing wind policy • Country-wide wind resource assessment also part of the project
USAID / SOUTH ASIAN REGIONAL INITIATIVE ON ENERGY (SARI) • Country-wide Wind and Solar Resource Assessment carried out under the USAID/SARI Programme amounting to US $ 1.9 Million • Project spanned over a two-year time period; initiated in 2004
CONCLUSION
EUROPEAN ENERGY SOURCES SHIFT TO NOTE SHARE OF RENEWABLE ENERGY IN ALL NEW POWER (GW) IN EUROPE DURING THE YEAR 2009
10 8 6 4
ENERGY SOURCE
SOLAR CSP
HYDRO
NUCLEAR
WASTE
OIL
BIOMASS
COAL
SOLAR PV
0
GAS
2
WIND
POWER GIGA WATTS
12
ENERGY CYCLE OF TRANSITION OF WEST SOLAR/AE 50 YRS
NUCLEAR 50 YRS
NIL
MILLIONS OF YRS
OIL & GAS
WOOD
COAL
THOUSANDS OF YRS
150 YEARS
ENERGY CYCLE OF TRANSITION OF REMOTE AREAS OF PAKISTAN
NIL
WOOD (MILLIONS OF YEARS)
ENERGY CYCLE OF TRANSITION RECOMMENDED STRATEGY PAKISTAN SOLAR/AE 50 YRS
NUCLEAR 50 YRS
NIL
MILLIONS OF YRS
OIL & GAS
WOOD
COAL
THOUSANDS OF YRS
150 YEARS
INNOVATIVE STRATEGIES A QUESTION IS, WHEN WOULD AN AVERAGE PAKISTANI USE ENERGY EQUAL TO ENGLAND OF 1970 ?
PLAN SUCH A TARGETTED GROWTH FOR THE YEAR 2030 OR 2050
IN REALITY IN PAKISTAN, SOLAR ENERGY AND WIND ARE THE ACTUAL SOURCES REST ALL ARE ALTERNATE SOURCES OF ENERGY