XBID NWE+ project Status Update
EMD WG Brussels, 15/01/2015 Martine Verelst
Progress Made Business Blueprint Phase deliverables : all, except one, signedoff end of December 2014. Identification of gaps Performance : good progress, almost finalised Contract negotiations progressing at low pace First User Group meeting held Open point : separate code base
EMD WG/ 15.01.2015 / Martine Verelst
2
Integrated Plan: Critical Path for Contract Signature from Dec 2014 Date Contract
W Until Dec.
1/12
8/12
15/12-02/01 Finalisation contractual points
4/5 WS in Paris
Draft main body
9
19
Agreement head of terms for Operational Agreement
05/01
19
3 QP update by DBAG
1
19
Equal Treatment
OTS
9
Alignment process with DBAG
PX Alignments
26 28 Receiving final version documents Batch 1
24
Agree approach doc. sep.
8 05
CBS Final Decision
Receiving final version documents Batch 2
BBP
Letter of Intent
Clarification Workshop
Physical Workshop
Planning Workshop, high level gap impact
Interim version
02/02
2
9
JSC – DBAG recommendation on CBS
Impact analysis (cat D)
12
5
Agreement on Gap Process
Provision to DBAG
16/02
Workshop TSOs/ DBAG (E Gaps )
WS PXs/ DBAG (E Gaps )
27
Final version contract
23
16
20
31
Start Contract Signature
Final NRA letter available
PX SC Approval
OTS Contract sign off
Discussion/clarification of OTS performance 13
OTS/LTS/TS decision
Detailed OTS specification
15 19
23
OTS Contract scope negotiation
16
Key Contract terms
13
PX response on CBS to DBAG
10
Discussion and finalisation Critical business process (CBP)
CBP signed off
Planning with reflection on Gaps
16
March
PX/DBAG board approval
Organisation of LIPs & impact on XBID (planning/budget)
Preparation UAT plan (incl. LIPs)
18
DBAG BBP deliverables Sign off
23/02
All agreements completed, costs closed except gaps cat A, D, E
Gap workshop 8 - Shipping Module etc. All outstand. issues with BBP deliverables solved
5
19
Clarification CC/WS
16 1st E Gap impact analysis completed & reviewed
30
6
HL UAT plan PXs to DBAG
detailed UAT plan PXs to DBAG
13
2nd round
1st round
Quality Plan updated by acceptance criteria
20
Project timeline plan signed off
Quality Plan sign off completed
Update BBP with agreements on gaps cat A, D, E
3rd round
CR/Gap optimisation & negotiation in 3 rounds
PX/TSO decision on Gaps
23 Approvals
Input/ Dependency
09/02
Contract finalisation
Impact analysis DBAG and review TSOs/PXs (cat E) 11
Milestone completed but not to required quality
Milestone at risk
Justification RTS to NRAs
Christmas & New Year
Budget Performance
8
4
Call DBAG/ PXs
Final QP by DBAG available
Decision on OTS
26
26/01
30
PXs-DBAG internal discussions on OTS
25
Missed Milestone
Milestone re-planned
Drafting NRA letter
WS DBAG/ PXs
RTS for QP (possibly with limited scope)
24
Completed Milestone
Finalisation with timeline
ITTF budget assumptions to be finalized
28
19/01
Finalization of contractual negotiation
Budget Pre-finalisation
QP update by PXs
12/01
Planned Milestone
TBD: IDSC DBAG contract approval
30
27
27
IDSC decision
6
IDSC decision
Interim version of cost request to NRAs, with BBP and indication on CRs
PX SC/I DSC/DBAG approval
13
IPX SC & DSC decision
31 24
Extraordinary IDSC Meeting (telco) Approval
25
25 Letter to NRA’s sent
NRA Approval
Tentative Project Timeline Will be updated and submitted to NRAs at end Feb 03.06.14
04.08.14
09.12.14
BBOP previous schedule
BBP(ESA Step 2 Phase 1)
Development of the local systems
BBP(ESA Step 2 Phase 2)
Development
Contingency
Test
Go-Live Preparati on
Contract preparation IAT
UAT Emergency
FAT I
UAT Functional FAT II
UAT Integrati on
UAT Performance
UAT Simulation
Conti ngen cy
Completed
Note - The contingency can be used in any of the testing step (applicable for IAT, FAT, UAT).
On-going Pending 4
Overview of Local Implementation Projects (LIPs) Draft LIP
Tentative Participants1
1
Nordic
Fingrid, EnDK, SvK, Statnett, NPS
2
DK2/DE (Kontek)
EnDK, 50Hz, NPS, EPEX
3
DK1/DE, DE/NL
EnDK, TenneT NL& DE, Amprion, EPEX, APX/Belpex, NPS
4
NorNed
Statnett, TenneT NL, APX/Belpex, NPS
5
FR/DE, CH/ DE, CH/FR, DE/AT
Amprion, TransnetBW, APG, RTE, Swissgrid, EPEX, NPS
6
NL/BE
Elia, TenneT NL, APX/Belpex
7
BritNed
BritNed, NG, TenneT NL, APX/Belpex, APX UK
8
FR/BE
RTE, Elia, APX/Belpex, EPEX
9
FR/ES
RTE, REE, EPEX, OMIE
10
IFA
RTE, NG, NPS, EPEX
11
AT/CH
APG, Swissgrid, EPEX
12
ES/PT
REE, REN, OMIE
TSOs and PXs participating for developing and implementing the XBID Solution PXs participating; TSOs observers PX observer status Adherence of PX to the project ongoing
1
4 7 10
2
3 6
8
5 11
9 12
1 The
list is based on the present status of PXs active in the concerned countries; it does not prevent any other PX joining as soon as they are selected as NEMO in one of the countries.
5